5510_Garfield_CCTV_Upgrade_(Addendum_#3_Revision).pdf

PDF 279 KB Posted

Attached to
5510 Garfield CCTV Upgrade State and local contract opportunity
Solicitation number
41008
Issued by
Sacramento County, San Francisco City, California

About this file

This is an Addendum #3 Revision Notice to Contractors for the County of Sacramento's 5510 Garfield CCTV Upgrade project (Contract #41008), issued by the Department of General Services, Construction and Procurement Services Division. The project involves furnishing all necessary labor, materials, equipment, and incidental work to complete an IP surveillance camera system upgrade for the Sacramento County Sheriff's Office at 5510 Garfield Avenue. The scope includes 20 line items of i-Pro equipment, ranging from multi-sensor IP cameras in various configurations (24MP dual-lens, 34MP outdoor vandal-resistant, 44MP quad multi-sensor, and 5MP models), an i-Pro network video recorder with expandable storage capacity, backup power supplies, and miscellaneous installation hardware and materials. A mandatory pre-bid meeting is scheduled for February 4, 2026, at 9:30 a.m. at the project site; attendance is required and non-attendance will result in bid rejection. Pre-bid questions must be submitted by February 11, 2026, at 4:00 p.m., with responses provided by February 13, 2026. Sealed bids are due electronically via the Sacramento County electronic bidding portal by February 26, 2026, at 2:00 p.m., with automatic bid opening occurring at 2:01 p.m. that same day.

The estimated construction cost is $108,000.00, with award based on base bid only without consideration of additive or deductive items. Bidders must hold a valid California Class C-7 contractor license and must be registered with the California Department of Industrial Relations. Bid security of not less than 10 percent of the aggregate bid is required in the form of a bid bond, certified check, cashier's check, or cash. The successful bidder must execute Performance and Payment Bonds each equal to 100 percent of the contract price. Prevailing wage requirements apply to this public works project as it exceeds the $25,000 threshold for construction work. The apparent low bidder must submit valid Certificates of Reported Compliance with California Air Resources Board Advanced Clean Fleets regulations for applicable vehicle fleets by 4:00 p.m. on the Monday following bid opening. No set-asides, incumbents, or specific restrictions limiting responses to particular organization types are identified. All inquiries must be submitted via the OpenGov portal, and contact with unauthorized County personnel during the selection process may result in disqualification.

View the file

Other files for this state and local contract opportunity

Show all 19

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

NOTICE TO CONTRACTORS

41008

5510 GARFIELD CCTV UPGRADE

County of Sacramento

9660 Ecology Lane

Sacramento, CA 95827

RELEASE DATE: January 28, 2026

DEADLINE FOR QUESTIONS: February 11, 2026

RESPONSE DEADLINE: February 26, 2026, 2:00 pm

RESPONSES MUST BE SUBMITTED ELECTRONICALLY TO:

https://secure.procurenow.com/portal/saccounty https://secure.procurenow.com/portal/%7bproject.government.code%7d

County of Sacramento

NOTICE TO CONTRACTORS

5510 Garfield CCTV Upgrade

1. Introduction

2. Notice to Contractors

3. Pricing Proposal

4. Vendor Submissions

Attachments:

A - 41008- OpenGov - Sheriff's Office 5510 Garfield Special Provisions CUPCCAA

Project (002)

B - North_Station_Informal_Public_Bid_SOW (3)

Notice to Contractors #41008 Title: 5510 Garfield CCTV Upgrade

1. Introduction

1.1. Summary

The Project includes, without limitation, furnishing all necessary labor, materials, equipment and other incidental and appurtenant Work necessary to satisfactorily complete the Project, as more specifically described in specifications. This Work will be performed in strict conformance with the specifications, permits from regulatory agencies with jurisdiction, and applicable regulations. The quantity of Work to be performed and materials to be furnished are approximations only, being given as a basis for the comparison of Bids. Actual quantities of Work to be performed may vary at the discretion of the County.

1.2. Contact Information

Any inquiries or requests regarding this solicitation must be submitted via OpenGov. Contact with unauthorized County personnel during the selection process may result in disqualification.

Brian Matthews

Electronic Security Services PM

Email: matthewsb@saccounty.gov

Phone: (916) 876-7053

Department:

DGS: CAPSD - Construction

Department Head:

Joshua Green

Department Director

1.3. Timeline

Release Project Date January 28, 2026

Pre-Bid Meeting (Mandatory) February 4, 2026, 9:30am

5510 Garfield Avenue Sacramento CA 95841

Question Submission Deadline February 11, 2026, 4:00pm

Question Response Deadline February 13, 2026, 4:00pm

Bid Submission Deadline February 26, 2026, 2:00pm

Bid Opening February 26, 2026, 2:01pm mailto:matthewsb@saccounty.gov tel:(916)876-7053

2. Notice to Contractors

2.1. ADVERTISEMENT SUMMARY

Notice is hereby given that the County of Sacramento will receive sealed bids for the following project:

BID DATE: Thursday, February 26, 2026

SUBMIT BIDS TO: COUNTY OF SACRAMENTO. SUBMIT ELECTRONIC RESPONSES VIA THE SACRAMENTO

COUNTY ELECTRONIC BIDDING PORTAL (SACCOUNTYEBIDS). BIDDERS MUST ELECTRONICALLY SUBMIT

THEIR BID ONLINE NO LATER THAN 2:00 PM ON THE DAY OF THE BID. BID OPENING(S) WILL

AUTOMATICALLY OCCUR ONLINE AT 2:01 PM AT THE FOLLOWING LINK: SACCOUNTYEBIDS.

Responses delivered by hand, fax, telephone, e-mail, or any postal carrier will not be accepted. If bidder uploads a file to SacCountyEbids, it is the bidder's responsibility to ensure the file is not corrupt or damaged. If County is unable to open an attachment because it is damaged, corrupt, infected, etc., it may disqualify bidder’s submission. See this training guide for assistance in entering your online response.

FOR: 5510 Garfield CCTV Upgrade

CONTRACT NUMBER: 41008

ESTIMATED CONSTRUCTION COST: $108,000.00

CONTRACTOR LICENSE REQUIRED: Class C-7

PRE-BID QUESTIONS DUE VIA Q&A: Date: Wednesday, February 11, 2026 No later than: 4:00 pm

PROJECT DESCRIPTION: The work to be performed under this contract includes the furnishing of all labor, materials, equipment, and other incidental work for: IP Surveillance Camera system upgrade

BASIS FOR AWARD: The basis for award shall be base bid only, with no additive or deductive items, or no consideration of additive or deductive items.

CONTRACT INFORMATION: Contract Documents are contained herein and include: Notice to

Contractors, the Sacramento County Standard Construction Specifications, the Special Provisions, the

Bid Proposal form and any attachments, exhibits, drawings, addenda, and/or documents provided by the Project Manager that pertain to this project.

• Contract Documents are available at: SacCountyEbids

• The Standard Construction Specifications, which are incorporated by reference in the Contract

Documents, may be downloaded at: https://saccountyspecs.saccounty.gov/Pages/default.aspx.

https://secure.procurenow.com/portal/saccounty http://help.procurenow.com/en/articles/5815468-opengov-procurement-vendor-training https://saccountyspecs.saccounty.gov/Pages/default.aspx

2.2. MANDATORY PRE-BID MEETING

A mandatory pre-bid meeting will be held on Wednesday, February 4, 2026, at 9:30 am, 5510 Garfield

Avenue Sacramento CA 95841. The project engineers will be present to provide a project summary and to answer questions.

Attendance of the Pre-Bid Conference is MANDATORY for this project. The mandatory pre-bid conference and walk-through will be held for the purpose of reviewing questions regarding the project.

A representative of the prime Contractor must be in attendance and sign the log. A representative of the

County will be present to review the project with the bidders, allow bidders to walk the site and to answer questions. Bids received from bidders who do not attend this meeting will be deemed non-responsive.

2.3. BID GUARANTEES

Each bid must be submitted on the bid forms provided in the Contract Documents; however, if none are provided, the surety may issue on its own paper. Each bid must also be accompanied by security in the form of a bid bond issued by a corporate surety, a certified check or cashier's check payable to the

Treasurer of Sacramento County, or cash for an amount not less than ten percent (10%) of the aggregate sum of the bid.

2.4. BONDS

The successful bidder shall be required to execute a material and labor Payment Bond and Performance

Bond, issued by a corporate surety, acceptable to the County of Sacramento, each for not less than one hundred percent (100%) of the contract price.

Pursuant to Public Contract Code, section 22300, the Contractor may, at its own expense, substitute securities for any money being withheld by the County to ensure performance under this contract. The

Contractor must notify the County of its intent to pursue this option prior to the issuance/execution of a contract.

2.5. LICENSE REQUIREMENTS

Award of this contract requires a valid California contractor's license with the classification identified above.

Public Contract Code, section 4104(a)(1), requires that any person making a bid must submit the name, location of the place of business, and the subcontractor’s license number on the bid form.

No contractor or subcontractor may be listed on a bid proposal for a public works project unless registered with the Department of Industrial Relations pursuant to Labor Code, section 1725.5 [with limited exceptions from this requirement for bid purposes only under Labor Code section 1771.1(a)].

No contractor or subcontractor may be awarded a contract for public work on a public works project unless registered with the Department of Industrial Relations pursuant to Labor Code, section 1725.5.

2.6. LABOR COMPLIANCE PROGRAM

The County of Sacramento received final approval from the Director of California Department of

Industrial Relations as a Labor Compliance Program effective March 15, 1994. All questions regarding this Labor Compliance Program and prevailing wage requirements should be directed to the Labor

Compliance Section at: 916-875-2711. In accordance with Section 1771.5 of the California Labor Code, the payment of the general prevailing rate of per diem wages or the general prevailing rate of per diem wages for holiday and overtime is not required for any public works project of $25,000 or less when the project is for construction work, or for any public works project of $15,000 or less when the project is for alteration, demolition, repair, or maintenance work.

This is a Construction project in accordance with Labor Code section 1771.5.

Pursuant to California Labor Code, section 1720 and following, and section 1770 and following, the successful bidder shall pay not less than the prevailing rate of per diem wages as determined by the

Director of the California Department of Industrial Relations. Copies of the prevailing wage determinations are on file at the office of the County of Sacramento Labor Compliance Program, 9700

Goethe Road, Suite D, Sacramento, CA 95827, and are also available at http://www.dir.ca.gov/DLSR/PWD.

2.7. ADVANCED CLEAN FLEETS REGULATION

Vehicles with a gross vehicle weight rating greater than 8,500 lbs. and light-duty package delivery vehicles operated in California may be subject to the California Air Resources Board

(CARB) Advanced Clean Fleets regulations. Such vehicles may therefore be subject to requirements to reduce emissions of air pollutants. For more information, see CARB Advanced

Clean Fleets and Advanced Clean Fleets Regulation & Advisories | California Air Resources

Board.

The apparent low bidder shall provide copies of valid Certificates of Reported Compliance as described in California Code of Regulations, title 13, ("13 CCR") section 2449(n) for the bidder’s fleet, and fleets of any listed subcontractors, of vehicles subject to 13 CCR section 2449 which may be use in performance of this project.

If the apparent low bidder’s fleet, or any subcontractor’s fleet, is exempt or is not subject to the regulation bidder shall clearly indicate the applicable exemption in the bidder’s response. For more information, see CARB Advanced Clean Fleets Regulation Exemptions and Extensions

Overview | California Air Resources Board.

Certificates of Reported Compliance and/or exemptions must be submitted by the apparent low bidder by 4:00PM on Monday following Bid Opening and must be received by the County prior to contract award.

https://ww2.arb.ca.gov/our-work/programs/advanced-clean-fleets https://ww2.arb.ca.gov/our-work/programs/advanced-clean-fleets https://ww2.arb.ca.gov/our-work/programs/advanced-clean-fleets/advanced-clean-fleets-regulation-advisories https://ww2.arb.ca.gov/our-work/programs/advanced-clean-fleets/advanced-clean-fleets-regulation-advisories https://ww2.arb.ca.gov/resources/fact-sheets/advanced-clean-fleets-regulation-exemptions-and-extensions-overview https://ww2.arb.ca.gov/resources/fact-sheets/advanced-clean-fleets-regulation-exemptions-and-extensions-overview

2.8. QUESTIONS

Direct pre-bid questions to the Project Manager, Brian Matthews, via the Q&A tab in the portal. ALL

PRE-BID QUESTIONS MUST BE SUBMITTED IN WRITING NO LATER THAN Wednesday, February 11, 2026

BY 4:00 pm. Questions received after that time will not be answered. Responses will be by addenda to the bid documents.

The County of Sacramento reserves the right to reject any or all bids, to waive any informality in any bid, and to determine which bid, in their judgment, is the lowest responsive bid of a responsible Bidder.

3. Pricing Proposal

Line Item Description Quantity Unit of

Measure Unit Cost Total

01 i-Pro multi-sensor IP camera WV-

S85702-F3L 2×4K (16MP) Dual Lens 3 ea

02 i-Pro WV-QSR507M1-W 1.5" NPT adapter for dual-head cameras 2 ea

03 -Pro WV-QWL506-W wall-mount brackets 2 ea

04 i-Pro multi-sensor IP camera WV-

S8573L 3×4K (24MP) Outdoor Vandal-

Resistant Cameras

3 ea

05 i-Pro WV-QSR503M1-W outdoor pendant mount adapters 2 ea

06 i-Pro WV-QWL501-W wall mount for large pendant cameras 1 ea

07 i-PRO quad multi-sensor WV-S8574L

4×4K (33MP)

2 ea

08 i-PRO Bullet cam WV-S15500-V3LN

5MP Outdoor Bullet 2 ea

09 i-PRO PTZ-multi-sensor combo WV-

X86531-Z2 4×5MP Multi-Sensor +

2MP PTZ

2 ea

10 i-PRO WV-QSR508F1-W pendant kit 2 ea

11 i-PRO PTZ WV-S66600-Z3LN 6MP

Outdoor PTZ with AI Engine 1 ea

12 i-PRO PPRM35AW parapet mount bracket 1 ea

13 i-PRO WV-QSR506F1-W mount bracket 1 ea

Line Item Description Quantity Unit of

Measure Unit Cost Total

14 i-PRO interior cam WV-S22500-V3L

5MP Vandal-Resistant Indoor Dome 4 ea

15 i-PRO interior multi-sensor WV-

S8544L 4x4MP Multi-directional with

AI Engine

2 ea

16 i-PRO 3 lens interior multi-sensor WV-

S8543L 1 ea

17 i-PRO NVR-RL-2-48TB-SO i-PRO

SRL3EXDL o Key specs: Dual Xeon

Silver CPUs, 128GB RAM Windows

Server 2022 Std on 2× M.2 SSD

(Minimum RAID5) 48TB storage

(expandable to 400TB) 1Gb and

10Gb network interfaces VI

Enterprise server activation & VI

Health Monitor 5-year limited hardware warranty with on-site service

1 ea

18 i-PRO compatible storage expansion

DCS4-C400T-2427 DCS 480 Series

(Minimum RAID5) with 400TB

1 ea

19 Eaton 5PX3000RTNG2 networked 2u back up power supply input 120v 2 ea

20 misc, Lift , installation hardware,patch cables,connectors, and any other bilable project material or other needed to complete project

1 ls

TOTAL

4. Vendor Submissions

4.1. What form of Bid Guaranty will Contractor be submitting?* Bid security must be a bidder bond, a certified check or cashier’s check payable to the Treasurer of the

County of Sacramento, or cash. Bids secured by personal checks or personal guarantees will be rejected.

☐ Scanned copy of Fully Executed Bid Bond

☐ E-bid Bond (Use Surety 2000)

☐ Cashier's or Certified Check

☐ Cash

*Response required

4.2. Bid Guaranty

Upload a scanned copy of your fully executed bid bond here if Contractor is submitting a scanned bid bond.

5. 3. E-Bid Bond Please enter your Bid Bond information from Surety2000 below If Contractor is submitting an E-Bid

Bond

5.1. Non-collusion Declaration*

The undersigned declares:

I am an authorized representative with binding authority for my company, the party making the foregoing bid.

The bid is not made in the interest of, or on behalf of, any undisclosed person, partnership, company, association, organization, or corporation. The bid is genuine and not collusive or sham. The bidder has not directly or indirectly induced or solicited any other bidder to put in a false or sham bid. The bidder has not directly or indirectly colluded, conspired, connived, or agreed with any bidder or anyone else to put in a sham bid, or to refrain from bidding. The bidder has not in any manner, directly or indirectly, sought by agreement, communication, or conference with anyone to fix the bid price of the bidder or any other bidder, or to fix any overhead, profit, or cost element of the bid price, or of that of any other bidder. All statements contained in the bid are true. The bidder has not, directly or indirectly, submitted his or her bid price or any breakdown thereof, or the contents thereof, or divulged information or data relative thereto, to any corporation, partnership, company, association, organization, bid depository, or to any member or agent thereof, to effectuate a collusive or sham bid, and has not paid, and will not pay, any person or entity for such purpose.

Any person executing this declaration on behalf of a bidder that is a corporation, partnership, joint venture, limited liability company, limited liability partnership, or any other entity, hereby represents that he or she has full power to execute, and does execute, this declaration on behalf of the bidder. I declare under penalty of perjury under the laws of the State of California that the foregoing is true and correct and that this declaration is executed on the date this bid is submitted.

☐ Please confirm

*Response required

5.2. Designation of Subcontractors - Unit Price Contracts*

Please download the below documents, complete, and upload.

• DESIGNATION_OF_SUBCONTRACTO...

*Response required

5.3. Bid Item Percentage Listing on Designation of Subcontractor form* Bidder shall certify that the bidder entered the PERCENTAGE OF BID ITEM SUBCONTRACTED in Column

(C) of the Designation of Subcontractor form NOT the percentage of total bid.

☐ Please confirm

*Response required https://government-project.s3.us-west-2.amazonaws.com/17213/fc3a4145-e6ee-47da-97f2-00cbed9173b9_DESIGNATION_OF_SUBCONTRACTORS.docx?X-Amz-Algorithm=AWS4-HMAC-SHA256&X-Amz-Content-Sha256=UNSIGNED-PAYLOAD&X-Amz-Credential=ASIA47RIURE4BVMYITUZ%2F20260224%2Fus-west-2%2Fs3%2Faws4_request&X-Amz-Date=20260224T151254Z&X-Amz-Expires=72000&X-Amz-Security-Token=IQoJb3JpZ2luX2VjEC4aCXVzLXdlc3QtMiJHMEUCIFkD%2Bff9u3BzskMGYQssBJavOw4Qy%2FrbwwBkXCQpZn9sAiEA%2F2R5%2FbAQUwlLgy1qr1KYud1p0JqAfcW0%2BovnKJMvyXcqlQUI9%2F%2F%2F%2F%2F%2F%2F%2F%2F%2F%2FARACGgw4OTIzNjQ2ODc2NzIiDO%2BgsBjx7EwrrG54sCrpBApYMLDwlImG8fQK0O4tDXdjglTywS7uNcK7s9c72wXDZV9ibnvJWpyPnKW1PZi%2BzYVXc4Ye0IKYHvfngNWWTmdJ1kYOAw4K4g5K86g7UKbZW7IDfEG4HtelE%2BHrF4lTNsAV2H8XqEUrA0InowtgqD1UM6ILSTLH5z9ixf0TJihXrPk4j8kwLlgvdOKlc434pzAYIMkVnLtCrGR5K6Lisf9sXQYYSDzxLBTwyiy62%2BdTdkpYbosauBjxLkKduBeF%2FECqdKaqAxZA9tevKFSdOSvRyJrF0ABclOQHRZt8q4nGtEKnMQzjooawgn4MKjy13cWM9RQIeIDd5uYdc7gR8XKvnynXHQpcjEElMTcVNyiJi4OTcmAN%2FETSb8jfW%2BwRIlQwRzXRCBY9pS8WlHssSWmV40Dl4ipOCh6LzhtxXNR0cCWG9zSEIl0KV1A9%2FFMIZ%2B%2BTlN2w390atnVdwawqb5l%2Fk3cnZXmla%2BnSSqcybgl5LPrYpkD96wCcQ%2FqWU%2BsmX59GvOIOXuZ4hD5P78ozKx3dlpVSJFN5q5RT5QJuljZS%2BRoRwvDJlVDUwRo21nxKWGJwaOc0waspyb%2BsihVOp%2F3gYbdchtijqt5zhQOiTGoFF32TRuqZ31kjzrgOUrKA1N9pGgrsq2qYOCBucWePcgWeKOzTvbwBlP2YUqHXvQfPoUCDY0fBrp%2BYzzI55H5MdAv9SbjukqCYtYix9XOKw%2FW78vpTIdhqT8%2FycR31QuVEYzOMoJkwo7AQDxLBtLVICQ1fi5v20jxiFa8XX%2FGdmJ6RnIoVU8zRJb3mVpqJNdG31PNeXBqKaBPHMLrf9swGOpkBINV0F6ydjFD60BSnn3q57oDKKaeNNNsuzAvTmk2Q652N1TYs1iDwp3rZqjkAkAHs5r4CyUGNdZhhZ8Cj1MLm3hbFlcbcXz6gk0fjCabnHrNxyvu1LjO0FYy0MuRNkZW6taQQ14gyKlck6rxaL0T8DWzw%2B%2B9O3zrlxkA1DzUJE3hoLm4taoiuPNjckR4WtCf7XcxQfsvnPq7h&X-Amz-Signature=308007c42a68870cd0f117c08bb48e203b59758773f8b666ff3e59698850e79f&X-Amz-SignedHeaders=host&response-content-disposition=attachment%3B%20filename%3D%22DESIGNATION_OF_SUBCONTRACTORS.docx%22&x-id=GetObject

5.4. Type of Business*

☐ C Corporation

☐ S Corporation

☐ Limited Liability C Corporation

☐ Partnership

☐ Limited Liability Partnership

☐ Sole Proprietor/Individual

☐ Other

*Response required

5.5. Type your Legal Company Name Here*

State your Company's Name Here. This will be verified against the California Secretary of State's

Website.

*Response required

5.6. Secretary of State Entity Number*

Provide your Entity Number from the CA Secretary of State. If not registered in CA, provide the Entity

Number from your registered state.

*Response required

5.7. Contractors State License Board (CSLB) Number*

Please enter your License Number here. This will be verified against the state database

*Response required

5.8. Contractors State License Board (CSLB) License Expiration Date * Enter your CSLB license expiration date:

5.9. Contractors State License Board (CSLB) License Classifications* Enter your current CSLB license classifications:

*Response required

5.10. California Department of Industrial Relations Registration* Please enter your Public Works Contractor Registration Number. This will be verified against the state database.

5.11. Provide the full contact name, title, and e-mail of the signatory for your firm. Provide contact information (full name, e-mail, phone number) for the contract manager for your firm in order to distribute Contract Documents, if awarded, including other recipients requiring a copy.* signatory: name, title, email contract manager/admin: name, email, phone

*Response required

5.12. PaymentWorks Contact*

Please provide the name and e-mail for a finance point-of-contact for your firm that will receive an invitation to complete the vendor registration process on the County's PaymentWorks portal.

To clarify, if you are set-up with other agencies using PaymentWorks, that information is not available to the County, so you must complete this process for the County.

*Response required

5.13. I hereby certify under penalty of perjury that the above statements are true.*

☐ Please confirm