This document provides details regarding a federal contract opportunity for improvements at the Riverside National Cemetery in Riverside, California. The Department of Veterans Affairs National Cemetery Administration will issue a solicitation on or about July 15, 2021 for project number 901-043, which involves improvements at the Riverside National Cemetery and has an acquisition value between $2,000,000 and $5,000,000. This is a 100% set-aside for Service-Disabled Veteran Owned Small Businesses. To be eligible, offerors must be verified as SDVOSBs and registered in the System for Award Management and Vendor Information Pages databases. Amendments to the solicitation will be posted on the Beta SAM.gov website. Offers are due by July 15, 2021 and must be submitted through Beta SAM.gov. The point of contact for any questions is Auvorie Benson of the Department of Veterans Affairs National Cemetery Administration.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C78621B0013 0005.docx | DOCX document | |
| RFI as of 9-23-21_(Revised).docx | DOCX document | |
| 36C78621B0013 0001.docx | DOCX document | |
| Procedure 5 Work Plan.pdf | ||
| 36C78621B0013 0004.docx | DOCX document | |
| 36C78621B0013 0003.docx | DOCX document | |
| RFI as of 9-13-21_VCI Responses.pdf | ||
| 901CM3043 Riverside NC_Amendment - 001 (GC201).pdf | ||
| Attendance Sheet 2021_08_26_15_40_08.pdf | ||
| 36C78621B0013 0002.docx | DOCX document | |
| IFB Lump Sum Division Spreadsheet.xlsx | XLSX spreadsheet | |
| 36C78621B0013_1.docx | DOCX document | |
| Wage Determination.txt | TXT text file | |
| 210727 Riverside 901CM3043 IFB Scope of Work.docx | DOCX document | |
| Attachment-_Contractor Cost Estimate Worksheet.xlsx | XLSX spreadsheet |
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Pre-Demolition Hazardous Materials Survey Report
VCI Riverside National Cemetery 22495 Van Buren Boulevard
Riverside, Riverside County, California
September 30, 2020 Terracon Project No. 60207159
Prepared for:
Vali Cooper International, LLC
Denver, Colorado
Prepared by:
Terracon Consultants, Inc.
Tustin, California
Ter racon Consul tants, Inc. 1421 Edinger Avenue, Suite C Tust in, Cal i forn ia 92780 P (949) 864-2051 F (949) 261-6110 terracon.com
September 30, 2020
Mr. Taqi Muhammad Vali Cooper International, LLC 18300 E. 71st Ave.
Denver, Colorado 80249
Telephone: (504) 378-7399 Email: taqi@valiint.com
Re: Pre-Demolition Hazardous Building Materials Consulting Services VCI Riverside National Cemetery 22495 Van Buren Boulevard Riverside, Riverside County, California Terracon Proposal No. 60207159
Dear Mr. Muhammad:
Terracon Consultants, Inc. (Terracon) is pleased to present the findings of the pre-demolition hazardous materials survey performed on August 25 – 28, 2020 at the above referenced site.
The survey was conducted in general accordance with Terracon’s Proposal Number P60207159 dated March 28, 2020 and revised August 14, 2020. It is Terracon’s understanding that Vali Cooper International, LLC is requesting this survey prior to the planned renovation of the lakes/canal, pump stations A and B and the north curb line and the demolition of the abandoned wastewater treatment plant at the referenced address in Riverside, California.
Terracon appreciates the opportunity to provide this service to Vali Cooper International, LLC.
If you have any questions regarding this report, please contact Mark Korte in our Tustin, California office at (949) 383-1977.
Sincerely, Terracon Consultants, Inc.
Danish Mansoor, CIH, CSP, CAC For Ken Pilgrim, CAC Asbestos and Industrial Hygiene Group Manager Principal sdmansoor Stamp
Ter racon Consul tants, Inc. 1421 Edinger Avenue, Suite C Tust in, Cal i forn ia 92780 P (949) 864-2051 F (949) 261-6110 terracon.com
TABLE OF CONTENTS
Page EXECUTIVE SUMMARY……………………………………………………………………....ii
1.0 INTRODUCTION
1.1 Project Objective
2.0 BUILDING DESCRIPTIONS
3.0 FIELD ACTIVITIES
3.1 Visual Assessment
3.2 Physical Assessment
3.3 Sample Collection and Analytical Results
3.4 Visual Mercury Survey
3.5 Other Hazardous Materials
4.0 REGULATORY OVERVIEW
5.0 GENERAL COMMENTS
APPENDICES
APPENDIX A ASBESTOS, LEAD AND PCB SAMPLE SUMMARY
APPENDIX B CONFIRMED ASBESTOS-CONTAINING MATERIALS
APPENDIX C ASBESTOS LABORATORY ANALYTICAL REPORTS
APPENDIX D LEAD LABORATORY ANALYTICAL REPORTS
APPENDIX E PCB LABORATORY ANALYTICAL REPORTS
APPENDIX F SAMPLE LOCATION DIAGRAMS
APPENDIX G LICENSES AND CERTIFICATIONS
Reliable ■ Responsive ■ Resourceful ii
EXECUTIVE SUMMARY
On August 25 – 28, 2020, Terracon conducted a pre-demolition hazardous materials survey of pump stations A and B, the north curb line, the north lakes/canal and the abandoned wastewater treatment plant located within the Riverside National Cemetery at 22495 Van Buren Boulevard in Riverside, California. The purpose of the survey was to identify suspect asbestos-containing material (ACM), lead-containing paints and building materials, PCB-containing materials and other potential hazards that may require removal or stabilization prior to any planned renovation and demolition activities.
Asbestos
The asbestos survey was conducted by a Certified Site Surveillance Technician (CSST) in general accordance with the sampling protocols established in Environmental Protection Agency (EPA) 40 Code of Federal Regulations (CFR) 763 and California Code of Regulations (CCR) 1529. Two-hundred eleven (211) bulk samples were collected from sixty-five (65) homogeneous areas of suspect ACM. Asbestos was confirmed in seventeen (17) of the samples collected from six (6) homogeneous areas. Please refer to Confirmed Asbestos- Containing Materials in Appendix B and Sample Location Diagrams in Appendix F for locations and approximate quantities of the confirmed ACMs.
Lead
Fourteen (14) paint chip samples were collected for purposes of compliance with the California Department of Occupational Safety and Health (Cal/OSHA) Lead Paint in Construction Standard. Based on the results of laboratory analysis, lead was detected in nine (9) of the paint chip samples collected. . Disturbance of materials containing any detectable lead must be conducted in accordance with Cal/OSHA Title 8 CCR 1532.1.
A summary of lead sample results is in Appendix A.
Polychlorinated Biphenyls (PCBs)
Three (3) samples of suspect PCB-containing sealants were collected for purposes of compliance with 40 CFR part 761. One (1) sampled contained PCBs above the laboratory method detection limit. No fluorescent light fixtures or associated ballasts were observed in the structures.
Other Hazardous Materials
No fluorescent light fixtures were observed throughout the buildings. Fluorescent light tubes contain mercury. Fluorescent tubes are regulated as universal waste.
Terracon did not observe any equipment with refrigerants.
Reliable ■ Responsive ■ Resourceful 1
PRE-DEMOLITION HAZARDOUS MATERIALS SURVEY REPORT
RIVERSIDE NATIONAL CEMETERY
22495 VAN BUREN BOULEVARD
RIVERSIDE, RIVERSIDE COUNTY, CALIFORNIA
Terracon Project No. 60207159
September 30, 2020
1.0 INTRODUCTION
Terracon Consultants, Inc. (Terracon) conducted a pre-demolition hazardous materials survey of pump stations A and B, the north curb line, the north lakes/canal and the abandoned wastewater treatment plant located within the Riverside National Cemetery at 22495 Van Buren Boulevard in Riverside, Riverside County, California. The survey and sampling activities were conducted on August 25 - 28, 2020 by a Certified Site Surveillance Technician (CSST) in general accordance with Terracon’s Proposal No. P60207159 dated March 18, 2020 and revised August 14, 2020
1.1 Project Objective
The survey objective was to evaluate accessible building materials and equipment for potential asbestos, lead and PCB content and to conduct a visual inspection for other potential environmental hazards associated with the structures.
2.0 BUILDING DESCRIPTIONS
The buildings, structures, and equipment included in the survey scope are located at 22495 Van Buren Boulevard in Riverside, Riverside County, California. This survey includes the Wastewater Treatment Plant, Pump Stations A & B, Concrete Curbs, Ponds and Canals within the property boundaries as indicated on the site plan.
The site buildings shared a common asphalt-paved parking lot, landscaped areas and utilities.
At the time of the survey, the Water Treatment Plant was abandoned with all water treatment equipment removed and the Pump Stations were operational.
Water Treatment Plant
The subject site consists of a former water treatment plant with a two-story concrete structure and basement . Interior finishes had been mostly removed, with the exception of some remaining plaster on walls. The exterior of the structure contained water basins that were empty at the time of the survey.
Pre-Demolition Hazardous Materials Survey Report Riverside National Cemetery ■ Riverside, California September 30, 2020 ■ Terracon Project No. 60207159
Reliable ■ Responsive ■ Resourceful 2
Pump Stations A and B
The subject pump stations consists of concrete pads with operating water pumps. Gunite lined ponds and canals associated with the pump stations were present. There were no interior finishes.
3.0 FIELD ACTIVITIES
The survey was conducted on August 25 – 28, 2020 by Mr. Mike Jarboe, a Certified Site Surveillance Technician (CSST) and (CDPH) Lead Inspector/Assessor. A copy of Mr. Korte’s and Mr. Jarboe’s respective licenses are attached in Appendix G. The survey was conducted consistent with the procedures outlined in our proposal dated August 14, 2020. A summary of the field activities is described below.
3.1 Visual Assessment
Asbestos
Terracon began the sampling activities with a visual assessment, identification and inventory of readily visible and accessible homogeneous areas of suspect ACM. A homogeneous area consists of building materials that appear similar throughout in terms of color and texture. The assessment included the interior, exterior, and roof of the waste water treatment plant and all accessible building/equipment materials located amongst the other subject areas. Building materials identified as glass (includes fiberglass), wood, masonry, metal, plastic were not considered suspect ACM.
Lead-Containing Materials
Terracon collected paint chip samples to determine the lead content in parts per million (ppm) of the predominant painted surfaces.
Inspection activities began with visual observations of painted surfaces to identify unique combinations of paint on building materials. A unique combination of paint consists of paint that is applied to a building material and has similar color, substrate and component.
Assessment was conducted throughout the visually accessible areas of each structure.
PCB-Containing Materials
Terracon conducted a visual inspection of building envelopes to identify sealants or caulking materials used on the exterior of the subject survey areas
September 30, 2020 ■ Terracon Project No. 60207159
Reliable ■ Responsive ■ Resourceful 3
3.2 Physical Assessment
Asbestos
A physical assessment of each homogeneous area of suspect ACM was conducted to determine the friability and condition of the material. A friable material is defined by the EPA as a material which can be crumbled, pulverized or reduced to powder by hand pressure when dry. Friability was determined via tactile assessment.
Lead Paint
A physical assessment of paint was conducted to assess the condition of the paint. Lead paint chip samples were collected to comply with Cal-OSHA regulations (Title 8 CCR 1532.1 – Lead Exposure in Construction) for the proposed demolition activities. Paint was sampled to identify potential worker exposure and potential disposal restrictions.
Other Hazardous Materials
All other potentially hazardous building materials and conditions were assessed visually.
3.3 Sample Collection and Analytical Results
Asbestos
Based on results of the visual observation, bulk samples of suspect ACM were collected in general accordance with AHERA sampling protocols. Representative samples of suspect materials were collected in each homogeneous area. Suspect ACMs were collected using wet methods, where applicable, to reduce the potential for fiber release. Samples were placed in sealable containers and labeled with unique sample numbers.
Samples of suspect ACM were delivered under chain-of-custody protocol to EMLab P&K.
Irvine, California. EMLab P&K is a laboratory accredited by the National Voluntary Laboratory Accreditation Program (NVLAP) under the National Institute of Standards and Technology (NIST) for analysis by PLM.
Two-hundred eleven (211) bulk samples were collected from sixty-five (65) homogeneous areas of suspect ACM. Asbestos was confirmed in seventeen (17) of the samples collected from six (6) homogeneous areas. Five (5) samples were subsequently analyzed by 400 point-count method. The laboratory results and chains-of-custody for the samples collected can be found in Appendix C.
Please refer to Confirmed Asbestos-Containing Materials in Appendix B and Sample Location
September 30, 2020 ■ Terracon Project No. 60207159
Reliable ■ Responsive ■ Resourceful 4
Diagrams in Appendix F for locations and approximate quantities of the confirmed ACMs.
Lead-Containing Materials
Fourteen (14) paint chip samples were collected for lead analysis. The samples were delivered under chain-of-custody to EMLab P&K. Irvine, California. The paint chip samples were analyzed by Flame Atomic Absorption spectroscopy. The sampling locations are provided in Appendix F. The lead survey sample summary can be found in Appendix A. The laboratory reports and chains of custody for the suspect lead paint samples can be found in Appendix D.
Based on the laboratory analytical results, nine (9) of the samples contained lead above the laboratory limit of detection and three (3) samples contained lead in concentrations above the California Department of Public Health (CDPH) definition of Lead-Based Paint.
The remaining samples did not contain lead above the laboratory method detection limit.
If renovation or demolition activities will impact any lead-containing materials contractors and employers are required to comply with the following regulations: 29 CFR 1926.62 and Title 8 CCR 1532.1. Construction work covered by federal and Cal/OSHA standards includes any repair or renovation activities or other activities that disturb in-place lead-containing materials.
Employers and Contractors must assure that no employee will be exposed to lead at concentrations greater than 50 micrograms per cubic meter (mg/m3) averaged over an eight-hour period without adequate protection. The Federal and California OSHA Standards also establish an action level of 30 mg/m3, which if exceeded, triggers the requirement for medical monitoring.
PCB-Containing Materials
Three (3) samples of various exterior materials were collected including exterior caulks and window putty. The materials were placed into individual plastic sampling containers and each sample was provided a discrete sample number, which was recorded on a chain of custody form. The samples were transported under chain of custody procedures to Test America in Irvine, California, for analysis. Test America is accredited by the California Department of Public Health Environmental Laboratory Accreditation Program (ELLAP) for the analysis of PCBs. Please refer to Appendix A for details on sample locations and sample results. The laboratory results and chain of custody for the suspect PCB-containing materials can be found in Appendix E.
The caulking samples were analyzed for PCB content using analytical method SW8082 with EPA approved extraction method 3546. When “<” appears in the PCB sample report, it should be interpreted as meaning concentrations were below the analytical method detection limit.
PCBs were detected above the laboratory limit of detection in one (1) of the three (3) materials sampled. No additional assessment appears warranted at this time unless
September 30, 2020 ■ Terracon Project No. 60207159
Reliable ■ Responsive ■ Resourceful 5 additional or inaccessible suspect materials are discovered during demolition work.
Fluorescent light fixtures with suspect PCB containing ballasts were not observed throughout the site buildings.
3.4 Visual Mercury Survey
A visual survey was conducted to identify mercury-containing lamps, fluorescent light tubes and other possible mercury-containing devices such as thermostats, switches, and gauges. No suspect mercury containing items were observed in the structures or site improvements within the survey scope.
3.5 Other Hazardous Materials
Equipment with refrigerants were not identified in the structures or other site improvement within the survey scope.
4.0 REGULATORY OVERVIEW
Asbestos
As a consequence of the health hazard from inhalation of asbestos fibers, a body of federal and state regulations has been developed. Federal regulations pertaining to asbestos are included in AHERA (US EPA 40 CFR 763); NESHAP (EPA 40 CFR 61); OSHA Asbestos Standards (29 CFR 1910.1001 and 29 CFR 1926.1101), and ASHARA (Asbestos School Hazard Abatement Reauthorization Act). Many states have additional requirements including state-specific licensing and certification. In California, these regulations include, but are not limited to: Cal/OSHA in Title 8, Sections 1529 and 5208 and the South Coast Air Quality Management District (SCAQMD) Rule 1403.
The federal asbestos NESHAP standard (40 CFR Part 61, Subpart M) regulates asbestos fiber emissions and asbestos waste disposal practices. NESHAP also requires the identification and classification of asbestos removal in the South Coast Air Quality Management District. Under NESHAP, ACM are classified as either friable, Category I non-friable or Category II non-friable ACM. Friable materials are those that, when dry, may be crumbled, pulverized or reduced to powder by hand pressure. Category I non-friable ACM includes packings, gaskets, resilient floor coverings and asphalt roofing products containing more than 1% asbestos. Category II non-friable ACM are any materials other than Category I materials that contain more than 1% asbestos.
Friable ACM, along with Category I and Category II non-friable ACM, which is in poor condition and has become friable or which will be subjected to drilling, sanding, grinding, cutting or abrading and which could be crushed or pulverized during anticipated renovation or demolition activities are considered regulated ACM (RACM).
September 30, 2020 ■ Terracon Project No. 60207159
Reliable ■ Responsive ■ Resourceful 6
Building materials confirmed to be ACM through the collection of bulk sampling and subsequent laboratory analysis, or presumed ACM, must be removed prior to intentional disturbance during planned renovation/demolition activities. Asbestos abatement must be conducted by Cal/OSHA-accredited asbestos abatement contractors. Third-party air monitoring is recommended during the abatement activities.
Cal/OSHA requires that only properly licensed and certified asbestos abatement contractors are allowed to remove ACM. As per NESHAP, all RACM shall be removed from a facility being demolished or renovated before any non-burning demolition or renovation begins that would break up, dislodge, or similarly disturb the material or preclude access to the material for subsequent removal. According to SCAQMD if more than 100 square feet of ACM is to be stripped, removed, dislodged, cut, drilled, or similarly disturbed, or for any demolition, the asbestos abatement contractor or facility owner must submit an Asbestos Notification of Demolition and Renovation form to SCAQMD along with the appropriate fees within at least 10 working days prior to the scheduled asbestos removal activity or demolition start date.
The federal OSHA Asbestos standard for construction (29 CFR 1926.1101) and the Cal/OSHA asbestos standard for general industry and the construction industry (CCR Title 8, Sections 5208 and 1529, respectively) regulate workplace exposure to asbestos. Both the federal OSHA and Cal/OSHA standards require that employee exposure to airborne asbestos fibers be maintained below 0.1 asbestos fibers per cubic centimeter of air (0.1 f/cc) as an eight-hour time weighted average. The federal OSHA and Cal/OSHA standards classifies construction and maintenance activities which could disturb ACM and specifies work practices and precautions which employers must follow when engaging in each class of regulated work.
However, workers who deliberately disturb any amount of asbestos should have pertinent training and wear proper personal protective equipment according to federal and state regulatory requirements (i.e., Cal/OSHA 8 CCR 1529 (g) (1) through (9) for Class I, II and III work).
Asbestos-containing construction materials (ACCM) is a term developed by Cal/OSHA out of concern for building materials used inside and outside a building that contain less than 1% asbestos. The definition of ACCM includes any manufactured building material that has more than one-tenth of 1% (>0.1%) asbestos content. The SCAQMD requires point counting of friable samples of ACM at concentrations of less than 10% to determine more accurately the content of asbestos and proper classification of the material for proper abatement and disposal requirements. Alternatively, materials may be presumed as ACMs. If the material is less than one tenth of 1%, the material is not regulated by the EPA however Cal/OSHA worker protection regulations apply if any asbestos is detected.
joel Highlight joel Highlight joel Highlight
September 30, 2020 ■ Terracon Project No. 60207159
Reliable ■ Responsive ■ Resourceful 7
Lead
The Resource Conservation and Recovery Act (RCRA) gave the USEPA authority to regulate the waste status of demolition and renovation debris, including lead-containing materials.
Specific notification and testing requirements must be addressed prior to transporting, treating, storing, or disposing of hazardous wastes. Lead-containing wastes are considered hazardous waste under RCRA if Toxicity Characteristic Leaching Procedure (TCLP) results exceed 5 milligrams per liter (mg/L). EPA exempts from most RCRA requirements those generators whose combined hazardous waste generation is less than 100 kilograms (kg) per month.
Detectable lead quantities may constitute a lead dust hazard during renovation/demolition activities. Personnel performing renovation/demolition activities that may disturb painted components with concentrations of lead above the designated analytical detection limit should comply with all current OSHA regulations in order to minimize employee exposure. OSHA regulates construction activities that disturb lead-containing material regardless of the concentration. Currently, any proposed renovation/demolition is subject to the OSHA regulations (29 CFR 1926.62 – Lead Exposure in Construction).
In California, the lead standard was adopted by Cal/OSHA as Title 8 CCR, Section 1532.1 (Occupational Lead Poisoning Prevention Program). The California Department of Public Health also regulates accreditations, certifications and work practices for activities involving lead-containing materials under Title 17 CCR. The federal and Cal/OSHA regulations define specific training requirements, engineering controls and working practices for construction personnel subject to this standard. Occupational exposure to lead occurring in the course of construction work, including maintenance activities, painting, alteration and repairs is subject to the OSHA Lead Exposure in Construction standard.
Contractors and employers are required to comply with 29 CFR 1926.62 and Title 8 CCR
1532.1. Construction work covered by federal and Cal/OSHA standards includes any repair or renovation activities or other activities that disturb in-place lead-containing materials.
Employers must assure that no employee will be exposed to lead at concentrations greater than 50 micrograms per cubic meter (mg/m3) averaged over an eight-hour period without adequate protection. The Federal and California OSHA Standards also establish an action level of 30 mg/m3, which if exceeded, triggers the requirement for medical monitoring.
PCBs
Polychlorinated Biphenyls (PCBs) belong to a broad family of man-made organic chemicals knowns as chlorinated hydrocarbons. PCBs were domestically manufactured from 1929 until banned from use in 1979. Their consistency ranges from thin, light colored liquids to black, waxy solids. PCBs have been demonstrated to cause a variety of adverse health effect and have been shown to cause cancer in animal studies.
joel Highlight
September 30, 2020 ■ Terracon Project No. 60207159
Reliable ■ Responsive ■ Resourceful 8
PCBs are found in building materials such window and exterior panel caulking, paints, mastics and any materials where maintaining elasticity over a prolonged period is required. However, PCBs are not limited to building materials with the characteristics stated above.
Refrigerants/Coolants
The refrigerants servicing the mechanical equipment may contain chlorofluorocarbon (CFC) or hydrochlorofluorocarbon (HCFC) refrigerants. Recovered refrigerants should be sent to an EPA-certified refrigerant reclaimer or destroyed by facilities that accept these substances.
Currently the EPA does not require technician certification (EPA Section 608 certification) in order to service stationary refrigeration and air-conditioning systems containing CFC/HCFCs.
However, the EPA plans to propose extending the technician certification requirement to cover the use and purchase of CFC/HCFCs.
5.0 GENERAL COMMENTS
Should suspect materials, other than those which were identified during this survey, be uncovered prior to, or during, planned demolition activities, those materials should be assumed asbestos, lead and PCB-containing until sampling and analysis is performed. Work should be conducted in accordance with applicable provisions of Cal/OSHA and federal standards.
This hazardous materials survey was conducted in a manner consistent with the level of care and skill ordinarily exercised by members of the profession currently practicing under similar conditions in the same locale. The results, findings, conclusions and recommendations expressed in this report are based on conditions observed during our of the subject structures, equipment and site improvements. The information contained in this report is relevant to the date on which this survey was performed and should not be relied upon to represent conditions at a later date. This report has been prepared on behalf of and exclusively for use by Vali Cooper International, LLC or specific application to their project as discussed. This report is not a biddable document. Contractors or consultants reviewing this report must draw their own conclusions regarding further investigation or remediation deemed necessary. No warranty, express or implied is made.
APPENDIX A
ASBESTOS, LEAD AND PCB SURVEY SAMPLE SUMMARY
HA Sample No. Description Sample Location Result
CA1-01 Window Putty Main Building First Floor ND
CA1-02 Window Putty Main Building First Floor 0.25
CA1-03 Window Putty Main Building Second Floor <0.25
HP7-04 Plaster (only 6'' High From Floor) Main Building Second Floor ND
HP7-05 Plaster (only 6'' High From Floor) Main Building Second Floor ND
HP7-06 Plaster (only 6'' High From Floor) Main Building First Floor ND
MS5-07 Barrier Paper Behind Plaster Main Building Second Floor ND
MS5-08 Barrier Paper Behind Plaster Main Building First Floor ND
MS5-09 Barrier Paper Behind Plaster Main Building First Floor ND
MS5-10 Filler Top of Roof Access Main Building Roof at Roof Access 2 % CH
MS5-11 Filler Top of Roof Access Main Building Roof at Roof Access 2 % CH
MS5-12 Filler Top of Roof Access Main Building Roof at Roof Access 2 % CH
MA5-13 Concrete Northeast Basin ND
MA5-14 Concrete Southeast Basin ND
MA5-15 Concrete Northwest Basin ND
MA5-16 Concrete Main Building Second Floor ND
MA5-17 Concrete Main Building Basement ND
MA5-18 Concrete Southwest East of Ramp ND
MA5-19 Concrete Center Basin ND
MA5-20 Concrete Ramp On Ramp North ND
MA5-21 Concrete Ramp On Ramp Center ND
MA5-22 Concrete Ramp On Ramp South ND
MA5-23 Stucco Debris in Basins Center Basin Center <0.25
MA5-24 Stucco Debris in Basins South of Northeast Basin <0.25
MA5-25 Stucco Debris in Basins Center Basin East <0.25
MS5-26
Water Proofing Behind Texture Coat (Top 6'' of
Basins and Bottom 4' of NE,NW,SE, and Center Basins
Southwest Small Basin ND
MS5-27
Water Proofing Behind Texture Coat (Top 6'' of
Basins and Bottom 4' of NE,NW,SE, and Center Basins
Northeast Basin- Southwest Corner ND
MS5-28
Water Proofing Behind Texture Coat (Top 6'' of
Basins and Bottom 4' of NE,NW,SE, and Center Basins
Southeast Basin- Southside ND
APPENDIX A
22495 Van Buren Boulevard Riverside, California
ASBESTOS SURVEY SAMPLE LOCATION SUMMARY
Water Treatment Plant
MS5-29 Texture Coating on Concrete Center Basin- East Side ND
MS5-30 Texture Coating on Concrete Northeast Basin- South ND
MS5-31 Texture Coating on Concrete Southeast Basin- North ND
MS5-32 Texture Coating on Concrete Northwest Basin- East ND
MS5-33 Texture Coating on Concrete Southwest Basin ND
MS5-34 Texture Coating on Concrete Northeast Basin- North ND
MS5-35 Texture Coating on Concrete Center Basin ND
CP2-36 4' Cement/Transite Pipe Debris in Southwest Basin (4'' pipe, pipe in pieces) Southwest Basin 15% CH
3% CR
CP2-37 4' Cement/Transite Pipe Debris in Southwest Basin (4'' pipe, pipe in pieces) Southwest Basin 15% CH
3% CR
CP2-38 4' Cement/Transite Pipe Debris in Southwest Basin (4'' pipe, pipe in pieces) Southwest Basin 15% CH
3% CR
MS5-39 Thick Texture Coat on Concrete Wall Between Northeast and Northwest Basins in Walkway Between Northwest and Northeast Basins ND
MS5-40 Thick Texture Coat on Concrete Wall Between Northeast and Northwest Basins in Walkway Between Northwest and Northeast Basins ND
MS5-41 Thick Texture Coat on Concrete Wall Between Northeast and Northwest Basins in Walkway Between Northwest and Northeast Basins ND
MS5-42 Wall Seam Mastic at Base of Exterior Wall and concrete Floor Main Building Southeast 2% CH
MS5-43 Wall Seam Mastic at Base of Exterior Wall and concrete Floor Main Building South 2% CH
MS5-44 Wall Seam Mastic at Base of Exterior Wall and concrete Floor Main Building Northeast 2% CH
MS5-45 Black Coating Inside Exhaust Vents First Floor Exhaust Vents ND
MS5-46 Black Coating Inside Exhaust Vents First Floor Exhaust Vents ND
MS5-47 Black Coating Inside Exhaust Vents First Floor Exhaust Vents ND
PM5-48
Unknown Gaskets Under 5-Gallon Metal
Containers on Top of Center Basins Bolted Down
Center Basin on Top ND
PM5-49
Unknown Gaskets Under 5-Gallon Metal
Containers on Top of Center Basins Bolted Down
Center Basin on Top ND
PM5-50
Unknown Gaskets Under 5-Gallon Metal
Containers on Top of Center Basins Bolted Down
Center Basin on Top ND
MS5-51 Black/Gray Sealant Behind Metal Top of Basin Walls Northeast Basin ND
MS5-52 Black/Gray Sealant Behind Metal Top of Basin Walls Northeast Basin ND
MS5-53 Black/Gray Sealant Behind Metal Top of Basin Walls Northeast Basin ND
PI5-54 Black Coating on Pipes Southeast Basin Northeast Side ND
PI5-55 Black Coating on Pipes Southeast Basin Northeast Side ND
PI5-56 Black Coating on Pipes Southeast Basin Northeast Side ND
MS5-57 Black Mastic on Floor Seams Southeast Basin ND
MS5-58 Black Mastic on Floor Seams Southeast Basin ND
MS5-59 Black Mastic on Floor Seams Southeast Basin ND
MS5-60 Black/Gray Mastic on 30' Blades and Center Mixer Northeast Basin ND
MS5-61 Black/Gray Mastic on 30' Blades and Center Mixer Northeast Basin ND
MS5-62 Black/Gray Mastic on 30' Blades and Center Mixer Northwest Basin ND
MS5-63 White Debris in Pipe (in wall) Northwest Basin ND
MS5-64 White Debris in Pipe (in wall) Northwest Basin ND
MS5-65 White Debris in Pipe (in wall) Northwest Basin ND
PI5-66 Pipe Wrap Block Center Basin ND
PI5-67 Pipe Wrap Block Center Basin ND
PI5-68 Pipe Wrap Block Center Basin ND
PI5-69 Block and Mortar Exterior East Wall ND
PI5-70 Block and Mortar Exterior East Wall ND
PI5-71 Block and Mortar Exterior East Wall ND
MS5-72 Black Tar on Concrete Floor Northwest Basin ND
MS5-73 Black Tar on Concrete Floor Northwest Basin ND
MS5-74 Black Tar on Concrete Floor Northwest Basin ND
PI5-75 White Coating on Pipe Northwest Basin ND
PI5-76 White Coating on Pipe Northwest Basin ND
PI5-77 White Coating on Pipe Northwest Basin ND
PM5-78 12''x12'' Gaskets on Pipes Southwest by Ramp ND
PM5-79 12''x12'' Gaskets on Pipes Southwest by Ramp ND
PM5-80 12''x12'' Gaskets on Pipes Southwest by Ramp ND
PM5-81 8'' Gasket on Pipes Southwest Basin ND
PM5-82 8'' Gasket on Pipes Southwest Basin ND
PM5-83 8'' Gasket on Pipes Southwest Basin ND
PM5-84 16'' Gasket in Basement on Pipes Basement ND
PM5-85 16'' Gasket in Basement on Pipes Basement ND
PM5-86 16'' Gasket in Basement on Pipes Basement ND
PM5-87 24'' Gasket in Basement on Pipes Basement ND
PM5-88 24'' Gasket in Basement on Pipes Basement ND
PM5-89 24'' Gasket in Basement on Pipes Basement ND
PM5-90 12''x24'' Gasket on Pipes Basement ND
PM5-91 12''x24'' Gasket on Pipes Basement ND
PM5-92 12''x24'' Gasket on Pipes Basement ND
PM5-93 Black and White Gaskets on Blades Northwest Basin ND
PM5-94 Black and White Gaskets on Blades Northwest Basin ND
PM5-95 Black and White Gaskets on Blades Northwest Basin ND
MS5-96 Black and Gray Pipe Wrap Buried Cement Enclosure ND
MS5-97 Black and Gray Pipe Wrap Buried Cement Enclosure ND
MS5-98 Black and Gray Pipe Wrap Buried Cement Enclosure ND
MA5-99 Concrete Buried Cement Enclosure ND
MA5-100 Concrete Buried Cement Enclosure ND
MA5-101 Concrete Buried Cement Enclosure ND
MA5-01 Concrete/Gunite Northeast Pond- South ND
MA5-02 Concrete/Gunite Northeast Pond- Northeast ND
MA5-03 Concrete/Gunite Northeast Pond- West ND
MA5-04 Concrete/Gunite Northwest Pond- West ND
MA5-05 Concrete/Gunite Northwest Pond- Northeast ND
MA5-06 Concrete/Gunite Northwest Pond- Northwest ND
MA5-07 Concrete/Gunite Northern Canal- West ND
MA5-08 Concrete/Gunite Northern Canal- Center ND
MA5-09 Concrete/Gunite Northern Canal- East ND
MS5-10 Pond Black Liner Northeast Pond ND
MS5-11 Pond Black Liner Northeast Pond ND
MS5-12 Pond Black Liner Northeast Pond ND
MS5-13 Pond Black Liner Northwest Pond ND
MS5-14 Pond Black Liner Northwest Pond ND
MS5-15 Pond Black Liner Northwest Pond ND
MS5-16 Pond Black Liner Under Concrete/Gunite Northern Canal ND
MS5-17 Pond Black Liner Under Concrete/Gunite Northern Canal ND
MS5-18 Pond Black Liner Under Concrete/Gunite Northern Canal ND
MS5-19 Pond Black Liner Lower Pond - Northeast ND
MS5-20 Pond Black Liner Lower Pond - Northeast ND
MS5-21 Pond Black Liner Lower Pond - Northwest ND
MA5-22 Concrete/Gunite Lower Pond - North ND
MA5-23 Concrete/Gunite Lower Pond - Northeast ND
MA5-24 Concrete/Gunite Lower Pond - Southwest ND
MA5-01 Concrete Curb on Road Near Pump Station A Curb ND
MA5-02 Concrete Curb on Road Near Pump Station A Curb ND
MA5-03 Concrete Curb on Road Near Pump Station A Curb ND
PM-01 6" Gaskets on Pipe Valves On Water Tank #7 ND
PM-02 6" Gaskets on Pipe Valves On Water Tank #5 ND
PM-03 6" Gaskets on Pipe Valves On Water Tank #3 ND
Pump Station #A
Northern Ponds and Canals
North Curb Line
PM-04 Gaskets on High Thrust Motor High Thrust Motor #1 ND
PM-05 Gaskets on High Thrust Motor High Thrust Motor #2 ND
PM-06 Gaskets on High Thrust Motor High Thrust Motor #3 ND
PM-07 Gasket on 12" Pipe, Front of High Thrust 1-3 Front of High Thrust #1 ND
PM-08 Gasket on 12" Pipe, Front of High Thrust 1-4 Front of High Thrust #2 ND
PM-09 Gasket on 12" Pipe, Front of High Thrust 1-5 Front of High Thrust #3 ND
MS5-10 14" Gasket on Pipe/Valve Center - North 40% CH
MS5-11 14" Gasket on Pipe/Valve Center - Center 40% CH
MS5-12 14" Gasket on Pipe/Valve Center - South 40% CH
MA5-13 24" x 24" Gasket on South of High Thrust Motors South of High Thrust Motors ND
MA5-14 24" x 24" Gasket on South of High Thrust Motors South of High Thrust Motors ND
MA5-15 24" x 24" Gasket on South of High Thrust Motors South of High Thrust Motors ND
CA5-16 Caulking under High Voltage # 1-4 High Voltage #1 ND
CA5-17 Caulking under High Voltage # 1-4 High Voltage #2 ND
CA5-18 Caulking under High Voltage # 1-4 High Voltage #3 ND
PM1-19 8" Gaskets on Pipes/Valves South ND
PM1-20 8" Gaskets on Pipes/Valves South ND
PM1-21 8" Gaskets on Pipes/Valves South ND
MA5-22 Concrete Pad #1 Northwest ND
MA5-23 Concrete Pad #1 Southwest ND
MA5-24 Concrete Pad #1 Southeast ND
MA5-25 Concrete Pad #2 South ND
MA5-26 Concrete Pad #2 East ND
MA5-27 Concrete Pad #2 Northwest ND
PM1-28 10" x 10" Square Gasket on High Thrust Motor High Thrust #1 ND
PM1-29 10" x 10" Square Gasket on High Thrust Motor High Thrust #2 ND
PM1-30 10" x 10" Square Gasket on High Thrust Motor High Thrust #3 ND
MA5-31 Concrete Pad #3 North ND
MA5-32 Concrete Pad #3 Northeast ND
MA5-33 Concrete Pad #3 Northwest ND
MA5-34 Asphalt South ND
MA5-35 Asphalt Northeast ND
MA5-36 Asphalt North ND
MA5-37 Block and Mortar Wall Northeast Behing Pad #1 ND
MA5-38 Block and Mortar Wall Northeast Behing Pad #2 ND
MA5-39 Block and Mortar Wall Northeast Behing Pad #3 ND
MA5-40 Concrete Wall Northwest Corner ND
MA5-41 Concrete Wall Northwest Corner ND
MA5-42 Concrete Wall Northwest Corner ND
PM1-01 10" Gasket Front of Engine Thrust Motors Front of Motor Thrust #1 ND
PM1-02 10" Gasket Front of Engine Thrust Motors Front of Motor Thrust #2 ND
PM1-03 10" Gasket Front of Engine Thrust Motors Front of Motor Thrust #3 ND
PM1-04 10" x 10" Gasket on Engine Thrust Motor Engine Motor Thrust #1 ND
PM1-05 10" x 10" Gasket on Engine Thrust Motor Engine Motor Thrust #2 ND
PM1-06 10" x 10" Gasket on Engine Thrust Motor Engine Motor Thrust #3 ND
PM1-07 6" Gaskets on Yardney Tanks Front of High Thrust #1 ND
PM1-08 6" Gaskets on Yardney Tanks Front of High Thrust #2 ND
PM1-09 6" Gaskets on Yardney Tanks Front of High Thrust #3 ND
PM1-10 18" Gaskets on Pipes Center ND
PM1-11 18" Gaskets on Pipes Center ND
PM1-12 18" Gaskets on Pipes Center ND
CA5-13 Caulking under High Voltage on Concrete East Pad A ND
CA5-14 Caulking under High Voltage on Concrete East Pad B ND
CA5-15 Caulking under High Voltage on Concrete East Pad B ND
MA5-16 Concrete Pad Pad #3 - South ND
MA5-17 Concrete Pad Pad #3 - North ND
MA5-18 Concrete Pad Pad #3 - Northwest ND
MA5-19 Concrete Pad A-C Pad A ND
MA5-20 Concrete Pad A-C Pad B ND
MA5-21 Concrete Pad A-C Pad C ND
MA5-22 Concrete Wall - 3' - 6' Tall North ND
MA5-23 Concrete Wall - 3' - 6' Tall East ND
MA5-24 Concrete Wall - 3' - 6' Tall South ND
MA5-25 Concrete Pad #2 Pad #2 - Northeast ND
MA5-26 Concrete Pad #2 Pad #2 - East ND
MA5-27 Concrete Pad #2 Pad #2 - West ND
MA5-28 Concrete Supports 2' x 2' x 2' Northeast ND
MA5-29 Concrete Supports 2' x 2' x 2' Center ND
MA5-30 Concrete Supports 2' x 2' x 2' South ND
Pump Station #B sdmansoor Line
MS5-31 Asphalt North ND
MS5-32 Asphalt Center ND
MS5-33 Asphalt Southwest ND
Legend:
ND-None Detected
Sample No. Description Sample Location Result (ppm)
Pb-01 Gray/Black Paint on Concrete Basement Ceiling 3,600
Pb-02 Tan Paint on Metal Northwest Basin on Mixer 88
Pb-03 Silver Paint on Metal 5 Gallon Metal Buckets 9,700
Pb-04 Tan Paint on Metal 2'x2' Valves in Basement 2,900
Pb-05 Tan Paint on Concrete Exterior Concrete Wall East of Northeast Basin 110
Pb-06 White Paint on Concrete Center Basin Wall 65
Pb-07 Multi-Color Paint on Concrete Basement 5,000
Pb-08 Tan Paint on Wood Second Floor Roll Up Door Frame 53,000
Pb-01 Light Green Paint on Metal West Tanks <39 ppm
Pb-02 Gray/Black Paint on Metal Engine Thrust Motor <39 ppm
Pb-03 Gray Paint on Metal Pipe West 63 ppm
Pb-01 Light Green Paint on Metal West Tanks <39 ppm
Pb-02 Gray/Black Paint on Metal Engine Thrust Motor <39 ppm
Pb-03 Gray Paint on Metal Pipe West 63 ppm
<-below the limit of detection
APPENDIX A
22495 Van Buren Boulevard Riverside, California
LEAD SURVEY SAMPLE SUMMARY
Water Treatment Plant
Pump Station #A
Pump Station #B
Sample No. Description Sample Location Result (mg/Kg)
PCB-01 Window Putty Exterior Window <0.69
PCB-01 Gray Caulking High Voltage Container 1.4
PCB-01 Gray Caulking Concrete Pad 1A/1B <0.74
APPENDIX A
22495 Van Buren Boulevard Riverside, California
PCB SAMPLE SUMMARY
<LOD - Less than Laboratory Limit of Detection
Water Treatment Plant
Pump Station #B
APPENDIX B
CONFIRMED ASBESTOS-CONTAINING MATERIALS SUMMARY
HA No. Description Material Location Percent/Type Asbestos NESHAP Classification Condition Estimated Quantity*
1 Window Putty Main Building Windows .25% CH NA Significantly Damaged 26 Windows
26 SF
4 Filler Top of Roof Access Main Building at Roof Hatch 2% CH Cat. II Good 12 SF
7 Stucco Debris Basins <.25% CH NA Significantly Damaged 900 SF
4' Cement/Transite Pipe Debris in Southwest
Basin (4'' pipe, pipe in pieces)
Southwest Basin 15% CH 3% CR Cat. II Significantly Damaged 15 LF
Wall Seam Mastic at Base of Exterior Wall and Concrete Floor
Main Building - Exterior Walls / Concrete Slab 2% CH Cat. II Good 225 LF, 100 SF
1 14" (approx.) Gasket on Pipe/Valve Center Pipe/Valve 40% CH Cat. I Good 10 Gaskets
10 SF
*Quantities listed are approximate for the total square footage of the building. Total quantities of materials to be abated is to be determined by the contractor. CH=Chrysotile RACM = Regulated Asbestos Containing Material, Cat. I = Category I Non-friable asbestos containing material, Cat. II – Category II Non-friable asbestos containing material, NA = Not Applicable
APPENDIX B
22495 Van Buren Boulevard Riverside, California
CONFIRMED ASBESTOS-CONTAINING MATERIALS
Water Treatment Plant
APPENDIX C
ASBESTOS LABORATORY ANALYTICAL REPORTS
Approved by:
Approved Signatory Danny Li
Report for:
Mark Korte, Danish Mansoor Terracon Consultants, Inc. - Tustin, CA 1421 Edinger Ave suite C Tustin, CA 92780
Regarding: Project: 60207159; Riverside National Cementary, Water Treatment Plant
EML ID: 2470629
All samples were received in acceptable condition unless noted in the Report Comments portion in the body of the report. The results relate only to the samples as received. The results include an inherent uncertainty of measurement associated with estimating percentages by polarized light microscopy. Measurement uncertainty data for sample results with >1% asbestos concentration can be provided when requested.
Eurofins EMLab P&K ("the Company") shall have no liability to the client or the client's customer with respect to decisions or recommendations made, actions taken or courses of conduct implemented by either the client or the client's customer as a result of or based upon the Test Results. In no event shall the Company be liable to the client with respect to the Test Results except for the Company's own willful misconduct or gross negligence nor shall the Company be liable for incidental or consequential damages or lost profits or revenues to the fullest extent such liability may be disclaimed by law, even if the Company has been advised of the possibility of such damages, lost profits or lost revenues. In no event shall the Company's liability with respect to the Test Results exceed the amount paid to the Company by the client therefor.
Dates of Analysis:
Asbestos PLM: 09-01-2020
Service SOPs: Asbestos PLM (EPA 40CFR App E to Sub E of Part 763 & EPA METHOD 600/R-93-116, SOP EM-AS-S-1267) NVLAP Lab Code 200757-0
EMLab ID: 2470629, Page 1 of 26EMLab P&K, LLC
Eurofins EMLab P&K 17461 Derian Ave, Suite 100, Irvine, CA 92614
(866) 888-6653 Fax (623) 780-7695 www.emlab.comClient: Terracon Consultants, Inc. - Tustin, CA C/O: Mark Korte, Danish Mansoor Re: 60207159; Riverside National Cementary, Water Treatment Plant
Date of Sampling: 08-27-2020 Date of Receipt: 08-28-2020 Date of Report: 09-01-2020
ASBESTOS PLM REPORT
Total Samples Submitted: 101 Total Samples Analyzed: 101
Total Samples with Layer Asbestos Content > 1%: 9
Location: 01-CA7-01, Window putty-main Bldg.-1st floor Lab ID-Version‡: 11777499-1
Sample Layers Asbestos Content White Window Putty ND
Sample Composite Homogeneity: Good
Location: 01-CA7-02, Window putty-main Bldg.-1st floor Lab ID-Version‡: 11777500-1
Sample Layers Asbestos Content White Window Putty < 1% Chrysotile
Sample Composite Homogeneity: Good
Location: 01-CA7-03, Window putty-main Bldg.-2nd floor Lab ID-Version‡: 11777501-1
Sample Layers Asbestos Content White Window Putty < 1% Chrysotile
Sample Composite Homogeneity: Good
Location: 02-HP7-04, Plaster (only 6" high from floor)-main Bldg. 2nd floor Lab ID-Version‡: 11777502-1
Sample Layers Asbestos Content Gray Plaster ND
Sample Composite Homogeneity: Good
Location: 02-HP7-05, Plaster (only 6" high from floor)-main Bldg. 2nd floor Lab ID-Version‡: 11777503-1
Sample Layers Asbestos Content Gray Plaster ND
Sample Composite Homogeneity: Good
EMLab ID: 2470629, Page 2 of 26EMLab P&K, LLC
The test report shall not be reproduced except in full, without written approval of the laboratory. The report must not be used by the client to claim product certification, approval, or endorsement by any agency of the federal government. Eurofins EMLab P&K reserves the right to dispose of all samples after a period of thirty (30) days, according to all state and federal guidelines, unless otherwise specified.
Inhomogeneous samples are separated into homogeneous subsamples and analyzed individually. ND means no fibers were detected. When detected, the minimum detection and reporting limit is less than 1% unless point counting is performed. Floor tile samples may contain large amounts of interference material and it is recommended that the sample be analyzed by gravimetric point count analysis to lower the detection limit and to aid in asbestos identification.
‡ A "Version" indicated by -"x" after the Lab ID# with a value greater than 1 indicates a sample with amended data. The revision number is reflected by the value of "x".
(866) 888-6653 Fax (623) 780-7695 www.emlab.comClient: Terracon Consultants, Inc. - Tustin, CA C/O: Mark Korte, Danish Mansoor Re: 60207159; Riverside National Cementary, Water Treatment Plant
Date of Sampling: 08-27-2020 Date of Receipt: 08-28-2020 Date of Report: 09-01-2020
ASBESTOS PLM REPORT
Location: 02-HP7-06, Plaster (only 6" high from floor)-main Bldg. 1st floor Lab ID-Version‡: 11777504-1
Sample Layers Asbestos Content Gray Plaster ND
Sample Composite Homogeneity: Good
Location: 03-MS5-07, Barrier paper bentino plaster-2nd floor Lab ID-Version‡: 11777505-1
Sample Layers Asbestos Content Brown Vapor Barrier ND
Composite Non-Asbestos Content: 60% Cellulose Sample Composite Homogeneity: Good
Location: 03-MS5-08, Barrier paper bentino plaster-1st floor Lab ID-Version‡: 11777506-1
Sample Layers Asbestos Content Brown Vapor Barrier ND
Composite Non-Asbestos Content: 60% Cellulose Sample Composite Homogeneity: Good
Location: 03-MS5-09, Barrier paper bentino plaster-1st floor Lab ID-Version‡: 11777507-1
Sample Layers Asbestos Content Brown Vapor Barrier ND
Composite Non-Asbestos Content: 60% Cellulose Sample Composite Homogeneity: Good
EMLab ID: 2470629, Page 3 of 26EMLab P&K, LLC
The test report shall not be reproduced except in full, without written approval of the laboratory. The report must not be used by the client to claim product certification, approval, or endorsement by any agency of the federal government. Eurofins EMLab P&K reserves the right to dispose of all samples after a period of thirty (30) days, according to all state and federal guidelines, unless otherwise specified.
Inhomogeneous samples are separated into homogeneous subsamples and analyzed individually. ND means no fibers were detected. When detected, the minimum detection and reporting limit is less than 1% unless point counting is performed. Floor tile samples may contain large amounts of interference material and it is recommended that the sample be analyzed by gravimetric point count analysis to lower the detection limit and to aid in asbestos identification.
‡ A "Version" indicated by -"x" after the Lab ID# with a value greater than 1 indicates a sample with amended data. The revision number is
(866) 888-6653 Fax (623) 780-7695 www.emlab.comClient: Terracon Consultants, Inc. - Tustin, CA C/O: Mark Korte, Danish Mansoor Re: 60207159; Riverside National Cementary, Water Treatment Plant
Date of Sampling: 08-27-2020 Date of Receipt: 08-28-2020 Date of Report: 09-01-2020
ASBESTOS PLM REPORT
Location: 04-MS5-10, Filler top of roof access-main Bldg. roof at top Lab ID-Version‡: 11777508-1
Sample Layers Asbestos Content Brown Cementitious Material 2% Chrysotile
Sample Composite Homogeneity: Good
Location: 04-MS5-11, Filler top of roof access-main Bldg. roof at top Lab ID-Version‡: 11777509-1
Sample Layers Asbestos Content Brown Cementitious Material 2% Chrysotile
Sample Composite Homogeneity: Good
Location: 04-MS5-12, Filler top of roof access-main Bldg. roof at top Lab ID-Version‡: 11777510-1
Sample Layers Asbestos Content Brown Cementitious Material 2% Chrysotile
Sample Composite Homogeneity: Good
Location: 05-MA5-13, Concrete-NE basin Lab ID-Version‡: 11777511-1
Sample Layers Asbestos Content Gray Concrete ND
Sample Composite Homogeneity: Good
EMLab ID: 2470629, Page 4 of 26EMLab P&K, LLC
The test report shall not be reproduced except in full, without written approval of the laboratory. The report must not be used by the client to claim product certification, approval, or endorsement by any agency of the federal government. Eurofins EMLab P&K reserves the right to dispose of all samples after a period of thirty (30) days, according to all state and federal guidelines, unless otherwise specified.
Inhomogeneous samples are separated into homogeneous subsamples and analyzed individually. ND means no fibers were detected. When detected, the minimum detection and reporting limit is less than 1% unless point counting is performed. Floor tile samples may contain large amounts of interference material and it is recommended that the sample be analyzed by gravimetric point count analysis to lower the detection limit and to aid in asbestos identification.
‡ A "Version" indicated by -"x" after the Lab ID# with a value greater than 1 indicates a sample with amended data. The revision number is
(866) 888-6653 Fax (623) 780-7695 www.emlab.comClient: Terracon Consultants, Inc. - Tustin, CA C/O: Mark Korte, Danish Mansoor Re: 60207159; Riverside National Cementary, Water Treatment Plant
Date of Sampling: 08-27-2020 Date of Receipt: 08-28-2020 Date of Report: 09-01-2020
ASBESTOS PLM REPORT
Location: 05-MA5-14, Concrete-SE basin Lab ID-Version‡: 11777512-1
Sample Layers Asbestos Content Gray Concrete ND
Sample Composite Homogeneity: Good
Location: 05-MA5-15, Concrete-NW basin Lab ID-Version‡: 11777513-1
Sample Layers Asbestos Content Gray Concrete ND
Sample Composite Homogeneity: Good
Location: 05-MA5-16, Concrete-main Bldg. 2nd floor Lab ID-Version‡: 11777514-1
Sample Layers Asbestos Content Gray Concrete ND
Sample Composite Homogeneity: Good
Location: 05-MA5-17, Concrete-main Bldg. basement Lab ID-Version‡: 11777515-1
Sample Layers Asbestos Content Gray Concrete ND
Sample Composite Homogeneity: Good
EMLab ID: 2470629, Page 5 of 26EMLab P&K, LLC
The test report shall not be reproduced except in full, without written approval of the laboratory. The report must not be used by the client to claim product certification, approval, or endorsement by any agency of the federal government. Eurofins EMLab P&K reserves the right to dispose of all samples after a period of thirty (30) days, according to all state and federal guidelines, unless otherwise specified.
Inhomogeneous samples are separated into homogeneous subsamples and analyzed individually. ND means no fibers were detected. When detected, the minimum detection and reporting limit is less than 1% unless point counting is performed. Floor tile samples may contain large amounts of interference material and it is recommended that the sample be analyzed by gravimetric point count analysis to lower the detection limit and to aid in asbestos identification.
‡ A "Version" indicated by -"x" after the Lab ID# with a value greater than 1 indicates a sample with amended data. The revision number is
(866) 888-6653 Fax (623) 780-7695 www.emlab.comClient: Terracon Consultants, Inc.
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .