A0004 Sample Form 014500.pdf

PDF 70 KB Posted

Attached to
Y1DB--CON | Construct Inpatient Dialysis | PR 598-23-1-8739-0001
Solicitation number
36C25622R0140
Issued by

About this file

This document package includes specifications for the construction of an approximately 2,600 square foot interior space for a new satellite inpatient dialysis unit at the North Little Rock Veterans Affairs Medical Center (VAMC). Key requirements include the construction of the facility in accordance with the attached statement of work, specifications and drawings. A price breakdown is required dividing the total project cost into material, labor, equipment and overall costs for each construction division. The total estimated cost, including general liability insurance, overhead and profit, and bonding, must be provided. The solicitation was issued by the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 16 to support project number 598-18-107 for constructing the inpatient dialysis unit at the Eugene Towbin Campus of the North Little Rock VAMC.

View the file

Other files

File Type Posted
A0005_App E_ACM Survey Report_2.pdf PDF
A0005_084113.pdf PDF
A0005_36C25622R0140 - RFIs_Additional Responses 03.07.23.pdf PDF
36C25622R0140 0005.pdf PDF
A0005_AE503 AMEND 0003.pdf PDF
A0005_App D_ACM Survey Report_1.pdf PDF
A0004 Contractor Rules of Behavior.pdf PDF
36C25622R0140 0004.docx DOCX document
A0004 36C25622R0140 - RFIs_ 021823 (003).pdf PDF
36C25622R0140 0003.docx DOCX document
signed Site Visit Attendance Sheet 01.17.23.pdf PDF
A0002 EP102 - FIRST FLOOR PLAN - SPECIAL SYSTEMS.pdf PDF
A0002 PK101 - PLUMBING SCHEDULES.pdf PDF
A0002 PJ102 - PLUMBING RISERS.pdf PDF
A0002 ADD. 2 NARRATIVE_Redacted.pdf PDF
A0002 PL102 - FIRST FLOOR PLAN - SANITARY SEWER.pdf PDF
A0002 EL101 - FIRST FLOOR PLAN - LIGHTING.pdf PDF
A0002 36C25622R0140 01272023.pdf PDF
A0002 EP101 - FIRST FLOOR PLAN - POWER.pdf PDF
A0002 EJ102 - ELECTRICAL DETAILS.pdf PDF
Amendment 36C25622R0140 0001 01.20.23.pdf PDF
Instructions to Offerors 01.20.23.pdf PDF
Attch F_EMR Form.pdf PDF
Attch A_ Final SOW for Construct Inpatient Dialysis.pdf PDF
Attch D_Subcontractor Information and Consent.pdf PDF
36C25622R0140_1.docx DOCX document
Attch C_598-18-107 100 Pct Drawings.pdf PDF
EXHIBIT A_PERFORMANCE RELEVANCY SURVEY.pdf PDF
Attch B_598-18-107 100 Pct Specifications.pdf PDF
Attch E_ Wage Determination.pdf PDF
EXHIBIT B_Past and Present Performance Questionnaire.pdf PDF
Show all 31

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONTRACTOR'S QUALITY CONTROL REPORT (QCR)

D A T E: R E P O R T N O.:

C O N T R A C T N U M B E R A N D N A M E O F C O N T R A C T O R: D E S C R I P T I ON A N D L O C A T I O N O F T H E W O R K:

W E A T H E R C L A S S I F I C A T I O N :

CLASS A

CLASS B

CLASS C

CLASS D

CLASS E

OTHER

C L A S S I F I C A T I O N :

C L A S S

T E M P E R A T U R E :

M A X M I N

P R E C I P I T A T I O N :

I N C H E S

(ER 1180-1-6)

No interruptions of any kind from weather conditions occurring on this or previous shifts.

Weather occurred during this shift that caused a complete stoppage of all work.

Weather occurred during this shift that caused a partial stoppage of work.

Weather overhead excellent or suitable during shift. Work completely stopped due to results of previous adverse weather.

Weather overhead excellent or suitable during shift but work partially stopped due to previous adverse manner.

Explain.

CONTRACTOR/SUBCONTRACTORS AND AREA OF RESPONSIBILITY FOR WORK PERFORMED TODAY: (Attach list of items of equipment either idle or working as appropriate.)

1. WORK PERFORMED TODAY: (Indicate location and description of work performed. Refer to work performed by prime and/or subcontractors by letter in Table above.)

2. TYPE AND RESULTS OF INSPECTION: (Indicate whether: P - Preparatory, I - Initial, or F - Follow-up and include satisfactory work completed or deficiencies with action to be taken.)

3. TESTS REQUIRED BY PLANS AND/OR SPECIFICATIONS PERFORMED AND RESULTS OF TESTS:

SAM 696FORM

1 SEP 79 Previous Edition May Be Used Until Exhausted

PURPOSE: Contractors Daily QC Report. Revision necessitated by EIG recommendation

MONTHLY USAGE: 1,500

PRESCRIBING DIRECTIVE: ER 1180-1-6

FUNCTIONAL CODE: 1180 Series - Engineer Contracts a.

b.

c.

d.

e.

f.

g.

vacobofint Rectangle vacobofint Rectangle vacobofint Sticky Note Accepted set by vacobofint

4. VERBAL INSTRUCTIONS RECEIVED: (List any instructions given by Government personnel on construction deficiencies.

retesting required, etc., with action to be taken.)

5. REMARKS: (Cover any conflicts in plans, specifications or instructions: acceptability of incoming materials: offsite surveillance activities; progress of work, delays, causes and extent thereof; days of no work with reasons for same.)

6. SAFETY: (Include any infractions of approved safety plan, safety manual or instructions from Government personnel.

Specify corrective action taken.)

CONTRACTOR'S CERTIFICATION: I certify that the above report is complete and correct and that all material and equipment used, work performed and tests conducted during this reporting period were in strict compliance with the contract plans and specifications except as noted above.

INSPECTOR

CONTRACTOR'S APPROVED AUTHORIZED REPRESENTATIVE

17-R-0002 Amendment 0003 Volume I (Phase II)
Amendment 0003 Narrative
Phase Two - Volume 1 of 3
Table of Contents
Bidding Requirements
DIVISION 1 - GENERAL REQUIREMENTS
01 00 00
LIST OF PERMITS REQUIRED
PROJECT SIGNS
WAGE RATES
01 00 01.02 DoVA CEMP
01 10 10 DESIGN REQUIREMENTS
1 DESCRIPTION OF FACILTIY AND SCOPE
2 DESIGN REQUIREMENTS
3 GENERAL REQS for PERMITTING, LIFE SAFETY and SECURITY REQUIREMENTS
4 SITE
5 ARCHITECTURE
6 CONVEYING SYSTEMS
7 INTERIOR DESIGN, SIGNAGE & F, F & E
8 STRUCTURAL DESIGN
9 HVAC
10 (not used)
11 PLUMBING
12 (not used)
13 FIRE PROTECTION & LIFE SAFETY
14 (not used)
15 ELECTRICAL
16 SECURITY SYSTEMS
17 COMMUNICATIONS
18 CORROSION AND CATHODIC PROTECTION
19 ENVIRONMENTS - HAZARDOUS MATERIALS
20 SUSTAINABLE DESIGN
21COMMSSIONING
01 10 12 DESIGN AFTER AWARD
01 14 00 WORK RESTRICTIONS
01 32 00.00 10 PROJECT SCHEDULE
01 33 00 SUBMITTAL PROCEDURES
Submittal Register
Standard Form 4025
01 33 29 SUSTAINABILITY REPORTING
01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00.00.10 QUALITY CONTROL
QCR-SAM FORM 696
01 45 00.15.01 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)
01 45 35 SPECIAL INSPECTIONS
01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS
01 57 19.01 20 SUPPLEMENTAL TEMPORARY ENVINROMENTAL CONTROLS
01 74 19 CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT
01 78 23 OPERATION AND MAINTENANCE DATA
17-R-0002 Amendment 0003 Volume II (Phase II)
Phase Two - Volume 2 of 3
Table of Contents
APPENDIX A - WORK RESTRICITIONS DOCUMENTS
APPENDIX B - PRESCIPTIVE SPECIFICATIONS
01 81 13 SUSTAINABLE CONSTRUCTION REQUIREMENTS
01 81 16 HEALTHCARE SUSTAINABLE DESIGN REQUIREMENTS
01 81 21 IAQ MANAGEMENT DURING CONSTRUCTION
01 81 22 IAQ PROTECTION BEFORE OCCUPANCY
01 91 00 GENERAL COMMISSIONING REQUREMENTS
07 08 00 FACILITY EXTERIOR CLOSURE COMMISSIONING
14 21 00 ELECTRIC TRACTION ELEVATOR
14 24 00 HYDRAULIC ELEVATOR
14 92 19 SIX (6") PNEUMATIC TUBES
21 09 00 COMMSSIONING OF FIRE SUPPRESION SYSTEM
22 08 00 COMMSSIONING OF PLUMBING SYSTEM
23 08 00 COMMSSIONING OF HVAC SYSTEM
26 08 00 COMMSSIONING OF ELECTRICAL SYSTEM
26 09 13 ELECTRICAL POWER MONITORING AND CONTROL
26 09 14 SCADA MONITORING SYSTEM
27 08 00 COMMSSIONING OF COMMUNICATIONS SYSTEMS
28 08 00 COMMSSIONING OF ELECTRONIC SAFETY AND SECURITY SYSTEMS
33 08 00 COMMISSIONING OF SITE UTILITY SYSTEMS
APPENDIX C - SITE ANALYSIS CONTEXT DRAWINGS
APPENDIX D - 2015 VA CFM PHYSICAL SECURITY DESIGN MANUAL
APPENDIX E - SPACE PROGRAM FOR DESIGN AND ROOM GUIDEPLATES
APPENDIX F - CONCEPTUAL PLANNING DIAGRAMS
APPENDIX G - LEGACY MEDICAL CENTER SYSTEMS TIE-IN MATRIX
APPENDIX H - 2014 TRANSPORTATION AND LOGISTICS REPORT & PNEUMATIC TUBE SYSTEM
APPENDIX I - LEED OWNER'S PROJECT REQUIREMENTS
17-R-0002 Amendment 0003 Volume III (Phase II)
Phase Two - Volume 3 of 3
Table of Contents
APPENDIX J - SITE PHASING & CPM SCHEDULE
APPENDIX K - 2014 SITE BOUNDARY, TOPOGRAPHIC AND UTILITY SURVEYS
APPENDIX L - GEOTECHNICAL & GEOPHYSICAL REPORTS
APPENDIX M - HVAC UTILITY SYSTEM CONNECTIONS
APPENDIX N - FIRE PROTECTION
APPENDIX O - WATER QUALITY REPORTS, WELL TESTS and CIVIL SITE POTABLE & SANITARY PLAN
APPENDIX P - EXISTING SITE UTILITY INFORMATION
APPENDIX Q - CIVIL SITE LIFT STATION INFORMATION
APPENDIX R - SITE ELECTRICAL / IT/COMMUNICATIONS & SECURITY SYSTEMS
APPENDIX S - EXISTING BUILDING 54 GENERATOR PLANT -
APPENDIX T - EXISTING BUILDING 1 - HAZARDOUSE MATERIALS DRAWINGS
APPENDIX U - EQUIPMENT INFORMATION
APPENDIX V - INTERIOR DESIGN INFORMATION
APPENDIX W - EXISTING EXTERIOR SIGNAGE INFORMATION
APPENDIX X - ENVIRONMENTAL INFORMATION
APPENDIX Y - INDEX OF ELECTRONIC EXISITNG BUILDING INFORMATION
APPENDIX Z - LARGE FORMAT SITE AND BUILDING DRAWINGS