695-19-104 Amend 05 Drawings.pdf
PDF 403 KB Posted
- Attached to
- Z1DA--Replace Fire Sprinkler System Risers Bldg. 111 Project 695-19-104 Federal contract opportunity
- Solicitation number
- 36C25221B0021
About this file
This document package includes construction drawings and specifications for replacing fire sprinkler risers in Building 111 at the Clement J. Zablocki VA Medical Center in Milwaukee, Wisconsin. The project involves demolishing existing risers and installing new sprinkler risers in seven phases over multiple weekends to minimize disruptions. Key details include replacing six-inch and three-inch zone isolation valves, installing new risers in Stairwell 6, and demolishing disconnected piping. Infection control measures and maintaining life safety are priorities. The related federal contract opportunity is a pre-solicitation notice for project 695-19-104 with a value between $1-2 million. The solicitation will be posted on July 8th with bid opening on August 10th. The project has a 660-day period of performance. The procurement is a 100% SDVOSB set-aside under NAICS 238220 with a $16.5 million size standard.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 695-19-104 Amend 05 Spec 01 01 10SN.pdf | ||
| 36C25221B0021 0005.docx | DOCX document | |
| 695-19-104 Amend 05 Spec 00 01 10 TOC.pdf | ||
| 695-19-104 Amend 05 Spec 01 35 26 Safety Requirements.pdf | ||
| 36C25221B0021 0004.docx | DOCX document | |
| S06 - Pre-Bid Walkthru Roster 07.20.21.pdf | ||
| 36C25221B0021 0003.docx | DOCX document | |
| S02 - Combined Riser PDF Attachment.pdf | ||
| 36C25221B0021 0002.docx | DOCX document | |
| S02 - Haz Material Report Attachment.pdf | ||
| S02 - Pre-Bid Walkthru Roster.pdf | ||
| S02 - Project Specifications updated 7 7 21.pdf | ||
| 36C25221B0021_1.pdf | ||
| 36C25221B0021 0001.docx | DOCX document | |
| S02 - DB Wage Determination.pdf | ||
| S02 - JNA for Fire Alarm Components.pdf | ||
| S02 - JNA for Hilti Firestop.pdf | ||
| S02 - Project Specifications.pdf | ||
| S02 - Drawings.pdf | ||
| 36C25221B0021_1.docx | DOCX document |
Show all 20
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
NOTE: NOT ALL SYMBOLS MAY BE USED ON THIS PROJECT
UPRIGHT SPRINKLER HEAD
FIRE LINE (NEW - BOLD)FL
PENDANT SPRINKLER HEAD
FIRE DEPARTMENT CONNECTION (FDC)
FIRE LINE (EXISTING - LIGHT - ITALIC)FL
POINT OF NEW CONNECTION
LIMIT OF DEMOLITION
NEW WORK KEYNOTE
DEMOLITION KEYNOTE
TAMPER SWITCH
FLOW SWITCH
CHECK VALVE
GATE VALVE
TEST AND DRAIN ASSEMBLY
BACKFLOW PREVENTER
T&D
TS
FS
ORDINARY HAZARD
GROUP 1 OCCUPANCY
DETAIL OR SECTION MARK
SHOWN ON DRAWING
DETAIL MODULE NUMBER
ORDINARY HAZARD
GROUP 2 OCCUPANCY
LIGHT HAZARD
BUTTERFLY VALVE
DRAIN VALVE WITH SIGHT GLASS
FIRE LINE (DEMOLITION - DASHED BOLD - ITALIC)FL
FIRE DRAIN (EXISTING - LIGHT - ITALIC)DRAIN
CALLOUT LINE
MATCHLINE
FIRE LINE (PREVIOUS PHASE - MEDIUM - ITALIC)FL
THE FIRE PROTECTION DRAWING IS DESIGNED TO BE IN CONFORMANCE WITH NFPA
13. IT IS A PERFORMANCE BASED DRAWING INDICATING THE EXTENT OF FIRE
PROTECTION WORK FOR THE AREA THAT THIS DRAWING REPRESENTS. THIS
DRAWING IS “FOR INFORMATION ONLY”, AS A REFERENCE FOR THE FIRE
PROTECTION CONTRACTOR TO BASE THE DESIGN OF THE FIRE PROTECTION
SYSTEM ON. THE CONTRACTOR SHALL VERIFY THE EXACT CONDITIONS THAT THIS
DRAWING REPRESENTS, INCLUDING ANY PERCEIVED CONCEALED SPACES, AND THE
BUILDING TYPE AND CONSTRUCTION AS OUTLINED IN THE INTERNATIONAL BUILDING
CODE, PRIOR TO THE START OF WORK. REFER TO THE INTERNATIONAL BUILDING
CODE, NFPA 13, AND THE PROJECT SPECIFICATIONS FOR OTHER FIRE PROTECTION
REQUIREMENTS.
FLUSHING CONNECTION
FEED OR CROSS MAIN.
TYPICAL TEE WITH
CROSS MAIN PITCH
TOWARDS FEED MAIN.
NOTE: INSTALL FLUSHING
CONNECTION AT END OF
CROSS MAINS.
2" NIPPLE 4" LONG
WITH CAP.
MECHANICAL TEE
NEW PIPING
MECHANICAL TEE
SCREWED END
NOTE: SEE FLOOR
PLAN FOR EXISTING
AND NEW PIPE SIZES.
STEEL BEAM
RETAINING STRAP
C-CLAMP
THREADED HANGER ROD
ADJUSTABLE RING HANGER
EXPANSION ANCHOR.
ANCHOR SHALL BE FM
LISTED AND APPROVED
FOR USE IN CRACKED
CONCRETE PER ACI 355.2
EXISTING CONCRETE SLAB
SPRINKLER PIPE
SET SCREW
SURGE RESTRAINER
INSTALL INSULATION AFTER
CAULKING SLEEVE, SEAL AS
REQUIRED.
FIRE RATED WALL AND OR SLAB.
STEEL PIPE SLEEVE TERMINATE
SLEEVE FLUSH WITH FINISHED
SURFACE.
FIRESTOPPING APPROVED
(BY LOCAL CODES)
FINISHED ESCUTCHEON PLATE
FLUSH AGAINST WALL AND OF
SIZE TO COMPLETELY COVER
OPENING.
APPROVED TYPE FIRE SAFE &
SMOKE TIGHT CAULKING SEALER
BETWEEN BARE PIPE AND SLEEVE.
SPRINKLER RISER
INDICATING BUTTERFLY VALVE
WITH TAMPER SWITCH AT OR ABOVE 7'- 0" AFF
WATER FLOW SWITCH
PRESSURE GAUGE
SPRINKLER PIPE TO ZONE
AUXILIARY DRAIN VALVE
1" INSPECTOR'S TEST VALVE
SIGHT GLASS
2" DRAIN CONNECTION TO EXISTING
DRAIN PIPING
CHECK VALVE
STANDPIPE HOSE CONNECTION
MOUNT 4'- 0" AFF
1. LOCATIONS SHOWN FOR EXISTING FIRE PROTECTION PIPE AND EQUIPMENT ARE APPROXIMATE. FIELD VERIFY THE EXACT LOCATIONS OF EXISTING FIRE PROTECTION LINES AND EQUIPMENT INCLUDING RISERS AND VALVES PRIOR TO START OF
WORK.
2. COORDINATE WITH COR FOR ANY SHUTDOWNS OR PLANNED INTERRUPTIONS OF THE FIRE PROTECTION SERVICE. GIVE THE COR AT LEAST TWENTY-EIGHT (28) DAYS NOTICE PRIOR TO PLANNED SHUTDOWN OR INTERRUPTION.
3. COORDINATE DEMOLITION OF FIRE PROTECTION PIPING WITH OTHER PIPING WHICH IS NOT TO BE REMOVED. PROTECT
OTHER PIPING WHICH IS NOT TO BE REMOVED FROM DAMAGE, DIRT, AND DEBRIS.
4. FIRE PROTECTION RELATED EQUIPMENT AND PIPING WHICH IS REMOVED FROM THE BUILDING IS TO BE TAKEN OFFSITE AND
DISPOSED OF.
5. REMOVE SPRINKLER MAINS AND BRANCHES TO THE ZONE CONTROL VALVE AS NEEDED TO INSTALL NEW SPRINKLER
SYSTEM.
1. USE NFPA-13 (CURRENT EDITION) AS A GUIDELINE WHEN PREPARING SUBMITTALS FOR REVIEW. DISREGARD ONLY THOSE ITEMS NOT APPLICABLE TO THE INDIVIDUAL BUILDING SYSTEM. FIRE PROTECTION MATERIALS, EQUIPMENT AND INSTALLATION SHALL BE IN ACCORDANCE WITH THE REQUIREMENTS OF NFPA-13 FOR THE INSTALLATION OF AUTOMATIC
SPRINKLER SYSTEM.
2. THIS FACILITY IS FULLY SPRINKLERED. EXISTING FIRE SUPPRESSION SYSTEM IS WET PIPE TYPE SYSTEM WITH COMPLETE SPRINKLER PROTECTION UNLESS NOTED OTHERWISE. STANDPIPE SIZES SHALL MATCH EXISTING.
3. FIRE PROTECTION CONTRACTOR SHALL TEST EXISTING FIRE PUMP AND RECORD STATIC AND RESIDUAL PRESSURE AT MOST REMOTE OUTLET. TEST SHALL BE PERFORMED BEFORE START AND AFTER COMPLETION OF NEW WORK.
4. SUBMIT ONE COMPLETE SET OF PUMP AND RISER TEST DATA, CERTIFIED AND STAMPED BY A PROFESSIONAL ENGINEER.
5. PIPING IS SHOWN IN SCHEMATIC FORM TO INDICATE APPROXIMATE ARRANGEMENT OF EQUIPMENT AND PIPING. SPRINKLER CONTRACTOR SHALL DESIGN THE SYSTEM AND ROUTE PIPING AS REQUIRED FOR CONFORMANCE WITH ACTUAL BUILDING CONDITIONS AND NFPA REQUIREMENTS. COORDINATE SPRINKLER WORK WITH ALL OTHER TRADES TO AVOID CONFLICT.
6. SUPPORT NEW PIPING AND EQUIPMENT FROM STRUCTURE. PROVIDE ALL SUPPLEMENTAL STEEL TO SPAN BETWEEN PRIMARY BUILDING STRUCTURAL MEMBERS. DESIGN SUPPLEMENTAL STEEL AND SUPPORTS INCLUDING REACTION LOADS
AT PRIMARY BUILDING STRUCTURAL MEMBERS.
7. CLEAN ENTIRE WORK AREA OF ALL DUST, DIRT, AND OTHER DEBRIS. MAINTAIN WORK AREA IN CLEAN CONDITION.
8. PROVIDE ALL LABOR, MATERIALS, TOOLS, EQUIPMENT, ETC. REQUIRED FOR COMPLETE AND FUNCTIONAL SYSTEM AS
SPECIFIED AND INDICATED ON THE DRAWINGS.
9. REPAIR OR REPLACE NON-CONFORMING AND INADEQUATE WORK AT NO ADDITIONAL COST TO THE VA.
10. PROVIDE FIRE STOPS / SEALANT AT ALL PIPE PENETRATIONS THROUGH FIRE RATED WALLS, FLOORS, AND CEILINGS.
11. ELECTRONIC FLOW AND TAMPER SWITCHES ARE TO BE REUSED AND INSTALLED AS WORK OF DIVISION 21. PROVIDE WIRING
TO FLOW AND TAMPER SWITCHES AS WORK OF DIVISION 26.
12. FURNISH AND INSTALL ARMOVER SUPPORTS FOR ALL END OF LINE BRANCH LINES IN ACCORDANCE WITH NFPA-13.
13. LOCATE THE INSPECTOR'S TEST CONNECTION AND MAIN DRAIN LOCATIONS IN ACCORDANCE WITH NFPA-13.
14. NEW STANDPIPES SHALL BE LOCATED AT EXISTING STANDPIPE LOCATIONS AND USE EXISTING OPENINGS IN THE FLOORS
EXCEPT IN PLACES NOTED ON THE PLANS.
15. STANDPIPE SYSTEM IS CLASS 1.
16. CONTRACTOR SHALL TEST EVERY VALVE AND ALARM DEVICE PRIOR TO BEGINNING WORK TO ENSURE WORKING CONDITION. PROVIDE TWO (2) NEW 6" ZONE ISOLATION VALVES AND THREE (3) 3" ZONE ISOLATION VALVES WITH TAMPER SWITCHES TO REPLACE EXISTING VALVES THAT CANNOT BE REUSED. PROVIDE A UNIT PRICE INCLUDING LABOR COST FOR REPLACING ANY ADDITIONAL VALVES IF REQUIRED. IF VALVES ARE NOT REQUIRED, TURN THEM OVER TO THE COR AT THE
END OF THE PROJECT.
17. PROVIDE FIVE (5) NEW HOSE CONNECTION VALVES WITH CAPS TO REPLACE EXISTING VALVES THAT CANNOT BE REUSED.
PROVIDE A UNIT PRICE INCLUDING LABOR COST FOR REPLACING ANY ADDITIONAL VALVES IF REQUIRED. IF VALVES ARE NOT
REQUIRED, TURN THEM OVER TO THE COR AT THE END OF THE PROJECT.
1. DURING THE TIME THAT THE FIRE PROTECTION RENOVATION WORK IS BEING PERFORMED, AND THE FIRE PROTECTION SYSTEM IS OUT OF COMMISSION, CONTRACTOR SHALL HAVE SUFFICIENT PERSONNEL ONSITE TO KEEP A “FIRE WATCH” ON THE FACILITY IN ACCORDANCE WITH VA REQUIREMENTS. AN OUT OF SERVICE TAG MUST BE PLACED AT THE FIRE ALARM PANEL AND THE FIRE DEPARTMENT CONNECTION. REFER TO INTERNATIONAL FIRE CODE CHAPTER 9, SECTION 901.7.
2. FIRE WATCH PERSONNEL ARE TO KEEP WATCH FOR FIRES IN THE GENERAL AREA OF PERFORMANCE, THE PERSONS
PERFORMING THE FIRE WATCH ARE NOT PERMITTED TO PERFORM ANY OTHER DUTIES.
3. FIRE WATCH PERSONNEL ARE TO HAVE FIRE EXTINGUISHING EQUIPMENT READILY AVAILABLE AND TO BE TRAINED IN ITS USE.
4. THE QUANTITY OF PERSONNEL INVOLVED IN THE FIRE WATCH IS TO BE ADEQUATE SUCH THAT EACH FLOOR, LEVEL, AND
ROOM OF THE FIRE AREA IS COVERED.
1. CONTRACTOR SHALL COMPLY WITH THE VA'S INFECTION CONTROL RISK ASSESSMENT REQUIREMENTS AND WRITTEN DUST
CONTROL PLAN.
2. EXISTING AIR QUALITY REQUIREMENTS AND OTHER UTILITY REQUIREMENTS FOR OCCUPIED AREAS SHALL BE MAINTAINED.
3. RENOVATION AREAS SHALL BE ISOLATED FROM OCCUPIED AREAS DURING CONSTRUCTION USING AIRTIGHT BARRIERS.
PROVIDE EXHAUST AIRFLOW IN A MANNER THAT SHALL BE SUFFICIENT TO MAINTAIN NEGATIVE AIR PRESSURE IN THE CONSTRUCTION ZONE. COORDINATE TEMPORARY BARRIERS WITH INTERIM LIFE SAFETY MEASURES.
4. FIRE PROTECTION SYSTEM REVISIONS SHALL BE PROPERLY PERFORMED TO LIMIT WATERBORNE OPPORTUNISTIC
PATHOGENS.
5. CRUCIAL VENTILATION SPECIFICATIONS FOR AIR BALANCE AND FILTRATION SHALL BE VERIFIED BEFORE OWNER'S
ACCEPTANCE.
BOLT
FLOOR SLAB
ESCUTCHEON
PLATE
PIPE SLEEVE
RISER CLAMP
FIRE-STOPPING
MATERIAL
BOLT
RISER CLAMP
PIPE SLEEVE
RISER PIPE
SECTION
TOP RISER PIPE
FOR ALL PHASES:
• CONSTRUCTION AND DEMOLITION SHALL BE COORDINATED TO MINIMIZE UNNECESSARY SHUTDOWNS AND DRAINAGE OF
PIPING.
• FOR SPRINKLER SYSTEM IMPAIRMENTS LASTING MORE THAN 8 HOURS:
○ FIRE DEPARTMENT MUST BE NOTIFIED.
○ VA POLICE MUST BE NOTIFIED.
○ DEDICATED FIRE WATCH MUST BE PRESENT.
• PHASE 1 MUST BE COMPLETED BEFORE PHASES 2 THROUGH 7. PHASES 2 THROUGH 7 SHALL BE COMPLETED IN ORDER.
• WORK FOR MULTIPLE PHASES MAY NOT OCCUR CONCURRENTLY.
PHASE 1 - SUB-BASEMENT:
A. INSTALL NEW MAINS IN SUB-BASEMENT PARALLEL TO EXISTING PIPING. PREPARE FUTURE CONNECTIONS AND CONNECT
DRAIN PIPING AS NECESSARY TO MINIMIZE DOWN TIME IN PHASE 1B.
B. SELECTIVE DEMOLITION AND REPLACEMENT OF EXISTING PIPING TO CONNECT EXISTING RISERS AND SYSTEM COMPONENTS
TO NEW MAINS.
C. COMPLETE DEMOLITION OF DISCONNECTED MAINS IN SUB-BASEMENT.
FOR PHASES 2 THROUGH 7:
• THE ALLOTTED SHUTDOWN DURATION IS FROM FRIDAY AT 16:00 TO MONDAY AT 06:00.
• THE SYSTEM IS TO BE DRAINED AT THE BEGINNING OF THE SHUTDOWN DURATION AND MUST BE REFILLED AND FULLY
OPERATIONAL BY THE END OF THE ALLOTTED SHUTDOWN DURATION.
• ALL WORK WITHIN THE STAIRWELLS INCLUDING BUT NOT LIMITED TO: INFECTION CONTROL, DEMOLITION, AND ABATEMENT SHALL BE PERFORMED FROM FRIDAY AT 16:00 TO MONDAY AT 06:00. BARRIERS, CORED HOLES, AND EXPOSED ABATEMENT
AREAS SHALL NOT BE LEFT BEHIND.
PHASE 2 - STAIRWELL 4:
A. REPLACE STAIRWELL RISER PIPING BETWEEN THE SUB-BASEMENT RISER ISOLATION VALVE AND ALL ZONE VALVES. REPLACE RISER IN SEGMENTS ALLOWING FOR RETURN OF THE SYSTEM TO FULL OPERATION WITHIN THE ALLOTTED SHUTDOWN
DURATION.
PHASE 3 - STAIRWELL 5:
A. REPLACE STAIRWELL RISER PIPING BETWEEN THE SUB-BASEMENT RISER ISOLATION VALVE AND ALL ZONE VALVES. REPLACE RISER IN SEGMENTS ALLOWING FOR RETURN OF THE SYSTEM TO FULL OPERATION WITHIN THE ALLOTTED SHUTDOWN
DURATION.
PHASE 4 - STAIRWELL 2:
A. REPLACE STAIRWELL RISER PIPING BETWEEN THE SUB-BASEMENT RISER ISOLATION VALVE AND ALL ZONE VALVES. REPLACE RISER IN SEGMENTS ALLOWING FOR RETURN OF THE SYSTEM TO FULL OPERATION WITHIN THE ALLOTTED SHUTDOWN
DURATION.
PHASE 5 - STAIRWELL 3:
A. REPLACE STAIRWELL RISER PIPING BETWEEN THE SUB-BASEMENT RISER ISOLATION VALVE AND ALL ZONE VALVES. REPLACE RISER IN SEGMENTS ALLOWING FOR RETURN OF THE SYSTEM TO FULL OPERATION WITHIN THE ALLOTTED SHUTDOWN
DURATION.
PHASE 6 - STAIRWELL 1:
A. REPLACE STAIRWELL RISER PIPING BETWEEN THE SUB-BASEMENT RISER ISOLATION VALVE AND ALL ZONE VALVES. REPLACE RISER IN SEGMENTS ALLOWING FOR RETURN OF THE SYSTEM TO FULL OPERATION WITHIN THE ALLOTTED SHUTDOWN
DURATION.
PHASE 7 - STAIRWELL 6:
A. CONSTRUCT NEW RISER IN STAIRWELL 6. PREPARE FUTURE CONNECTIONS AND CONNECT DRAIN PIPING AS NECESSARY TO
MINIMIZE DOWN TIME IN PHASE 7B.
B. CONNECT EXISTING ZONE VALVES TO NEW RISER AND REINSTALL EXISTING HOSE VALVES ON NEW RISER.
C. DEMOLISH DISCONNECTED RISER PIPING EXPOSED IN STAIRWELL AND CAP PIPING AT WALL AND FLOOR.
KW KILOWATT
KWHR KILOWATT-HOUR
L/S LITER PER SECOND
M METER
MC MECHANICAL CONTRACTOR
MED MEDICAL
MER MECHANICAL EQUIPMENT ROOM
MH MANHOLE
MOU MEMORANDUM OF UNDERSTANDING
NC NORMALLY CLOSED
NIC NOT IN CONTRACT
NO NORMALLY OPEN
NOM NOMINAL
NTS NOT TO SCALE
OC ON CENTER
OD OUTSIDE DIAMETER
PA PASCAL
PC PLUMBING CONTRACTOR
PD PRESSURE DROP
PDI PLUMBING AND DRAINAGE INSTITUTE
PG PRESSURE GAUGE
PPM PARTS PER MILLION
PRV PRESSURE REDUCING VALVE
PSI POUNDS PER SQUARE INCH
PSIA POUNDS PER SQUARE INCH ABSOLUTE
PSIG POUNDS PER SQUARE INCH GAUGE
SAN SANITARY SEWER
SP SUMP PUMP
SPR SPRINKLER LINE
SQFT SQUARE FOOT
SS STAINLESS STEEL
ST STORAGE TANK
TD TRENCH DRAIN
TDH TOTAL DYNAMIC HEAD
TEMP TEMPERATURE
TYP TYPICAL
UPC UNIFORM PLUMBING CODE
V SANITARY VENT
VB VACUUM BREAKER
WCO WALL CLEANOUT
WG WATER GAUGE
WL WATER LINE
WM WATER METER
WPD WATER PRESSURE DROP
YCO YARD CLEANOUT
A/E ARCHITECT/ENGINEER
AFF ABOVE FINISHED FLOOR
AP ACCESS PANEL
AS AUTOMATIC SPRINKLER
ASME AMERICAN SOCIETY OF MECHANICAL ENGINEERS
ASPE AMERICAN SOCIETY PLUMBING ENGINEERS
ASR AUTOMATIC SPRINKLER RISER
BAS BUILDING AUTOMATION SYSTEM
BFF BELOW FINISHED FLOOR
BFP BACKFLOW PREVENTER
BHP BREAK HORSEPOWER
BOP BOTTOM OF PIPE
C CELSIUS
CO CLEANOUT
DCW DOMESTIC COLD WATER
DN DOWN
DOE DEPARTMENT OF ENERGY
DWG DRAWING
EC ELECTRICAL CONTRACTOR
EL ELEVATION
EPA ENVIRONMENTAL PROTECTION AGENCY
EPACT ENERGY POLICY ACT
ET EXPANSION TANK
EX EXISTING
F FAHRENHEIT
FBO FURNISHED BY OTHERS
FCO FLOOR CLEANOUT
FD FLOOR DRAIN
FDC FIRE DEPARTMENT (HOSE) CONNECTION
FM FLOW METER
FPC FIRE PROTECTION CONTRACTOR
FS FLOOR SINK
G GALLON
GC GENERAL CONTRACTOR
GCO GRADE CLEANOUTS
GPD GALLONS PER DAY
GPH GALLONS PER HOUR
GPM GALLONS PER MINUTE
HD HUB DRAIN
HP HORSEPOWER
HYD HYDRANT
INV INVERT
IPC INTERNATIONAL PLUMBING CODE
IW INDIRECT WASTE
1. REHABILITATION WORK CATEGORY: RENOVATION. SWAPPING OF FIRE SPRINKLER RISERS ON ONE-TO-ONE BASIS.
Engineers Architects
Revisions: Date
Drawing Title
Approved: Project Director
Project Title
Location
VA PROJECT NUMBER
Building Number
Drawing Number
Dwg of
VA FORM 08-6231
Office of Construction and Facilities Management
CONSULTANTS: PROJECT MANAGER
Date Checked Drawn
FULLY SPRINKLERED
ACG Project Number
Headquarters:
Apogee Consulting Group, P.A.
1151 Kildaire Farm Road, Suite 120 Cary, North Carolina 27511 www.acg-pa.com 919-858-7420 U.S. Department of Veterans Affairs# © COPYRIGHT Apogee Consulting Group, P.A.
/4
/2
:3
:0
A M
C
U s e rs \n s to lt z \D o c u m e n ts \F
-2
-1
R n s to lt z .r v t
FX001
FIRE SUPPRESSION GENERAL
INFORMATION AND DETAILS
2 17NAS, WLF
REPLACE FIRE SPRINKLERS
BLDG. 111
5000 W. NATIONAL AVENUE
MILWAULKEE, WI 53295
MAY 18, 2021
BID SET
695-19-10420-137
RBK
FIRE SUPPRESSION SYMBOLS
Scale: No Scale
MECHANICAL TEE AND FLUSHING CONNECTION DETAIL
Scale: No Scale
PIPE HANGER SUPPORT DETAIL
Scale: No Scale
SPRINKLER PIPE SLEEVE THRU FIRE RATED WALL
Scale: No Scale
TYPICAL FLOOR CONTROL VALVE ASSEMBLY DETAIL
FIRE SUPPRESSION DEMOLITION GENERAL NOTES
FIRE SUPPRESSION GENERAL NOTES
BUILDING AND OCCUPANT SAFETY - INTERRUPTION OF
FIRE PROTECTION SERVICE
INFECTION CONTROL MEASURES
Scale: No Scale
PIPE FLOOR SUPPORT DETAIL
PHASING PLAN
FIRE SUPPRESSION ABBREVIATIONS
LIFE SAFETY NOTES (NFPA-101)
1 AMENDMENT NO. 05 08/02/2021
DocuSign Envelope ID: 59B571C7-4F53-404E-B75F-6E06FB2A110E
8/4/2021
| Sheets |
| FX001 - FIRE SUPPRESSION GENERAL INFORMATION AND DETAILS |
| 2021-08-04T11:28:22-0700 | |
| Digitally verifiable PDF exported from www.docusign.com |
File details come from the government source that posted it. Updated .