This document contains a master submittal list and federal contract opportunity notice for a construction project to expand an emergency department at a VA medical center. The master submittal list details over 100 submittal items required for the project and organized by construction division. These include shop drawings, product data, samples, test reports, warranties, and operation and maintenance manuals for various construction systems and materials. The related federal contract opportunity is a pre-solicitation notice for a renovation project valued between $5-10 million to build a new radiology, police holding, and administrative area adjacent to an existing emergency department. The solicitation is expected to be issued on May 25th, 2021 and close on June 24th, 2021. This is a 100% set-aside for Service-Disabled Veteran-Owned Small Businesses. The work is to be performed at the James H. Quillen VA Medical Center in Mountain Home, Tennessee.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C24921B0008 0002.pdf | ||
| 081710_Add1.pdf | ||
| 000110_Add1.pdf | ||
| Amendment 0001.pdf | ||
| 087100_Add1.pdf | ||
| Revised drawings 6-21-2021.pdf | ||
| 010000_Add1.pdf | ||
| 224000 Add1.pdf | ||
| 099659_Add1.pdf | ||
| Amendment Summary.pdf | ||
| Pre bid sign in sheet.pdf | ||
| RFI Form - Expand Emergency Dept.pdf | ||
| Mt Home ED Final CD Specs_Revised 210512.pdf | ||
| WD TN20210111 1-1-2021.pdf | ||
| Mt Home ED Final CD Drawings _Revised 210512.pdf | ||
| 36C24921B0008_1.pdf | ||
| Contractor EMR Certification Form.pdf | ||
| 36C24921B0008.docx | DOCX document |
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Section Submittal
Group Description
01 33 23
THIS SECTION APPLIES TO ALL SUBMITTALS IN THE PROJECT SPECIFICATIONS
Security Plan
Duplicate Keys and lock combinations
Electronic security memorandum
Phasing plan
As-built drawings
013216.01 1 3 blue line copies of the complete CPM schedule within 45 calendar days after receipt of Notice to Proceed
Qualification proposal to COR within 10 days of bid acceptance
Provide all computer-produced time/cost estimates monthly
Submit 3 blue line copies of interim schedule within 20 days of notice to proceed
Cost per work activity/event and responsibility code for all activities/events
Supporting data to project schedule
Electronic file containing all info needed to produce a schedule
Submit monthly AIA application and certificate for payment documents
Submit updated schedule after each monthly schedule meeting
Within 30 days of VA approval of updated project schedule, submit revised electronic file of activity/event changes
Submit any requests for change of completion date to contracting officer and show all CPM logic revisions, durations changes, and cost changes
Preconstruction Submittals
Updated Submittal Register
Submit the APP to the COR for review 15 days prior to the date of preconstruction conference for acceptance.
Submit AHAs to the COR at least 15 calendar days prior to the start of each phase.
Deficiencies in submitted APP will be brought to the COR within 14 days of submittal and contractor shall revise the plan.
Submit training records to COR for review for compliance with contract requirements 15 calendar days prior to the date of preconstruction conference for acceptance.
1 Interim CQC Plan
2 CQC Plan
Accreditation Requirements
Written Reports
Verbal Reports
01 57 19 1 Environmental Protection Plan
Debris Management Plan
Waste Management Plan
Monthly summary of construction and demolition debris diversion and disposal
Master Submittal List
DIVISION 01
01 00 00
01 32 16.15 1
01 33 23 1
01 35 26 1
01 45 00
01 45 29 1
01 74 19 1
Sustainability Action Plan
Project Materials Cost Data
Low Pollutant-Emitting Materials Tracking Spreadsheet
Construction Indoor Air Quality Management Plan
Products
Sustainable Construction Progress Report
Closeout
Survey Report
Circuit Trace Report (see Electrical Drawings)
01 81 13 1
02 41 00 1
DIVISION 02
DIVISION 03 - NOT USED
Shop Drawings
Manufacturers Certificates
Design Calculations for specified live loads including dead loads
Furnish setting drawings and instructions for installation of anchors to be preset into concrete masonry work
Sustainable Design
Shop Drawings
Manufacturer's Literature and Data
Manufacturer's Certificate for unmarked labor
Submittal drawings
Manufacturer's Lit and Data
Samples
Sustainable construction submittals
Certify each product complies comply with specifications
Substantiate qualifications comply with specifications
06 10 00 1
06 20 00 1
05 50 00
DIVISION 06
DIVISION 05
DIVISION 04 - NOT USED
Shop Drawings, Product Data and Samples
Submittal Drawings
Manufacturer's Literature and Data
Photographs
Field Inspection Reports
Infrared Roof Moisture Survey Report
Submittal drawings
Manufacturer's Literature and Data
Sustainable Construction Submittals
Submittal Drawings
Manufacturer's Literature and Data
Samples
Sustainable Construction Submittals
Certificates
Qualifications
Field quality control reports
Temporary protection plan
Operation and Maintenance Data
Manufacturer's Literature and Data
Certificates
Miscellaneous Items
Sustainable Design
Installer Qualifications
Inspector Qualifications
List of FM, UL, or WH classification number of systems installed
Certified laboratory test reports for ASTM E814 test for systems not listed by FM, UL, or WH proposed for useManufacturer's Literature and Data
Submit Certificates from Manufacturer
Lab Tests
Joint Certification
Sustainable Design
Installer Qualifications
Contractor Qualifications
Cured samples of exposed sealants for each color
07 21 13 1
07 84 00 1
07 92 00 1
The following sections are to be submitted concurrently for review: 072200, 072726, 075419, 076000, 077200
07 01 50.19
DIVISION 07
07 54 23 1
Shop Drawings
Manufacturers Literature and Data
Sustainable Construction Submittals
Test Reports
Substantiate qualifications comply with specifications
Shop Drawings
Manufacturers Literature and Data
Sustainable Construction Submittals
Test Reports
Samples
Operation and Maintenance Data
Shop Drawings
Manufacturer's Literature and Data
Sustainable Submittal
Certificates
Qualifications
Operation and Maintenance Data
Warranty
Shop Drawings
Manufacturer's Literature and Data
Sustainable Construction
Product Data for each element of work
Manufacturer's standard color chart
Certificates
Shop Drawings
Submittal Drawings
Manufacturer's Literature and Data
Samples
Sustainable Construction Submittals
Test Reports
Certificates
Qualifications
Delegated Design Drawings and Calculations
Operation and Maintenance Data
Submittal Drawings
Manufacturer's Literature and Data
Sustainable Construction Submittals
Certificates
Qualifications
Hardware Schedule
Samples and Manufacturer's literature
Certificate of Compliance
Submittal Drawings
Manufacturer's Literature and Data
Sustainable Construction Submittals
08 41 13 1
08 56 66 1
08 17 10 1
The following sections are to be submitted concurrently for review: 081113, 081400, 084113, 087100, 087113
DIVISION 08
08 71 13 1
08 71 00 1
08 14 00 1
08 11 13 1
08 31 13 1
08 34 53
Test Reports
Qualifications
Operation and Maintenance Data
Sustainable Design
Manufacturer's Certificates
Manufacturer's Warranty
Manufacturer's Literature and Data
Samples
Preconstruction Adhesion and Compatibility Test Report
Shop Drawings
Manufacturer's Literature and Data
Color Samples
Written approval confirming product compatibility with subfloor material manufacturer and flooring manufacturer
Product Data
Test Data
Manufacturers Literature and Data
Shop Drawings
Test Results
Manufacturers Literature and Data
Shop Drawings
Samples
Test Results
Certificates
Sustainable Design
Samples
Product Data
Certification
Installer Qualifications
Samples
Manufacturers Literature and Data
Manufacturers Certifications: Acoustical units, each type, in accordance with specification requirements
Manufacturers Literature and Data
Samples
Sustainable Construction
Operation and Maintenance Data
Manufacturer's Literature and Data
Samples
Sustainable Construction
Certifications
Qualifications
Warranty
Sustainable Design
Manufacturers Literature and Data
Samples
Shop Drawings
09 65 16 1
09 29 00 1
09 30 13 1
09 51 00 1
09 22 16 1
09 05 16 1
08 71 13 1
DIVISION 09
09 65 19 1
08 80 00 1
08 90 00 1
09 65 13
Test Reports
Manufacturers Literature and Data
Qualification Data
Sustainable Submittal
Samples
Shop Drawings
Certifications and Approvals
Warranty
09 67 23.20 1
Sustainable Design
Painter Qualifications
Manufacturer's Literature and Data
Sample Panels
Sample of Identity Markers
Manufacturer's Literature and Data
Manufacturers Literature and Data
Qualification Data
Sustainable Submittal
Samples
Shop Drawings
Certifications and Approvals
Warranty
Sustainable Design Submittals
Interior Sign Samples
Exterior Sign Samples
Manufacturer's Literature
Sign Location Plan
Shop Drawings
Full size layout patterns for dimensional letters
Manufacturer's Qualifications
Installer's Qualifications
Samples
Shop Drawings
Manufacturer's Literature and Data
Sustainable Design Submittals
Shop Drawings
Manufacturer's Literature
Manufacturer's Qualifications
Product Qualifications
Service Qualifications
O & M Manuals
2 Certifications Comply with Contract Documents
Certifications Properly installed, adjusted and tested in accordance with Manufacturer's instructions.
Sustainable Design
Shop Drawings
Manufacturer's Literature and Data
Test Report
Manufacturer's Qualifications
Installers Qualifications
Manufacturer's Warranty
Shop Drawings
Manufacturer's Literature and Data
Samples
Manufacturer's Certificates
Qualifications
10 21 23
10 28 00 1
10 14 00
10 25 13
09 91 00 1
Division 10
09 96 59 1
10 26 00
Operation and Maintenance Data
10 44 13 1 Manufacturer's Literature and Data
Shop Drawings
Manuals
Certifications
Manufacturers Literature and Data
Samples
Shop Drawings
Fire Testing
Manufacturer's warranty
Manufacturers Literature and Data
Samples
Shop Drawings
Certification
Shop Drawings
Samples
Coordinated set of equipment anchorage drawings prior to installation
Coordinated set of bracing drawings for seismic protection of piping prior to installation
Bracing drawings for seismic protection of suspended ductwork and suspended electrical and communication cables
Design Calculations
ICBC Evaluation Reports
Design Calculations
Submittal Drawings
Manufacturers Literature and Data
Samples
Sustainable Construction Submittals
Test Reports
Qualificationns
Delegated Design Drawings and Calculations
Operation and Maintenance Data
Manufacturers Literature and Data
Shop Drawings
Qualifications
Coordination Drawings
Manufacturer's Literature and DATA Sheets For: All Products Listed
Calculations
As Built Drawings
Valve Charts
Testing Certificates
O&M Manuals
113 05 41
12 24 21 1
12 36 00 1
DIVISION 13
DIVISION 12
12 32 00 1
DIVISION 21
21 13 13
DIVISION 14
14 92 00 1
DIVISION 11
11 05 12 1
13 49 00 1
Manufacturer's Literature And DATA For:
All Part 2 Products
Welders Certificates
Hangers, Inserts, Supports And Bracing
Wall Floor And Ceiling Plates
Pipe Sleeves
As-Built Documentation -
Drawing Red Lines
Final Testing Certifications
O&M Manuals For All Sections Submitted Together
Submit Under Driven Product
Manufacturer's Literature And DATA
Shop Drawings
3 Certification
4 O&M Manuals See 22 05 11
Manufacturer's Literature And DATA For:
All Part 2 Products
As Built Documents
Valve Charts
O&M Manuals See 22 05 11
Manufacturer's Literature And DATA For:
Ball Valves
Balancing Valves
Check Valves
3 Test And Balance Reports For Balancing Valves
4 O&M Manuals See 22 05 11
Manufacturer's Literature And DATA For:
Each Insulation Type
2 Samples
22 08 00 See Section 01 91 00 For Commissioning Requirements
Manufacturer's Literature And DATA For:
All Part 2 Products
As-Built Documentation - See 22 05 11
O&M Manuals See 22 05 11
Manufacturer's Literature And DATA For:
All Part 2 Products
As-Built Documentation - See 22 05 11
O&M Manuals See 22 05 11
DIVISION 22
22 05 11
22 05 12
22 05 19
22 05 23
22 07 11
22 11 00
22 13 00
Manufacturer's Literature And Data For:
All Fixtures
3 O&M Manuals For All Sections Submitted Together
Installer Qualifications
Testing Agency Qualifications
Certifications
As-Built Documentation - See 22 05 11
O&M Manuals See 22 05 11
Manufacturer's Literature And DATA For:
All Part 2 Products
Installer Qualifications
Testing Agency Qualifications
Certifications
As-Built Documentation - See 22 05 11
O&M Manuals See 22 05 11
1 Coordination Drawings
Manufacturer's Literature And Data
Equipment And Materials Identification
Hangers, Inserts, Supports, Bracing
Wall, Floor And Ceiling Plates
5 O&M Manuals For All Sections Submitted Together
Shop Drawings
Manuals
Certifications
Completed System Readiness Checklist
Manufacturer's Literature And Data
Vibration Isolators: Floor Mountings, Hangers, Snubbers, Thrust Restraints
1 Names And Qualifications
2 Design Review Report
3 Duct Leakage Report
4 System Readiness Report
Final Tab Report
Vibration Test Report
Sound Test Report
Shop Drawings
Samples
23 08 00 1 Commissioning related submittals
Manufacturer's Literature and Data
Product Certificates
Licenses
As Built Control Drawings
O&M Manuals
Performance Report Prior to Final Inspection
22 63 00
Division 23
23 05 11 2
23 05 12 1
22 40 00
22 62 00
23 05 93
23 07 11 1
23 09 23 1
23 05 41
Manufacturer's Literature and Data
Certified Data Report
Welder's Qualifications
Coordination Drawings
As-Built Piping Diagrams
As-Built Piping Diagrams
Shop Drawings
Certifications
Design Manual
1 Coordination Drawings See 23 05 11
Manufacturer's Literature And Data For:
Schedule Of Duct Systems
Sealants And Gaskets
Volume Dampers And Back Draft Dampers
Hangers
Flexible Connections
Flexible Duct And Accessories
Instrument Test Fittings
Manufacturer's Literature and Data
Certified Sound Power Levels
Motor Ratings
Belt Guards
O&M Manuals
Certified Fan Performance Curves
Roof Curbs
Manufacturer's Literature and Data
Samples
Certificates
O&M Manuals
Manufacturer's Literature And Data For:
Air Inlets And Outlets
General Requirements
Requirements
O&M Manuals
Samples
1 Shop Drawings and Product Data
2 Certifications
1 Shop Drawings - Plans and Product Data
Field Test Reports
Certifications
1 Shop Drawings - Plans and Product Data
2 Certifications
1 Shop Drawings - Product Data and Drawings
26 05 33
126 05 11
26 05 36
26 05 19
26 05 26
Division 26
23 21 13 1
23 34 00 1
23 36 00 1
23 37 00 1
23 23 00 1
23 31 00
2 Certifications
Product Data - Software
Completed study
2 Certifications
1 Shop Drawings and Product Data
2 O&M Manuals
3 Certifications
1 Shop Drawings and Product Data
2 Certifications
3 O&M Manuals
Shop Drawings and Product Data
Seismic Certification
O&M Manuals
Certifications
1 Shop Drawings and Product Data
2 Manuals
3 Certifications
Shop Drawings and Product Data
Manuals
Certifications
1 Shop Drawings and Product Data
2 Manuals
3 Certifications
1 Shop Drawings and Product Data
2 Manuals
3 Certifications
1 Shop Drawings and Product Data
2 Manuals
3 Certifications
Parts List
Manufacturer Product Information
Source Quality Control
Installer Qualifications
Delegated Design
Equipment Anchors and Support
Test Equipment List
Submittal Drawings
Sustainable design
2 Test reports
Closeout submittals
Maintenance Material Submittals
27 05 11 Requirements
Shop Drawings and Product Data
Test Reports
Certifications
27 05 11 Requirements
Shop Drawings and Product Data
26 43 13
26 22 00
27 05 11
26 29 21
26 51 00
26 29 11
26 27 26
26 05 73
26 05 36
27 05 26
26 09 23
26 24 16
Division 27
27 05 33
2 Certifications
27 05 11 Requirements
Certifications
Shop Drawings and Product Data
2 Closeout Submittals
27 05 11 Requirements
Pictorial Layouts
Equipment Technical Literature
Environmental Requirements
27 05 11 Requirements
Shop Drawings and Product Data
Certifications
2 Closeout submittals
27 10 00
27 11 00 1
27 15 00
Drawings and Product Data
Interconnection Methods
Equipment Technical Literature
System Engineering Drawings
System Survey
O&M Manuals
As-Built
Submittals shall be in full compliance of the Contract Documents
Group 1 Technical Data Package
Group 2 Technical Data Package
Group 3 Technical Data Package
Group 4 Technical Data Package
Group 5 Technical Data Package
FIPS 201 Compliance Certificates
Samples
Completed System Readiness Checklist
Manufacturer's Literature and Data
Shop Drawings
Wiring Diagrams
Cable Administration Drawings
Project Planning Documents
Certificates
Maintenance Data
Certificates of Compliance
Pre-installation and As-Built Design Package
Manufacturer Security System Cut Sheets
Certification of Underwriter's Laboratories
2 Systems Readiness Checklists
1 Shop Drawings and Product Submittals
2 Manuals
3 Certifications
Submittals shall be in full compliance of the Contract Documents
Rock Excavation Report
Furnish to COR ( Personnel resumes, Soil samples & Procedure/Location for disposal of unused material)
28 23 00
28 31 00
28 05 00 1
28 05 13
27 52 23
Division 28
Division 31 - NOT USED
31 20 00 1
1 Submittal Drawings
Manufacturer's Literature and Data
Samples
Test Reports
Certificates
Qualifications
Concrete Mix Design
Select subbase job mix design
Proposed hot and cold weather concreting methods
Land surveyor's construction staking notes, before placing concrete
Submittal Drawings
Manufacturer's Literature and Data
Certificates
Qualifications
32 31 40 1
32 05 23
Division 32 - NOT USED
File details come from the government source that posted it. Updated .