2018_-_El_Capitan_Bridge_Inspection_Report.pdf
PDF 5 MB Posted
- Attached to
- CA NPS BP 2017(1), Bridge Preservation Yosemite
- Solicitation number
- 69056718B000030
About this file
2018 - El Capitan Bridge Inspection Report
View the file
Other files
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STRUCTURE SUMMARY STRUCTURE NO. 8800-002P
EL CAPITAN BRIDGE INSPECTION DATE: 7/12/18
BRIDGE IDENTIFICATION AND DESCRIPTION
MAIN SPAN MATERIAL: ....... STEEL NO. OF MAIN SPANS:
MAIN SPAN TYPE: ............... STRINGER/MULTI-BEAM or GIRDER NO. OF APPR. SPANS:
# OF BEAMS, MAIN SPAN: .. 5 STRUCT. TOTAL LENGTH: .. 125.0 FT (38.1 M)
DECK TYPE: ......................... CONCRETE CAST-IN-PLACE MAX. SPAN LENGTH: .......... 45.0 FT (13.7 M)
WEARING SURFACE: .......... BITUMINOUS DECK WIDTH: ...................... 43.0 FT (13.1 M)
ABUT. FOUNDATIONS: ........ SPREAD FOOTING ON PILES CURB TO CURB WIDTH: ..... 27.0 FT (8.2 M)
PIER FOUNDATION(S): ........ SPREAD FOOTING ON PILES YEAR BUILT:
ABUTMENT / PIER MAT'L: ... MASONRY YEAR RECONSTRUCTED: .. N/A
PROJ./PLAN REF. NO: ......... 1B2 / RG367 SKEW ANGLE: ..................... 0 °
NPS ROAD CLASS: .............. 1 - PRINCIPAL PARK ROAD FRACTURE CRITICAL: ........ NO
STRUCTURE HISTORY: ...... 2009 - NEW ASPHALT OVERLAY. 2015 - ADDITIONAL SCOUR ANALYSIS PERFORMED.
LOCATION
YOSEMITE NATIONAL PARK MILE POINT: ..................... 0.28 (KM PT 0.45)
STATE: ................................. CALIFORNIA LOCATION: 10.3 miles east from El Portal boundary line on CA Route 140 (El Portal Road). Turn left (north),FACILITY CARRIED: ............ EL CAPITAN CROSSOVER then 1/4 mile toward El Capitan to bridge.
FEATURE INTERSECTED: .. MERCED RIVER
STRUCTURE EVALUATION SUMMARY
This steel multi-beam bridge is in fair structural condition, but has problems with scour and undermining, the extent of which is outlined below. Severe decay of the south timber fascia in the east span has caused the timber sidewalk above to be temporarily closed until repairs are complete. Other deficiencies include decay of the remaining fascia timber; deterioration of the mortar joints in the abutment breastwalls, bearing seats, and pier walls; and several locations of collision damage to the steel railing. Additional defects noted were missing rail sleeves; loose bolts at the rail posts; minor curb spalls; and a 14" drop-off at the west end of the south sidewalk.
It should also be noted that this structure has been deemed "scour critical", i.e. calculations from a 1998 scour study indicate the bridge foundations may be susceptible to undermining and instability during a major flood event. An additional scour evaluation was performed in 2015, and recommended installing additional engineered riprap in front of both abutments and around the piers, as well as monitoring the foundations for scour following major flood events.
It should be noted that the substructure footings are founded on timber piling. During this inspection, the abutment footings (pile caps) were exposed full length with up to 8" of undermining. Undermining of the northeast wingwall footing is present, and extends back for approximately 2'. Scour is present at the piers, with up to 5' of the footing (pile cap) exposed at the downstream end of the east pier. An underwater inspection performed in August 2018 further detailed the location and extent of the scour and its effects.
INSPECTION TEAM: J. ANDERSON, D. CHRISTENSEN
CONDITION ASSESSMENT:
JEFFREY ANDERSON, P.E., FIELD TEAM LEADER 720-963-3384
REPORT REVIEW:
MARCUS MILLER, P.E., BRIDGE INSPECTION ENGINEER 703-404-6252
REPORT APPROVAL: DATE: 12/4/18
JORGOMAI CEESAY, PH.D., P.E., BIP SUPERVISORY ENGINEER 703-404-6244
STRUCTURE SUMMARY STRUCTURE NO. 8800-002P
STRUCTURE EVALUATION SUMMARY CONTINUED
Corrective measures should be taken as outlined in this report to prevent the possible development of more serious or costly problems in the future.
RECOMMENDATIONS AND ESTIMATED COSTS STRUCTURE NO. 8800-002P
A (Critical) - Structure is closed, in imminent danger of collapse, or presents a critical safety hazard.
B (Major) - Structure exhibits severe deterioration, presents a safety hazard, or is designated a high priority due to age and/or condition.
C (Moderate) - Structure is deficient, functionally obsolete, or requires substantial repairs to prevent a serious deficiency or unsafe condition.
D (Minor) - Structure is generally in good condition. Preventative maintenance may be required.
E (Special) - Structure is under construction or reconstruction.
C226 PRIORITY OF IMPROVEMENT
ITEM
NO.
ROUTINE MAINTENANCE QTY. UNIT UNIT
COST
PRELIM.
COST
ESTIMATE
ITEM
NO.
REHABILITATION/RECONSTRUCTION
(TYPICALLY NEEDED WITHIN 5 YEARS)
QTY. UNIT
UNIT
COST
PRELIM. COST
ESTIMATES
REHAB. RECONSTR.
S
S
PRELIMINARY ESTIMATE TOTAL* :
(*Includes typical contract costs for mobilization, traffic control, and design/construction engineering; but does not include detour bridges, work beyond the bridge limits, or work not listed above. Estimates are approximate and are for preliminary planning purposes only; they should not be used as a complete or final engineers estimate.)
REMARKS: It is recommended the south sidewalk be temporarily closed until repairs to sidewalk are complete
It is recommended that bridge foundations be monitored for scour following major flood events.
Cost estimates assume that recommended actions will be combined with similar work being performed on other structures.
FIELD INSPECTION REPORT STRUCTURE NO. 8800-002P
CONDITION RATING CODES FOR ITEMS 58 - 62, 222, 223
N NOT APPLICABLE
9 EXCELLENT CONDITION
8 VERY GOOD CONDITION - no problems noted.
7 GOOD CONDITION - some minor problems.
6 SATISFACTORY CONDITION - structural elements show some minor deterioration.
5 FAIR CONDITION - all primary structural elements are sound but may have minor section loss, cracking, spalling, or scour.
4 POOR CONDITION - advanced section loss, deterioration, spalling, or scour.
3 SERIOUS CONDITION - loss of section, deterioration, spalling, or scour have seriously affected primary structural components. Local failures are possible.
Fatigue cracks in steel or shear cracks in concrete may be present.
2 CRITICAL CONDITION - advanced deterioration of primary structural elements. Fatigue cracks in steel or shear cracks in concrete may be present or scour may have removed substructure support. Unless closely monitored it may be necessary to close the structure until corrective action can be taken.
1 “IMMINENT” FAILURE CONDITION - major deterioration or sec ion loss present in critical structural components or obvious vertical or horizontal movement affecting structure stability. Structure is closed to traffic but corrective action may return structure to light service.
0 FAILED CONDITION - out of service; beyond corrective action.
CONDITION RATING CODE EQUIVALENTS FOR SUB-ELEMENTS
G = GOOD (CODES 7 - 9) F = FAIR (CODES 5 - 6) P = POOR (CODES 0 - 4)
58. DECK 6
1. DECK SLAB F
2. EXPANSION JOINTS N
3. WEARING SURFACE G
4. RIDEABILITY G
5. CURBS, SIDEWALKS, AND MEDIAN P
6. PARAPETS AND/OR RAILINGS P
7. DRAINS AND DRAINAGE P
8. UTILITIES N
9. DEFLECTION AND/OR VIBRATION G
10. OTHER N
59. SUPERSTRUCTURE 6
1. BEARING DEVICES
2. GIRDERS OR BEAMS
3. ARCH(ES) OR SLAB(S)
4. FLOOR BEAMS AND STRINGERS
5. TRUSSES
6. DIAPHRAGMS AND BRACING
7. PAINT
8. FASCIA(E)
9. DEFLECTION AND/OR VIBRATION
10. ALIGNMENT
11. OTHER
60. SUBSTRUCTURE
ABUTMENTS
1. BREASTWALLS OR COLUMNS
2. PILE BENTS
3. CAPS AND/OR BEARING SEATS
4. BACKWALLS AND/OR BULKHEADS
5. FOUNDATIONS (SPREAD FTG)
6. WINGWALLS
7. WEEP HOLES
8. EXPANSION JOINTS
9. EROSION AND/OR SCOUR
10. SETTLEMENT OR DEFLECTION
11. SLOPE PROTECTION
12. OTHER
PIER(S)
13. WALLS AND/OR COLUMNS
14. PILE BENTS
15. CAPS AND/OR BEARING SEATS
16. FOUNDATIONS
17. EROSION AND/OR SCOUR
18. SETTLEMENT OR DEFLECTION
19. OTHER
F F N N N G F P G G N
F N F G G F N P F G N N
F N F N F G N
58.1
58.2,3,7
58.5
58.6
ITEM REFERENCE AND REMARKS
MINOR TRANSVERSE CRACKING WITH EFFLORESCENCE ON DECK
UNDERSIDE, SPACED APPROXIMATELY 6' ON CENTER IN CENTER
SPAN AND AT ISOLATED LOCATIONS IN EAST AND WEST SPANS.
TRANSVERSE CRACKS WITH EFFLORESCENCE FROM CRACKS IN
OVERHANGS OF WEST SPAN. MINOR CRACKING OF DECK HAUNCH
AREAS OVER DIAPHRAGMS.
DECK EXPANSION JOINTS PAVED OVER; STEEL HEADERS NOT
VISIBLE. TOP OF DECK COVERED WITH ASPHALT WEARING
SURFACE; MINOR TRANSVERSE CRACKING OF WEARING SURFACE
AT DECK ENDS.
DECK DRAINS PAVED OVER; NO LONGER FUNCTIONING.
SIDEWALKS ARE PAVED WITH ASPHALT OVER TIMBER DECKING.
TIMBER DECKING IS IN GENERALLY GOOD CONDITION (EXCEPT AS
NOTED BELOW), BUT EXHIBITS MINOR WHITE SPOTS ON
UNDERSIDE. MODERATE TRANSVERSE CRACKING OF ASPHALT.
SOUTH SIDEWALK IN EAST SPAN IS SAGGING DUE TO SEVERE
DECAY OF SOUTHEAST FASCIA TIMBER LOG. SAGGED SECTION
WAS BARRICADED OFF DURING THIS INSPECTION.
SPALLING OF CURB ALONG NORTH SIDE. SEVERAL AREAS OF
MINOR COLLISION DAMAGE ALONG CURBS WITH SPALLING. MINOR
VERTICAL AND TRANSVERSE CRACKING OF CURBS.
LOOSE/MISSING ANCHOR NUTS ON SEVERAL RAIL POST PLATES.
RAIL POST ANCHOR BOLT NUTS MISSING AT EAST END OF SOUTH
RAILING. DEBRIS ACCUMULATED ON TOP OF RAIL ANCHORAGES
CAUSING CORROSION OF ANCHOR BOLTS. NUMEROUS GAPS EXIST
BETWEEN BRIDGE RAIL SECTIONS WHERE SPLICE SLEEVES HAVE
SLIPPED OR HAVE NOT BEEN INSTALLED.
ONE SECTION OF SOUTH RAIL IN EAST SPAN AND ONE SECTION IN
CENTER SPAN ARE BENT. NORTHWEST APPROACH RAIL IS
DAMAGED. MINOR VERTICAL AND TRANSVERSE CRACKS WITH
MINOR DELAMINATION OF GROUT PADS AT EAST END OF NORTH
RAILING; MINOR SPALLING AT EAST END OF SOUTH RAILING.
MINOR COLLISION DAMAGE ON TO WEST END OF SOUTH RAILING
AT TURNDOWN WITH WELD CRACKED AROUND BASE.
ITEM REFERENCE AND REMARKS
STREAM BED COMPOSITION : 9.
AVERAGE CLEAR OPENING 8.
NORMAL VELOCITY 7.
ADEQUACY OF OPENING 6.
OTHER 5.
WATERWAY OBSTRUCTIONS 4.
CHANNEL PROTECTION 3.
EROSION AND/OR SCOUR 2.
ALIGNMENT 1.
61. CHANNEL 5
G F N F N
LOW
SUFF
14 FT.
SANDY
222. APPROACHES 7
1. APPROACH SLABS
2. RELIEF JOINTS
3. APPROACH GUARDRAIL
4. SURFACING
5. EROSION
6. SETTLEMENT
7. SIGNS
8. ALIGNMENT
9. OTHER
N N N G F G F G N
223. RETAINING WALL N
1. WALL
2. WEEP HOLES
3. FOUNDATION
4. EROSION AND/OR SCOUR
5. SETTLEMENT OR DEFLECTION
6. OTHER
36. TRAFFIC AND SAFETY FEATURES
A. BRIDGE RAILINGS
B. TRANSITIONS
C. APPROACH GUARDRAILS
D. APPROACH GUARDRAIL ENDS
TRAFFIC SAFETY RATING CODES
0 - Does not meet standards or a safety feature is required and none is provided.
1 - Meets currently acceptable standards.
N - Not applicable or a safety feature is not required.
59.1,2,6,7 MINOR SPOT RUSTING OF BEARING PLATES AT ISOLATED
LOCATIONS, NOT ACCESSED DURING THIS INSPECTION.
CORROSION ON BOTTOM FLANGES FOR FULL LENGTH OF
EXTERIOR GIRDERS. SPOT CORROSION ON FLANGES OF INTERIOR
GIRDERS.
HIGH WATER DEBRIS IN SUPERSTRUCTURE OF WEST SPAN.
59.8 SOUTHEAST FASCIA LOG HAS SEVERE DECAY IN TOP FACE FOR
FULL LENGTH. ALL FASCIA LOGS HAVE MINOR TO MODERATE
DECAY IN TOP 12". MINOR TO MODERATE CHECKING OF FASCIA
LOGS. MISSING TIE BOLT NUTS ON FASCIA LOG AT BOTH SIDES OF
WEST PIER. DECAY IN SIDEWALK SUPPORT LOG ON NORTH SIDE
OF CENTER SPAN. SEVERAL ANCHOR BOLT NUTS ARE LOOSE OR
MISSING FROM FASCIA LOGS WHICH SUPPORT SIDEWALKS.
DISCONNECTED CURB FASCIA BOARD ON SOUTH SIDE OVER
CENTER SPAN. TIMBER FASCIA HAS PULLED AWAY FROM DECK UP
TO 6" AT NORTHWEST AND SOUTHWEST CORNERS; MODERATE
DETERIORATION. SEVERE DECAY IN SOUTHEAST FASCIA HAS
CAUSED SIDEWALK TO SAG IN SPAN 1. NORTH (UPSTREAM)
FASCIA HAS IMPACT DAMAGE IN SEVERAL AREAS.
60.1,13 MINOR CRACKING AND DETERIORATION OF MORTAR THROUGHOUT
ABUTMENT BREASTWALLS AND PIER WALLS. HORIZONTAL
SEPARATION, UP TO 1/2" WIDE, OF MORTAR JOINTS AT CENTER/TOP
OF WEST ABUTMENT.
60.3,15 FLOOD DEBRIS ON PIER AND ABUTMENT CAPS. MODERATE
HORIZONTAL CRACK IN FIRST MORTAR JOINT DOWN FROM TOP AT
BEARING AREA OF BOTH ABUTMENTS. MODERATE CHECKING IN
ENDS OF TIMBER CAPS. MODERATE DECAY IN NORTH END OF
BOTH PIER TIMBER CAPS AND SOUTH END OF WEST PIER TIMBER
CAP.
NUTS MISSING FROM ANCHOR BOLTS CONNECTING TIMBER CAPS
TO PIER WALLS AT SOUTH END OF EAST PIER AND NORTH END OF
WEST PIER.
60.6,10 MINOR MOSS GROWTH AND SOME EFFLORESCENCE ON
WINGWALLS, MOSS GROWTH NOT PRESENT DURING THIS
INSPECTION.
MINOR SETTLEMENT OF NORTHEAST WINGWALL. LARGE TREE
GROWING ADJACENT TO SOUTHEAST WINGWALL.
60.8 SEVERE DETERIORATION OF VERTICAL JOINT FILLER AT
NORTHEAST RETAINING WALL/WINGWALL.
ADDITIONAL ITEM REFERENCE AND REMARKS
60.9,17 MODERATE SCOUR AND EROSION AT ABUTMENTS, WINGWALLS AND PIERS; ABUTMENTS AND PIERS ARE ON
FOUNDED ON TIMBER PILES, HOWEVER.
WEST ABUTMENT FOOTING EXPOSED AND UNDERMINED UP TO 8" FULL LENGTH; CONCRETE IS ABRADED. EAST ABUTMENT FOOTING EXPOSED FULL LENGTH AND UNDERMINED UP TO 8" ALONG UPSTREAM THIRD.
NORTHEAST WINGWALL FOOTING EXPOSED FULL HEIGHT X 8'L; UNDERMINING 5'L ON NORTH SIDE X 32"L ON
WEST SIDE X UP TO 1.5'D X 2' UNDER NEAR EAST END.
MODERATE SCOUR ALONG PIERS, MOST PRONOUNCED AT DOWNSTREAM END OF EAST PIER WHERE FOOTING
EXPOSED UP TO 5'.
SEE AUGUST 2018 UNDERWATER INSPECTION REPORT FOR ADDITIONAL INFORMATION.
61.2 SEE BRIDGE FILE FOR SCOUR EVALUATION.
61.2 SEVERE SLOUGHING ALONG EAST BANK, BOTH SIDES, WITH SEVERAL UNDERMINED TREES. PREVIOUSLY
REPORTED SANDBAR AT WEST UPSTREAM SIDE IS NO LONGER VISIBLE.
61.4 HEAVY ACCUMULATION OF LOGS AND DEBRIS IN CHANNEL AT UPSTREAM SIDE OF CENTER SPAN AND BOTH PIERS. PREVIOUSLY NOTED PILINGS PROTRUDING FROM STREAMBED IN CHANNEL UNDER EAST AND WEST SPANS NOT VISIBLE DURING THIS INSPECTION. MODERATE SILT BUILDUP IN WEST SPAN ALONG WEST PIER.
222.5,6 MODERATE EROSION AT END OF SOUTHWEST APPROACH SIDEWALK WITH 14" DROP-OFF.
222.7 NO TYPE 3 OBJECT MARKERS PRESENT AT BRIDGE CORNERS.
36.B,C,D NO APPROACH GUARDRAILS PRESENT.
STRUCTURE LOAD RATING STRUCTURE NO. 8800-002P
TRUCK TYPE
INVENTORY RATING (NORMAL TRAFFIC) OPERATING RATING (MAXIMUM LOAD)
TONS METRIC TONS TONS METRIC TONS
H 22 20 37 34
HS 30 27 51 46
TYPE 3 27 24 46 42
TYPE 3S2 43 39 72 65
TYPE 3-3 53 48 89 81
DESIGN LOADING: H15 (M13.5)
X CAPACITY MEETS OR EXCEEDS DESIGN LOAD
CAPACITY IS LESS THAN DESIGN LOAD
ORIGINAL LOAD RATING CALCULATION APPLICABLE
X ORIGINAL LOAD RATING CALCULATION REVISED
DATE OF LOAD RATING CALCULATION: 4/16
LOAD RATING CONTROLLED BY: MOMENT CAPACITY OF BEAMS
REMARKS: SEE BRIDGE FILE FOR LOAD RATING CALCULATIONS.
STRUCTURE INVENTORY AND APPRAISAL STRUCTURE NO. 8800-002P
STRUCTURE IDENTIFICATION
(201) PARK: YOSEMITE NATIONAL PARK
(202) STRUCTURE NAME: .......... EL CAPITAN BRIDGE
(203) STRUCTURE KIND: ............1 - BRIDGE
(204) STRUCTURE NUMBER: ..... 8800-002P
(205) NPS REGION: .................... 6 - PACIFIC WEST
(206) ROUTE CODE NUMBER: ... 11
(207) ROAD SECTION NO: ..........002P
(208) NPS ROAD CLASS: ............ 1 - PRINCIPAL PARK ROAD
(209) WITHIN NPS BNDRY?: .......YES
(210) OPERATING UNIT: ............. PARK
(211) PROJECT NO(S): ................1B2
(212) DRAWING NUMBERS: ....... RG367
(21) MAINTAINED BY: ................. 66 - NATIONAL PARK SERVICE
(22) OWNER: ............................... 66 - NATIONAL PARK SERVICE
(1) STATE:
(2) STATE HWY. AGENCY DIST:
(3) COUNTY CODE:
(4) CITY/PLACE CODE:
(5) INVENTORY ROUTE:
(6) FEATURES INTERSECTED:
(7) FACILITY CARRIED:
(8) STATE STRUCTURE NO:
(9) LOCATION:
(10) INV. RTE. - MIN. VERT. CLR: ..
(11) MILE POINT:
(27) YEAR BUILT:
(106) YEAR RECONSTRUCTED:
(20) TOLL:
(37) HISTORICAL DESIGNATION: ..
069 - CALIFORNIA (CA)
043 - MARIPOSA
167000110
MERCED RIVER
EL CAPITAN CROSSOVER
8800002P0000000
10.3 miles east from El P
99.99 FT (99.99 M)
0.28 (KM PT 0.45)
N/A
3 - FREE ROAD
5 - NOT ELIGIBLE
STRUCTURE DESCRIPTION, FOUNDATION, AND DECK TYPE
(43A) MAIN STR. MATERIAL: ..
(43B) MAIN STR. TYPE:
(45) NO. OF MAIN SPANS:
(48) MAX. SPAN LENGTH:
(49) STRUCTURE LENGTH:
(216A) ABUTMENT #1 FDN:
(216B) ABUTMENT #2 FDN:
(217A) PREDOM. PIER FDN.: ..
(217B) SECOND. PIER FDN: ...
(107) DECK TYPE:
3 - STEEL
02 - STRINGER/MULTI-BEAM or GIRDER
45.0 FT (13.7 M)
125.0 FT (38.1 M)
3 - SPREAD FOOTING ON PILES
3 - SPREAD FOOTING ON PILES
3 - SPREAD FOOTING ON PILES
3 - SPREAD FOOTING ON PILES
1 - CONCRETE CAST-IN-PLACE
(44A) APPR. STR. MATERIAL: ........ 0 - OTHER
(44B) APPR. STR. TYPE: ................ 00 - OTHER
(46) NO. OF APPROACH SPANS: .. 0
(108) WEAR SURFACE/PROTECT SYSTEM:
A) TYPE WEARING SURFACE: .. 6 - BITUMINOUS
B) TYPE MEMBRANE: ................. 0 - NONE
C) TYPE PROTECTION: .............. 0 - NONE
(218) IS SALT USED?: ..................... NO
LOAD RATING AND POSTING
(31) DESIGN LOAD: ................. 2 - H15 (M13.5) (41) LOAD RESTRICTION: ......... A - OPEN, NO RESTRICTION
(66) INVENTORY RATING: ...... 30.0 TONS (27.2 METRIC TONS) (70) BRIDGE POSTING: .............. 5 - NO POSTING REQUIRED
(64) OPERATING RATING: ...... 51.0 TONS (46.3 METRIC TONS)
INSPECTION DATES
(90) INSPECTION DATE: 7/18 (91) FREQ. OF INSP: 24 MONTHS (92 / 93) CRITICAL FEATURE INSPECTION (CFI):
(219) ADD. STUDIES NEEDED: N - 0 - NONE (A) FRACTURE CRITICAL: ... NO
INSP. EVERY: MONTHS - LAST INSP. : (220) SPECIAL STUDY TYPE: 5 - SCOUR
(B) UNDERWATER: .............. YES
(221) SPECIAL STUDY DATE: 9/98 INSP. EVERY: 60 MONTHS - LAST INSP. : 8/18
(C) SPECIAL INSPECTION: .. NO
INSP. EVERY: MONTHS - LAST INSP. :
STRUCTURE INVENTORY AND APPRAISAL STRUCTURE NO. 8800-002P
GEOMETRY, TRAFFIC, AND NAVIGATIONAL DATA
(16) LATITUDE: ............................. 37°43'26.60"
(17) LONGITUDE: ......................... 119°37'53.50"
(19) DETOUR LENGTH: ............... 5 MI (8 KM)
(28A) LANES ON STRUCT:
(28B) LANES UNDER STRUCT: ... 00
(42A) SERVICE ON: ..................... 5 - HIGHWAY-PEDESTRIAN
(42B) SERVICE UNDER: .............. 5 - WATERWAY
(29) AVG. DAILY TRAFFIC:
(30) YEAR OF ADT:
(114) FUTURE ADT:
(115) YEAR OF FUTURE ADT:
(101) PARALLEL STRUCTURE: ... N - NONE
(38) NAVIGATION CONTROL?: ... 0
(39) VERTICAL CLEARANCE: ...... 0.0 FT (0.0 M)
(40) HORIZ. CLEARANCE: ........... 0.0 FT (0.0 M)
(111) ABUT. OR PIER PROT:
LATERAL UNDERCLEARANCE:
(55) RIGHT: ....................... 0.0 FT (0.0 M)
(56) LEFT: ......................... 0.0 FT (0.0 M)
(51) CURB TO CURB WIDTH:
(52) DECK WIDTH:
(32) APPR. ROADWAY WIDTH:
(213) APPR. PAVEMENT WIDTH:
LEFT SHOULDER:
RIGHT SHOULDER:
(33) BRIDGE MEDIAN:
(34) SKEW ANGLE:
(35) DECK FLARE?:
(47) TOTAL HORIZ. CLEARANCE:
(50) SIDEWALKS:
LEFT :
RIGHT :
(214) BRIDGE RAIL TYPE:
RAIL CONFIGURATION:
MATERIAL:
DESIGN TYPE:
(215) BRIDGE RAIL HEIGHT:
(53) MIN. VRT. CLEAR. OVER DECK:
(54) MIN. VRT. UNDERCLEARANCE:
27.0 FT (8.2 M)
43.0 FT (13.1 M)
38.0 FT (11.6 M)
22.0 FT (6.7 M)
8.0 FT (2.4 M)
8.0 FT (2.4 M)
0 - NO MEDIAN
0 °
NO
27.0 FT (8.2 M)
5.7 FT (1.7 M)
5.7 FT (1.7 M)
1 - FULL HEIGHT (NO PARAPE
6 - ALUMINUM
1 - CONTINUOUS RAIL
3.83 FT (1.17 M)
99.99 FT (99.99 M)
0.00 FT (0.00 M)
CONDITION AND APPRAISAL DATA, PROPOSED IMPROVEMENTS, AND COST
(58) DECK:
(59) SUPERSTRUCTURE:
(60) SUBSTRUCTURE:
(61) CHANNEL:
(62) CULVERT: ...........................N
(222) APPROACHES:
(223) RETAINING WALL: ........... N
(36) TRAFFIC SAFETY FEAT: ... 1000
(75A) TYPE OF WORK:
(75B) WORK DONE BY:
(76) IMPROVEMENT LENGTH: ..
(67) STRUCTURAL EVALUATION:
(68) DECK GEOMETRY:
(69) UNDERCLEARANCES:
(71) WATERWAY ADEQUACY:
(72) APPROACH ALIGNMENT:
(113) SCOUR CRITICAL:
(225) PURPOSE OF IMPROVEMENT:
(226) PRIORITY OF IMPROVEMENT:
(227) MAINTENANCE COST:
(228) REHAB./RECONSTR. COST: ...
(229) CONSTRUCTION COST:
N
3 - Scour critical; foundations un
2 - REHAB/RECONSTRUCTION
C - MODERATE
$19,000
$273,000
$0
ADDITIONAL INFORMATION
(230) STRUCTURE HISTORY:
2009 - NEW ASPHALT OVERLAY. 2015 - ADDITIONAL SCOUR ANALYSIS PERFORMED.
(231) ADDITIONAL CONSIDERATIONS:
(330) ADDITIONAL CONFIG. INFO.:
Span #1, #3 - 42', #2 - 45'; Type 302 (Steel Girder) 5-each https://119�37'53.50 https://37�43'26.60
APPENDIX STRUCTURE NO. 8800-002P
PHOTOGRAPHS STRUCTURE NO. 8800-002P
PHOTO #1 - LOOKING WEST
FLOW
PHOTO #2 - SOUTH (DOWNSTREAM) SIDE
PHOTO #3 - EROSION AT END OF APPROACH
SIDEWALK AT SOUTHWEST CORNER
PHOTO #4 - BROKEN END WELD AND SCRAPE
AT END OF SOUTHWEST APPROACH RAIL
PHOTO #5 - DAMAGED RAIL AT END OF NORTHWEST CORNER
PHOTO #6 - GENERAL TOPSIDE VIEW LOOKING WEST
PHOTO #7 - MISSING AND DISCONNECTED NUTS ON TOP OF BRIDGE
RAIL
PHOTO #8 - DISCONNECTED RAIL EXPANSION CONNECTION ON
NORTH SIDE NEAR WEST ABUTMENT
PHOTO #9 - DEBRIS ACCUMULATED ON TOP OF RAIL ANCHORAGES
WITH CORRODED ANCHOR BOLTS
PHOTO #10 - SPALLING OF CURB ALONG NORTH SIDE
PHOTO #11 - DISCONNECTED CURB FASCIA BOARD ON SOUTH SIDE
OVER CENTER SPAN
PHOTO #12 - MISSING TIE BOLT NUTS ON FASCIA LOG AT SOUTH SIDE
OF WEST PIER
PHOTO #13 - DECAY IN SIDEWALK SUPPORT LOG ON NORTH SIDE OF
CENTER SPAN
PHOTO #14 - GENERAL UNDERSIDE VIEW LOOKING TOWARD WEST
PIER
PHOTO #15 - GENERAL UNDERSIDE VIEW OF SIDEWALKS, SOUTH SIDE
SHOWN
PHOTO #16 - TRANSVERSE CRACKING OF DECK IN EAST SPAN, THREE
CRACKS IN TWO BAYS
PHOTO #17 - GENERAL VIEW OF EAST ABUTMENT
PHOTO #18 - GENERAL VIEW OF WEST ABUTMENT
PHOTO #19 - WEST ABUTMENT FOOTING UNDERMINED UP TO 8" FULL
LENGTH; CONCRETE IS ABRADED
PHOTO #20 - GENERAL VIEW OF EAST PIER
PHOTO #21 - GENERAL VIEW OF WEST PIER
PHOTO #22 - MISSING CAP NUT AT NORTH SIDE OF WEST PIER
PHOTO #23 - DECAY IN SOUTH SIDE OF WEST PIER CAP LOG
PHOTO #24 - HIGH WATER DEBRIS IN SUPERSTRUCTURE OF WEST
SPAN
PHOTO #25 - HEAVY CHANNEL DEBRIS IN CENTER SPAN
PHOTO #26 - EFFLORESCENCE FROM GROUT BETWEEN WINGWALL
STONES, SOUTHEAST CORNER SHOWN
PHOTO #27 - EXPOSED WINGWALL FOOTING
AT NORTHEAST CORNER
PHOTO #28 - EROSION OF UPSTREAM BANK
PHOTO #29 - LOOKING UPSTREAM
PHOTO #30 - LOOKING DOWNSTREAM
File details come from the government source that posted it.