36A77619Q0091-0001001.docx
DOCX document 90 KB Posted
- Attached to
- Phoenix OPC IOTA IDIQ CO: Heidi Gallaher
- Solicitation number
- 36A77619Q0091
About this file
36A77619Q0091 0001 ATTACHMENT O - Task Order 1 Phoenix Outpatient Clinic PWS.docx
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36A77619Q0091-0001000.docx | DOCX document | |
| 36A77619Q0091-0001002.docx | DOCX document | |
| 36A77619Q0091-004.doc | DOC document | |
| 36A77619Q0091-012.docx | DOCX document | |
| 36A77619Q0091-005.xlsx | XLSX spreadsheet | |
| 36A77619Q0091-008.pdf | ||
| 36A77619Q0091-009.docx | DOCX document | |
| 36A77619Q0091-010.docx | DOCX document | |
| 36A77619Q0091-006.pdf | ||
| 36A77619Q0091-007.pdf | ||
| 36A77619Q0091-003.docx | DOCX document | |
| 36A77619Q0091-015.pdf | ||
| 36A77619Q0091-002.docx | DOCX document | |
| 36A77619Q0091-011.pdf | ||
| 36A77619Q0091-018.xls | XLS spreadsheet | |
| 36A77619Q0091-017.docx | DOCX document | |
| 36A77619Q0091-016.docx | DOCX document | |
| 36A77619Q0091-014.pdf | ||
| 36A77619Q0091-013.xlsx | XLSX spreadsheet | |
| 36A77619Q0091-000.docx | DOCX document | |
| 36A77619Q0091-001.docx | DOCX document |
Show all 21
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PERFORMANCE WORK STATEMENT (PWS)
DEPARTMENT OF VETERANS AFFAIRS
Veterans Health Administration (VHA)
Phoenix Outpatient Clinic Phoenix VA Health Care System in Phoenix, AZ Project Title:
INITIAL OUTFITTING, TRANSITION, AND ACTIVATION SERVICES (IOT&A) IDIQ
Task Order #1 Project Management Support & Activation Pre-Planning Services Date:
March 26, 2019 PWS Version Number:
3.0
1.0 BACKGROUND / INTRODUCTION
The Phoenix Outpatient Clinic is a new lease, approximately 203,000 net usable square feet (NUSF) Outpatient Clinic in the vicinity of Phoenix, AZ, including 1,370 parking spaces. The new facility would expand VA outpatient services by closing space and utilization gaps identified in the Strategic Capital Investment Planning (SCIP) process. This project would allow VA to enhance and expand these services provided to Veterans in a right-sized, state-of-the-art, energy efficient health care facility.
2.0 SCOPE OF WORK
Contractor shall conduct all necessary Planning, Initial Outfitting, Transition, and Activation (OIT&A) activities in accordance with this Preformance Work Statement (PWS). The Contractor shall provide professional services to include all labor, materials, transportation, and equipment to conduct and provide IOT&A support services to accomplish the PWS tasks. The scope includes project support for planning, outfitting, and transitioning the staff and patient services associated with the Phoenix Project Management Office. This task order includes comprehensive project management support services, comprehensive interior design and space planning services, CONOPS, STRATCOM, and Transition Planning and acquisition planning.
The CBOC ”Day One” date is expected tentatively beginning of November 1, 2021.
3.0 PERIOD OF PERFORMANCE
The period of performance under this task order shall be thirty (30) months from date of award.
4.0 TYPE OF ORDER
Award will be made on a Firm-Fixed-Price basis.
5.0 PLACE OF PERFORMANCE
Tasks under this PWS shall be performed off-site at the contractor’s facility and at the Government sites listed below. For work performed at a Government facility, contractor will be required to meet at the existing and new OPC locations, and main hospital:
Phoenix Outpatient Clinic SW Corner 32nd Street and Van Buren, Phoenix AZ
6.0 TRAVEL
The Government anticipates travel to perform the tasks associated with the effort, as well as to attend program-related meetings throughout the Period of Performance. The Government will award firm-fixed price travel for this Task Order. Pre-approval by the COR is not necessary for any travel associated with this Task Order. The estimated number of trips, anticipated locations, and estimated duration of trips in support of the tasks is to be determined by the Contractor and provided as part of quote and Task Order award.
7.0 specific tasks and deliverables:
7.1 COMPREHENSIVE PROJECT MANAGEMENT SUPPORT SERVICES
The Contractor shall provide comprehensive project management support to the Phoenix VA Health Care System for the IOT&A tasks identified below. The Contractor shall utilize Project Management Institute (PMI) best practices to manage cost, schedule, quality, risk and resources. The Contractor shall provide expertise to support contract execution per established strategies and plans, support all program milestones, and provide support for briefings and meetings as required. The Contractor shall submit a Monthly Status Report to communicate to the VA the status of the project, progress, and lessons learned.
The PM designated to serve as the Government’s primary point of contact shall be responsible for the overall coordination and scheduling of the contract team's work. The PM shall not be reassigned without notification to the CO. The PM must be on-site to facilitate, schedule, and lead regular meetings with the Phoenix VA Health Care Sytem staff, to ensure the timely and effective completion of tasks and deliverables required this each task order.
In addition to the plans, schedules, and report requirements detailed in the deliverable schedule below, the following additional guidance shall be followed for submission of the Share Site, Integrated Master Schedule (IMS), and Meeting Facilitation:
Contractor Share Site for Information Sharing: The Contractor shall develop and maintain a SharePoint-like site for project documentation and information sharing. The site or software shall be able to provide automatic email updates to designated members as new documents are uploaded or require Government review (example: Submittal Exchange). All project documentation shall be compatible with systems utilized by the medical facility and easily accessible with files downloadable by all parties. The database shall meet "for official use only" (FOUO) and sensitive but unclassified information handling requirements. The site shall be organized in a logical manner.
Project schedules, project reports, and management plans shall be shared with the Government by posting on the Contractor's SharePoint-like site. Updating shall be completed as required per the deliverable schedule and posted on the Contractor share site, unless otherwise agreed upon by the COR. Revisions to schedules and plans since the last update shall be tracked and clearly identified.
Activation Integrated Master Schedule (AIMS): The Contractor is responsible for developing and managing an AIMS. The AIMS must coordinate the Activation Project Schedule, IT Project Schedule, Construction Schedule, and any other applicable milestones dates that impact the activation of the project. This entails coordination with the VA Office of Construction and Facilities Management, the construction Contractor, the Office of Information & Technology, Contracting Office(s) involved and other programs/experts as required. Services may include the preparation of various professional reports and presentations, including verbal, graphic, slides, and photographs of projects.
In managing the AIMS, the Contractor shall advise the Government of suspense dates that need to be met by the Government and/or Government Contractors to ensure on-time execution such as, but not limited to, delivery dates for items purchased by the Government, information that the Contractor needs from the Government to complete the requirements of the tasks, and certain AIMS milestone dates. The Contractor is responsible for tracking these dates and keeping the parties informed. However, the Contractor is not responsible for enforcing dates or ensuring work is completed on schedule to the extent the dates and/or work are not a requirement of the Contractor as described herein. The Contractor shall report in a timely manner any schedule deviations to the Activation Team, CO and COR. Upon the Government's acceptance of the schedule deviation, the Contractor shall prepare and submit for approval a revised AIMS.
In the event a schedule deviation impacts the period of performance of the task order, the Contractor shall provide in writing to the CO the reason for the delay, associated points of contact, and a request for extension. Extension requests must detail the amount of additional time required and are not automatically granted.
Meeting Facilitation Services: The Contractor shall schedule meetings with key stakeholders and appropriate personnel (to be identified by the Government). Where meeting frequency is not specified herein, the Contractor shall establish the meeting frequency in manner that ensures the ability to meet the requirements of the task order. Meetings include project status meetings, CONOPs meetings, planning meetings, information management meetings, user group meetings, and any additional meetings as deemed necessary by the Contractor to meet the requirements of the task order.
The Contractor shall prepare meeting agendas which shall be distributed to attendees 48 hours prior to the subject meeting. The Contractor shall prepare meeting minutes. Meeting minutes shall document the purpose of the meeting, discussions, and decisions reached. When applicable, meeting minutes shall include "ACTION ITEMS" to include a description of the item, the responsible individual(s), and due date. Meeting minutes will be distributed to attendees for review and approval.
The Contractor shall organize and conduct user-group meetings with key stakeholders and working groups across the facility to the extent required to adequately manage this activation project. A list of key stakeholders will be provided to the Contractor after award.
At a minimum, each department will constitute a working group. The Contractor may identify additional ad hoc groups as necessary. The Contractor shall guide groups to consensus by identifying requirements, facilitating group discussions, and documenting decisions as a part of the documentation of meeting minutes. The Contractor shall facilitate the groups to assess, analyze, recommend, and document solutions as developed jointly by the Contractor and the stakeholders and/or group members.
| Deliverable # |
| Deliverables |
| Description |
| Due Date |
| TO1-001 |
| Activation Project Schedule |
| Contractor shall develop, or update an draft, and mainntaine a detailed activation project schedule. The Activation Project Schedule shall track all major milestones to demonstrate effective management and execution of the project by the contractor, illustrate timely performance, and identifies delays or potential delays to the project. The Activation Project Schedule shall include dates from the construction schedule through Day One, and project closeout. The schedule shall identify key tasks, start and completion dates, duration of tasks to be completed by the contractor to satisfy the requirements of the PWS. The contractor shall annotate any schedule deviations in monthly updates. |
1 Month from Task Order award; updated monthly
| TO1-002 |
| Individual Service Project Schedules |
| Contractor shall develop a detailed Individual Service Project Schedule created from the Activation Project Schedule to provide individual reports to specific services. The details included in the Activation Project Schedule shall also be included in the Individual Service Project Schedules. |
| 1 Month from Task Order award; updated monthly |
| TO1-003 |
| Activation Integrated Master Schedule (AIMS) |
| The AIMS shall be a color coded, time-lined graphic which marks the start and end dates of major element or sub-element milestones/gateway of construction which may impact the start, duration, or completion date of scheduled IOT&A tasks, shows major start and end dates of milestone/gateway events for purchased items, shows scheduled activities in activating or approving building systems and support contracts, and shows IOT&A events which may be impacted by schedule acceleration or slippage by others. A complete AIMS will include and demonstrate all construction milestone/gateway dependencies with both Government and contractor IOT&A-related processes from contract award to the completion of the contract itself. |
| 1 Month from Task Order award; updated monthly |
| TO1-004 |
| Project Phasing and Facility Staffing Plan |
| The Plan shall identify the number and types of positions that are recommended for hire and/or transfer from existing facility to staff the new facility. VA staffing requirements can be located at http://vaww.va.gov/ohrm/HRLibrary/Dir-Policy.htm. The plan shall be submitted with each stage of the AIMS submissions. |
| 2 Months from Task Order award; updated monthly |
| TO1-005 |
| Integrated Staff “Faces and Spaces” Program |
| The contractor shall provide a program which identifies personnel, service, equipment, and location which is flexible to location and changes for the existing location in transition to the new location. The contractor shall use the program to create a move plan and identify any special characteristics of the space. In addition, the Faces to Spaces will show any re-use equipment, existing jack numbers for personnel that will be relocating and any equipment this is relocating that is currently connected to the VA network. |
| 6 Months from Task Order award; updated monthly |
| TO1-006 |
| Transition Plan |
| The contractor shall develop and maintain a transition plan for each TO ensuring that it is updated to reflect the current status and changes as they occur throughout the life of the project. The transition plan at a minimum should address all major actions necessary for successful completion of project or as described in the TO. The transition plan should, at a minimum, include a delivery and installation plan, a government acceptance plan, a security plan, a sequencing and outfitting plan, a calibration and testing plan, a department master move schedule, a department activity (individual service report), a cleaning and housekeeping plan, a training plan and a Day in the Life plan. |
| 6 Months from Task Order award; updated monthly |
| TO1-007 |
| Monthly Project Status Report |
| The Monthly Project Status report shall give an overview of the progression of the project and describe the work completed during the reporting/billing period. The report shall include status of milestone items in the master project schedule, discuss moderate to high risk items, and a summary of meetings attended. The report shall discuss any “lessons learned” during the reporting/billing period. The Monthly Project Status Report shall correlate to and be submitted with the monthly invoice. The report shall cover the same time period as the invoice |
| 1 Month from Task Order award; updated monthly |
| TO1-009 |
| Risk Management Plan |
| The Contractor shall submit a Risk Management Plan. The plan shall include an itemized listing of project-specific risks, challenges and perceived problems that are anticipated to threaten the project. Risks identified shall include probability of occurrence, and level of impact. With each issue specified, the Contractor shall list their proposed solution to mitigate or resolve the risk/challenge/problem. The plan shall cover all phases of the work. When identifying risks/solutions the Contractor should consider items in areas that may cause the project to: |
-not be completed on time. Proposed execution schedule will be evaluated as part of the technical factor;
-not finish within budget;
-generate change orders;
-result in owner dissatisfaction;
-result in poor quality of services; and/or -any other areas identified by the IOT&A contractor.
Risk Management should be a regular coordination meeting agenda item to ensure Risks are being managed per the RMP. The RMP shall be updated as additional risks are identified through coordination meetings or day to day project execution.
1 Month from Task Order award; updated monthly
| TO1-010 |
| Change Management Plan |
| The Contractor shall develop and submit a Change Management Plan for the Design and Construction Phases, with the purpose of minimizing cost and schedule risks associated with changes to the project scope. The Contractor shall identify appropriate members for a Change Management Committee, which will include key VA personnel and contractor personnel, and may include participation by representatives of the non-VA contributors to this project. The Change Management Plan shall develop processes for submitting, reviewing, and approving or disapproving change requests. The Change Management Committee will review all change requests and make recommendations to the Gainesville Primary Care CMO, who is the final approval authority for all proposed changes. |
| 1 month from Task Order award; updated monthly |
| TO1-011 |
| Share Site for Information Sharing |
| Develop and maintain a Share site for information sharing amongst all key stakeholders. The site shall be organized in a logical manner |
| 1 Month from Task Order award; updated as required |
| TO1-012 |
| Meeting Minutes |
| Minutes of all meetings to include agenda, attendees, discussions, action items and who is responsible, etc. |
| 48 hours after meeting |
| TO1-013 |
| Meeting Facilitation Report |
| Report to include all meetings scheduled and facilitated. Report should include a copy of all meeting minutes provided and proof of dissemination. |
| 1 Month from Task Order award; Monthly thereafter |
7.2 DESIGN AND PLANNING SERVICES
Provide comprehensive interior design (CID) services or coordination of CID services, ensuring incorporation of evidence-based healthcare concepts. FF&E must complement any interior packages developed by the Architect/Engineer firm associated with the construction project and/or the healthcare facility’s standards as provided by the Government. The Contractor may be required to identify FF&E to purchase, receive and install FF&E and visual arts and/or inventory, uninstall, pack, and reinstall existing FF&E and visual arts in the healthcare facility’s current inventory identified for reuse in the new facility following approval by the COR. Design support services include developing a basis of design for the FF&E, laying in FF&E for each work area on floor plans, design reviews, developing 3D designs of space with FF&E, and preparing cut sheets for FF&E and artwork.
The Phoenix VA Health Care System will use Attainia software (license provided by the Government for use by the IOT&A Contractor) to manage its FF&E for this activation project. The IOTA contractor will validate FF&E (room content list) for this project. “Validating” in the sense means a generic item has been identified by a specific manufacturer and model has not yet been identified.
IOT&A Contractor will develop the Attainia list from the “validated” phase through the “approved” phase. “Approve” in this sense means the manufacturer and model has been selected, to include the salient characteristics of the item. The IOT&A Contractor will be responsible for finalizing furniture, fixtures, and artwork with end users with the purpose of moving the items from “validated” to “approved” in the Attainia database. The IOT&A Contract shall upload and update the Attainia database. The IOT&A Contractor shall coordinate with the Attainia Contractor for database training for project maintenance.
The IOT&A Contractor will be responsible for identifying salient characteristics for all FF&E with the end users and for recording in the Attainia database. This also ties in to the acquisition support services required under this PWS as the end-user identified salient characteristics will be included in “brand name or equal” procurement packages. A completed Justification and Approval (J&A) form will be required to be included in any procurement packages for any items that require a specific manufacturer or model.
The Attachement C FF&E List is the most recent Project Content List available. Please note that this list does not include the removal of the following clinics from the list; Digestive Diseases, Physical Medicine, Employee Wellness, Audiology & Speech Pathology, Comp. & Pension, Eye Clinic and Prosthetics. The Primary Care and Mental Health Clnics have been expanded from the original space program and a small Veteran Resource Center has been added.
The Contractor shall develop the initial design based upon the FF&E list (Attachment C). The contractor will lay into the drawings provided by the VA all the FF&E based upon the equipment list and program for design information. The drawings provided by VA may be limited to walls and mechanical, electrical, and plumbing (MEP) locations. The general contractor will be required to identify all MEP information necessary and timelines needed. The IOT&A contractor is to develop the make and model of all equipment with DD2 submittal. The VA will be responsible to provide the correct points of contact for the user group meetings and the authority to make equipment decisions such as identification of make and model of equipment, locations of all equipment, and any Justifications and Authorizations (J&As) planned for the procurement of specified equipment. Upon completion of the Contractor's initial design (to include all furniture, equipment, medical equipment, artwork, desktop technology equipment, copiers, printers, fax machines, etc.) the Contractor shall review for code and work flow efficiency. In addition, the Contractor shall call out in each room all utility conflicts and recommended resolutions. Items shall be color-coded on the drawings (i.e. reuse = red, construction contractor provided = black, IOT&A installed = blue) for easy identification.
After the initial layouts have been completed, the Contractor shall send the drawings and room equipment lists to the COR for government review and comment. The Government will have 15 days to review and comment and will return the drawings to the Contractor to update.
Activation contractors can assume that the accelerated timelines below exist for submittal reviews:
| Design Development 1 |
| within 45 calendar days of award |
| VA Review |
| 15 working days |
| Design Development 2 |
| within 30 calendar days after VA review |
| VA Review |
| 15 working days |
| 75% Construction Documents |
| within 45 calendar days after DD2 approval |
| VA Review |
| 15 working days |
| 100% Construction Documents |
| within 30 calendar days after VA review |
| VA Review |
| 15 working days |
The IOT&A contractor will provide their own basis of design room typicals, salient characteristics, data sheets, room by rooms lists, and provide to the VA thirty days after signing the lease by he VA. This is to give the general contractor’s A/E time to incorporate the provided basis of design into the first submittal back to the VA. This information may be limited to specified furniture and equipment manufacturers pre-selected as a basis of design only.
User group meetings shall be scheduled approximately seven days after the Government provides the Contractor its comments to the initial design. At the user group meetings, the Contractor and Government stakeholders will go through each room and discuss the layout and equipment designed in each room. The IOT&A Contractor shall advise the Attainia POC to attend and participate in these meetings. Any corrections will be made at this meeting along with an update of salient characteristics for the FF&E so that the Basis of Design can be completed. Estimation is one day charrettes for each department. Once completed, a sign-off from the COR will close the effort.
The contractor shall verify the as-designed MEP will support the new design and identify any potential issues related to required utilities for planned FF&E. The contractor shall verify the design meets with applicable state, local, and federal requirements (e.g. ADA, Building Codes, NFPA 101,etc.). The Contractor shall notify the COR of any discrepancies. A gap analysis will be performed where discrepancies are identified between Concept of Operations (CONOPS), requirements, and infrastructure provided in accordance with the construction documents, with facilitation towards workable solutions. The Contractor shall develop finish selections to complement the interior design package provided by the Government. These selections shall be presented in a finalized color board.
The Contractor shall develop the artwork package. Artwork involves a detailed design process which includes selection of the artwork, sizing, and placement. Each piece of art shall be matted and framed. The design shall include the selection of the artwork, matting, glazing, and framing. Each piece of art shall be individually placed and mounted using approved security mounting. The design effort shall consider all types of artwork to include, but not limited to, donated art, recognition walls, purchased art, commissioned art, original art, installation/security, and matting/framing. Each piece of art should only be used once in the facility. The Contractor shall provide an artwork placement plan and artwork cut sheets.
| Deliverable # |
| Deliverables |
| Description |
| Due |
| TO1-014 |
| FF&E Cut Sheets |
| Cut Sheets shall include a photo of the item and the specifications, instructions, dimensions, etc., that apply that specific item. Cut sheet information shall be specific enough to convey information to the VA as they will need to purchase and install the product but general enough to allow competition across multiple manufacturers. Contractor shall prioritize cut sheets for long lead-time items. |
| 2 Months after Task Order award; updated monthly |
| TO1-015 |
| Artwork Cut Sheets |
| Artwork Cut Sheets shall include the following information: |
1) Job name, number, location, and date
2) The title of the artwork and the artist’s name, manufacturer (if applicable), item number, size and room number it is to be placed
3) A picture of the proposed artwork in color. If the piece is recommended or commissioned, provide a picture or brochure showing the commissioned artist’s work.
4) Frame description and sample 2 Months after Task Order award; updated monthly
| TO1-016 |
| Design Review Report |
| The Design Review Report documents the Contractor’s review of the as-designed mechanical, electrical, plumbing (MEP) to verify the building as designed will support the planned FF&E. The report shall document the Contractor’s gap analysis where discrepancies were identified between CONOPS, requirements and facility as designed, to include recommendations for workable solutions. The report shall also document the Contractor’s review of the space layout plan to verify planned placement of FF&E meets with applicable state, local and federal requirements (e.g., ADA, fire codes) |
| May 2019 ; Updated Monthly |
| TO1-017 |
| FF&E Layouts |
| Space plans showing FF&E placement. FF&E layouts are to be used for user group meetings, to assist in the validation of the FF&E, and to facilitate outfitting. Finalized FF&E layouts are by room are to be affixed to each room (on the door or other prominent location) to facilitate installation, inspection, and acceptance. Each layout shall identify the applicable location/room |
| May 2019; updated Monthly |
| TO1-018 |
| 3-Dimensional Design Renditions |
| 3D design renditions of FF&E items and 3D renditions of FF&E items within planned paces Revit, or other similar program agreed upon between the Contractor and the VA Interior Designer |
| TBD |
| TO1-019 |
| Artwork Placement Plan |
| The Artwork Placement Plan shall identify each piece of artwork and the planned location of each piece/composition of pieces. When applicable, the plan shall identify any unique mounting or other requirements/considerations for the piece(s). |
| TBD |
| TO1-020 |
| Design Submittal 1 |
| Contractor must deliver to the landlord A/E all latest project information such as CONOPS, Attainia Updates and specific design requests as a result of user group meetings that occur prior to the delivery of DD1. Site activation team to provide due date of information to the A/E Contractor to the activation Contractor so to ensure A/E has time to include. |
Design submittal 1 shall include:
1) Revit drawing showing typical rooms according to the TIL or existing layouts done by the A/E or based upon the IOT&A contractors room typical design which was developed using the VA TIL as a start plus any consistent changes found during the design of other projects
2) Generic Cut Sheets for all JSNs for the equipment on the drawings if selected by the VA prior to activation contractor on-board.
3) Room by room should match drawings
4) Listing of MEP needed per room to support equipment. The listing of the MEP will show recommended locations but not specifications for the MEP, like circuits, loads, amps, etc. It will be the responsibility of the A/E to size the MEP based upon the excel spreadsheet equipment list which is based upon the MEP infrastructure as specified in the MILSTD 1691.
5) Responsible party JSN matrix to show who is responsible for the different FF&E in the facility
6) Initial CONOPS report, inventory of existing FF&E, recommended re-use report which includes data sheets for any selected reuse TBD based on availability of final construction schedule
| TO1-021 |
| Design Submittal 2 |
| Design submittal 2 shall include: |
1) Revit drawing showing all rooms based upon information from user group meetings and updated drawings from the A/E
2) BOD Cut Sheets for all JSNs for the equipment on the drawings if selected by the VA prior to the activation contractor on board
3) Room by Room should match drawings
4) Responsible party JSN Matrix updated to reflect updated design TBD based on availability of construction schedule
| TO1-022 |
| Master Key Plan |
| Identify Master Key plan, or update existing draft, to include door/furniture cores and electronic and mechanical access control devices. The plan should include an assessment of compliance with applicable Homeland Security and VA security requirements. |
1) Contractor to ensure that compatible VA core door hardware is specified and used.
2) Provide a list of new cores and staff assignment to assist VA Locksmith in making the cores and keys required.
3) Key plan and access control plan should be based on security design requirements for access control: Dept. of Veterans Affairs Physical Security Design Manual, January 2015, Section 10.2.
4) Hard key vs. prox access: PIV scramble pads will be utilized for all exterior doors and common hallways. Individual services relocating to the new facility will retain service masters and sub-service master keys.
5) Security access control plan: All Physical Access Control Systems, PACS, must be Homeland Security Presidential Directive 12 compliant.
2 Months from Task Order award; updated monthly
| TO1-023 |
| Room-by-Room Master Equipment List (MEL) |
| The Room-by-Room MEL identifies all items listed by room. The MEL shall include reuse when applicable. The MEL shall be web-based during the project with MEL delivered on a disc at project completion. Incorporate the use of Attainia |
| 6 Months after Task Order award; updated monthly |
| TO1-024 |
| Updated Drawings |
| After all reviews are completed, the Contractor shall provide the final updated documents to the Government. A copy of the Revit Model is to be included as part of the submittal. Floor plans are to be submitted in PDF and Revit format. Final As Builds to be delivered at project closeout. |
| July 2021 |
| TO1-025 |
| Signage/Way-Finding Plan |
| The Signage & Way-Finding Plan shall identify each type of sign and the planned location. When applicable, the plan shall identify any unique mounting or other requirements/considerations for the piece(s). Once the general contractor provides their portion of the signage plan, the IOT&A contractor will follow the VA signage and wayfinding guidelines to complete the remainder of the plan. The Way-Finding Plan shall be coordinated with the Artwork Plan. Location and types of signs are to be shows on the 3-D renderings of the clinics. |
| 6 Months from Task Order award; updated monthly |
7.3 comprehensive furniture, fixtures, and equipment (FF&E) planning support
The Contractor shall provide FF&E planning services to support the systems necessary to meet functional requirements of the facility. The Contractor shall use MILSTD 1691, JSN, for all FF&E, new and potential reuse (CAT R) equipment. All FF&E shall be identified using JSN nomenclature.
The Contractor shall utilize Attainia (license provided by the Government) to maintain update FF&E database during the activation project. The Contractor shall also validate the Integrated camera system, Robbery/Panic/Duress alarm systems, motion intrusion alarm systems (as required), Electronic Physical Access Control Systems if coded as “VC” of “VV” items.
The Contractor shall perform a physical inventory of all existing FF&E, medical equipment, and IM/IT systems. The Contractor shall assess existing FF&E for reuse in new facility by conducting a life-cycle analysis on each FF&E item from the inventory and provide this analysis to the VA with recommendations. In general, if an item has an estimated useful life of two years or more from the date of anticipated occupancy of the new facility it should be reused. The life cycle analysis shall include maintenance histories and any other information the Contractor deems relevant. The inventory reuse analysis shall be documented in a report. At a minimum, the report shall identify factors used in determining whether an item was fit for reuse, identify the items to be reused, identify the items to be dispositioned during the implementation phase, and a brief explanation of why the item is unfit for reuse.
The Contractor shall identify which items will require testing, the type of testing required, and who is responsible for performing the testing and training.
The Contractor shall identify the items that must be installed by a 3rd party vendor or OEM responsible for uninstalling/reinstalling each resuse item identified.
The Contractor shall develop a Rough Order of Magnitude (ROM) Cost Estimate for FF&E to include the cost of each item to purchase, transport, warehouse, install, test, and train, as applicable.
| Deliverable # |
| Deliverables |
| Description |
| Deliverable |
| TO1-026 |
| FF&E Change Management Log |
| The contractor shall document requested and approved changes to the FF&E in a change management log |
| 1 Month from Task Order award; updated monthly |
| TO1-027 |
| Warranty Management Plan (WMP) |
| The contractor will be required to provide a W04MP for use by the end-user to ensure proper actions are taken to maintain and sustain medical and non-medical equipment installed as part of the contract. The WMP shall be delivered with the acquisition plan deliverable and with each design submittal. A final WMP is required with the final acquisition plan |
| July 2021 |
| TO1-028 |
| FF&E Equipment Reuse and Disposal Plan |
| The contractor shall develop and maintain an Equipment Reuse and Disposal Plan to ensure full coordination of activities and that the information updated reflects status and changes as they occur throughout the life of the project. The Equipment Reuse and Disposal Plan should outline how the contractor will determine if equipment is reusable. Equipment determined to be reusable shall be incorporated into the IO Procurement plan to ensure all reuse equipment is accounted for in the Final budget and procurement efforts. The Equipment Reuse and Disposal plan shall also describe how non-reusable equipment will be disposed and final location of disposed equipment. Accountable equipment whether reusable or designated for disposal will need to be coordinated with the Supply Chain Management Service to ensure equipment property records are accurately updated |
| 2 Months after Task Order award; updated monthly |
| TO1-029 |
| Maintenance Support Plan (MSP) |
| The contractor shall develop, maintain and provide to the Government a Maintenance Support Plan (MSP) for all critical and non-critical installed medical equipment to also include FF&E. The MSP will include maintenance schedules, warranties and life-cycle analysis. The MSP will clearly describe installed building equipment by name, type, manufacture, date installed, location and photo of the item. The MSP will identify maintenance schedules, inspection requirements and the method of service performance; (Service Contract/Maintenance Staff); Files created and maintained by the contractor shall be in a format acceptable by the Government and placed on the shared drive for maintenance access. |
| July 2021 |
| TO1-030 |
| Existing FF&E Inventory Report |
| The contractor shall maintain the FF&E list provided by Attainia (separate contactor). |
| 1 Month after Task Order award; updated as required |
| TO1-031 |
| Rough Order of Magnitude (ROM) |
| The ROM is the total estimated cost by item to purchase, warehouse, deliver, install, test, and train (as applicable) for the project The ROM shall be provided at DD1, DD2, CD2 and final acquisition plan |
| 2 Months after Task Order award; updated monthly |
| TO1-032 |
| Inventory Control Plan |
| The Contractor shall provide a JSN Responsibility Matrix of the Contractor's processes for conducting physical inventories, life cycle analysis of inventory items, strategies for reuse of existing items and for acquisition of new items, the Contractor's basis of design for casework, and other applicable processes related to the facility's inventory and IOT&A activities. As part of the acquisition strategy, items shall be classified as (1) Contractor Purchased and Contractor Installed, (2) Contractor Purchased and Veterans Affairs Installed, (3) Veterans Affairs Purchased and Contractor Installed, or (4) Veterans Affairs Purchased and Veterans Affairs Installed. The Contractor shall maintain an updated version of the plan as it is developed on a SharePoint-like site accessible for review by the COR and other key Government stakeholders. A final complete and comprehensive plan will be provided to the Government upon completion of the period of performance. |
The Contractor shall determine strategies for reuse of existing items (CAT R), acquisition of new items, and disposition of all other items. Each strategy shall be under a separate heading in the plan for clarity. The Reuse (CAT R) strategy may be determined by items being used at a newly built/renovated VA facility at the same campus. The disposition strategy may include VA facility reuse within the same campus or through the GSA disposal/reuse process, as determined. The acquisition strategy should include strategies to procure (purchase) new items required to activate the facility.
2 Months after Task Order award; updated monthly
7.4 Acquisition Services
The contractor shall develop the Acquisition Plan for the activation project. The Acquisition Plan shall identify, at a minimum, long lead time items, number of packages, and estimated timelines for procurement by package group. The contractor shall ensure employees performing acquisition services are well-versed in federal acquisition regulations prescribed by the Federal Acquisition Regulation (FAR) and the Veterans Affairs Acquisition Regulation (VAAR). NOTE: The number of acquisition packages has not been determined. The development of procurement packages will be defined/awarded under a separate TO.
Identify the number of procurement packages for the project using FF&E list provided for in attachment C.
· Develop an activation project acquisition plan
· Identify new items to be purchased
· Identify long lead-time items
· Identify items that require early installation
| Deliverable # |
| Deliverables |
| Description |
| Due |
| TO1-033 |
| Acquisition Plan |
| The contractor shall develop the Acquisition Plan to include a procurement package list (how the procurement packages should be organized), how many packages are anticipated to be needed, milestone dates to ensure the FF&E is available to meet the project schedule, and any identified associated risks and mitigation suggestions. |
| 2 Month after Task Order award; updated as required |
| TO1-034 |
| Acquisition Schedule |
| The contractor shall identify the number of procurement packages by type, date needed to “procure by” to account for acquisition timelines as well as manufacturing lead times, planned installation dates, and where each package is in the process. The schedule shall also identify the deadline to have the package in for government review prior to submission to contracting for acquisition |
| 2 Month after Task Order award; updated as required |
| TO1-035 |
| Initial Outfitting (IO) Procurement Plan |
| The contractor shall develop and maintain an IO Procurement plan incorporating factors identified during the FF&E validation process and the FF&E reuse determination process as well as any other requirements identified during the life of the project ensuring that it is updated to reflect current status and changes as they occur throughout the life of the project. The IO Procurement Plan shall describe the steps for procuring IO FF&E, scheduling the procurements to ensure on time delivery and installation, and how procurement packages will be submitted to the Government for review and approval. The IO Procurement Plan should highlight equipment identified as long lead time items to ensure time frames can be incorporated into the transition plan. The plan should be utilized to monitor ongoing reconciliation of the equipment budget and schedule. |
| 2 Month after Task Order award; updated as required |
| TO1-036 |
| IO Equipment Scheduling, Installation & Maintenance Plan |
| The Contractor shall develop and maintain an Initial Outfitting (IO) Equipment Scheduling and Installation and Maintenance Plan incorporating factors identified in the IO Procurement Plan, Transition Plan, and AIMS to ensure full coordination of activities ensuring that the information updated to reflect status and changes as they occur throughout the life of the project. |
| 2 Month after Task Order award; updated as required |
| TO1-037 |
| JSN Responsibility Matrix (Attachment K) |
| The contractor shall develop and maintain JSN Responsibility Matrix. The matrix is to be updated to reflect current status and changes as they occur throughout the life of the project. The matrix shall highlight FF&E identified as long lead time items to ensure time frames can be incorporated into the transition plan. The matrix should be utilized to monitor ongoing reconciliation of the FF&E budget and schedule. It should contain any specific information related to equipment procurements, responsibility of FF&E (VA, VV, CC, etc.) |
When applicable, the JSN Responsibility Matrix shall identify the appropriate Minimum Technical Requirement (MTR) number for each JSN in accordance with Attachment K.
2 Month after Task Order award; updated as required
7.6 Concept of Operations (CONOPS) and Transition Services
Provide transition planning and relocation services for the reorganization and consolidation of existing facilities and/or the opening of new facilities. Services should include all necessary actions to ensure efficient and effective transition of functions to new locations. The services may include the development of work and relocation plans and schedules; verification of critical field dimensions prior to installation; coordination of relocation plans and schedules with other professional, crafts, and trades persons; and moving and installation of existing or new equipment; FF&E, or otherwise identified items. Services should be provided and completed with maximum cost efficiency and minimum disruption to operations. The contractor shall facilitate clinic micro-CONOPS (departmental) and macro CONOPS (global: i.e. patient transport, infection control, security) that are interdependent across departments. The contractor shall meet with key stakeholders in processes that involve multiple departments throughout Phoenix VA Healthcare System and facilitate groups to identify, determine and document key organizational CONOPS for use in the new facilities. Specific task(s) associated with this type of work will be identified and qualified in each individual TO.
· Micro (departmental) level CONOPs: assess current operations, define new operations, and obtain facility approval of business practices based on new conditions in space, equipment, staffing, and operations. Includes assessing how the programmed space and design will be used in the new facility in terms of patient care delivery and best practices for patient outcomes, and document departmental hours of operation, work flow, staff work spaces, staff efficiency, egress of patients and staff, movement of equipment and supplies within the department, and safety and security for patients and staff.
· Macro (clinic wide operations) level CONOPs: assess current operations, define new operations, and obtain facility approval of business practices based on new conditions in space, equipment, staffing, and operations. Includes overall workflow assessment, departmental adjacency requirements, staffing efficiency recommendations, shared support spaces, patient transport, signage/wayfinding, staff egress, movement of equipment and supplies, safety, emergency management planning, security, infection control, and best practices.
· Information Management CONOPs: determine IT governance, determine roles and responsibilities, and review supporting infrastructure and functionality of each system; define system CONOPS, system functional and technical requirements, and identify any necessary changes to infrastructure indicated in construction drawings.
· IT/IM CONOPS: assess and determine the infrastructure required to support low-voltage systems (medical and non-medical). The contractor shall provide support to research technologies available to improve efficiency of clinic operations.
· Medical Equipment/Medical network CONOPs: determine Medical Equipment/Medical network governance, determine roles and responsibilities, and review infrastructure and functionality of each system; define system CONOPS, system functional and technical requirements, and identify any necessary changes to infrastructure indicated in construction drawings.
· Management CONOPs: management processes affecting activation activities: meet with key stakeholders involved in short, medium, or long-range IOT&A activities; identify, determine, and document best business practices for managing activities in the transition to the new clinic. Likely areas include equipment planning, information management, medical logistics, transition planning, and governance.
· Workflow CONOPs: looking for opportunities to optimize flexibility in the space, patient flow, material flow, and staffing to maximize efficiencies in the design.
· Transition and Preplanning Governance CONOPs: high-level requirements and processes required to accomplish activation and preplanning activities. Transition CONOPs will build upon STRATCOM and other CONOPs and details how to transition from current state to the required future state at the new facility. Transition CONOPs shall support the schedule development and acquisition, installation, and occupancy timelines. The contractor shall provide detailed transition CONOPs by functional area. The contractor shall identify key requirements and constraints that will empower or impede decision making processes, approvals, or the ability to manage well the activation activities. The contractor shall make recommendations for improvement where constraints, impediments, or other problems are identified. This information shall be documented in the Transition Plan.
· General CONOPS: Develop welcome/orientation kits for new employees, (i.e. facility maps, policies, service access, contact information, etc.)
| Deliverable # |
| Deliverables |
| Description |
| Due |
| TO1-040 |
| Micro-CONOPs |
| Micro CONOPS shall define how each specific operational unit conducts business. See task description above. |
| 2 Month after Task Order award; updated as required |
| TO1-041 |
| Macro CONOPs |
| Macro CONOPS shall be developed at the departmental level. See task description above. |
| 2 Month after Task Order award; updated as required |
| TO1-042 |
| Information Management CONOPS |
| Information Management CONOPS shall be developed as described in the task above |
| 2 Month after Task Order award; updated as required |
| TO1-043 |
| Medical Equipment/Medical Network CONOPS |
| Medical Equipment/Medical Network CONOPS shall be developed as described in the task above |
| 2 Month after Task Order award; updated as required |
| T01-044 |
| Management CONOPS |
| Management CONOPS shall be developed as described in the task above |
| 2 Month after Task Order award; updated as required |
| TO1-045 |
| Workflow CONOPS |
| Workflow CONOPS shall be developed as described in the task above |
| 2 Month after Task Order award; updated as required |
| TO1-046 |
| Transition and Pre-planning (Planning Governance) CONOPS |
| Transition CONOPS shall build upon STRATCOM and other CONOPS. Transition CONOPS support the schedule development, acquisition, installation, and occupancy timelines. The contractor shall provide Transition CONOPS by functional areas. The Transition CONOPS shall also include a Day in the life Plan. The Day in the Life plan describes the contractor’s plans for preparing Day in the Life scenarios to help prepare employees to work in the newly activated space |
| 2 Month after Task Order award; updated as required |
| TO1-047 |
| General CONOPS |
| General CONOPS shall be developed to include welcome kits/orientation kits for new employees to include new facility maps, policies, contact information, etc.) |
| 2 Month after Task Order award; updated as required |
| TO1-048 |
| IT/IM CONOPs |
| IT/IM CONOPS shall define requirements and determine infrastructure required to support low-voltage systems (medical and non-medical). contractor shall provide support to research technologies available to improve efficiency of clinic operations |
| 2 Month after Task Order award; updated as required |
7.11 Technical Request for Information (RFI) Assistance
In collaboration with the Resident Engineer (RE), provide technical assistance that may include design/build Request for Proposal (RFP) review for space/equipment requirements. Work with internal services to identify space and FF&E needs, and provide technical assistance pertaining to Department of Veterans Affairs Physical Security Design Manual for Life Safety.
| Deliverable # |
| Deliverables |
| Description |
| Due |
| TO1-064 |
| Monthly RFI Report |
| The plan shall describe the types of communication and target audiences for communicating information regarding the activation project. The Communication Plan shall address both internal and external stakeholders and address STRATCOM objectives and processes |
| Within 15 working days of receipt of request. |
| TO1-065 |
| Third Party Life Safety Review |
| The Contractor shall provide the third-party life safety review and report. |
| Within 15 working days of receipt of request. |
7.13 Strategic communications (stratcom) support services
In collaboration with Health Care System leadership, provide communications with all levels of the organization, the media and other stakeholders. The contractor shall be responsible for drafting communication releases, and handling public conferences and meetings regarding the project. STRATCOM includes external and internal communications support for community outreach and engagement, media and public relations; Congressional partners, Veterans Service Organizations, medical center staff and other key stakeholders. All communications must be coordinated through the project Program Manager and/or COR prior to dissemination to include the following:
· Develop STRATCOM objectives
· Finalize STRATCOM objectives
· Strategic communications planning
· Program/Project/Change management communications for business initiatives
·…