36C25220R0053-0004004.pdf
PDF Posted
- Attached to
- Z2DA--Legionella Corrections, 537-18-301B Federal contract opportunity
- Solicitation number
- 36C25220R0053
About this file
This document provides details for a federal construction contract opportunity to address Legionella corrections at the Jesse Brown VA Medical Center in Chicago, Illinois. The contract is set aside for Service-Disabled Veteran-Owned Small Businesses and involves eliminating dead ends prone to harboring Legionella growth in the water distribution system and installing mixing valves to prevent scalding. Prospective offerors are encouraged to attend a pre-proposal site visit with additional details to be provided in the solicitation package. Proposals are due on or about March 23, 2020 for the contract, which has a magnitude between $1 million and $2 million. The work must be completed within 265 calendar days of receipt of a notice to proceed. Offerors must represent that they are an eligible SDVOSB concern under the assigned NAICS code of 238220 at the time of submission.
36C25220R0053 0004 Atch 04 00 01 10_REV1 Table Of Contents.pdf
View the file
Other files for this federal contract opportunity
Show all 26
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Jesse Brown VAMC March 30, 2020 Legionella Corrections Issued for Bid and Construction Chicago, IL Project No. 537-18-103B
04-01-19
00 01 10-1
DEPARTMENT OF VETERANS AFFAIRS
VHA MASTER SPECIFICATIONS
TABLE OF CONTENTS
Section 00 01 10 REV1
DATE Revisions
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00 REV1 General Requirements 12-18 3/30/2020 01 32 16.15
REV 1
Project Schedules (Small Projects – Design/Bid/Build 04-13 3/30/2020
01 33 23 Shop Drawings, Product Data, and Samples 05-17 01 35 26 Safety Requirements 02-17 01 42 19 Reference Standards 05-16 01 45 00 Quality Control 03-19 01 58 16 Temporary Interior Signage 07-15 01 74 19 Construction Waste Management 09-13
DIVISION 02 – EXISTING CONDITIONS
02 41 00 Demolition 08-17
DIVISION 05 – METALS
05 50 00 Metal Fabrications 08-18
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 84 00 Firestopping 02-16 07 92 00 Joint Sealants 10-17
DIVISION 09 – FINISHES
09 05 16 Subsurface Preparation for Floor Finishes 02-15 09 06 00 Schedule for Finishes 04-15 09 22 16 Non-Structural Metal Framing 06-18 09 23 00 Gypsum Plastering 10-15 09 24 00 Portland Cement Plastering 10-15 09 26 00 Veneer Plastering 10-15 09 29 00 Gypsum Board 06-18 09 51 00 Acoustical Ceilings 12-18 09 65 13 Resilient Base and Accessories 02-16 09 65 16 Resilient Sheet Flooring 05-18 09 68 00 Carpeting 10-15 09 91 00 Painting 01-16 09 96 59 High-Build Glazed Coatings 07-14
Jesse Brown VAMC March 30, 2020 Legionella Corrections Issued for Bid and Construction Chicago, IL Project No. 537-18-103B
04-01-19
00 01 10-2
DIVISION 22 – PLUMBING
22 05 11 Common Work Results for Plumbing 07-16 22 05 23 General-Duty Valves for Plumbing Piping 09-15 22 07 11 Plumbing Insulation 09-15 22 11 00 Facility Water Distribution 09-15 22 13 00 Facility Sanitary and Vent Piping 09-15 22 40 00 REV1 Plumbing Fixtures 09-15 3/30/2020
File details come from the government source that posted it. Updated .