This document provides details for an upcoming Invitation for Bid for Project 612-501 to construct a new Dermatology Outpatient Service Building. The contractor will be responsible for providing all labor, materials, permits, licenses, and supervision to construct the new building according to provided specifications and drawings. The place of performance is VA Northern California Healthcare System in Mather, CA. The period of performance is 500 days from issuance of the Notice to Proceed. The solicitation will be issued on or around July 20, 2019 and will be posted on FBO.gov along with any amendments. This project is set aside for Service-Disabled Veteran-Owned Small Businesses and the NAICS code is 236220 for Commercial and Institutional Building Construction with a small business size standard of $36.5 million. The magnitude of construction is between $5-10 million.

36C26118B0618 36C26118B0618_2.docx

View the file

Other files

File Type Posted
36C26118B0618-0004001.docx DOCX document
36C26118B0618-0004000.docx DOCX document
36C26118B0618-0003000.docx DOCX document
36C26118B0618-0003001.pdf PDF
36C26118B0618-0003002.pdf PDF
36C26118B0618-0002000.docx DOCX document
36C26118B0618-0001000.docx DOCX document
36C26118B0618-0001001.pdf PDF
36C26118B0618-008.pdf PDF
36C26118B0618-012.pdf PDF
36C26118B0618-017.pdf PDF
36C26118B0618-007.pdf PDF
36C26118B0618-015.pdf PDF
36C26118B0618-003.pdf PDF
36C26118B0618-013.pdf PDF
36C26118B0618-010.pdf PDF
36C26118B0618-011.pdf PDF
36C26118B0618-014.pdf PDF
36C26118B0618-004.pdf PDF
36C26118B0618-005.pdf PDF
36C26118B0618-006.pdf PDF
36C26118B0618-016.pdf PDF
36C26118B0618-009.pdf PDF
36C26118B0618-001.docx DOCX document
Show all 24

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

36C26118B0618

1. SOLICITATION NUMBER

2. TYPE OF SOLICITATION

3. DATE ISSUED

PAGE OF PAGES

4. CONTRACT NUMBER

5. REQUISITION/PURCHASE REQUEST NUMBER

6. PROJECT NUMBER

7. ISSUED BY

CODE

8. ADDRESS OFFER TO

a. NAME

b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE

DOCUMENTS (

Title, identifying number, date) 12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

12b. CALENDAR DAYS

13. ADDITIONAL SOLICITATION REQUIREMENTS:

STANDARD FORM 1442 (REV. 8/2014)

STANDARD FORM 1442

Prescribed by GSA-FAR (48 CFR) 52.236-1(d)

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

SOLICITATION

SOLICITATION

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

9. FOR INFORMATION

CALL:

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

SEALED BID (IFB)

NEGOTIATED (RFP)

11. The Contractor shall begin performance within ____________ calendar days and complete it within calendar days after receiving award, notice to proceed. This performance period is mandatory negotiable. (See _____________________________).

YES

NO

a.

Sealed offers in original and ___________________copies to perform the work required are due at the place specified in Item 8 by _____________ (hour) local time _____________________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, the date and time offers are due.

b.

An offer guarantee is, is not required.

c.

All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

d.

Offers providing less than _______________________ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

of 74 36C26118B0618 X 08-06-2019 36C26118B0618 612-19-1-1112-0004 612-501 Department of Veterans Affairs VA Sierra Pacific Network (VISN 21) VA Northern California HealthCare System 5342 Dudley Blvd., Bldg 98 McClellan CA 95652-1012 Department of Veterans Affairs VA Northern California Healthcare System Attn: Robert Parke 3230 Peacekeeper Way, Bldg. 209 McClellan CA 95652-1012 Robert Parke 916-923-4922 Project: 612-501, Dermatology Outpatient Services Building NAICS Code: 236220, Commercial and Institutional Building Construction Small Business Size Standard: $36.5 million IAW VAAR 836.204 - the magnitude of construction is between $5,000,000 and $10,000,000

Project Description: The Contractor shall furnish all labor, materials, equipment, project management, supervision, and transportation to Construct Dermatology Outpatient Service Building, including general construction, site work, modular building demolition, site improvements, site utilities, concrete foundations, structural steel framing, exterior building envelope systems, prefabricated steel stairs, elevator system, interior finishes, and all other associated civil, mechanical, plumbing, electrical, fire protection, and telecommunication work as shown on the drawings and as specified. All work is to be completed in accordance with the Statement of Work, drawings, specifications and attachments.

Place of Performance: VA Northern California Healthcare System (VANCHCS) at 10535 Hospital Way, Mather, CA 95655

Note #1 to bidders: A pre-bid conference and site-visit shall be held on August 1 , 2019 at :00AM PDT in Building 650 3rd Floor Engineering lobby located at 10535 Hospital Way, Mather, CA 95655.

Note #2 to bidders: This Procurement is a 100% Total Service Disabled Veteran Owned Small Business Set-Aside (SDVOSB) per PL 109-461.

Note #3 to bidders: IAW FAR 14, Sealed Bids. Award will be base on price and price related factors.

Note #4 to bidders: All Request for Information (RFI's) shall be submitted to the Contract Specialist at robert.parke2@va.gov , in writing, by August 28th, 2019 @ 3:00 PM PDT.

Note #5 to bidders: Bid Bonds, Payment Bonds and Performance Bonds shall be required under this solicitation and any resultant contract.

Note #6 to bidders: Guaranteed Period Services are applicable to this solicitation see Specification Sections 14 21 00, 21 05 11, 23 09 23, and 28 31 00.

Note #7 to bidders: The current Wage Rate Requirement Decision is included in the solicitation "CA20190007"

X X 52.211-10 X

10:00 AM PDT

09-0 -2019 X

14. NAME AND ADDRESS OF OFFEROR

15. TELEPHONE NUMBER

16. REMITTANCE ADDRESS

CODE

FACILITY CODE

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this offer is accepted by the Government in writing within __________ calendar days after the date offers are due.

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

AMENDMENT

NUMBER

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER 20b. SIGNATURE 20c. OFFER DATE

21. ITEMS ACCEPTED:

22. AMOUNT

23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

ITEM

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c 41 U.S.C. 3304(a) (

26. ADMINISTERED BY

27. PAYMENT WILL BE MADE BY

PHONE:

FAX:

28. NEGOTIATED AGREEMENT

29. AWARD

Your Contractor agrees offer on this solicitation is hereby accepted as to the items listed. This to furnish and deliver all items or perform all work requirements identified award consummates the contract, which consists of (a) the Government on this form and any continuation sheets for the consideration stated in solicitation and your offer, and (b) this contract award. No further cont-this contract. The rights and obligations of the parties to this contract ractual document is necessary.

shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31a. NAME OF CONTRACTING OFFICER

TO SIGN

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. AWARD DATE

BY

OFFER

AWARD

STANDARD FORM 1442 (REV. 8/2014) BACK

(Include ZIP Code) (Include area code) (Include only if different than Item 14.)

(Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each) (Type or print) (4 copies unless otherwise specified) (Type or print) (Type or print) (Contractor is required to sign this document and return _______ copies to issuing office.)

(Contractor is not required to sign this document.)

(Must be fully completed by offeror) (To be completed by Government)

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

Department of Veterans Affairs VA Sierra Pacific Network (VISN 21) VA Northern California HealthCare System 5342 Dudley Blvd., Bldg. 98 McClellan CA 95652-1012 Department of Veterans Affairs FMS-VA-2(101) Financial Services Center PO Box 149971 Austin TX 78714-9971 Brett Vegeto Contracting Officer

Table of Contents

PART I - THE SCHEDULE1
SECTION A - SOLICITATION/CONTRACT FORM1
A.1 SF 1442 SOLICITATION, OFFER, AND AWARD (Construction, Alteration, or Repair)1
A.2 SF 1442 SOLICITATION, OFFER, AND AWARD (CONSTRUCTION, ALTERATION, OR REPAIR)– BACK2
INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS6
2.1 BID INSTRUCTIONS6
2.2 STATEMENT OF WORK12
2.3 BID SCHEDULE15
2.4 PRICING BREAKDOWN17
PROPOSAL REQUEST FOR INFORMATION (RFI) FORM20
2.5 52.216-1 TYPE OF CONTRACT (APR 1984)21
2.6 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014)21
2.7 52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)21
2.8 52.228-1 BID GUARANTEE (SEP 1996)22
2.9 52.233-2 SERVICE OF PROTEST (SEP 2006)23
2.10 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB 1995)23
2.11 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)24
2.12 VAAR 852.211-72 TECHNICAL INDUSTRY STANDARDS (NOV 2018)25
2.13 VAAR 852.228-72 ASSISTING SERVICE-DISABLED VETERAN-OWNED AND VETERAN-OWNED SMALL BUSINESSES IN OBTAINING BONDS (DEC 2009)25
2.14 VAAR 852.233-70 PROTEST CONTENT/ALTERNATIVE DISPUTE RESOLUTION (OCT 2018)25
2.15 VAAR 852.233-71 ALTERNATE PROTEST PROCEDURE (OCT 2018)26
REPRESENTATIONS AND CERTIFICATIONS27
3.1 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (OCT 2018)27
3.2 52.209-7 INFORMATION REGARDING RESPONSIBILITY MATTERS (OCT 2018)30
3.3 52.209-13 VIOLATION OF ARMS CONTROLS TREATIES OR AGREEMENTS—CERTIFICATION (JUN 2018)32
GENERAL CONDITIONS34
4.1 52.204-19 INCORPORATION BY REFERENCE OF REPRESENTATIONS AND CERTIFICATIONS (DEC 2014)34
4.2 52.204-23 PROHIBITION ON CONTRACTING FOR HARDWARE, SOFTWARE, AND SERVICES DEVELOPED OR PROVIDED BY KASPERSKY LAB AND OTHER COVERED ENTITIES (JUL 2018)34
4.3 52.209-9 UPDATES OF PUBLICLY AVAILABLE INFORMATION REGARDING RESPONSIBILITY MATTERS (OCT 2018)35
4.4 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984) ALTERNATE I (APR 1984)36
4.5 52.219-28 POST-AWARD SMALL BUSINESS PROGRAM REREPRESENTATION (JUL 2013)37
4.6 52.222-35 EQUAL OPPORTUNITY FOR VETERANS (OCT 2015)38
4.7 52.222-40 NOTIFICATION OF EMPLOYEE RIGHTS UNDER THE NATIONAL LABOR RELATIONS ACT (DEC 2010)38
4.8 52.222-42 STATEMENT OF EQUIVALENT RATES FOR FEDERAL HIRES (MAY 2014)40
4.9 52.223-9 ESTIMATE OF PERCENTAGE OF RECOVERED MATERIAL CONTENT FOR EPS-DESIGNATED ITEMS (MAY 2008)40
4.10 52.223-20 AEROSOLS (JUN 2016)41
4.11 52.223-21 FOAMS (JUN 2016)42
4.12 52.225-11 BUY AMERICAN—CONSTRUCTION MATERIALS UNDER TRADE AGREEMENTS (OCT 2016) ALTERNATE I (MAY 2014)42
4.13 52.225-12 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS UNDER TRADE AGREEMENTS (MAY 2014) ALTERNATE II (JUN 2009)47
4.14 SUPPLEMENTAL INSURANCE REQUIREMENTS48
4.15 52.236-4 PHYSICAL DATA (APR 1984)49
4.16 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)49
4.17 VAAR 852.203-70 COMMERCIAL ADVERTISING (MAY 2018)52
4.18 VAAR 852.219-10 VA NOTICE OF TOTAL SERVICE-DISABLED VETERAN-OWNED SMALL BUSINESS SET-ASIDE (JUL 2016)(DEVIATION)53
4.19 VAAR 852.219-74 LIMITATIONS ON SUBCONTRACTING—MONITORING AND COMPLIANCE (JUL 2018)54
4.20 VAAR 852.228-70 BOND PREMIUM ADJUSTMENT (JAN 2008)54
4.21 VAAR 852.232-70 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS (WITHOUT NAS–CPM) (NOV 2018) (ALTERNATE I)55
4.22 VAAR 852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (NOV 2018)58
4.23 VAAR 852.236-71 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (APR 2019)59
4.24 VAAR 852.236-79 CONTRACTOR PRODUCTION REPORT (APR 2019)60
4.25 VAAR 852.236-80 SUBCONTRACTS AND WORK COORDINATION (APR 2019) ALTERNATE I (APR 2019)60
4.26 VAAR 852.236-88 CONTRACT CHANGES--SUPPLEMENT (JUL 2002)61
4.27 VAAR 852.236-90 RESTRICTION ON SUBMISSION AND USE OF EQUAL PRODUCTS (APR 2019)63
4.28 VAAR 852.242-70 GOVERNMENT CONSTRUCTION CONTRACT ADMINISTRATION (APR 2019)64
4.29 VAAR 852.246-75 WARRANTY OF CONSTRUCTION—GUARANTEE PERIOD SERVICES (OCT 2018)65
4.30 VAAR 852.270-1 REPRESENTATIVES OF CONTRACTING OFFICERS (JAN 2008)65
4.31 MANDATORY WRITTEN DISCLOSURES65
4.32 IT CONTRACT SECURITY65
ADDITIONAL ATTACHMENTS76
5.1 Full Dermatology Specifications - See attached Document76
5.2 C27 - 02-12-18 - ARCHITECTURAL - MATHER - DERMATOLOGY - 10TH SUBMITTAL_Part1 - See attached Document76
5.3 C27 - 02-12-18 - ARCHITECTURAL - MATHER - DERMATOLOGY - 10TH SUBMITTAL_Part2 - See attached Document76
5.4 C27 - 02-12-18 - ARCHITECTURAL - MATHER - DERMATOLOGY - 10TH SUBMITTAL_Part3 - See attached Document76
5.5 C27 - 02-12-18 - PLUMBING - MATHER – DERMATOLOGY - See attached Document76
5.6 C27 - 02-12-18 - MECHANICAL - MATHER – DERMATOLOGY - See attached Document76
5.7 C27 - 02-12-18 - ELECTRICAL - MATHER - DERMATOLOGY - 10TH SUBMITTAL - See attached Document76
5.8 C27 - 02-12-18 - FIRE - MATHER - DERMATOLOGY - 10TH SUBMITTAL - See attached Document76
5.9 C27 - 02-12-18 - CIVIL - MATHER - DERMATOLOGY - 10TH SUBMITTAL - See attached Document76
5.10 C27 - 02-12-18 - STRUCTURAL - MATHER - DERMATOLOGY - 10TH SUBMITTAL - See attached Document76
5.11 C27 - 02-12-18 - TELECOM - MATHER - DERMATOLOGY - 10TH SUBMITTAL2 - See attached Document76
5.12 3373222_000_GeoRpt_121216_FNL - See attached Document76
5.13 VHA DIRECTIVE 7715 - See attached Document76
5.14 VHA Directive 1192 Influenza - See attached Document76
5.15 P07 - Wage Determination - CA20190007 - See attached Document76

INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS

2.1 BID INSTRUCTIONS

SUBMISSION OF BIDS:

The bidder shall submit the following documents in response to this Invitation for Bids:

(a) One (1) fully completed and signed Standard Form 1442 with blocks 14 – 20 completed, acknowledgment of all amendments either via entering data in block 19 of the SF1442 OR by completing blocks 15 a, b, and c of the Amendment(s) (SF30’s) and returning with bid.

(b) One (1) fully completed Pricing Breakdown Sheet (provided with the Solicitation)

(c) One (1) fully completed Price Schedule (provided with the Solicitation)

(d) One (1) original completed/signed SF24 Bid Bond with Raised Seals, and Power of Attorney as required.

(e) Documentation of Safety & Environmental Record

(f) Documentation of Experience Modification Rate (EMR) *Note: Bidders are responsible for insuring and verifying their bid and all required bid documents are received at the public bid opening address stated below by the date and time specified in block 13A of the SF 1442 Solicitation (subject to amendment).

*Note: See VAAR 852.236-90 for instructions on brand name bid submission requirements.

*Note: Bidders are cautioned to carefully review System for Award Management in regards to Representations and Certifications. See FAR 52.204-7, 52.204-8, 52.209-7 & 52.209-9 for specific instruction as needed.

*Note: Bidders are cautioned to carefully review VAAR Clause 852.219-10 – VA Notice of Total Service-Disabled Veteran-Owned Small Business Set-Aside and the contents there-of.

*Note: Electronic bids of any form (to include: facsimile, email, etc.) will not be accepted.

BIDS AND BONDS ARE TO BE DELIVERED OR HAND CARRIED TO:

Department of Veterans Affairs Network Contracting Office 21 (NCO 21) Attn.: Robert Parke, Contracting Officer 3230 Peacekeeper Way, Building 209 McClellan, CA 95652

Delivery Packages and envelops must have the following on the outside of the package:

Company Name Construct Dermatology Outpatient Services Building

IFB – 36C26118B0618

INFORMATION FOR BIDDERS:

-Bids received after bid opening date and time will be rejected.

-Any exception to the terms and conditions of the IFB will result in a nonresponsive bid.

-Bidders must acknowledge (in writing only) amendments to this solicitation, otherwise a bid shall be determined nonresponsive.

CONTRACT TYPE:

-The awarded contract will be a firm fixed price (FFP) contract.

-This solicitation is a total set-aside for Service-Disabled Veteran-Owned Small Business (SDVOSB) per FAR 19 and IAW with PL 109-461.

PROSPECTIVE CONTRACTORS’ RESPONSIBILITY: Purchases shall be made from, and contracts shall be awarded to, responsible prospective contactors only. The presumed winning bidder must be determined as “Responsible” by the Contracting Officer in accordance with FAR Part 9, Contractor Qualifications. To aid in making this determination, bidders shall provide, at bid-opening all documents as required under “Submission of Bids” above.

These documents will be reviewed promptly after bid-opening. This information, along with other information obtained from Government systems, such as the OSHA and EPA online inspection history databases will be used to make the Determination of Responsibility. Failure to affirm being within the guidelines below or submit this information may result in a determination of Non-Responsibility and make the bid ineligible for award. The Contracting Officer will obtain additional information as needed and specified in FAR 9.105-1 to make the Determination of Responsibility, to include, but not limited to the Federal Awardee Performance and Integrity Information System (FAPIIS), Excluded Parties List System (EPLS), and Past Performance Information Retrieval System (PPIRS).

PER VHA DIRECTIVE 7715 (06 April 2017): SAFETY & ENVIRONMENTAL RECORD AND EXPERIENCE MODIFICATION RATE (EMR): To be eligible for consideration and award, the contractor shall have no more than three serious, or one repeat, or one willful OSHA or EPA violation(s) in the past 3 years and have an EMR of equal to or less than 1.0.

All Bidders shall submit the following information pertaining to their past Safety & Environmental Record and EMR with their bid, on provided certification form.

1. SAFETY & ENVIRONMENTAL RECORD: A self-certification that the bidder has no more than three (3) serious, or one (1) repeat or one (1) willful OSHA or any EPA violation(s) in the past three years.

1. EMR: All bidders shall submit information regarding their current EMR. This information shall be obtained from the bidder’s insurance carrier and be furnished on the insurance carrier’s letterhead. Bidder will also enter the information on provided form.

BID OPENING:

**Note to bidders: Bids are due Friday, September 6th, 2019 at 10:00 am PDT at the address specified in Block 8 of SF1442.

Public Bid opening will be Friday, September 6th, 2019 at 10:05 am in Building 209, Main Conference 3230 Peacekeeper Way, Building 209, McClellan, CA 95652. (Subject to Amendment) **Solicitation number and title must be written on the outside of the delivery package.

**Note to bidders: At the time of Bid Opening, an apparent low, responsive, responsible bidder will be selected; however, actual low bidder chosen for award shall be subject to verification and confirmation of required, submitted bid documents.

PRE-BID SITE VISIT: Bidders are urged and expected to inspect the site where services are to be performed and to satisfy themselves regarding all general and local conditions that may affect the cost of performing construction services. In no event shall failure to inspect the site constitute grounds for a claim after contract award.

See Provision 52.236-27 for specific information regarding the project pre-bid site visit.

This pre-bid site visit will be the only opportunity for potential bidders to visit the site.

All potential bidders, subcontractors, and suppliers are strongly encouraged to attend this pre-bid site visit.

REQUEST FOR INFORMATION (RFI): To obtain clarifications and/or additional information concerning the contract requirements or specifications, submit a written RFI utilizing the RFI Form included in this IFB, which is to be sent via email to robert.parke2@va.gov. See RFI Form for specifics.

RFI’s will be responded to as necessary in amendment format which will be posted on FBO. Deadline for submission of RFIs for this IFB is August 28th, 2019 at 3:00PM PDT. No questions will be answered after this date/time unless determined to be in the best interest of the Government as determined by the Contracting Officer. Telephone request for information will not be accepted or returned.

PLANS/SPECIFICATIONS/DRAWINGS: Drawings and specifications are attached in electronic format to this solicitation. Bidders are responsible for downloading and printing their own bid sets. The VA will not provide hard copies of the drawings and specifications to any bidder. Contractors are responsible for ensuring that any construction document package used for bidding or construction is complete and up-to-date.

TRAINING: All employees of the general contractor and subcontractors shall have the 10-hour OSHA certified construction safety course and/or other relevant competency training, as determined by the COR with input from the ICRA (Infection Control Risk Assessment) team. The General Contractor’s Competent Person/Superintendent shall have completed the 30-hour OSHA certified construction safety course. Documentation of training shall be submitted to the Contracting Officer for review and approval prior to any work being performed. No ID badge will be issued to an employee who does not provide this documentation. There shall be no exceptions to this requirement.

PREPARATION OF BIDS: The Federal Government will NOT pay for any costs incurred in preparation and submission of bids.

PRIVACY AND CONFIDENTIALITY: Contractors to the Department of Veteran Affairs may be unintentionally exposed to sensitive information. Information may be overheard, seen on documents or electronic devices, or observed that could potentially violate the privacy and confidentiality of our veterans, employees, volunteers, and their families. Regulations such as, but not limited to the Health Insurance Portability and Accountability Act of 1996 (HIPAA), Freedom of Information Act (FOIA) and Privacy Act of 1974 have been enacted to protect sensitive information from being improperly disclosed. Information should not be divulged or released to anyone unless specifically authorized by this contract or its’ attached documents in accordance with the contracted services. Failure to comply with applicable statutes and regulation can result in the termination of this contract and civil and criminal penalties, including fines and imprisonment. All suspected or actual breeches of privacy and confidentiality should be reported immediately to the Contracting Officer, Contracting Officer’s Representative (COR) or the Facility Privacy Officer.

The C&A requirements do not apply and a Security Accreditation Package is not required. If the contractor opts to use a computer or computer system for processing contract documents, the requirements of FIPS 140-2 for encryption of contract documents must be met.

SYSTEM FOR AWARD MANAGEMENT (SAM): Federal Acquisition Regulations require that federal contractors register in the System for Award Management (SAM) database at http://www.sam.gov and enter all mandatory information into the system. Bids shall be deemed non-responsive and rejected if the contractor is not registered in SAM prior to BID submission. Bidders are strongly encouraged to ensure they have an active DUNS number and are registered in SAM prior to submitting their bid.

ADDITIONAL VETBIZ INFORMATION:

(a) Eligibility of SDVOSBs continues to be governed by the Small Business Administration regulations, 13 CFR subparts 125.8 through 125.13, as well as the FAR, except where expressly directed otherwise by the VAAR, and 38 CFR verification regulations for SDVOSBs.

(b) At the time of submission of offer, the offeror must represent to the contracting officer that it is a—

(1) SDVOSB concern

(2) Small business concern under the North American Industry Classification System (NAICS) code assigned to the acquisition; and

(3) Verified for eligibility in the VIP database.

(c) A joint venture may be considered an SDVOSB or VOSB concern if

(1) At least one member of the joint venture is an SDVOSB or VOSB concern, and makes the representations in paragraph (b) of this section;

(2) Each other concern is small under the size standard corresponding to the NAICS code assigned to the procurement;

(3) The joint venture meets the requirements of paragraph 7 of the size standard explanation of affiliates in FAR 19.101; and

(4) The joint venture meets the requirements of 13 CFR 125.15(b), modified to include Veteran-owned small businesses where this CFR section refers to SDVOSB concerns.

(d) Any SDVOSB or VOSB concern (nonmanufacturer) must meet the requirements in FAR 19.102(f) to receive a benefit under this program.

JOINT VENTURES: See 13 C.F.R. § 121.103

(e) Affiliation based on joint ventures: A joint venture is an association of individuals and/or concerns with interests in any degree or proportion consorting to engage in and carry out no more than three specific or limited-purpose business ventures for joint profit over a two year period, for which purpose they combine their efforts, property, money, skill, or knowledge, but not on a continuing or permanent basis for conducting business generally.

This means that a specific joint venture entity generally may not be awarded more than three contracts over a two year period, starting from the date of the award of the first contract, without the partners to the joint venture being deemed affiliated for all purposes. Once a joint venture receives one contract, SBA will determine compliance with the three awards in two years rule for future awards as of the date of initial offer including price.

As such, an individual joint venture may be awarded more than three contracts without SBA finding general affiliation between the joint venture partners where the joint venture had received two or fewer contracts as of the date it submitted one or more additional offers which thereafter result in one or more additional contract awards. The same two (or more) entities may create additional joint ventures, and each new joint venture entity may be awarded up to three contracts in accordance with this section. At some point, however, such a longstanding inter-relationship or contractual dependence between the same joint venture partners will lead to a finding of general affiliation between and among them.

For purposes of this provision and in order to facilitate tracking of the number of contract awards made to a joint venture, a joint venture must be in writing and must do business under its own name, and it may (but need not) be in the form of a separate legal entity, and if it is a separate legal entity it may (but need not) be populated (i.e., have its own separate employees). SBA may also determine that the relationship between a prime contractor and its subcontractor is a joint venture, and that affiliation between the two exists, pursuant to paragraph (e)(4) of this section.

NOTICE TO PROCEED (NTP): A notice to proceed shall be issued after award at the beginning of each phase and represent a fully executed contract. The NTP date and time “to be determined” after award to a successful bidder. Each subsequent phase NTP shall not be issued until the preceding Phase has been issued a beneficial occupancy. Primary factor in determination to issue Phase I NTP shall be the Prime Contractor’s submission of, and the Government’s review and approval of both Payment and Performance Bonds, both of which are enforceable legal documents.

SOLICITATION AUTHORITY: This Invitation For Bid (IFB) is conducted under FAR Part 14 - Sealed Bidding, where firms are bidders and shall submit bids. References to RFP and Bidder’s, in technical specification sections and technical drawings are strictly coincidental and strictly for purposes of administrative convenience and efficiency. The Contracting Officer exercises final authority over all aspects of this IFB and any resultant contract.

SOLICITATION CLAUSES AND PROVISIONS : Please note that this IFB, and any resultant contract, and all clauses and provisions located there, supersede and contain final authority. Those clauses and provisions that may be referenced in IFB technical specification sections and technical drawings are strictly coincidental and for purposes of administrative convenience and efficiency.

SOLICITATION DEFINITIONS: Throughout this IFB, and any resultant contract, the terms Contracting Officer's Representative (COR), Project Engineer (PE), Resident Engineer (RE), and Project Manager (PM), all denote the same engineering official and may be used equally and interchangeably as described by the Contracting Officer (CO).

BRAND NAME OR EQUAL: The IFB may include the salient characteristics of the “or equal” aspect for determination of what is equal to any cited brand name. See FAR 52.211-6 for “brand name or equal” information. This is an extremely long, detailed, and comprehensive IFB, including all specifications and drawings. Please note that, wherever a brand name is cited, contractor shall ensure, in any resultant contract, that any equal has the salient characteristics of the brand name. Lack of confirmation shall be grounds for Government inspection at any time and Government direction for replacement of materials or equipment by the Contractor at no increase in contract price or time.

WORK DAYS AND HOURS

Normal work days and hours for this project range from 06:00 AM – 6:30 PM Monday - Friday. Access to the work site may be restricted to these hours and days. Work during other than normal work days and hours may be required, but days and hours must still be coordinated in advance with the Contracting Officer through the COR.

FEDERAL HOLIDAYS ARE:

New Year's Day Labor Day Martin Luther King Day Columbus Day Presidents' Day Veterans' Day Memorial Day Thanksgiving Independence Day Christmas

2.2 STATEMENT OF WORK

Department of Veterans Affairs (VA) VA Northern California Health Care System (NCHCS) Project Number: 612-501

SCOPE OF WORK

1.1 GENERAL

1.2 INTRODUCTION

A. Building title shall be Dermatology Outpatient Service, building 644. The site is located at the VA Mather campus, 10535 Hospital Way, Mather, California 95655. The location of the building design shall be on the West side of the campus just across from building 646, and will include the demolition of parking spots for the construction of the new building. Specifications shall govern the drawings language. The building design shall include a new 14,110 square feet, add a net of 10 parking stalls for a 2 story Outpatient Dermatology Service building. The buildings occupancy will be B/New Business and the building type will be II B/II (000). The duration for construction is 500 days. The projects construction shall be phased and completed with a 90-day delay before demolition of modular buildings 801, 805, 806 and 807 as well as any associated foundation, walkways, ramps, and utilities for the buildings. Coordination with the local utility company SMUD is required and must be completed by the Contractor.

B. Visits to the site by bidders may be made only by appointment with the Contracting Officer.

C. Offices of K. F. Davis Engineering, Inc., as Architect-Engineers, will render certain technical services during construction. Such services shall be considered as advisory to the Government and shall not be construed as expressing or implying a contractual act of the Government without affirmations by the Contracting Officer or his/her duly authorized representative.

D. Before placement and installation of work subject to tests by testing laboratory retained by the contractor, the contractor shall notify the COR in sufficient time to allow COR witnessing of testing laboratory personnel proper taking and testing of specimens and field inspection. Such prior notice shall be no less than three work days unless otherwise designated by the COR.

E. All employees of general contractor and subcontractors shall comply with VA security management program and obtain permission of the VA Police, be identified by project and employer, and restricted from unauthorized access.

1.3 STATEMENT OF BID ITEM(S)

A. Item I, GENERAL CONSTRCUTION: Work includes general construction, site work demolition, modular building demolition, site improvements, site utilities, concrete foundations, structural steel framing, exterior building envelope systems, prefabricated steel stairs, elevator system, interior finishes, and all other associated civil, mechanical, plumbing electrical, fire protection, and telecommunication work as shown on the drawings and as specified.

B. Bid Deduct 1: DELETE ALL WORK ASSOCIATED WITH BUILDING A PARKING LOT IN SITE AREA 2.

C. Bid Deduct 2: DELETE ALL WORK ASSOCIATED WITH DEMOLITION OF MODULAR BUILDINGS AND RELCOTION OF SMOKING SHELTER IN SITE AREA 2.

D. Bid Deduct 3: DELETE ALL WORK ASSOCIATED WITH BUILDING A NEW PAVED DRIVEWAY IN SITE AREA 3.

E. Bid Deduct 4: DELETE ALL WORK ASSOCIATED WITH DEMOLITION OF MODULAR BUILDINGS IN SITE AREA 3.

F. BID DEDUCT NO. 5: DELETE ALL ROOF EQUIPMENT SCREENS AND ASSOCIATED STRUCTURAL SUPPORTS.

G. BID DEDUCT NO. 6: DELETE ALL WORK ASSOCIATED WITH INDEPENDENT THIRD PARTY COMMISSIONING.

H. BID DEDUCT NO. 7: DELETE ALL INTERIOR SIGNAGE.

I. BID DEDUCT NO. 8: DELETE CMU WALL IN ITS ENTIRETY AND REPLACE WITH ENGINEERED 10 FOOT HIGH CHAIN LINK FENCE MOUNTED ON CONCRETE FOOTINGS. THE (2) CHAIN LINK GATES SHOWN ON THE DRAWINGS SHALL REMAIN.

J. BID DEDUCT NO. 9: DELETE PORTION BUILDING ON SECOND FLOOR CONSISTING OF ROOMS 2A05, 2A05A, 2A05B, 2A06, 2AC2D, AND 2AC2E AND REPLACE WITH ROOF DECK INSULATION, EPDM ROOFING, AND DRAINS SURROUNDED BY 4 FT. HIGH PARAPET (ELECTRICAL ROOM 2AC1A, IT ROOM 2A08 TO REMAIN). PROVIDE EXTERIOR WALL AND 3 FOOT WIDE BY 7 FOOT HIGH INSULATED METAL DOOR AT END OF CORRIDOE 2AC1 (BETWEEN CONFERENCE ROOM 2A04 AND H.A.C. 2AC1D). PROVIDE ROOF WALKWAY PADS CONNECTING CORRIDOR 2AC1 WITH EXTERIOR STAIR 1. AT EXTERIOR SIDE OF REMAINING ROOMS, PROVIDE ALUMINUM COMPOSITE WALL PANEL CONSTRUCTION TO MATCH ADJACENT.

K. BID DEDUCT NO. 10: DELETE ALL EXTERIOR ALUMINUM SUN SHADES AND ASSOCIATED STRUCTURAL SUPPORTS.

L. BID DEDUCT NO. 11: DELETE SECOND FLOOR DRINKING FOUNTAIN AND PROVIDE PLUMBING STUB-OUT INSIDE WALL WITH FLUSH-MOUNTED ACCESS PANEL.

M. BID DEDUCT NO. 12: DELETE ALL SINKS FROM EXAM ROOMS AND PROVIDE ONLY PLUMBING STUBOUTS.

N. BID DEDUCT NO. 13: DELETE ALL ROLLER SHADES AND ROLLER LIGHTPROOF SHADES.

2.3 BID SCHEDULE

Statement of Bid Items

BID SCHEDULE FOR PROJECT 612-501

BASE BID ITEM #1 - Provide all materials, labor, tools, equipment, transportation, supervision, project management, administrative support, and specialized expertise necessary to Construct the Dermatology Outpatient Services Building as required by SOW, drawings and specifications as provided. The work shall include general construction, site work demolition, site, improvements, site utilities, concrete foundations, structural steel framing, exterior building envelope systems, prefabricated steel stairs, elevator system, interior finishes, and all other associated civil, mechanical, plumbing, electrical, fire protection, and telecommunication work as shown on the drawings as specified. All work is to be done in accordance with the Statement of Work, drawings, specifications, and attachments at the Veterans Affairs Northern California Healthcare System (VANCHCS) located in Mather, CA.

1 JOB $ ________________

Deductive Alternate No. 1: This alternate will delete ALL WORK ASSOCIATED WITH ITEMS B, C, D AND E FROM THE STATEMENT OF BID ITEMS: Same as BASE BID ITEM #1 except delete the following work: ALL WORK ASSOCIATED WITH ITEMS B, C, D AND E FROM THE STATEMENT OF BID ITEMS.

1 JOB $ ________________

Deductive Alternate No. 2: This alternate will delete ALL WORK ASSOCIATED WITH ITEMS F, G AND H FROM THE STATEMENT OF BID ITEMS: Same as Deductive Alternate No. 1 except delete the following work: ALL WORK ASSOCIATED WITH ITEMS F, G AND H FROM THE STATEMENT OF BID ITEMS.

1 JOB $ ________________

Deductive Alternate No. 3: This alternate will delete ALL WORK ASSICIATED WITH ITEM I FROM THE STATEMENT OF BID ITEMS: Same as Deductive Alternate No. 2 except delete the following work: ALL WORK ASSOCIATED WITH ITEM I FROM THE STATEMENT OF BID ITEMS.

1 JOB $ ________________

Deductive Alternate No. 4: This alternate will delete ALL WORK ASSOCIATED WITH ITEM J FROM THE STATEMENT OF BID ITEMS: Same as Deductive Alternate No. 3 except delete the following work: ALL WORK ASSOCIATED WITH ITEM J FROM THE STATEMENT OF BID ITEMS.

1 JOB $ ________________

Deductive Alternate No. 5: This alternate will delete ALL WORK ASSOCIATED WITH ITEMS K, L, M AND N FROM THE STATEMENT OF BID ITEMS: Same as Deductive Alternate No. 4 except delete the following work: ALL WORK ASSOCIATED WITH ITEMS K, L, M AND N FROM THE STATEMENT OF BID ITEMS.

1 JOB $ ________________

NOTE: Award will be made on the Base Bid Item, but if the bids exceed the funds available, a single award will be made on Deductive Alternate No #1. In the event the bid exceeds the funds available for on Deductive Alternate No #1, a single award will be made on Deductive Alternate No #2. In the event the bid exceeds the funds available for on Deductive Alternate No #2, a single award will be made on Deductive Alternate No #3. In the event the bid exceeds the funds available for on Deductive Alternate No #3, a single award will be made on Deductive Alternate No #4. In the event the bid exceeds the funds available for on Deductive Alternate No #4, a single award will be made on Deductive Alternate No #5. Bidder’s must submit a bid for all items to be considered for award. Failure to provide a price for all Bid Items will result in a non-responsive bid.

2.4 PRICING BREAKDOWN

PROVIDE COMPLETE DIVISIONAL COST BREAK-OUT FOR COMPLETE PROJECT

REF
DESCRIPTION
TOTAL

DIV01

DIVISION 1 – GENERAL REQUIREMENTS

DIV02
DIVISION 2 – EXISTING CONDITIONS
DIV03
DIVISION 03 – CONCRETE
DIV04
DIVISION 04 – MASONRY
DIV05
DIVISION 05 - METALS
DIV06
DIVISION 06 – WOODS AND PLASTIC
DIV07
DIVISION 07 – THERMAL AND MOISTURE PROTECTION
DIV08
DIVISION 08 – DOORS AND WINDOWS
DIV09
DIVISION 09 - FINISHES
DIV10
DIVISION 10 - SPECIALTIES
DIV11
DIVISION 11 - EQUIPMENT
DIV12
DIVISION 12 - FURNISHINGS
DIV14
DIVISION 14 – CONVEYING EQUIPMENT
DIV21
DIVISION 21 – FIRE SPRINKLER SYSTEM
DIV22
DIVISION 22 – PLUMBING
DIV23
DIVISION 23 – HEATING, VENTIALTING, & AIR CONDITIONING
DIV26
DIVISON 26 – ELECTRICAL
DIV27
DIVISION 27 – COMMUNICATIONS
DIV28
DIVISION 28 – ELECTRONIC SAFETY AND SECURITY
DIV31
DIVISION 31 - EARTHWORK (CIVIL)
DIV32
DIVISION 32 – EXTERIOR IMPROVEMENTS (CIVIL)
DIV33
DIVISION 33 – UTILITIES (CIVIL)
DIV34
DIVISION 34 – TRANSPORTATION (CIVIL)

SUB TOTAL:

BONDS AND INSURANCE

OVERHEAD

PROFIT

TOTAL BID FOR THIS PROJECT:

*Total bid amount to be recorded on SF1442, block 17.

*This document is to be used only for price analysis per FAR 14.408-2

CONTRACTOR CERTIFICATION REGARDING SAFETY AND ENVIRONMENTAL

Contractor Certification Regarding Project: 612-501 (Construct Dermatology Outpatient Services Building)

2016
2017
2018
2019

Number of serious, willful, or repeat violations from OSHA within the last 3 years. Please attach explanation for any violations. (Four serious, one repeat, or one willful disqualifies the contractor.)

Company’s Current Insurance Experience Modification Rate (EMR) = _____________ (Note: Contractor must support the EMR with a signed letter from Insurance Carrier on their letterhead.)

Signature: ______________________________________________

Typed Name: ______________________________________________________

Title: ______________________________________________________

36C26118B0618

Page 1 of Page 1 of

PROPOSAL REQUEST FOR INFORMATION (RFI) FORM

SOLICITATION: 36C26118B0618 – Construct Dermatology Outpatient Service Building located at VA Northern California Healthcare System (VANCHCS), Mather, CA

NOTE: ALL PRE-PROPOSAL INQUIRIES SHALL BE SUBMITTED VIA EMAIL TO robert.parke2@va.gov BY AN EDITABLE USE OF THIS FORM. Please identify, in numerical sequence, each set of inquiries that you send.

Question(s) is/are on the solicitation [ ] Question(s) is/are on the drawings, specifications, technical data [ ]

Company Name and Offeror: ________________________________________________

From (person submitting question): _________________________________________________________

Date of Proposal Inquiry: __________________________________________

Phone Number: ___________________________

Proposal Inquiry: (Type inquiry below)

Proposal RFI #1 –

Proposal RFI #2 –

Proposal RFI #3 - Add additional as necessary

2.5 52.216-1 TYPE OF CONTRACT (APR 1984)

The Government contemplates award of a Firm-Fixed-Price contract resulting from this solicitation.

(End of Provision)

2.6 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014) (a)(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements, of this solicitation.

(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.

(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.

(2) The due date for receipt of offers will not be extended as a result of an offeror's request for a wage determination for a secondary site of the work.

(End of Provision)

2.7 52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)

(a) The offeror's attention is called to the Equal Opportunity clause and the Affirmative Action Compliance Requirements for Construction clause of this solicitation.

(b) The goals for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade on all construction work in the covered area, are as follows:

Goals for minority participation for each trade
Goals for female participation for each trade
16.1 %
6.9 %

These goals are applicable to all the Contractor's construction work performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the geographical area where the work is actually performed. Goals are published periodically in the Federal Register in notice form, and these notices may be obtained from any Office of Federal Contract Compliance Programs office.

(c) The Contractor's compliance with Executive Order 11246, as amended, and the regulations in 41 CFR 60-4 shall be based on (1) its implementation of the Equal Opportunity clause, (2) specific affirmative action obligations required by the clause entitled "Affirmative Action Compliance Requirements for Construction," and (3) its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade. The Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The transfer of minority or female employees or trainees from Contractor to Contractor, or from project to project, for the sole purpose of meeting the Contractor's goals shall be a violation of the contract, Executive Order 11246, as amended, and the regulations in 41 CFR 60-4. Compliance with the goals will be measured against the total work hours performed.

(d) The Contractor shall provide written notification to the Deputy Assistant Secretary for Federal Contract Compliance, U.S. Department of Labor, within 10 working days following award of any construction subcontract in excess of $10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the—

(1) Name, address, and telephone number of the subcontractor;

(2) Employer's identification number of the subcontractor;

(3) Estimated dollar amount of the subcontract;

(4) Estimated starting and completion dates of the subcontract; and

(5) Geographical area in which the subcontract is to be performed.

(e) As used in this Notice, and in any contract resulting from this solicitation, the "covered area" is Northern California Healthcare System City of McClellan, State of California Sacramento County (End of Provision)

2.8 52.228-1 BID GUARANTEE (SEP 1996)

(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.

(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States. The Contracting Officer will return bid guarantees, other than bid bonds—

(1) To unsuccessful bidders as soon as practicable after the opening of bids; and

(2) To the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.

(c) The amount of the bid guarantee shall be 20 percent of the bid price or 3,000,0000, whichever is less.

(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.

(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.

(End of Provision)

2.9 52.233-2 SERVICE OF PROTEST (SEP 2006)

Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from:

Robert Parke

Hand-Carried Address:

Department of Veterans Affairs Network Contracting Office (NCO) 21

3230 Peacekeeper Way, Building 209 McClellan CA 95652 Mailing Address:

Department of Veterans Affairs Network Contracting Office (NCO) 21

5342 Dudley Blvd., Bldg. 98 McClellan CA 95652

(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.

(End of Provision)

2.10 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB 1995)

(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.

(b) An organized site visit has been scheduled for— August 15, 2019 @ 10:00AM PDT

(c) Participants will meet at—

Department of Veterans Affairs
VA Northern California Healthcare System

3rd Floor, B650 - Enigneering and Facility Management Lobby

10535 Hospital Way
Mather, CA 95655

(End of Provision)

2.11 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)

This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):

http://www.acquisition.gov/far/index.html http://www.va.gov/oal/library/vaar/

(End of Provision)

FAR Number
Title
Date
52.204-7
SYSTEM FOR AWARD MANAGEMENT
OCT 2018
52.204-16
COMMERCIAL AND GOVERNMENT ENTITY CODE REPORTING
JUL 2016
52.204-22
ALTERNATIVE LINE ITEM PROPOSAL
JAN 2017
52.211-6
BRAND NAME OR EQUAL
AUG 1999
52.214-3
AMENDMENTS TO INVITATIONS FOR BIDS
DEC 2016
52.214-4
FALSE STATEMENTS IN BIDS
APR 1984
52.214-5
SUBMISSION OF BIDS
DEC 2016
52.214-6
EXPLANATION TO PROSPECTIVE BIDDERS
APR 1984
52.214-7
LATE SUBMISSIONS, MODIFICATIONS, AND WITHDRAWALS OF BIDS
NOV 1999
52.214-18
PREPARATION OF BIDS—CONSTRUCTION
APR 1984
52.214-19
CONTRACT AWARD—SEALED BIDDING—CONSTRUCTION
AUG 1996
52.214-34
SUBMISSION OF OFFERS IN THE ENGLISH LANGUAGE
APR 1991
52.214-35
SUBMISSION OF OFFERS IN U.S. CURRENCY
APR 1991

2.12 VAAR 852.211-72 TECHNICAL INDUSTRY STANDARDS (NOV 2018)

(a) The Contractor shall conform to the standards established by: Department of Veterans Affairs VA Northern California Healthcare System as to the requirements outlined in specifications and drawings.

(b) The Contractor shall submit proof of conformance to the standard. This proof may be a label or seal affixed to the equipment or supplies, warranting that the item(s) have been tested in accordance with the standards and meet the contract requirement. Proof may also be furnished by the organization listed above certifying that the item(s) furnished have been tested in accordance with and conform to the specified standards.

(c) Offerors may obtain the standards cited in this provision by submitting a request, including the solicitation number, title and number of the publication to: Department of Veterans Affairs robert.parke2@va.gov

(d) The offeror shall contact the Contracting Officer if response is not received within two weeks of the request.

(End of Provision)

2.13 VAAR 852.228-72 ASSISTING SERVICE-DISABLED VETERAN-OWNED AND VETERAN-OWNED SMALL BUSINESSES IN OBTAINING BONDS (DEC 2009) Prime contractors are encouraged to assist service-disabled veteran-owned and veteran-owned small business potential subcontractors in obtaining bonding, when required. Mentor firms are encouraged to assist protégé firms under VA's Mentor-Protégé Program in obtaining acceptable bid, payment, and performance bonds, when required, as a prime contractor under a solicitation or contract and in obtaining any required bonds under subcontracts.

(End of Clause)

2.14 VAAR 852.233-70 PROTEST CONTENT/ALTERNATIVE DISPUTE RESOLUTION (OCT 2018)

(a) Any protest filed by an interested party shall—

(1) Include the name, address, fax number, email and telephone number of the protester;

(2) Identify the solicitation and/or contract number;

(3) Include an original signed by the…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .