This document package includes construction drawings and specifications for plumbing upgrades at two buildings at the Amarillo VA Health Care System in Amarillo, Texas. The drawings show demolition of existing plumbing systems and installation of new systems on the first floor of Building 4 and basement of Building 7. Key details include upgrading the freight elevators in both buildings, replacement of sanitary, storm, and domestic water piping, and addition of a sump pump system in the basement of Building 7. The related federal contract opportunity is solicitation number 36C25723B0003 for project number 671-22-196 to replace the keying system at the facility. The Department of Veterans Affairs Veterans Health Administration VISN 17 is listed as the contracting agency. The documents provide requirements for planned plumbing system upgrades at two buildings on the Amarillo VA campus.

View the file

Other files

Show all 24

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Scale: NTS

Department of Veteran Affairs

TABLE OF CONTENTS

DWG # DWG TITLE

P-001 PLUMBING COVER SHEET

P-101 PLUMBING FLOOR PLANS, SCHEDULES AND DETAILS - BUILDINGS 4 + 7

X X X X DEMOLITION

EQUIPMENT

RELOCATE

REVISION

TEXT

BACKGROUND

SCOPE

COLUMN LINE

PLUMBING LAYERS PLUMBING SYMBOLS

B#-FC-# EQUIPMENT TAG (BUILDING NO -

EQUIP NAME - EQUIP NUMBER)

REVISION DELTAS

SHEET NOTES5

RELOCATE

GENERAL NOTES

1. ALL WORK SHALL BE PERFORMED IN A CLEAN AND WORKMANLIKE MANNER. CARE SHALL

BE EXERCISED TO MINIMIZE ALL INCONVENIENCE OR DISTURBANCE TO OTHER AREAS OF

THE BUILDING WHICH ARE TO REMAIN IN OPERATION. ISOLATE WORK AREAS BY MEANS

OF TEMPORARY PARTITIONS AND/OR TARPS TO KEEP DUST AND DIRT WITHIN THE

CONSTRUCTION AREA.

2. NO PIPING, EQUIPMENT, ETC. SHALL BE REMOVED, DISCONNECTED OR SHUT DOWN

WITHOUT PRIOR REVIEW WITH THE COR AND/OR ENGINEER TO CONFIRM THAT AREAS TO

REMAIN IN OPERATION WILL NOT BE AFFECTED. IF AREAS NOT WITHIN THE SCOPE OF

WORK ARE AFFECTED BY ANY SHUTDOWN, REMOVAL OR DISCONNECTION, SUFFICIENT

ADVANCE NOTICE SHALL BE GIVEN TO THE COR AND/OR OWNER INDICATING WHICH

AREAS WILL BE AFFECTED, WHEN THE PROPOSED SHUTDOWN WILL OCCUR, AND FOR

HOW LONG A PERIOD OF TIME.

3. ALL ITEMS INDICATED AS BEING DEMOLISHED OR REMOVED SHALL BE DISPOSED OF

OFF-SITE.

4. THE PLUMBING CONTRACTOR SHALL FIELD VERIFY ALL DIMENSIONS AND EXISTING

CONDITIONS PRIOR TO PROCEEDING WITH ALL WORK. WHERE DISCREPANCIES OCCUR

BETWEEN THESE DOCUMENTS AND EXISTING CONDITIONS, THE DISCREPANCY SHALL BE

REPORTED TO THE COR AND/OR ENGINEER FOR RESOLUTION.

5. ALL SHUT DOWNS OF EXISTING SYSTEMS SHALL BE SCHEDULED AND APPROVED BY THE

COR PRIOR TO COMMENCEMENT OF SAID WORK.

6. CLEAN THE JOB SITE DAILY AND REMOVE FROM THE PREMISES ALL DIRT AND DEBRIS

CAUSED BY THE PERFORMANCE OF THE WORK INCLUDED IN THIS CONTRACT.

7. USE OF THE OWNER'S ELEVATORS AND BUILDING CORRIDORS FOR THE HANDLING OF

NEW AND/OR REMOVED EQUIPMENT AND MATERIALS SHALL BE AT THE DIRECTION OF THE

COR AND SHALL BE COORDINATED WITH HIS OPERATIONS.

8. THE PLUMBING CONTRACTOR SHALL BE RESPONSIBLE FOR THE SAFEKEEPING OF HIS

OWN PROPERTY ON THE JOB SITE. OWNER ASSUMES NO RESPONSIBILITY FOR

PROTECTION OF PROPERTIES AGAINST FIRE, THEFT AND ENVIRONMENTAL CONDITIONS.

9. EXCEPT WHERE INDICATED AS BEING RELOCATED, EXISTING MATERIALS THAT ARE

REMOVED SHALL NOT BE REUSED IN NEW SYSTEMS.

10. PROVIDE ALL NECESSARY TEMPORARY OR PERMANENT CAPS OR PLUGS FOR PIPING. DO

NOT LEAVE PIPING OPEN ENDED.

11. WHERE USED, THE TERM "PROVIDE" SHALL MEAN "FURNISH AND INSTALL".

12. THE PLUMBING CONTRACTOR SHALL COORDINATE HIS WORK WITH ALL OTHER TRADES

PRIOR TO FABRICATION, PURCHASE AND/OR INSTALLATION OF ANY WORK.

13. THE BALANCING CONTRACTOR SHALL TAKE FLOW (GPM) AND PRESSURE READINGS

PRIOR TO THE START OF WORK ON ALL DUCTWORK THAT SERVES AREAS NOT PART OF

THIS PROJECT BUT WHERE FLOW TO THOSE AREAS IS AFFECTED BY THIS PROJECT'S

WORK. AFTER MODIFICATIONS TO SYSTEMS COVERED UNDER THIS PROJECT ARE

COMPLETED, THE BALANCING CONTRACTOR SHALL BALANCE THE NON-AFFECTED AREAS

TO THEIR ORIGINAL FLOW AND PRESSURE OR NEW FLOW AND PRESSURE IF NOTED.

14. IF PLUMBING CONTRACTOR ENCOUNTERS WHAT APPEARS TO BE A HAZARDOUS OR

QUESTIONABLE MATERIAL, HE SHALL DISCONTINUE WORK IMMEDIATELY AND CONTACT

THE COR AND/OR OWNER'S REPRESENTATIVE.

15. USE OF OWNER'S UTILITIES (I.E. ELECTRICITY, WATER, HVAC, ETC.) FOR WORK INDICATED

ON THESE DOCUMENTS SHALL BE APPROVED BY THE COR PRIOR TO COMMENCEMENT OF

SAID WORK.

16. THE PLUMBING CONTRACTOR SHALL CONFORM TO OWNER'S SAFETY AND SECURITY

GUIDELINES IN THE PERFORMANCE OF ALL WORK INCLUDED IN THIS CONTRACT.

17. ALL BRANCH PIPING SHALL BE FURNISHED WITH SHUT OFF VALVES AND SHALL BE

LOCATED IN ACCESSIBLE LOCATION BY OFFSETTING BRANCH PIPING WITH VALVES DOWN

NEAR CEILING. PROVIDE ACCESS PANEL FOR ALL VALVES, CLEANOUTS, EQUIPMENT, ETC.

IN NON ACCESSIBLE CEILING AREAS.

18. ALL SUSPENDED PIPING, DUCTWORK, CONDUIT AND CABLE TRAYS SHALL BE PROVIDED

WITH, SEISMIC SWAY BRACES IN ACCORDANCE WITH THE MASON INDUSTRIES SEISMIC

RESTRAINT GUIDELINES FOR SUSPENDED PIPING, DUCTWORK AND ELECTRICAL SYSTEMS

AND THE APPLICABLE CODES. INSTALLED SYSTEM SHALL MATCH EXISTING, RIGID OR

CABLE TYPE.

19. GENERAL LOCATION OF FIXTURES ARE INDICATED ON PLUMBING PLANS. REFERENCE

ARCHITECTURAL PLANS AND INTERIOR ELEVATIONS FOR SPECIFIC LOCATIONS.

20. RESTORE EXISTING FIRE PROOFING TO BEAMS, DECKS AND ALL OTHER BUILDING

ELEMENTS WHICH ARE DISTURBED OR MODIFIED AS A RESULT OF NEW WORK BEING

INSTALLED. RESTORED CONDITIONS SHALL MATCH EXISTING PRIOR TO NEW WORK BEING

PERFORMED.

21. ALL EXISTING PIPE INSULATION REMOVED, AS REQUIRED TO PERFORM SCOPE OF WORK,

SHALL BE REPAIRED USING LIKE MATERIAL TO THAT WHICH IS EXISTING.

22. PIPE ROUTINGS ARE DIAGRAMMATIC IN NATURE. PROVIDE OFFSETS, DROPS AND RISERS

AS NECESSARY TO AVOID EXISTING ELECTRICAL, HVAC, PLUMBING, FIRE PROTECTION,

ETC. SYSTEMS WHICH MAY INTERFERE WITH GENERAL ROUTING SHOWN ON DRAWINGS.

23. VERIFY EXISTING PLUMBING SYSTEM SIZES PRIOR TO FABRICATION OF NEW PLUMBING

SYSTEMS. ANY EXISTING PLUMBING SYSTEMS DIFFERING IN SIZE FROM THAT NOTED ON

DRAWINGS SHALL BE BROUGHT TO THE ATTENTION OF THE OWNER'S REPRESENTATIVE

AND ENGINEER.

24. NOT ALL SYMBOLS, ABBREVIATIONS AND EQUIPMENT ABBREVIATIONS INDICATED APPEAR

ON THESE CONTRACT DRAWINGS

25. ALL PIPING IN FINISHED ROOMS OR SPACES SHALL BE CONCEALED IN A FURRED CHASE

OR ABOVE HARD SUSPENDED CEILING, OR ACOUSTICAL CEILING.

26. ACCESS PANELS IN HARD SUSPENDED CEILINGS ARE REQUIRED FOR ALL VALVES, TRAPS,

DAMPERS, CLEANOUTS, CONTROLS, ETC. ACCESS PANELS SHALL BE FURNISHED AND

INSTALLED UNDER THE ARCHITECTURAL SPECIFICATIONS. COORDINATE LOCATION WITH

PLUMBING INSTALLATION AND DEMONSTRATE ACCESS TO EQUIPMENT SERVED.

27. ALL PRESSURES LISTED ARE GAGE PRESSURE, UNLESS OTHERWISE NOTED.

28. PRIOR TO CONSTRUCTION, PLUMBING CONTRACTOR TO DETERMINE EXACT INVERT

ELEVATION, SIZE, DEPTH, AND LOCATION OF UTILITIES WHERE CONNECTIONS ARE TO

OCCUR. NOTIFY COR AND ENGINEER OF ANY DISCREPANCIES BETWEEN DRAWINGS AND

FIELD CONDITIONS.

29. PLUMBING CONTRACTOR SHALL KEEP ONE SET OF CONTRACT DRAWINGS ASIDE AT THE

SITE TO MARK UP ALL DEVIATIONS FROM CONTRACT DRAWINGS AND ANY DATA THAT IS

PERTINENT FOR COMPLETION OF DOCUMENTS. AT COMPLETION OF PROJECT, TRANSFER

MARKS TO A SET OF REPRODUCIBLE DRAWINGS AND DELIVER THIS SET OF DRAWINGS TO

OWNER PRIOR TO FINAL ACCEPTANCE.

POINT OF CONNECTION BETWEEN NEW

AND EXISTING WORK

LIMIT OF DEMOLITION

POINT OF CONNECTION

CAP

PIPE UP

PIPING SYMBOLS

PIPE DOWN

TEE

FLOW DIRECTION

FLOOR DRAIN

FLOOR SINK

PUMP

REDUCER

ANGLED GLOBE

AUTOMATIC BALANCING CONTROL

BALANCING

BALL

BUTTERFLY

CHECK

CIRCUIT SETTER

CONTROL - FLOAT OPERATED

FLOW METER

GATE

GLOBE

M

MODULATING CONTROL

ABBREVIATIONS

GENERAL DEMOLIION NOTES

1. SCHEDULE ALL SHUTDOWNS THAT AFFECT UTILITIES AND PORTIONS OF THE BUILDING

THAT MUST REMAIN IN OPERATION WITH THE COR.

2. DEMOLITION WORK AT ALL TIMES SHALL BE SUBJECT TO THE DIRECTION AND APPROVAL

OF THE COR AND CARRIED OUT IN SUCH A MANNER SO AS NOT TO INTERFERE WITH THE

NORMAL OPERATION OF THE BUILDING.

3. DISPOSE OF ALL REMOVED MATERIALS IN AN APPROVED MANNER.

4. ISOLATE, DRAIN, AND REFILL EXISTING SYSTEMS AS REQUIRED TO ACCOMMODATE

INSTALLATION OF EXISTING AND NEW SYSTEMS.

5. PROVIDE ALL NECESSARY TEMPORARY/PERMANENT CAPS OR PLUGS FOR PIPING. DO

NOT LEAVE PIPING OPEN ENDED.

6. ALL EXISTING PIPING SHALL BE FIELD VERIFIED FOR PROPER DEMOLITION. CONTRACTOR

SHALL NOTIFY ENGINEER IMMEDIATELY IF ANY DISCREPANCIES FROM CONTRACT

DOCUMENTS OCCUR THAT MAY EFFECT EXISTING OPERATIONS.

7. DEMOLITION OF PIPING INCLUDES ALL ASSOCIATED VALVES, ACCESSORIES, INSULATION,

HANGERS, AND SUPPORTS.

8. COORDINATE WITH COR ON REMOVAL AND PLACEMENT OF EQUIPMENT NOTED TO BE

TURNED OVER TO COR. FOR EQUIPMENT NOT DESIRED BY COR, CONTRACTOR SHALL

REMOVE OFF SITE IN AN APPROVED MANNER.

DETAIL NUMBER

DRAWING SYMBOLS

M-XXX

X

DRAWING NUMBER

SECTION LETTER

DRAWING NUMBERM-XXX

X

COLD WATER

HOT WATER

HOT WATER RETURN

SANITARY SEWER (WASTE)

VENT

EXISTING COLD WATER

EXISTING HOT WATER

EXISTING HOT WATER RETURN

EXISTING SANITARY SEWER

EXISTING VENT

MODULATING CONTROL BUTTERFLY

PLUG

PNEUMATIC CONTROL

PRESSURE REDUCING (PRV)

PRESSURE REGULATING

PRESSURE SAFETY

SHUTOFF

THREE-WAY MODULATING CONTROL

THREE-WAY TWO POSITION CONTROL

TWO POSITION CONTROL

WATER BALANCE DEVICE

WYE STRAINER

UNION

TEMPERATURE GAGE

PRESSURE GAGE

TEST PLUG

AUTOMATIC AIR VENT

MANUAL AIR VENTMV

AV

EQUIP. ABBREVIATIONS

AAHX AIR TO AIR HEAT EXCHANGER

ACC AIR COOLED CONDENSER

ACCH AIR COOLED CHILLER

ACCU AIR COOLED CONDENSING UNIT

ACU AIR CONDITIONING UNIT

AF AFTER FILTER

AHU AIR-HANDLING UNIT

AS AIR SEPARATOR

B BOILER

BDR BASE BOARD RADIATOR

BHW HOT WATER HEATING BOILER

BHX BOILER BLOWDOWN HEAT

EXCHANGER

BT BLOWOFF TANK

CC COOLING COIL

CCD COOLING COIL CONDENSATE

DRAIN

CFP CHEMICAL FEED PUMP

CH CHILLER

CHP CHILLED WATER PUMP

COMP COMPRESSOR UNIT

CP CONDENSATE PUMP

CS CONDENSATE STORAGE TANK

CSG CLEAN STEAM GENERATOR

CT COOLING TOWER

CU CONDENSING UNIT

CUH CABINET UNIT HEATER

CWCC CHILLED WATER COOLING COIL

CWP CONDENSER WATER PUMP

DXCC DIRECT EXPANSION COOLING COIL

EC EVAPORATIVE COOLER

ECU EVAPORATIVE CONDENSER UNIT

EDH ELECTRIC DUCT HEATER

EF EXHAUST FAN

EH EXHAUST HOOD

ERC ELECTRIC REHEAT COIL

ERP ELECTRIC RADIANT PANEL

ET EXPANSION TANK

EUH ELECTRIC UNIT HEATER

EWC EVAPORATIVE WATER COOLER

FCU FAN COIL UNIT (4 PIPE)

FCUC FAN COIL UNIT COOLING ONLY

FCUH FAN COIL UNIT HEATING ONLY

FHX FLUE GAS/FEEDWATER HEAT

EXCHANGER

FPTU FAN POWERED TERMINAL UNIT

FTR FIN TUBE RADIATION

H HUMIDIFER

HC HEATING COIL

HD HOOD

HP HEAT PUMP

HPDT HIGH PRESSURE DRIP TRAP

HRC HEAT RECOVERY COIL

HRD HEAT RECOVERY DEVICE

HRP HYDRONIC RADIANT (CEILING)

PANEL

HRW HEAT RECOVERY WHEEL

HUM HUMIDIFIER UNIT MOUNTED

HVU HEATING AND VENTILATING UNIT

HWC HOT WATER COIL

HWHC HOT WATER HEATING COIL

HWP HEATING HOT WATER PUMP

HWUH HOT WATER UNIT HEATER

HX HEAT EXCHANGER

ICF IN-LINE CENTRIFUGAL FAN

IU INDUCTION UNIT

LLHX LIQUID TO LIQUID HEAT

EXCHANGER

MAU MAKE-UP AIR UNIT

P PUMP

PF PRE-FILTER

PHC PREHEAT COIL

PTAC PACKAGED TERMINAL AIR

CONDITIONER

RAHX ROTARY AIR HEAT EXCHANGER

RCCH REMOTE CONDENSER

CHILLER

RCU RECIPROCATING CHILLER UNIT

RF RETURN FAN

RHC REHEAT COIL

SAD SOUND ATTENUATING DEVICE

SF SUPPLY FAN

SH STEAM HUMIDIFIER

SHC STEAM HEATING COIL

SSHX STEAM TO STEAM HEAT

EXCHANGER

ST STEAM TRAP

SUH STEAM UNIT HEATER

SWHX STEAM TO WATER HEAT

EXCHANGER

TU TERMINAL UNIT

UC UNIT COOLER

UH UNIT HEATER

VUH VERTICAL UNIT HEATER

WCCH WATER COOLED CHILLER

WCCU WATER COOLED CONDENSING

UNIT

WCHP WATER COOLED HEAT PUMPS

WCPU WATER COOLED PACKAGED UNIT

WEF WALL EXHAUST FAN

WF WATER FILTER

RISER SYSTEM

RISER NUMBER

MEDICAL VACUUM

MEDICAL AIR

STORM WATER, BELOW GRADE

STORM WATER

MA MA MA

MV MV MV

SD SD

SD SD

OXYGEN0 0 0

NATURAL GAS, BELOW GRADE

NATURAL GAS

NG NG NG

NG NG NG

MA

MV

NG

NG

SDSD

SDSD

DIRECTION OF PIPE PITCH (DOWN)

FLOW ELEMENT

DIRECTION OF FLOW

ANCHOR

REDUCER OR INCREASER

ECCENTRIC REDUCER

TOP CONNECTION, 45° OR 90°

BOTTOM CONNECTION, 45° OR 90°

SIDE CONNECTION

CAPPED OUTLET

RISE OR DROP IN PIPE

UNION

PIPE UP

PIPE DOWN

INVERTED BUCKET TRAP SET INCLUDING PIPING

ACCESSORIES

FLOAT & THERMOSTATIC TRAP SET

INCLUDING PIPING ACCESSORIES

STRAINER

THERMOMETER

PRESSURE GAGE

CLEAN OUT

HOSE BIB

ABS ACRYLONITRILE BUTADIENE

STYRENE

AC ALTERNATING CURRENT

A/E ARCHITECT/ENGINEER

AFF ABOVE FINISH FLOOR

AFG ABOVE FINISH GRADE

AG AIR GAP

AISI AMERICAN IRON AND STEEL

INSTITUTE

ASHRAE AMERICAN SOCIETY OF HEATING

REFRIGERATION, AIR

CONDITIONING ENGINEERS

ASJ ALL SERVICE JACKET

ASME AMERICAN SOCIETY OF

MECHANICAL ENGINEERS

ASPE AMERICAN SOCIETY OF PLUMBING

ENGINEERS

ASR AUTOMATIC SPRINKLER RISER

AWG AMERICAN WIRE GAUGE

BACNET BUILDING AUTOMATION AND

CONTROL NETWORK

BAS BUILDING AUTOMATION SYSTEM

BFP REDUCED PRESSURE BACKFLOW

PREVENTER

BHP BRAKE HORSEPOWER

BTU BRITISH THERMAL UNIT

BTU/H BRITISH THERMAL UNIT PER HOUR

C CELSIUS

CDA COPPER DEVELOPMENT

ASSOCIATION

CGA COMPRESSED GAS ASSOCIATION

CFM CUBIC FEET PER MINUTE

CO CLEANOUT

COR CONTRACTING OFFICER'S

REPRESENTATIVE

CPVC CHLORINATED POLYVINYL

CHLORIDE

CRS CORROSION RESISTANT STEEL

CV CONTROL VALVE

CXA COMMISSIONING AGENT

DB DECIBELS

DB(A) DECIBELS (A WEIGHTED)

DDC DIRECT DIGITAL CONTROL

DFU DRAINAGE FIXTURE UNITS

DI DEIONIZED WATER

DOE DEPARTMENT OF ENERGY

DW DISHWASHER

DWG DRAWING

ECC ENGINEERING CONTROL CENTER

AKA BAS

EL ELEVATION

EPA ENVIRONMENTAL PROTECTION

AGENCY

(E) EXISTING

F FAHRENHEIT

FCO FLOOR CLEANOUT

FD FLOOR DRAIN

FDC FIRE DEPARTMENT (HOSE)

CONNECTION

FOP FUEL OIL PUMP

FOR FUEL OIL RETURN

FOS FUEL OIL SUPPLY

FOV FUEL OIL VENT

FS FLOW SWITCH

FU FIXTURE UNITS

GAL GALLON

GPD GALLONS PER DAY

GPH GALLONS PER HOUR

GPM GALLONS PER MINUTE

GPR GAS PRESSURE REGULATOR

GRS GAS REGULATOR STATION

GT GREASE TRAP

GVTR GAS VENT THROUGH ROOF

H&CW HOT AND COLD WATER

HB HOSE BIBB

HD HUB DRAIN

HDPE HIGH DENSITY POLYETHYLENE

HG MERCURY

HOA HANDS-OFF-AUTOMATIC

HP HORSEPOWER

HWCP HOT WATER CIRCULATING PUMP

HX HEAT EXCHANGER

HYD HYDRANT

HZ HERTZ

ID INSIDE DIAMETER

IE INVERT ELEVATION

INV INVERT

IPC INTERNATIONAL PLUMBING CODE

KPA KILOPASCAL

KW KILOWATT

KWH KILOWATT HOUR

LAV LAVATORY

LB POUND

LBS/HR POUNDS PER HOUR

LNG LIQUID NATURAL GAS

L/MIN LITERS PER MINUTE

L/S LITERS PER SECOND

M METER

MA MEDICAL AIR

MAV MEDICAL AIR VENT

MAX MAXIMUM

MBH 1000 BTU PER HOUR

ABBREVIATIONS

MFG MANUFACTURER

MG MILLIGRAM

MG/L MILLIGRAMS PER LITER

ML MILLILITER

MM MILLIMETER

MIN MINIMUM

MV MEDICAL VACUUM

N2 NITROGEN

N20 NITROGEN OXIDE

NC NORMALLY CLOSED

NF OIL FREE DRY (NITROGEN)

NG NATURAL GAS

NIC NOT IN CONTRACT

NO NORMALLY OPEN

NOM NOMINAL

NPTF NATIONAL PIPE THREAD FEMALE

NPS NOMINAL PIPE SIZE

NPT NOMINAL PIPE THREAD

NTS NOT TO SCALE

O2 OXYGEN

OC ON CENTER

OD OUTSIDE DIAMETER

OR OPERATING ROOM

OSD OPEN SIGHT DRAIN

OS&Y OUTSIDE STEM AND YOKE

PA PASCAL

PD PRESSURE DROP OR DIFFERENCE

PDI PLUMBING AND DRAINAGE

INSTITUTE

PG PRESSURE GAUGE

PID PROPORTIONAL-INTEGRAL-

DIFFERENTIAL

PLC PROGRAMMABLE LOGIC

CONTROLLERS

PP POLYPROPYLENE

PPM PARTS PER MILLION

PRV PRESSURE REDUCING VALVE

PSI POUNDS PER SQUARE INCH

PSIA POUNDS PER SQUARE INCH

ATMOSPHERE

PSIG POUNDS PER SQUARE INCH GAUGE

PTFE POLYTETRAFLUOROETHYLENE

PVC POLYVINYL CHLORIDE

PVDF POLYVINYLIDENE FLUORIDE

PW POTABLE WATER

RD ROOF DRAIN

RO REVERSE OSMOSIS

RPM REVOLUTIONS PER MINUTE

RTD RESISTANCE TEMPERATURE

DETECTORS

RTRP REINFORCED THERMOSETTING

RESIN PIPE

SCFM STANDARD CUBIC FEET PER

MINUTE

SDI SILT DENSITY INDEX

SDMH STORM DRAIN MANHOLE

SF SQUARE FEET

SPEC SPECIFICATION

SPS STERILE PROCESSING SERVICES

SQFT SQUARE FEET

SS SANITARY SEWER

STD STANDARD

SUS SAYBOLT UNIVERSAL SECOND

SW STORM WATER

SWP STEAM WORKING PRESSURE

TCV TEMPERATURE CONTROL VALVE

TD TRENCH DRAIN

TDH TOTAL DYNAMIC HEAD

TEMP TEMPERATURE

TFE TETRAFLUOROETHYLENE

THHN THERMOPLASTIC HIGH-HEAT

RESISTANT NYLON COATED WIRE

THWN THERMOPLASTIC HEAT & WATER

RESISTANT NYLON COATED WIRE

TMV THERMOSTATIC MIXING VALVE

T/P TEMPERATURE AND PRESSURE

TP TRAP PRIMER

TSTAT THERMOSTAT

TYP TYPICAL

V VOLT

VA VETERANS ADMINISTRATION

VAC VACUUM

VAC VOLTAGE IN ALTERNATING

CURRENT

VAMC VETERANS ADMINISTRATION

MEDICAL CENTER

VA TIL WWW.CFM.VA.GOV/TIL/INDEX.ASP

VHA VETERANS HEALTH

ADMINISTRATION

VSD VARIABLE SPEED DRIVE

VTR VENT THROUGH ROOF

W WASTE

WC WATER CLOSET

WCO WATER CLEANOUT

WG WATER GAUGE

WH WALL HYDRANT

WOG WATER, OIL, GAS

WPD WATER PRESSURE DROP

WS WASTE STACK

WSFU WATER SUPPLY FIXTURE UNITS

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text P-001

AutoCAD SHX Text

PLUMBING COVER SHEET

AutoCAD SHX Text Drawing Title

AutoCAD SHX Text Approved: Project Director

AutoCAD SHX Text Project Title

AutoCAD SHX Text Date

AutoCAD SHX Text Location

AutoCAD SHX Text Checked

AutoCAD SHX Text Building No.

AutoCAD SHX Text Project Number

AutoCAD SHX Text Drawing Number

AutoCAD SHX Text Drawn

AutoCAD SHX Text Revisions:

AutoCAD SHX Text Date

AutoCAD SHX Text

CONSULTANTS:

AutoCAD SHX Text

ARCHITECT/ENGINEERS:

AutoCAD SHX Text one eighth inch = one foot

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text three inches = one foot

AutoCAD SHX Text 6"

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text 6"

AutoCAD SHX Text one and one half inches = one foot

AutoCAD SHX Text one inch = one foot

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text 6"

AutoCAD SHX Text 6"

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text three quarters inch = one foot

AutoCAD SHX Text one half inch = one foot

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text three eighths inch = one foot

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text one quarter inch = one foot

AutoCAD SHX Text

VA FORM 08-6231

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text F

AutoCAD SHX Text E

AutoCAD SHX Text D

AutoCAD SHX Text C

AutoCAD SHX Text B

AutoCAD SHX Text A

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text Office of Construction and Facilities Management

AutoCAD SHX Text

STAMP:

AutoCAD SHX Text

UPGRADE FREIGHT ELEVATORS BLDG 4 & 7

AutoCAD SHX Text 504-22-102

AutoCAD SHX Text

RV

AutoCAD SHX Text

JS

AutoCAD SHX Text 04/13/2022

AutoCAD SHX Text Floor No.

AutoCAD SHX Text DAV ENERGY SOLUTIONS 2207 GARNET AVE, SUITE 1 SAN DIEGO, CA 92109 619-770-8552 WWW.DAVENERGY.COM

AutoCAD SHX Text Dwg. of 02

AutoCAD SHX Text DAV ENERGY SOLUTIONS 2207 GARNET AVE, SUITE 1 SAN DIEGO, CA 92109 619-770-8552 WWW.DAVENERGY.COM

AutoCAD SHX Text

ISSUED FOR CONSTRUCTION

AutoCAD SHX Text 07/29/2022

AutoCAD SHX Text 4 & 7

AutoCAD SHX Text

MULTIPLE

AutoCAD SHX Text THOMAS E. CREEK, AMARILLO VA HEALTH CARE SYSTEM - AMARILLO TEXAS 6010 W AMARILLO BLVD, AMARILLO, TX 79106

AutoCAD SHX Text R

AutoCAD SHX Text

SAN

AutoCAD SHX Text

AutoCAD SHX Text

FE

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

CO

P-101

BUILDING 4 FIRST FLOOR PLUMBING PLAN

SCALE: 1/4" = 1'-0"

Department of Veteran Affairs

SHEET NOTES

CONNECT TO NEAREST SANITARY LINE

WITH INDIRECT DRAIN, OR AIR GAP.

CONNECT TO EXISTING SEWAGE PIPING

WITH INDIRECT DRAIN.

UP TO CEILING

CONNECT TO BATHROOM DRAIN

LOCATED ON FIRST FLOOR.

KEY NOTES

P-101

BUILDING 7 BASEMENT PLUMBING PLAN

SCALE: 1/4" = 1'-0"

Pump Stop Pump Start

Sump Cover

Check Valve

SUMP PUMP DETAIL2

N

N

TYPE "W" HUB DRAIN 1

EMS EQUIPMENT

STORAGE

1009B

STORAGE

1009A POLICE STORAGE

STORAGE

1005A

CANTEEN

STORAGE

1005D

RESTROOM

RESTROOM

1005C

ELEV 1

ELEVATOR

MACHINE

ELEV 2

(E) 6" GW

(E) 6" SS

(E) 4" GW

(E) 3" GW

(E) 6" GW

BELOW SLAB

P - 1

P - 21-1/2"Ø

1-1/2"Ø

(E) 3" SS

2 2

STORAGE

MECHANICAL

4A

STORAGE

OFFICE

STORAGE

OFFICE

2ELECTRICAL

MECHANICAL

B03A

ELEVATOR

PARTIALLY

EXCAVATED

PARTIALLY

EXCAVATED

OFFICE

2A

OFFICE

P - 3

1-1/2"Ø

AutoCAD SHX Text

AutoCAD SHX Text

BUILDINGS 4 & 7 PLUMBING DESIGN

AutoCAD SHX Text Drawing Title

AutoCAD SHX Text Approved: Project Director

AutoCAD SHX Text Project Title

AutoCAD SHX Text Date

AutoCAD SHX Text Location

AutoCAD SHX Text Checked

AutoCAD SHX Text Building No.

AutoCAD SHX Text Project Number

AutoCAD SHX Text Drawing Number

AutoCAD SHX Text Drawn

AutoCAD SHX Text Revisions:

AutoCAD SHX Text Date

AutoCAD SHX Text

CONSULTANTS:

AutoCAD SHX Text

ARCHITECT/ENGINEERS:

AutoCAD SHX Text one eighth inch = one foot

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text three inches = one foot

AutoCAD SHX Text 6"

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text 6"

AutoCAD SHX Text one and one half inches = one foot

AutoCAD SHX Text one inch = one foot

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text 6"

AutoCAD SHX Text 6"

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text three quarters inch = one foot

AutoCAD SHX Text one half inch = one foot

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text three eighths inch = one foot

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text one quarter inch = one foot

AutoCAD SHX Text

VA FORM 08-6231

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text F

AutoCAD SHX Text E

AutoCAD SHX Text D

AutoCAD SHX Text C

AutoCAD SHX Text B

AutoCAD SHX Text A

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text Office of Construction and Facilities Management

AutoCAD SHX Text

STAMP:

AutoCAD SHX Text

ISSUED FOR CONSTRUCTION

AutoCAD SHX Text 07/29/2022

AutoCAD SHX Text

UPGRADE FREIGHT ELEVATORS, BLDG 4 + 7

AutoCAD SHX Text 504-22-102

AutoCAD SHX Text

RV

AutoCAD SHX Text

JS

AutoCAD SHX Text 04/13/2022

AutoCAD SHX Text Floor No.

AutoCAD SHX Text DAV ENERGY SOLUTIONS 2207 GARNET AVE, SUITE 1 SAN DIEGO, CA 92109 619-770-8552 WWW.DAVENERGY.COM

AutoCAD SHX Text Dwg. of 02

AutoCAD SHX Text DAV ENERGY SOLUTIONS 2207 GARNET AVE, SUITE 1 SAN DIEGO, CA 92109 619-770-8552 WWW.DAVENERGY.COM

AutoCAD SHX Text 4 & 7

AutoCAD SHX Text

MULTIPLE

AutoCAD SHX Text P-101

AutoCAD SHX Text THOMAS E. CREEK, AMARILLO VA HEALTH CARE SYSTEM - AMARILLO TEXAS 6010 W AMARILLO BLVD, AMARILLO, TX 79106

Sheets and Views
VA Amarillo Elevator-Sheet - P001 - 20220728-Layout1
VA Amarillo Elevator-Sheet - P101 - 20220728-Layout1