Base Bid
| ITEM NUMBER |
| DESCRIPTION OF SUPPLIES/SERVICES |
| Qty |
| UNIT |
AMOUNT
| 0001 |
| The work includes, demolition of an existing portions of the building as outlined in the documents to facilitate the overall design |
and connection to the new addition. The project includes a two-story addition, which resides over a raised crawl space (7’-0” height) with the mechanical penthouse on the roof. The project included modification to the existing loading dock and the new structure has new an elevator, HVAC, electrical and plumbing systems, which support the mission of the projects. Along with the new building construction the project includes, alterations to the roads, sidewalks, grading changes, drainage modifications, utility relocations, landscaping/irrigation and connection as necessary for the construction of the, Primary Care-Mental Health Integration Improvements, for Minor Project 436-113
| 1 |
| JB |
TOTAL
Deducts
| ITEM NUMBER |
| DESCRIPTION OF SUPPLIES/SERVICES |
| Qty |
| UNIT |
AMOUNT
| 0001 |
| Alternate A, OMIT VESTIBULE STRUCTURE: Work includes the omission of all labor, material, equipment, and supervision to construct the |
enclosed vestibule. Provide sidewalk, and stairs from existing sidewalk to entrance doors as well as an ADA ramp with code compliant handrails and guardrails.
| 1 |
| JB |
TOTAL
| ITEM NUMBER |
| DESCRIPTION OF SUPPLIES/SERVICES |
| Qty |
| UNIT |
AMOUNT
| 0002 |
| ALTERNATE B, OMIT ELEVATOR: Work includes the omission of all labor, material, equipment and supervision to perform the furnishing and installation of the elevator. The elevator tower shaft shall not be constructed, new adjacent wall construction and floor slab shall |
continue to the stair and the interior space on the basement and first floor shall be conference rooms and all work associated to create the conference room shall be provided within this alternate.
| 1 |
| JB |
TOTAL
| ITEM NUMBER |
| DESCRIPTION OF SUPPLIES/SERVICES |
| Qty |
| UNIT |
AMOUNT
| 0003 |
| Alternate C, OMIT SLIDING EXAM/PATIENT ROOM DOORS: Work includes the |
omission of all labor, material, equipment, and supervision to provide sliding doors at the patient and staff entry into exam rooms. Typical 42” laminate wood swing doors and hardware outlined in the hardware schedule shall be provided within this alternate. (Government will furnish a revised door and hardware schedule with acceptance of the item.)
| 1 |
| JB |
TOTAL
| ITEM NUMBER |
| DESCRIPTION OF SUPPLIES/SERVICES |
| Qty |
| UNIT |
AMOUNT
| 0004 |
| Alternate D, REDUCE CRAWLSPACE: Work includes the omission of all labor, material, equipment, and supervision to provide a 7’ head height in the crawlspace and concrete slab floor. The crawl space shall be constructed with a 4’ head height from 82’ t/slab to 85’ t/slab depth |
with a typical dirt/earth floor.
| 1 |
| JB |
TOTAL
| ITEM NUMBER |
| DESCRIPTION OF SUPPLIES/SERVICES |
| Qty |
| UNIT |
AMOUNT
| 0005 |
| Alternate E, OMIT CANOPY EXTENSION (EXISTING BUILDING): Work includes |
the omission of all labor, material, equipment, and supervision to provide canopy extension at loading dock.
| 1 |
| JB |
TOTAL
| ITEM NUMBER |
| DESCRIPTION OF SUPPLIES/SERVICES |
| Qty |
| UNIT |
AMOUNT
| 0006 |
| Alternate F: OMIT ALL REMODEL WORK ON FIRST FLOOR: Work includes the omission of all labor, material, equipment and supervision to all renovation work in existing building 154A on the First Floor. Room A187, Eye Resource shall be converted into a corridor. Remove door to |
this room for egress. Work shall remain to addition of Storage RoomA164 to maintain fire exits. All other rooms on First floor shall be existing to remain.
| 1 |
| JB |
TOTAL
| ITEM NUMBER |
| DESCRIPTION OF SUPPLIES/SERVICES |
| Qty |
| UNIT |
AMOUNT
| 0007 |
| Alternate G: OMIT SECURITY GATE: Work includes the omission of all labor, material, equipment, and supervision to install the security |
gate and security fence.
| 1 |
| JB |
TOTAL
Note: Offerors shall provide prices on the base bid and all deductive alternates. The base bid shall be priced including all deductive alternates. Each deductive alternate shall have its own price exclusive of the base bid price.
Deductive alternates are listed in descending order of priority. The Government intends to award the base bid with no deducts based on funding limitations. If the low offeror for the base bid is within the Government’s budget award will be made to the lowest priced technically acceptable offeror. If the price for base bid is not within the Government’s budget, the Government will evaluate the price for base bid minus deduct alternate A. If the low offeror for the base bid less deduct alternate A is within the Government’s budget award will be made to the lowest priced technically acceptable offeror. Evaluation of price will continue in the same fashion until the lowest price technically acceptable offeror is within the Government’s budget.