This document contains responses to questions regarding solicitation number 36C25223B0010 to replace air handling units in Building 5 at a Department of Veterans Affairs medical center. The solicitation is seeking to remove existing pneumatic controls, tubing, junction boxes and piping. Responses indicate that the existing materials cannot remain in walls but as-builts are available showing locations. Walls have tested negative for asbestos. The VA will relocate furniture as needed for demolition work. No additional time is being provided to submit proposals in response to this solicitation from the Veterans Health Administration and Veterans Integrated Service Network 12 to replace air handling units.

View the file

Other files for this federal contract opportunity

Other files attached to Z1DA--695-22-107 Replace Building 5 AHUs, newest first.
File Type Posted
S06 - 695-22-107 Amend 0006 Questions 02.27.23.pdf PDF
36C25223B0010 0006.docx DOCX document
36C25223B0010 0005.docx DOCX document
Attachment 3B - ACM Report Bldg. 5 Basement.pdf PDF
S06 - 695-22-107 Amend 0004 Questions 02.21.23.pdf PDF
36C25223B0010 0004.docx DOCX document
Attachment 2D - VA Temp AC Unit Photo 4.pdf PDF
Attachment 2C - VA Temp AC Unit Photo 3.pdf PDF
Attachment 2B - VA Temp AC Unit Photo 2.pdf PDF
Attachment 2G - VA Temp AC Unit Photo 7.pdf PDF
Attachment 2F - VA Temp AC Unit Photo 6.pdf PDF
Attachment 2E - VA Temp AC Unit Photo 5.pdf PDF
Attachment 2A - VA Temp AC Unit Photo 1.pdf PDF
Attachment 1 - VA Temp AC Unit Cutsheets and O_M.pdf PDF
S06 - 695-22-107 Amend 0004 Specifications.pdf PDF
Attachment 4 - Bldg. 5 Tab Report.pdf PDF
Attachment 3A - ACM Report Bldg. 5 MERs.pdf PDF
36C25223B0010 0003.docx DOCX document
36C25223B0010 0002.docx DOCX document
S06 - Site Visit Attendance Sheet_695-22-107 01.11.23.pdf PDF
36C25223B0010 0001.docx DOCX document
S02 - Drawings Part 2.pdf PDF
S02 - Drawings Part 4.pdf PDF
S02 - Firestop_SingleSourceJustification_MPT-SAT_SIGNED.pdf PDF
S02 - Specifications.pdf PDF
36C25223B0010.docx DOCX document
S02 - Wage Determination_11_11_22.pdf PDF
S02 - HVAC_BAS_Controls_SingleSourceJustification_MPT-SAT_SIGNED.pdf PDF
S02 - Drawings Part 3.pdf PDF
S02 - Drawings Part 1.pdf PDF
Show all 30

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Reference RFI Question #15, Amendment 36C25223B0010.

1) Would the VA allow the "abandon Pneumatic controls, tubing, junction boxes and piping" to remain in place behind / contained inside the walls? Walls are assumed to be plaster.

If the anser is "No":

a) As-Builts of the existing Pneumatic controls system to identified the amount of cutting and patching required? OR

b) An advised LF of cutting and patching to be anticipated? AND

c) Consdiering the age of the building do the walls contain asbestos? Has the plaster / walls been tested? If the walls contain asbestos we would need a qty of asbestos to be abated.

d) All furniture will have to be relocated by VA to allow demoltion of the controls taht runs with in the walls. Confirm?

e) Is additional time to prepare an accurate proposal?

1) No.

a) The existing compressor and existing thermostats are shown on Drawing Sheets M-100 through M-

105. The pneumatic control panel is located in Mechanical Room 203 which was shown on the bid walkthrough.

b) The existing compressor and existing thermostats are shown on Drawing Sheets M-100 through M-

105. The pneumatic control panel is located in Mechanical Room 203 which was shown on the bid walkthrough.

c) Based on routine testing done by the facility and testing that has been outsourced, the plaster/walls tests have returned negative. If the contractor encounters any potential ACM, they are to stop work immediately and notify the COR. Standard contract modification processes are available for unforeseen site conditions.

d) Yes the VA will relocate furniture required to demolish controls within the wall, with advance notice to the COR.

c) Not at this time.

695-22-107, Replace Building 5 AHUs

36C25223B0010 RFIs Contractor RFI/Comment VA ResponsesRFI No.

S06 ‐ 695‐22‐107 Amend 0005 Questions 02.24.23 1 of 1