This is a Renovations Specifications document for the Oregon Youth Authority (OYA) MYCF Valley Cottage project, prepared by Beaman Architecture, Ltd., detailing comprehensive technical and administrative requirements for architectural, structural, HVAC, plumbing, and electrical renovations to two existing one-story, 5,500-square-foot juvenile housing facilities located at 2630 N. Pacific Highway in Woodburn, Oregon. The specifications encompass 31 divisions of work including general requirements, demolition and hazardous materials abatement, concrete, masonry, metals, wood and composite materials, thermal and moisture protection, openings, finishes, equipment, furnishings, mechanical systems, fire suppression, plumbing, HVAC, electrical, communications, electronic safety and security, earthwork, and exterior improvements. Work will be conducted in phases with residents temporarily relocated during each phase, and the project will be constructed under a single prime contract with phased completion dates as noted in the Invitation to Bid. The contractor must submit an updated construction schedule before commencing each phase, identify move-out and move-in dates for resident youth, and maintain weather-tight conditions throughout construction while accommodating full owner occupancy of adjacent facilities during the entire construction period.
Administrative requirements mandate a full-time superintendent dedicated to project management, with project manager and superintendent subject to owner and architect approval and review. Construction activities are restricted to Monday through Friday, 7:30 a.m. to 4:00 p.m., with contractor personnel required to wear OSHA-approved safety equipment and identification tags provided by the owner. The contractor must engage a dedicated third-party security staff person to monitor and enforce owner safety and security requirements, provide daily email reports to the owner's designated representative, and coordinate all movements through secure site perimeters. The contractor is responsible for all submittal procedures, including electronic PDF submissions with specific formatting requirements, 14-day review periods, and re-submission protocols, as well as quality assurance and quality control plans, testing and inspection schedules, and detailed documentation of compliance with architectural and engineering specifications. All tools must be collected at day's end per OYA requirements, controlled substances are prohibited on site, and the contractor must obtain owner written permission at least two days in advance for utility interruptions or disruptive operations.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
OYA MYCF Valley Cottage
Renovations
SPECIFICATIONS
December 2024
The OYA MYCF Valley Cottage Renovations Specifications (“Specifications”) include detailed technical specifications in Division 02 and beyond that apply to this ITB and any resulting Contract. Provisions in Division 01 (General Requirements) that are included in the Specifications are intended to be complementary and are in addition to the General Conditions and Supplemental General Conditions, and do not replace or modify the provisions therein. In the event of any conflict or discrepancy between the Specifications and the General Conditions or Supplemental Conditions, the General Conditions and Supplemental Conditions shall control, in accordance with the order of precedence provisions in Section A.3.1 of the General Conditions. All references in the Specifications to “General Conditions of the Contract” or “Supplementary Conditions of the Contract” should be construed to refer to the General Conditions and Supplemental General Conditions (Exhibit 4).
Architects Project No. 18105
OYA MYCF VALLEY
COTTAGE RENOVATIONS
TABLE OF CONTENTS Page 1
TABLE OF CONTENTS
Note: It shall be the Contractor’s responsibility to verify that each Project Manual contains the pages listed in this Table of Contents.
SPECIFICATION LIST
DIVISION 01: GENERAL REQUIREMENTS
011000 SUMMARY
012500 SUBSTITUTION PROCEDURES
012600 CONTRACT MODIFICATION PROCEDURES
Architect’s Supplemental Instructions Form
Contract Administration Change Order Form
013100 PROJECT MANAGEMENT AND COORDINATION
Request for Interpretation Form
013150 SAFETY AND SECURITY REQUIREMENTS
013200 CONSTRUCTION PROGRESS DOCUMENTATION
013300 SUBMITTAL PROCEDURES
014000 QUALITY REQUIREMENTS
014200 REFERENCES
015000 TEMPORARY FACILITIES AND CONTROLS
016000 PRODUCT REQUIREMENTS
017300 EXECUTION
017700 CLOSEOUT PROCEDURES
017823 OPERATION AND MAINTENANCE DATA
017839 PROJECT RECORD DOCUMENTS
017900 DEMONSTRATION AND TRAINING
019113 GENERAL COMMISSIONING REQUIREMENTS
DIVISION 02: EXISTING CONDITIONS
024119 SELECTIVE STRUCTURE DEMOLITION
Hazardous Materials Survey Reports
028213 ASBESTOS ABATEMENT
028216 ASBESTOS AIR MONITORING REQUIREMENTS
028313 LEAD HANDLING PROCEDURES
028416 MERCURY-CONTAINING LAMP REMOVAL AND DISPOSAL
AND PCB ABATEMENT AND SPILL CLEANUP
DIVISION 03: CONCRETE
033053 MISCELLANEOUS CAST-IN-PLACE CONCRETE
DIVISION 04: MASONRY
042000 UNIT MASONRY
042300 GLASS UNIT MASONRY
DIVISION 05: METALS
050513 SHOP-APPLIED METAL FINISHES
054000 COLD-FORMED METAL FRAMING
055000 METAL FABRICATIONS
TABLE OF CONTENTS Page 2
DIVISION 06: WOOD, PLASTICS AND COMPOSITES
Executive Order No. 12-16
061053 MISCELLANEOUS ROUGH CARPENTRY
061600 SHEATHING
061800 GLUED-LAMINATED CONSTRUCTION
062013 EXTERIOR FINISH CARPENTRY
062023 INTERIOR FINISH CARPENTRY
064116 PLASTIC-LAMINATE-FACED ARCHITECTURAL CABINETS
066400 PLASTIC PANELING
DIVISION 07: THERMAL AND MOISTURE PROTECTION
071113 BITUMINOUS DAMPPROOFING
071900 WATER REPELLENTS
072100 THERMAL INSULATION
072500 WEATHER BARRIERS
074113 METAL ROOF PANELS
074213 METAL WALL PANELS
076200 SHEET METAL FLASHING AND TRIM
077200 ROOF ACCESSORIES
079200 JOINT SEALANTS
079201 SECURITY SEALANTS
DIVISION 08: OPENINGS
080000 DOOR SCHEDULE
081113 HOLLOW METAL DOORS AND FRAMES
081416 FLUSH WOOD DOORS
083113.53 SECURITY ACCESS DOORS AND FRAMES
087100 DOOR HARDWARE
Door Hardware Schedule
087163 DETENTION DOOR HARDWARE
088000 GLAZING
088836 SWITCHABLE PRIVACY GLASS
088853 SECURITY GLAZING
DIVISION 09: FINISHES
090000 ROOM FINISH SCHEDULE
092216 NON-STRUCTURAL METAL FRAMING
092900 GYPSUM BOARD
093000 TILING
095113 ACOUSTICAL PANEL CEILINGS
095123 ACOUSTICAL TILE CEILINGS
095450 ACOUSTIC WOOD CEILINGS
096513 RESILIENT BASE AND ACCESSORIES
096516 RESILIENT SHEET FLOORING
096516.13 LINOLEUM FLOORING
097216.16 WALL-CLADDING SYSTEMS
099100 PAINTING
TABLE OF CONTENTS Page 3
DIVISION 10: SPECIALTIES
102600 WALL AND DOOR PROTECTION
102813.63 DETENTION TOILET ACCESSORIES AND MISCELLANEOUS
EQUIPMENT
104413 FIRE EXTINGUISHER CABINETS
DIVISION 11: EQUIPMENT
113200 LAUNDRY EQUIPMENT
114000 FOODSERVICE EQUIPMENT
DIVISION 12: FURNISHINGS
123623.13 PLASTIC-LAMINATE-CLAD COUNTERTOPS
123662 SIMULATED STONE AND POLYCARBONATE FABRICATIONS
124813 ENTRANCE FLOOR MATS AND FRAMES
125600 INSTITUTIONAL FURNITURE
DIVISION 20: MECHANICAL
201000 GENERAL MECHANICAL REQUIREMENTS
201002 ADDITIONS OR REMODELED FACILITIES
201003 SECURITY PROVISIONS
201004 EXCAVATION AND BACKFILL
201005 SEISMIC PROVISIONS
201006 PROJECT FINALIZATIONS
201007 TESTING, ADJUSTING AND BALANCING
DIVISION 21: FIRE SUPPRESSION
211313 FIRE PROTECTION
DIVISION 22: PLUMBING
220503 PLUMBING PIPING AND VALVES
220504 PLUMBING SPECIALTIES
220529 SUPPORTS, ANCHORS, CURBS, SEALS AND FLASHINGS
220553 MECHANICAL IDENTIFICATION
220700 PLUMBING INSULATION
223000 PLUMBING EQUIPMENT
223100 EQUIPMENT INSTALLED ONLY
224000 PLUMBING FIXTURES
DIVISION 23: HEATING, VENTILATING AND AIR CONDITIONING
230513 MOTORS
230529 SUPPORTS, ANCHORS, CURBS, SEALS AND FLASHINGS
230553 MECHANICAL IDENTIFICATION
230700 HVAC INSULATION
230923 ENERGY CONTROL SYSTEMS
232300 REFRIGERANT PIPING AND SPECIALTIES
233100 DUCTWORK
TABLE OF CONTENTS Page 4
233300 DUCTWORK ACCESSORIES
233400 HVAC FANS
233700 AIR OUTLETS AND INLETS
233813 COMMERCIAL KITCHEN HOODS
236313 AIR COOLED HEAT PUMP UNITS
237200 AIR-TO-AIR ENERGY RECOVERY EQUIPMENT
238216 AIR COILS
DIVISION 26: ELECTRICAL
260101 BASIC ELECTRICAL REQUIREMENTS
260102 PROJECT FINALIZATION
260160 ELECTRICAL DEMOLITION FOR REMODELING
260513 MEDIUM VOLTAGE CABLES
260519 BUILDING WIRE AND CABLE
260520 EQUIPMENT WIRING
260526 GROUNDING AND BONDING
260530 CONDUIT
260532 BOXES
260543 DUCT BANK
260553 ELECTRICAL IDENTIFICATION
260923 ENCLOSED CONTACTORS
260943 NETWORK LIGHTING CONTROLS
262416 PANELBOARDS
262712 UTILITY SERVICE ENTRANCE
262716 CABINETS AND ENCLOSURES
262726 WIRING DEVICES
262727 SUPPORTING DEVICES
262813 FUSES
262816 ENCLOSED SWITCHES
262817 ENCLOSED CIRCUIT BREAKERS
262913 ENCLOSED MOTOR CONTROLLERS
263353 STATIC LIGHTING INVERTERS
264302 SURGE PROTECTION DEVICES
265100 INTERIOR LIGHTING
265600 EXTERIOR LIGHTING
DIVISION 27: COMMUNICATIONS
270500 COMMON WORK RESULTS FOR COMMUNICATIONS
270526 GROUNDING AND BONDING FOR TELECOMMUNICATIONS
270529 HANGERS AND SUPPORTS FOR COMMUNICATIONS
SYSTEMS
270533 CONDUITS AND BACKBOXES FOR COMMUNICATIONS
SYSTEMS
270536 CABLE TRAY FOR COMMUNICATIONS CIRCUITS
271100 COMMUNICATIONS EQUIPMENT ROOM FITTINGS
271300 COMMUNICATIONS BACKBONE CABLING
271500 COMMUNICATIONS HORIZONTAL CABLING
DIVISION 28: ELECTRONIC SAFETY AND SECURITY
280101 GENERAL PROVISIONS FOR LOW VOLTAGE WORK
280500 LOW VOLTAGE SYSTEMS - CONDUIT/PATHWAYS AND
WIRING ONLY
TABLE OF CONTENTS Page 5
282300 NETWORK VIDEO SYSTEM - CONDUIT/PATHWAYS AND
WIRING ONLY
283120 ADDRESSABLE FIRE ALARM SYSTEM
DIVISION 31: EARTHWORK
312000 EARTH MOVING
DIVISION 32: EXTERIOR IMPROVEMENTS
329200 TURF AND GRASSES
*LOW VOLTAGE SPECIFICATIONS (Numbered Separately and Located Together)
000101 PROJECT TITLE PAGE
000110 TABLE OF CONTENTS
011000 SUMMARY
406710 CONTROL PANELS
407001 INSTRUMENTATION AND PROCESS SYSTEMS
END OF TABLE OF CONTENTS
SUMMARY 011000 - 1
SECTION 011000 - SUMMARY
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Project information.
2. Work covered by Contract Documents.
3. Phased construction.
4. Work by Owner.
5. Owner-furnished products.
6. Access to site.
7. Coordination with occupants.
8. Work restrictions.
9. Specification and drawing conventions.
1.2 PROJECT INFORMATION
A. Project Identification: OYA MYCF Valley Cottage Alterations Package and Renovations Package which are to be Bid and Built as One Project.
1. Project Location: 2630 N. Pacific Hwy. Woodburn, Oregon.
B. Owner: State of Oregon, Oregon Youth Authority 530 Center St. NE, Salem, Oregon.
1. Owner's Authorized Representative: Stacy Davis, State-Wide Construction Manager, 530 Center Street NE, Suite 500, Salem, Oregon 97301.
C. Architect: Michael Beaman, Beaman Architecture, Ltd., mb@beamanarch.com or Telephone:
503.236.3300.
1.3 WORK COVERED BY CONTRACT DOCUMENTS
A. The Work of Project is defined by the Contract Documents and consists of the following:
1. Architectural, Structural, HVAC, Plumbing and Electrical Renovations to two existing one story, 5,500 square foot juvenile housing facilities (Cottages) located within a secure campus.
B. Type of Contract:
1. Project will be constructed under a single prime contract.
1.4 PHASED CONSTRUCTION
A. The Work shall be conducted in phases with each phase substantially complete as noted in Invitation to Bid.
mailto:mb@beamanarch.com
SUMMARY 011000 - 2
B. Before commencing Work of each phase, submit an updated copy of Contractor's construction schedule showing the sequence, commencement, and completion dates and move-out and -in dates of resident Youth for all phases of the Work.
1.5 WORK BY OWNER
A. General: Cooperate fully with Owner so work may be carried out smoothly, without interfering with or delaying work under this Contract or work by Owner. Coordinate the Work of this Contract with work performed by Owner.
B. Concurrent Work: Owner may perform the following construction operations at Project site.
Those operations will be conducted simultaneously with work under this Contract.
1. Installation of security cameras and related equipment, although provision and installation of all wiring, conduits, raceways, etc. required by that equipment is by Contractor.
1.6 OWNER-FURNISHED PRODUCTS
A. Owner will furnish products indicated. The Work includes receiving, unloading, handling, storing, protecting, and installing Owner-furnished products.
B. Owner-Furnished Products:
1. Security Cameras, including installation and programming of cameras, excluding back boxes and cabling.
1.7 ACCESS TO SITE
A. General: Contractor shall have limited use of Project site for construction operations as indicated on Drawings by the Contract limits and as indicated by requirements of this Section.
B. Use of Site: Limit use of Project site to areas within the Contract limits indicated. Do not disturb portions of Project site beyond areas in which the Work is indicated.
1. Driveways, Walkways and Entrances: Keep driveways, loading areas, and entrances serving premises clear and available to Owner, Owner's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials.
a. Schedule deliveries to minimize use of driveways and entrances by construction operations.
b. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.
C. Condition of Existing Buildings: Maintain portions of existing buildings affected by construction operations in a weather-tight condition throughout construction period. Repair damage caused by construction operations.
SUMMARY 011000 - 3
1.8 COORDINATION WITH OCCUPANTS
A. Full Owner Occupancy: Owner will occupy site and existing, adjacent buildings during entire construction period. Cooperate with Owner during construction operations to minimize conflicts and facilitate Owner usage. Perform the Work so as not to interfere with Owner's day-to-day operations. Maintain existing exits unless otherwise indicated.
1. Maintain access to existing walkways, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from Owner.
2. Notify Owner not less than 72 hours in advance of activities that will affect Owner's operations.
B. Owner Limited Occupancy of Completed Areas of Construction: Owner reserves the right to occupy and to place and install equipment in completed portions of the Work, prior to Substantial Completion of the Work, provided such occupancy does not interfere with completion of the Work.
Such placement of equipment and limited occupancy shall not constitute acceptance of the total Work.
1. Successfully complete all required inspections by authorities having jurisdiction before limited Owner occupancy.
2. Before limited Owner occupancy, mechanical and electrical systems shall be fully operational, and required tests and inspections shall be successfully completed. On occupancy, Owner will operate mechanical and electrical systems serving occupied portions of Work. See General Conditions for complete requirements.
3. On occupancy, Owner will assume responsibility for maintenance and custodial service for occupied portions of Work.
1.9 WORK RESTRICTIONS
A. Work Restrictions, General: Comply with restrictions on construction operations.
1. Comply with General and Supplementary Conditions of the Contract.
B. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Owner unless permitted under the following conditions and then only after providing temporary utility services according to requirements indicated:
1. Notify Owner not less than two days in advance of proposed utility interruptions.
2. Obtain Owner's written permission before proceeding with utility interruptions.
C. Noise, Vibration, and Odors: Coordinate operations that may result in high levels of noise and vibration, odors, or other disruption to Owner occupancy with Owner.
1. Notify Owner not less than two days in advance of proposed disruptive operations.
2. Obtain Owner's written permission before proceeding with disruptive operations.
D. Controlled Substances: Use of tobacco products and other controlled substances on Project site is not permitted.
E. Employee Identification: Owner will provide identification tags for Contractor personnel working on Project site. Require personnel to use identification tags at all times.
SUMMARY 011000 - 4
F. Employee Screening: Comply with Owner's requirements for drug and background screening of Contractor personnel working on Project site.
1.10 SUPERVISION
A. The Contractor shall employ a competent superintendent and necessary assistants, as needed, to oversee execution of the Project.
B. There shall be a full time Project superintendent assigned to this Project who shall be in attendance at the Project site during the progress of all the Work.
C. The superintendent and Project manager, if the Contractor utilizes a Project manager, shall be reviewed and approved by the Architect and Owner, and neither shall be changed except with the consent of the Architect and Owner. Any new superintendent or new Project manager must be satisfactory to the Architect and Owner. The superintendent, and any Project manager, shall represent the Contractor and all communications given to the superintendent or Project manager are deemed given to the Contractor. All communications that affect construction are to be confirmed in writing.
D. Provide other administrative and supervisory personnel as required for proper performance of the Work.
1.11 SAFETY AND SECURITY
A. Contractor and all employees to wear appropriate safety clothing as approved by Owner.
B. Contractor to have a safety program, meeting OSHA requirements, i.e. Hard Hats, OSHA signage at appropriate areas stating ‘Construction Access Only, Hard Hats Required”, and conduct work by means and methods that foster a safe working environment. It is also the responsibility of the contractor to conform to the safety guidelines and on site requirements outlined in the Supplemental General Conditions regarding tools, equipment and material storage and OYA offender Prohibited Items.
C. General: Gather and collect all tools at day’s end as per requirements of the Oregon Youth Authority as defined in Supplemental General Conditions.
Hours of work:
1. On-Site Work Days and Hours: Construction activities can occur Monday through Friday 7:30 a.m. to 4:00 p.m.
1.12 SPECIFICATION AND DRAWING CONVENTIONS
A. Specification Content: The Specifications use certain conventions for the style of language and the intended meaning of certain terms, words, and phrases when used in particular situations.
These conventions are as follows:
1. Imperative mood and streamlined language are generally used in the Specifications. The words "shall," "shall be," or "shall comply with," depending on the context, are implied where a colon (:) is used within a sentence or phrase.
2. Specification requirements are to be performed by Contractor unless specifically stated otherwise.
SUMMARY 011000 - 5
B. Division 01 General Requirements: Requirements of Sections in Division 01 apply to the Work of all Sections in the Specifications.
C. Drawing Coordination: Requirements for materials and products identified on Drawings are described in detail in the Specifications. One or more of the following are used on Drawings to identify materials and products:
1. Terminology: Materials and products are identified by the typical generic terms used in the individual Specifications Sections.
2. Abbreviations: Materials and products are identified by abbreviations published as part of the U.S. National CAD Standard and scheduled on Drawings.
3. Keynoting: Materials and products are identified by reference keynotes.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 011000
SUBSTITUTION PROCEDURES 012500 - 1
SECTION 012500 - SUBSTITUTION PROCEDURES
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes administrative and procedural requirements for substitutions.
B. Related Requirements:
1. Section 016000 "Product Requirements" for requirements for submitting comparable product submittals for products by listed manufacturers.
1.2 DEFINITIONS
A. Substitutions: Changes in products, materials, equipment, and methods of construction from those required by the Contract Documents and proposed by Contractor.
1. Substitutions for Cause: Changes proposed by Contractor that are required due to changed Project conditions, such as unavailability of product, regulatory changes, or unavailability of required warranty terms.
2. Substitutions for Convenience: Changes proposed by Contractor or Owner that are not required in order to meet other Project requirements but may offer advantage to Contractor or Owner.
1.3 ACTION SUBMITTALS
A. Substitution Requests: Submit three copies of each request for consideration. Identify product or fabrication or installation method to be replaced. Include Specification Section number and title and Drawing numbers and titles.
1. Substitution Request Form: Use CSI Form 13.1A.
2. Documentation: Show compliance with requirements for substitutions and the following, as applicable:
a. Statement indicating why specified product or fabrication or installation cannot be provided, if applicable.
b. Coordination information, including a list of changes or revisions needed to other parts of the Work and to construction performed by Owner and separate contractors that will be necessary to accommodate proposed substitution.
c. Detailed comparison of significant qualities of proposed substitution with those of the Work specified. Include annotated copy of applicable Specification Section.
Significant qualities may include attributes such as performance, weight, size, durability, visual effect, sustainable design characteristics, warranties, and specific features and requirements indicated. Indicate deviations, if any, from the Work specified.
d. Product Data, including drawings and descriptions of products and fabrication and installation procedures.
e. Samples, where applicable or requested.
f. Certificates and qualification data, where applicable or requested.
SUBSTITUTION PROCEDURES 012500 - 2
g. List of similar installations for completed projects with project names and addresses and names and addresses of architects and owners.
h. Material test reports from a qualified testing agency indicating and interpreting test results for compliance with requirements indicated.
i. Research reports evidencing compliance with building code in effect for Project, from ICC-ES.
j. Detailed comparison of Contractor's construction schedule using proposed substitution with products specified for the Work, including effect on the overall Contract Time. If specified product or method of construction cannot be provided within the Contract Time, include letter from manufacturer, on manufacturer's letterhead, stating date of receipt of purchase order, lack of availability, or delays in delivery.
k. Cost information, including a proposal of change, if any, in the Contract Sum.
l. Contractor's certification that proposed substitution complies with requirements in the Contract Documents except as indicated in substitution request, is compatible with related materials, and is appropriate for applications indicated.
m. Contractor's waiver of rights to additional payment or time that may subsequently become necessary because of failure of proposed substitution to produce indicated results.
3. Architect's Action: If necessary, Architect will request additional information or documentation for evaluation within seven days of receipt of a request for substitution.
Architect will notify Contractor of acceptance or rejection of proposed substitution within 15 days of receipt of request, or seven days of receipt of additional information or documentation, whichever is later.
a. Forms of Acceptance: Change Order, Construction Change Directive, or Architect's Supplemental Instructions for minor changes in the Work.
b. Use product specified if Architect does not issue a decision on use of a proposed substitution within time allocated.
1.4 QUALITY ASSURANCE
A. Compatibility of Substitutions: Investigate and document compatibility of proposed substitution with related products and materials. Engage a qualified testing agency to perform compatibility tests recommended by manufacturers.
1.5 PROCEDURES
A. Coordination: Revise or adjust affected work as necessary to integrate work of the approved substitutions.
PART 2 - PRODUCTS
2.1 SUBSTITUTIONS
A. Substitutions for Cause: Submit requests for substitution immediately on discovery of need for change, but not later than 15 days prior to time required for preparation and review of related submittals.
SUBSTITUTION PROCEDURES 012500 - 3
1. Conditions: Architect will consider Contractor's request for substitution when the following conditions are satisfied. If the following conditions are not satisfied, Architect will return requests without action, except to record noncompliance with these requirements:
a. Requested substitution is consistent with the Contract Documents and will produce indicated results.
b. Requested substitution provides sustainable design characteristics that specified product provided.
c. Substitution request is fully documented and properly submitted.
d. Requested substitution will not adversely affect Contractor's construction schedule.
e. Requested substitution has received necessary approvals of authorities having jurisdiction.
f. Requested substitution is compatible with other portions of the Work.
g. Requested substitution has been coordinated with other portions of the Work.
h. Requested substitution provides specified warranty.
i. If requested substitution involves more than one contractor, requested substitution has been coordinated with other portions of the Work, is uniform and consistent, is compatible with other products, and is acceptable to all contractors involved.
B. Substitutions for Convenience: Not allowed.
END OF SECTION 012500
CONTRACT MODIFICATION PROCEDURES 012600 - 1
SECTION 012600 - CONTRACT MODIFICATION PROCEDURES
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes administrative and procedural requirements for handling and processing Contract modifications.
B. Related Requirements:
1. Section 012500 "Substitution Procedures" for administrative procedures for handling requests for substitutions made after the Contract award.
1.2 MINOR CHANGES IN THE WORK
A. Architect will issue supplemental instructions authorizing minor changes in the Work, not involving adjustment to the Contract Sum or the Contract Time, on Form included in Project Manual.
1.3 PROPOSAL REQUESTS
A. Owner-Initiated Proposal Requests: Architect will issue a detailed description of proposed changes in the Work that may require adjustment to the Contract Sum or the Contract Time. If necessary, the description will include supplemental or revised Drawings and Specifications.
1. Work Change Proposal Requests issued by Architect are not instructions either to stop work in progress or to execute the proposed change.
2. Within 20 days, after receipt of Proposal Request, submit a quotation estimating cost adjustments to the Contract Sum and the Contract Time necessary to execute the change.
a. Include a list of quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made. If requested, furnish survey data to substantiate quantities.
b. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.
c. Include costs of labor and supervision directly attributable to the change.
d. Include an updated Contractor's construction schedule that indicates the effect of the change, including, but not limited to, changes in activity duration, start and finish times, and activity relationship. Use available total float before requesting an extension of the Contract Time.
e. Quotation Form: Use Forms acceptable to Architect.
B. Contractor-Initiated Proposals: If latent or changed conditions require modifications to the Contract, Contractor may initiate a claim by submitting a request for a change to Architect.
1. Include a statement outlining reasons for the change and the effect of the change on the Work. Provide a complete description of the proposed change. Indicate the effect of the proposed change on the Contract Sum and the Contract Time.
CONTRACT MODIFICATION PROCEDURES 012600 - 2
2. Include a list of quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made. If requested, furnish survey data to substantiate quantities.
3. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.
4. Include costs of labor and supervision directly attributable to the change.
5. Include an updated Contractor's construction schedule that indicates the effect of the change, including, but not limited to, changes in activity duration, start and finish times, and activity relationship. Use available total float before requesting an extension of the Contract Time.
6. Comply with requirements in Section 012500 "Substitution Procedures" if the proposed change requires substitution of one product or system for product or system specified.
7. Proposal Request Form: Use Form acceptable to Architect.
1.4 CHANGE ORDER PROCEDURES
A. On Owner's approval of a Work Changes Proposal Request, Architect will issue a Change Order for signatures of Owner and Contractor on form included in Project Manual.
1.5 WORK CHANGE DIRECTIVE
A. Work Change Directive: Architect may issue a Work Change Directive on form similar to AIA Document G714. Work Change Directive instructs Contractor to proceed with a change in the Work, for subsequent inclusion in a Change Order.
1. Work Change Directive contains a complete description of change in the Work. It also designates method to be followed to determine change in the Contract Sum or the Contract Time.
B. Documentation: Maintain detailed records on a time and material basis of work required by the Work Change Directive.
1. After completion of change, submit an itemized account and supporting data necessary to substantiate cost and time adjustments to the Contract.
PART 2 - PRODUCTS (Not Used)
END OF SECTION 012600
BEAMAN ARCHITECTURE LTD
1634 SE 54TH AVENUE, PORTLAND, OR 97215 503.236.3300
ARCHITECT’S SUPPLEMENTAL INSTRUCTIONS
PROJECT: Oregon Youth Authority MYCF Valley Cottage NO.:
Renovations
CONTRACTOR: TBD DATE:
CONTRACT: GENERAL BEAMAN JOB NO.: 18105
REFERENCE: City of _____________
DESCRIPTION OF WORK TO BE PERFORMED:
ASI NO. #-#
ASI NO. #-#
◼ Referenced Drawings: X#-# ◼ Attached Drawings: X#-#
If above work results in a change in cost or time to the Contract, advise Architect within 21 calendar days.
Include a complete and itemized breakdown of costs for change.
COPIES TO:
◼ OWNER .............................. Stacy Davis – Oregon Youth Authority
◼ CONTRACTOR ................... TBD
CITY .................................... City of ____________________
Michael Beaman, Architect President, Beaman Architecture, Ltd.
Change Order No. 1 Oregon Youth Authority MYCF Valley Cottage Renovations
Page 1 of 2 DASPS-#-#
CHANGE ORDER
PROJECT NO. DASPS-#-#
CHANGE ORDER # 1
STATE OR
Date: COUNTY Marion
Contract For: Oregon Youth Authority MYCF Valley Cottage Renovations
Owner: Oregon Youth Authority
Issued To:
This Change Order covers changes to the subject contract as described herein. The Contractor shall construct, furnish equipment and materials, and perform all the work necessary or required to complete the Change Order items for the price agreed upon.
You are hereby requested to comply with the following changes from the contract plans and specifications:
Item No. Description of Bid / Alternates Selected
Subtotal Total
1. Base Bid
Total Bid / Alternates Selected
Item No. Description of Accepted Changes
DECREASE (-) INCREASE (+)
in Contract Price in Contract Price
1. ------ -------
2. ------ ------
3. ------ ------
4. ------ ------
------0
Item Justification
1.
FINANCIAL INFORMATION
(1) Amount of Original Contract:
(2) Amount of this Change Order:
(3) Amount of Prior Change Orders, 0 through 0:
(4) Adjusted Contract Amount (1+2+3):
Note: This change order is to document the changes as described. The “Contract Amount” price reflects the price as bid. The “Adjusted Contract Amount” reflects the revised contractor pricing included in the referenced Change Order Request prices.
Change Order No. 1 Oregon Youth Authority MYCF Valley Cottage Renovations
Page 2 of 2 DASPS-#-#
CHANGE IN CONTRACT TIME
Original Contract Time (days) to Substantial Completion
NTP date:
Net Change under Previous Change Orders (days)
Time Extension/Reduction this Change Order (days)
X Calendar Days
Contract Time with All Approved Change Orders (days)
X Calendar Days
Original Contract Substantial Completion Date
Adjusted Contract Substantial Completion Date
ACCEPTANCE AND ENDORSEMENTS
Accepted:
We, the undersigned, have given careful consideration to the change proposed, and hereby agree; if this proposal is approved, that we will provide all equipment, furnish all materials, except as may be otherwise noted above, and perform all services necessary for the work specified, and will accept as full payment therefor the fees and prices shown above.
Adjustment to Contract Price and Time listed include full and complete compensation for all changed work, and all costs or expenses, extended overhead and impact costs resulting from this Change Order.
Contractor Signature:
Printed Name / Company:
Title: Contracts Date:
OYA Approval: Date
OYA PPO Facilities Manager
DASPS Approval: Date
State Procurement Analyst
Recommended: Date
Beaman Architecture Ltd.
PROJECT MANAGEMENT AND COORDINATION 013100 - 1
SECTION 013100 - PROJECT MANAGEMENT AND COORDINATION
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:
1. General coordination procedures.
2. Requests for Information (RFIs).
3. Project meetings.
B. Contractor is to have a Full-Time Superintendent dedicated to this Project, to administrate, manage and coordinate construction activities.
C. Related Requirements:
1. Section 017300 "Execution" for procedures for coordinating general installation services.
2. Section 017700 "Closeout Procedures" for coordinating closeout of the Contract.
1.2 DEFINITIONS
A. RFI: Request from Owner, Architect, or Contractor seeking information required by or clarifications of the Contract Documents.
1.3 INFORMATIONAL SUBMITTALS
A. Subcontract List: Prepare a written summary identifying individuals or firms proposed for each portion of the Work, including those who are to furnish products or equipment fabricated to a special design. Include the following information in tabular form:
1. Name, address, and telephone number of entity performing subcontract or supplying products.
2. Number and title of related Specification Section(s) covered by subcontract.
3. Drawing number and detail references, as appropriate, covered by subcontract.
B. Key Personnel Names: Within seven days of starting construction operations, submit a list of key personnel assignments, including superintendent and other personnel in attendance at Project site. Identify individuals and their duties and responsibilities; list addresses and telephone numbers, including home, office, and cellular telephone numbers and e-mail addresses. Provide names, addresses, and telephone numbers of individuals assigned as alternates in the absence of individuals assigned to Project.
1.4 GENERAL COORDINATION PROCEDURES
A. Coordination: Coordinate construction operations included in different Sections of the Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate
PROJECT MANAGEMENT AND COORDINATION 013100 - 2
construction operations, included in different Sections that depend on each other for proper installation, connection, and operation.
1. Schedule construction operations in sequence required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation.
2. Coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair.
3. Make adequate provisions to accommodate items scheduled for later installation.
B. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to, the following:
1. Preparation of Contractor's construction schedule.
2. Preparation of the schedule of values.
3. Installation and removal of temporary facilities and controls.
4. Delivery and processing of submittals.
5. Progress meetings.
6. Pre-installation conferences.
7. Project closeout activities.
8. Startup and adjustment of systems.
1.5 REQUESTS FOR INFORMATION (RFIs)
A. General: Immediately on discovery of the need for additional information or interpretation of the Contract Documents, Contractor shall prepare and submit an RFI in the form specified.
1. Architect will return RFIs submitted to the Architect by other entities controlled by Contractor with no response.
2. Coordinate and submit RFIs in a prompt manner so as to avoid delays in Contractor's work or work of subcontractors.
B. Content of the RFI: Include a detailed, legible description of item needing information or interpretation and the following:
1. Project name.
2. Project number.
3. Date.
4. Name of Contractor.
5. Name of Architect.
6. RFI number, numbered sequentially.
7. RFI subject.
8. Specification Section number and title and related paragraphs, as appropriate.
9. Drawing number and detail references, as appropriate.
10. Field dimensions and conditions, as appropriate.
11. Contractor's suggested resolution. If Contractor's suggested resolution impacts the
Contract Time or the Contract Sum, Contractor shall state impact in the RFI.
12. Contractor's signature.
13. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.
PROJECT MANAGEMENT AND COORDINATION 013100 - 3
a. Include dimensions, thicknesses, structural grid references, and details of affected materials, assemblies, and attachments on attached sketches.
C. RFI Forms: Software-generated version of form bound in Project Manual with substantially the same content as indicated above, acceptable to Architect.
1. Attachments shall be electronic files in Adobe Acrobat PDF format.
D. Architect's Action: Architect will review each RFI, determine action required, and respond.
Allow seven working days for Architect's response for each RFI. RFIs received by Architect after 1:00 p.m. will be considered as received the following working day.
1. The following Contractor-generated RFIs will be returned without action:
a. Requests for approval of submittals.
b. Requests for approval of substitutions.
c. Requests for approval of Contractor's means and methods.
d. Requests for coordination information already indicated in the Contract
Documents.
e. Requests for adjustments in the Contract Time or the Contract Sum.
f. Requests for interpretation of Architect's actions on submittals.
g. Incomplete RFIs or inaccurately prepared RFIs.
2. Architect's action may include a request for additional information, in which case Architect's time for response will date from time of receipt of additional information.
3. Architect's action on RFIs that may result in a change to the Contract Time or the Contract Sum may be eligible for Contractor to submit Change Proposal according to Section 012600 "Contract Modification Procedures."
a. If Contractor believes the RFI response warrants change in the Contract Time or the Contract Sum, notify Architect in writing within 10 days of receipt of the RFI response.
E. RFI Log: Prepare, maintain, and submit a tabular log of RFIs organized by the RFI number.
Submit log weekly. Software log with not less than the following:
1. Project name.
2. Name and address of Contractor.
3. Name and address of Architect.
4. RFI number including RFIs that were returned without action or withdrawn.
5. RFI description.
6. Date the RFI was submitted.
7. Date Architect's response was received.
F. On receipt of Architect's action, update the RFI log and immediately distribute the RFI response to affected parties. Review response and notify Architect within seven days if Contractor disagrees with response.
1.6 PROJECT MEETINGS
A. General: Schedule and conduct meetings and conferences at Project site unless otherwise indicated.
PROJECT MANAGEMENT AND COORDINATION 013100 - 4
1. Attendees: Inform participants and others involved, and individuals whose presence is required, of date and time of each meeting. Notify Owner and Architect of scheduled meeting dates and times.
2. Agenda: Prepare the meeting agenda. Distribute the agenda to all invited attendees.
3. Minutes: Entity responsible for conducting meeting will record significant discussions and agreements achieved. Distribute the meeting minutes to everyone concerned, including Owner, and Architect, within three days of the meeting.
B. Pre-Construction Conference: Schedule and conduct a pre-construction conference before starting construction, at a time convenient to Owner and Architect, but no later than seven days after execution of the Agreement. Architect will forward a meeting agenda to the Contractor upon request.
1. Conduct the conference to review responsibilities and personnel assignments.
2. Attendees: Authorized representatives of Owner, Architect, and their consultants;
Contractor and its superintendent; major subcontractors; suppliers; and other concerned parties shall attend the conference. Participants at the conference shall be familiar with Project and authorized to conclude matters relating to the Work.
3. Agenda: Discuss items of significance that could affect progress, including the following:
a. Tentative construction schedule.
b. Phasing.
c. Critical work sequencing and long-lead items.
d. Designation of key personnel and their duties.
e. Lines of communications.
f. Procedures for processing field decisions and Change Orders.
g. Procedures for RFIs.
h. Procedures for processing Applications for Payment.
i. Distribution of the Contract Documents.
j. Submittal procedures.
k. Preparation of record documents.
l. Use of the premises and existing buildings.
m. Work restrictions.
n. Working hours.
o. Owner's occupancy requirements.
p. Responsibility for temporary facilities and controls.
q. Parking availability.
r. Office, work, and storage areas.
s. Equipment deliveries and priorities.
t. First aid.
u. Security.
v. Progress cleaning.
4. Minutes: Contractor will record and distribute meeting minutes.
C. Project Closeout Conference: Schedule and conduct a project closeout conference, at a time convenient to Owner prior to completion on each site.
1. Conduct the conference to review requirements and responsibilities related to Project closeout.
2. Attendees: Authorized representatives of Owner, Contractor and its superintendent and other concerned parties shall attend the meeting. Participants at the meeting shall be familiar with Project and authorized to conclude matters relating to the Work.
3. Agenda: Discuss items of significance that could affect or delay Project closeout, including the following:
PROJECT MANAGEMENT AND COORDINATION 013100 - 5
a. Preparation of record documents.
b. Procedures required prior to inspection for Substantial Completion and for final inspection for acceptance.
c. Submittal of written warranties.
d. Requirements for preparing operations and maintenance data.
e. Requirements for delivery of material samples, attic stock, and spare parts.
f. Requirements for demonstration and training.
g. Preparation of Contractor's punch list.
h. Procedures for processing Applications for Payment at Substantial Completion and for final payment.
i. Submittal procedures.
j. Responsibility for removing temporary facilities and controls.
4. Minutes: Contractor will record and distribute meeting minutes.
D. Progress Meetings: Conduct progress meetings at weekly intervals.
1. Coordinate dates of meetings with preparation of payment requests.
2. Attendees: In addition to representatives of Owner, Contractor, and other entities concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented at these meetings. All participants at the meeting shall be familiar with Project and authorized to conclude matters relating to the Work.
3. Agenda: Review and correct or approve minutes of previous progress meeting. Review other items of significance that could affect progress. Include topics for discussion as appropriate to status of Project.
a. Contractor's Construction Schedule: Review progress since the last meeting.
Determine whether each activity is on time, ahead of schedule, or behind schedule, in relation to Contractor's construction schedule. Determine how construction behind schedule will be expedited; secure commitments from parties involved to do so. Discuss whether schedule revisions are required to ensure that current and subsequent activities will be completed within the Contract Time.
1) Review schedule for next period.
b. Review present and future needs of each entity present, including the following:
1) Interface requirements.
2) Sequence of operations.
3) Status of submittals.
4) Deliveries.
5) Access.
6) Site utilization.
7) Temporary facilities and controls.
8) Progress cleaning.
9) Quality and work standards.
10) Status of correction of deficient items.
11) Field observations.
12) Status of RFIs.
13) Status of proposal requests.
14) Pending changes.
15) Status of Change Orders.
16) Pending claims and disputes.
17) Documentation of information for payment requests.
PROJECT MANAGEMENT AND COORDINATION 013100 - 6
4. Minutes: Contractor will record and distribute the meeting minutes to each party present and to parties requiring information.
a. Schedule Updating: Revise Contractor's construction schedule after each progress meeting where revisions to the schedule have been made or recognized.
Issue revised schedule concurrently with the report of each meeting.
PART 2 - PRODUCTS (Not Used)
END OF SECTION 013100
CONTRACTOR NAME
CONTRACTOR ADDRESS
REQUEST FOR INTERPRETATION
PROJECT: Oregon Youth Authority MYCF Valley Cottage Renovations RFI NO.:
CONTRACTOR: DATE:
DOCUMENT REFERENCE:
DESCRIPTION:
REQUEST:
REPLY REQUIRED BY: SIGNED:
REPLY:
SIGNED: DATE:
SAFETY AND SECURITY REQUIREMENTS 013150 - 1
SECTION 013150 - SAFETY AND SECURITY REQUIREMENTS
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes administrative provisions for coordinating safety and security operations on Project including, but not limited to, the following:
1. Owner's safety and security requirements.
2. Administrative and supervisory personnel.
1.2 SAFETY AND SECURITY REQUIREMENTS
A. All Contractor and subcontractor personnel shall wear OSHA approved high visibility vests at all times. This is to ensure not only the normal safety protocol and procedure but also to allow OYA staff to quickly differentiate Contractor staff from residents and other visitors.
B. Contractor shall provide the following personnel and level of service for implementation of Owner's Safety and Security Requirements:
1. Provide a dedicated Security Staff (SS) person, who is dedicated to observing, recording, and enforcing all Owner Safety and Security Requirements for construction personnel.
a. SS personnel shall be provided by a third party, security personnel provider and paid for by the Contractor. The security personnel shall not be an employee of the Contractor.
b. The Owner will review and approve the person(s) assigned to these positions.
2. Position No. 1:
a. SS shall be present during all times when construction personnel are on site inside of the secure perimeter. The SS Position No. 1 shall be on site whenever the Contractor is performing construction activities including but not limited to material movement or temporary facilities construction and shall monitor and enforce clean up, tool control activities, unlocking and locking vehicles and storage facilities inside the secure perimeter, and end of work period jobsite sweeps.
3. Position No. 2:
a. SS shall be present during all times when material hauling is occurring at the access gate. SS shall be responsible for opening and securing the gate and monitoring access activities. SS shall be responsible for monitoring and enforcing cleanup and end of work jobsite sweeps for the entire route used for hauling materials between the work areas and the gate.
b. SS Position No. 2 is not required to be on site if there are no hauling activities in progress.
4. SS Position No. 1 or Position No. 2 are not required to be present for activities that include only jobsite inspections or meetings where no tools are used and no construction activity is being performed. SS Position No. 1 or Position No. 2 are not required to be
SAFETY AND SECURITY REQUIREMENTS 013150 - 2
present for activities relating to any portion of the work which is outside of the secure perimeter.
5. SS shall provide a daily report, via e-mail, to Owner's designated representative and/or Owner's Site Security personnel.
6. SS shall coordinate with and report to Owner's designated Site Security personnel for all movement activities through secure site and building perimeters.
7. SS shall monitor any temporary facilities such as temporary stairs, lifts or other, to ensure that no access is provided to residents.
8. SS shall observe and record when any temporary facility that is to remain in place (such as a temporary scaffold) is secured at the end of each construction activity period.
9. If SS encounters any construction activity that is out of compliance with Owner's Safety and Security Specifications or the requirements of this Section, the SS shall have the authority, under the guidance of the Contractor, to immediately advise and address construction personnel on the nature of the issue and require construction personnel to take immediate steps to bring procedures into compliance.
10. SS will coordinate directly with Owner's Site Security personnel for the following:
a. Contractor and material movements through site or building secure perimeter.
b. End of work period jobsite sweeps.
c. End of work period Confirmation that all Construction personnel have exited the site.
d. Any safety and security specification violation that is not immediately brought into compliance.
PART 2 - PRODUCTS (Not Used)
END OF SECTION 013150
CONSTRUCTION PROGRESS DOCUMENTATION 013200 - 1
SECTION 013200 - CONSTRUCTION PROGRESS DOCUMENTATION
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes administrative and procedural requirements for documenting the progress of construction during performance of the Work, including the following:
1. Startup construction schedule.
2. Contractor's construction schedule.
3. Construction schedule updating.
4. Special reports.
B. Related Requirements:
1. Section 013300 "Submittal Procedures" for submitting schedules and reports.
1.2 DEFINITIONS
A. Activity: A discrete part of a project that can be identified for planning, scheduling, monitoring, and controlling the construction project. Activities included in a construction schedule consume time and resources.
1. Critical Activity: An activity on the critical path that must start and finish on the planned early start and finish times.
2. Predecessor Activity: An activity that precedes another activity in the network.
3. Successor Activity: An activity that follows another activity in the network.
B. CPM: Critical path method, which is a method of planning and scheduling a construction project where activities are arranged based on activity relationships. Network calculations determine when activities can be performed and the critical path of Project.
C. Critical Path: The longest connected chain of interdependent activities through the network schedule that establishes the minimum overall Project duration and contains no float.
D. Event: The starting or ending point of an activity.
E. Float: The measure of leeway in starting and completing an activity.
1. Float time belongs to Owner.
2. Free float is the amount of time an activity can be delayed without adversely affecting the early start of the successor activity.
3. Total float is the measure of leeway in starting or completing an activity without adversely affecting the planned Project completion date.
F. Resource Loading: The allocation of manpower and equipment necessary for the completion of an activity as scheduled.
CONSTRUCTION PROGRESS DOCUMENTATION 013200 - 2
1.3 INFORMATIONAL SUBMITTALS
A. Format for Submittals: Submit required submittals in the following format:
1. PDF electronic file.
B. Startup construction schedule.
1. Approval of startup construction schedule will not constitute approval of schedule…
This is the start of the file's text. The full file is on GovTribe.