Q&A_6-19-18.pdf
PDF 72 KB Posted
- Attached to
- MT DAR 2018(1), Defense Access Roads FY 2018
- Solicitation number
- 69056718B000015
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Bid_Opening_Summary.pdf | ||
| Amendment_A003.pdf | ||
| Q&A_6-20-18.pdf | ||
| Amendment_A002.pdf | ||
| Amendment_A001.pdf | ||
| Plan_Request_form.pdf | ||
| mt-d201801_DAR2018(1)_Plans_Signoff_2018-05-15.pdf | ||
| IFB_MT_DAR_2018(1).pdf | ||
| PROJECT_DESCRIPTION_DAR_2018.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Defense Access Roads FY 2018
MT DAR 2018(1)
# General Technical Question Answer Date
1 X What is the unit of measure “CTSM” for Temporary Traffic Control. Railroad Flagger?
CTSM stands for Contingent Sum. This pay item is to cover reimbursement for the work described under Section 107.04.
6/18/18
2 X Has there been any amendments for this project?
Yes. This was posted on 5/29/2018 at https://www.fbo.gov/index.php?s=opportu nity&mode=form&id=67082cc9257cfa87a4 147477d048836f&tab=core&_cview=1
6/18/18
3 X Does this project still bid on June 21st at 2:00 p.m.?
Yes. 6/18/18