This is an Invitation for Bids (IFB) and associated contract documents issued by the Brandywine Conservancy and Museum of Art for the Hoffmans Mill Dam Removal project located at 1 Hoffmans Mill Road, Chadds Ford, Pennsylvania. The project involves the complete demolition and removal of Hoffmans Mill Dam, a run-of-river rockfill dam located across the Brandywine Creek in Chadds Ford and Pennsbury Townships. Bids must be submitted online via PennBid (www.Pennbid.net) no later than Monday, July 20, 2026 at 5:00 PM local time, with bids to be privately opened and read thereafter. A mandatory pre-bid conference is scheduled for Tuesday, July 7, 2026 at 10:00 AM at the northwestern corner of the gravel parking area at the Brandywine Museum of Art; bidders who do not attend this conference will not be eligible to submit a bid. The work must be substantially completed on or before October 15, 2026, and completed and ready for final payment on or before December 31, 2026. The contract will be awarded to the responsible bidder whose bid is in the best interests of the project.
Bids must be submitted on a lump sum basis and must be accompanied by bid security equal to 10 percent of the maximum bid price (base bid plus all alternates) in the form of a bid bond. The contract includes liquidated damages of $2,000 per day for each day of delay beyond the substantial completion date. The successful bidder must furnish a performance bond and payment bond, each equal to 100 percent of the contract price, and a maintenance bond equal to 10 percent of the contract price, all to remain in effect until one year after final payment. Required insurance includes workers' compensation, commercial general liability with minimum coverage of $1,000,000 per occurrence and $2,000,000 general aggregate, automobile liability, excess or umbrella liability of $5,000,000, and contractors' pollution liability of $1,000,000 per occurrence and $4,000,000 aggregate. The owner is exempt from Pennsylvania state sales and use taxes (Exemption No. 75586711), and such taxes must not be included in the bid. Progress payments will be made monthly with 10 percent retainage until substantial completion. The bidder must demonstrate qualifications including financial data, previous experience, present commitments, state contractor license number if applicable, and must provide subcontractor and supplier information within five days of bid submission or upon owner request.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BRANDYWINE CONSERVANCY AND MUSEUM OF ART
BIDDING REQUIREMENTS, CONTRACT FORMS, and GENERAL CONDITIONS for
HOFFMAN�S MILL DAM REMOVAL
at
1 HOFFMANS MILL ROAD, CHADDS FORD, PA 19317
HOFFMAN�S MILL DAM REMOVAL
BRANDYWINE CONSERVANCY & MUSEUM OF ART
Rev. June 26, 2026
TABLE OF CONTENTS
BIDDING REQUIREMENTS, CONTRACT FORMS, AND GENERAL CONDITIONS
Section Section
Number Title
----- Title Sheet
----- Table of Contents
00 11 13 Advertisement for Bids
00 21 00 Instructions to Bidders
00 41 00 Bid Form
00 43 13 Bid Bond
00 52 13 Agreement
00 61 13.13 Performance Bond
00 61 13.16 Payment Bond
00 61 19 Warranty Bond
00 71 00 Standard General Conditions
00 73 00 Supplementary Conditions
00 73 43.13 Federal Wage Rate Requirements
00 73 43.16 State Wage Rate Requirements
TECHNICAL SPECIFICATIONS
DIVISION ONE -- GENERAL REQUIREMENTS
01 71 13 Mobilization and Demobilization
DIVISION TWO � SITE WORK
02 41 19 Selective Demolition
DIVISION THIRTY-ONE � EARTHWORK
31 23 19 Dewatering and Control of Water
31 25 00 Erosion & Sediment Control
31 37 00 Riprap
DIVISION THIRTY-TWO � EXTERIOR IMPROVEMENTS
32 01 00.91 Site Restoration
32 93 13 Topsoil and Seeding
Rev. June 26, 2026 00 11 13 - 1 Advertisement for Bids
SECTION 00 11 13
ADVERTISEMENT FOR BIDS
BRANDYWINE CONSERVANCY AND MUSEUM OF ART
CHADDS FORD, PENNSYLVANIA
HOFFMAN�S MILL DAM REMOVAL
General Notice
Brandywine Conservancy and Museum of Art (Owner) is requesting Bids for the construction of the following Project:
Hoffman�s Mill Dam Removal
Bids for the construction of the Project will be received at the Brandywine Conservancy and Museum of
Art submitted online via PennBid at www.Pennbid.net, until Monday, July 20, 2026 at 5:00 PM local time. At that time the Bids received will be privately opened and read.
The Project includes the following Work:
Demolition and removal of Hoffman�s Mill Dam, a run-of-river rockfill dam located across the
Brandywine Creek.
Bids are requested for the following Contract: Hoffman�s Mill Dam Removal
Obtaining the Bidding Documents
Information and Bidding Documents for the Project can be found at the following designated website:
www.Pennbid.net
Bidding Documents may be downloaded from the designated website. Prospective Bidders are urged to register with the designated website as a plan holder, even if Bidding Documents are obtained from a plan room or source other than the designated website in either electronic or paper format. The designated website will be updated periodically with addenda, lists of registered plan holders, reports, and other information relevant to submitting a Bid for the Project. All official notifications, addenda, and other Bidding Documents will be offered only through the designated website. Neither Owner nor
Engineer will be responsible for Bidding Documents, including addenda, if any, obtained from sources other than the designated website.
Pre-bid Conference
A mandatory pre-bid conference for the Project will be held on Tuesday, July 7th, 20026 at 10:00 AM at the northwestern corner of the gravel parking area at the Brandywine Museum of Art, 1 Hoffmans Mill
Road, Chadds Ford, PA 19317. Bids will not be accepted from Bidders that do not attend the mandatory pre-bid conference.
Instructions to Bidders.
For all further requirements regarding bid submittal, qualifications, procedures, and contract award, refer to the Instructions to Bidders that are included in the Bidding Documents.
Rev. June 26, 2026 00 11 13 - 2 Advertisement for Bids
This Advertisement is issued by:
Owner: Brandywine Conservancy and Museum of Art
By: Robert Daniels
Title: Assistant Director of Community Services
Date: June 29, 2026
Rev. June 26, 2026 00 21 00 - i Instructions to Bidders
SECTION 00 21 00
INSTRUCTIONS TO BIDDERS FOR CONSTRUCTION CONTRACT
TABLE OF CONTENTS
Page
Article 1� Defined Terms
Article 2� Bidding Documents
Article 3� Qualifications of Bidders
Article 4� Pre-Bid Conference
Article 5� Site and Other Areas; Existing Site Conditions; Examination of Site; Owner�s Safety Program;
Other Work at the Site
Article 6� Bidder�s Representations and Certifications
Article 7� Interpretations and Addenda
Article 8� Bid Security
Article 9� Contract Times
Article 10� Substitute and �Or Equal� Items
Article 11� Subcontractors, Suppliers, and Others
Article 12� Preparation of Bid
Article 13� Basis of Bid
Article 14� Submittal of Bid
Article 15� Modification and Withdrawal of Bid
Article 16� Opening of Bids
Article 17� Bids to Remain Subject to Acceptance
Article 18� Evaluation of Bids and Award of Contract
Article 19� Bonds and Insurance
Article 20� Signing of Agreement
Article 21� Sales and Use Taxes
Rev. June 26, 2026 00 21 00 - 1 Instructions to Bidders
ARTICLE 1�DEFINED TERMS
1.01 Terms used in these Instructions to Bidders have the meanings indicated in the General Conditions and Supplementary Conditions. Additional terms used in these Instructions to Bidders have the meanings indicated below:
A. Issuing Office�The office from which the Bidding Documents are to be issued, and which registers plan holders.
ARTICLE 2�BIDDING DOCUMENTS
2.01 Bidder shall obtain a complete set of Bidding Requirements and proposed Contract Documents
(together, the Bidding Documents). Bidding documents are available at no cost via PennBid
(https://pennbid.bonfirehub.com). See the Agreement for a list of the Contract Documents. It is
Bidder�s responsibility to determine that it is using a complete set of documents in the preparation of a Bid. Bidder assumes sole responsibility for errors or misinterpretations resulting from the use of incomplete documents, by Bidder itself or by its prospective Subcontractors and Suppliers.
2.02 Bidding Documents are made available for the sole purpose of obtaining Bids for completion of the Project and permission to download or distribution of the Bidding Documents does not confer a license or grant permission or authorization for any other use. Authorization to download documents, or other distribution, includes the right for plan holders to print documents solely for their use, and the use of their prospective Subcontractors and Suppliers, provided the plan holder pays all costs associated with printing or reproduction. Printed documents may not be re-sold under any circumstances.
2.03 Owner has established a Bidding Documents Website as indicated in the Advertisement or invitation to bid. Owner recommends that Bidder register on the PennBid portal at https://pennbid.bonfirehub.com/and obtain a complete set of the Bidding Documents from such website. . Bidders may rely that sets of Bidding Documents obtained from the Bidding Documents
Website are complete, unless an omission is blatant. Registered plan holders will receive Addenda issued by Owner.
2.04 Electronic Documents
A. When the Bidding Requirements indicate that electronic (digital) copies of the Bidding
Documents are available, such documents will be made available to the Bidders as Electronic
Documents in the manner specified.
1. Bidding Documents will be provided in Adobe PDF (Portable Document Format) (.pdf) that is readable by Adobe Acrobat Reader Version 25 or later. It is the intent of the
Engineer and Owner that such Electronic Documents are to be exactly representative of the paper copies of the documents. However, because the Owner and Engineer cannot totally control the transmission and receipt of Electronic Documents nor the
Contractor�s means of reproduction of such documents, the Owner and Engineer cannot and do not guarantee that Electronic Documents and reproductions prepared from those versions are identical in every manner to the paper copies.
B. Unless otherwise stated in the Bidding Documents, the Bidder may use and rely upon complete sets of Electronic Documents of the Bidding Documents, described in
Paragraph 2.06.A above. However, Bidder assumes all risks associated with differences
Rev. June 26, 2026 00 21 00 - 2 Instructions to Bidders arising from transmission/receipt of Electronic Documents versions of Bidding Documents and reproductions prepared from those versions and, further, assumes all risks, costs, and responsibility associated with use of the Electronic Documents versions to derive information that is not explicitly contained in printed paper versions of the documents, and for Bidder�s reliance upon such derived information.
ARTICLE 3�QUALIFICATIONS OF BIDDERS
3.01 To demonstrate Bidder�s qualifications to perform the Work, after submitting its Bid and within five days of Owner�s request, Bidder must submit the following information:
A. Written evidence establishing its qualifications such as financial data, previous experience, and present commitments.
B. A written statement that Bidder is authorized to do business in the state where the Project is located, or a written certification that Bidder will obtain such authority prior to the
Effective Date of the Contract.
C. Bidder�s state or other contractor license number, if applicable.
D. Subcontractor and Supplier qualification information.
E. Other required information regarding qualifications.
3.02 Bidder is to submit the following information with its Bid to demonstrate Bidder�s qualifications to perform the Work:
A. Written evidence establishing its qualifications such as financial data, previous experience, and present commitments.
B. A written statement that Bidder is authorized to do business in the state where the Project is located, or a written certification that Bidder will obtain such authority prior to the
Effective Date of the Contract.
C. Bidder�s state or other contractor license number, if applicable.
D. Subcontractor and Supplier qualification information.
E. Other required information regarding qualifications.
3.03 A Bidder�s failure to submit required qualification information within the times indicated may disqualify Bidder from receiving an award of the Contract.
3.04 No requirement in this Article 3 to submit information will prejudice the right of Owner to seek additional pertinent information regarding Bidder�s qualifications.
ARTICLE 4�PRE-BID CONFERENCE
4.01 A mandatory pre-bid conference will be held at the time and location indicated in the
Advertisement or invitation to bid. Representatives of Owner and Engineer will be present to discuss the Project. Proposals will not be accepted from Bidders who do not attend the conference. It is each Bidder�s responsibility to sign in at the pre-bid conference to verify its participation. Bidders must sign in using the name of the organization that will be submitting a
Rev. June 26, 2026 00 21 00 - 3 Instructions to Bidders
Bid. A list of qualified Bidders that attended the pre-bid conference and are eligible to submit a
Bid for this Project will be issued in an Addendum.
4.02 Information presented at the pre-Bid conference does not alter the Contract Documents. Owner will issue Addenda to make any changes to the Contract Documents that result from discussions at the pre-Bid conference. Information presented, and statements made at the pre-bid conference will not be binding or legally effective unless incorporated in an Addendum.
ARTICLE 5�SITE AND OTHER AREAS; EXISTING SITE CONDITIONS; EXAMINATION OF SITE; OWNER�S
SAFETY PROGRAM; OTHER WORK AT THE SITE
5.01 Site and Other Areas
A. The Site is identified in the Bidding Documents. By definition, the Site includes rights-of-way, easements, and other lands furnished by Owner for the use of the Contractor. Any additional lands required for temporary construction facilities, construction equipment, or storage of materials and equipment, and any access needed for such additional lands, are to be obtained and paid for by Contractor.
5.02 Existing Site Conditions
A. Underground Facilities: Underground Facilities are shown or indicated on the Drawings.
Information and data regarding the presence or location of Underground Facilities are not intended to be categorized, identified, or defined as Technical Data.
5.03 Other Site-related Documents
A. No other Site-related documents are available.
5.04 Owner�s Safety Program
A. Site visits and work at the Site may be governed by an Owner safety program. If an Owner safety program exists, it will be noted in the Supplementary Conditions.
5.05 Other Work at the Site
A. Reference is made to Article 8 of the Supplementary Conditions for the identification of the general nature of other work of which Owner is aware (if any) that is to be performed at the
Site by Owner or others (such as utilities and other prime contractors) and relates to the
Work contemplated by these Bidding Documents. If Owner is party to a written contract for such other work, then on request, Owner will provide to each Bidder access to examine such contracts (other than portions thereof related to price and other confidential matters), if any.
ARTICLE 6�BIDDER�S REPRESENTATIONS AND CERTIFICATIONS
6.01 Express Representations and Certifications in Bid Form, Agreement
A. The Bid Form that each Bidder will submit contains express representations regarding the
Bidder�s examination of Project documentation, Site visit, and preparation of the Bid, and certifications regarding lack of collusion or fraud in connection with the Bid. Bidder should review these representations and certifications, and assure that Bidder can make the representations and certifications in good faith, before executing and submitting its Bid.
B. If Bidder is awarded the Contract, Bidder (as Contractor) will make similar express representations and certifications when it executes the Agreement.
Rev. June 26, 2026 00 21 00 - 4 Instructions to Bidders
ARTICLE 7�INTERPRETATIONS AND ADDENDA
7.01 Owner on its own initiative may issue Addenda to clarify, correct, supplement, or change the
Bidding Documents.
7.02 Bidder shall submit all questions about the meaning or intent of the Bidding Documents to
Engineer in writing. Contact information and submittal procedures for such questions are as follows:
A. Questions shall be submitted via the �Ask a Question� feature in PennBid.
7.03 Interpretations or clarifications considered necessary by Engineer in response to such questions will be issued by Addenda via the PennBid portal. Bidders who have registered and downloaded documents from PennBid will be notified by email when an addendum has been posted.
Questions received less than seven days prior to the date for opening of Bids may not be answered.
7.04 Only responses set forth in an Addendum will be binding. Oral and other interpretations or clarifications will be without legal effect. Responses to questions are not part of the Contract
Documents unless set forth in an Addendum that expressly modifies or supplements the Contract
Documents.
ARTICLE 8�BID SECURITY
8.01 A Bid must be accompanied by Bid security made payable to Owner in an amount of 10 percent of Bidder�s maximum Bid price (determined by adding the base bid and all alternates) and in the form of a Bid bond issued by a surety meeting the requirements of Paragraph 6.01 of the General
Conditions. Such Bid bond will be issued in the form included in the Bidding Documents.
8.02 The Bid security of the apparent Successful Bidder will be retained until Owner awards the contract to such Bidder, and such Bidder has executed the Contract, furnished the required
Contract security, and met the other conditions of the Notice of Award, whereupon the Bid security will be released. If the Successful Bidder fails to execute and deliver the Contract and furnish the required Contract security within 15 days after the Notice of Award, Owner may consider Bidder to be in default, annul the Notice of Award, and the Bid security of that Bidder will be forfeited, in whole in the case of a penal sum bid bond, and to the extent of Owner�s damages in the case of a damages-form bond. Such forfeiture will be Owner�s exclusive remedy if
Bidder defaults.
8.03 The Bid security of other Bidders that Owner believes to have a reasonable chance of receiving the award may be retained by Owner until the earlier of 7 days after the Effective Date of the
Rev. June 26, 2026 00 21 00 - 5 Instructions to Bidders
Contract or 61 days after the Bid opening, whereupon Bid security furnished by such Bidders will be released.
8.04 Bid security of other Bidders that Owner believes do not have a reasonable chance of receiving the award will be released within 7 days after the Bid opening.
ARTICLE 9�CONTRACT TIMES
9.01 The number of days within which, or the dates by which, the Work is to be (a) substantially completed and (b) ready for final payment, and (c) Milestones (if any) are to be achieved, are set forth in the Agreement.
9.02 Bidder must set forth in the Bid the time by which Bidder must achieve Substantial Completion, subject to the restrictions established in Paragraph 13.07 of these Instructions. The Owner will take Bidder�s time commitment regarding Substantial Completion into consideration during the evaluation of Bids, and it will be necessary for the apparent Successful Bidder to satisfy Owner that it will be able to achieve Substantial Completion within the time such Bidder has designated in the Bid. The Successful Bidder�s time commitments will be entered into the Agreement or incorporated in the Agreement by reference to the specific terms of the Bid.
9.03 Provisions for liquidated damages, if any, for failure to timely attain a Milestone, Substantial
Completion, or completion of the Work in readiness for final payment, are set forth in the
Agreement.
ARTICLE 10�SUBSTITUTE AND �OR EQUAL� ITEMS
10.01 The Contract for the Work, as awarded, will be on the basis of materials and equipment specified or described in the Bidding Documents without consideration during the bidding and Contract award process of possible substitute or �or-equal� items. In cases in which the Contract allows the Contractor to request that Engineer authorize the use of a substitute or �or-equal� item of material or equipment, application for such acceptance may not be made to and will not be considered by Engineer until after the Effective Date of the Contract.
10.02 The Contract for the Work, as awarded, will be on the basis of materials and equipment specified or described in the Bidding Documents, and those �or-equal� or substitute or materials and equipment subsequently approved by Engineer prior to the submittal of Bids and identified by
Addendum. No item of material or equipment will be considered by Engineer as an �or-equal� or substitute unless written request for approval has been submitted by Bidder and has been received by Engineer within 10 days of the issuance of the Advertisement for Bids or invitation to
Bidders. Each such request must comply with the requirements of Paragraphs 7.05 and 7.06 of the General Conditions, and the review of the request will be governed by the principles in those paragraphs. The burden of proof of the merit of the proposed item is upon Bidder. Engineer�s decision of approval or disapproval of a proposed item will be final. If Engineer approves any such proposed item, such approval will be set forth in an Addendum issued to all registered Bidders.
Bidders cannot rely upon approvals made in any other manner.
10.03 All prices that Bidder sets forth in its Bid will be based on the presumption that the Contractor will furnish the materials and equipment specified or described in the Bidding Documents, as
Rev. June 26, 2026 00 21 00 - 6 Instructions to Bidders supplemented by Addenda. Any assumptions regarding the possibility of post-Bid approvals of
�or-equal� or substitution requests are made at Bidder�s sole risk.
ARTICLE 11�SUBCONTRACTORS, SUPPLIERS, AND OTHERS
11.01 A Bidder must be prepared to retain specific Subcontractors and Suppliers for the performance of the Work if required to do so by the Bidding Documents or in the Specifications. If a prospective
Bidder objects to retaining any such Subcontractor or Supplier and the concern is not relieved by an Addendum, then the prospective Bidder should refrain from submitting a Bid.
11.02 The apparent Successful Bidder, and any other Bidder so requested, must submit to Owner a list of the Subcontractors or Suppliers proposed for the following portions of the Work within five days after Bid opening:
11.03 If requested by Owner, such list must be accompanied by an experience statement with pertinent information regarding similar projects and other evidence of qualification for each such
Subcontractor or Supplier. If Owner or Engineer, after due investigation, has reasonable objection to any proposed Subcontractor or Supplier, Owner may, before the Notice of Award is given, request apparent Successful Bidder to submit an acceptable substitute, in which case apparent
Successful Bidder will submit a substitute, Bidder�s Bid price will be increased (or decreased) by the difference in cost occasioned by such substitution, and Owner may consider such price adjustment in evaluating Bids and making the Contract award.
11.04 If apparent Successful Bidder declines to make any such substitution, Owner may award the
Contract to the next lowest Bidder that proposes to use acceptable Subcontractors and Suppliers.
Declining to make requested substitutions will constitute grounds for forfeiture of the Bid security of any Bidder. Any Subcontractor or Supplier, so listed and against which Owner or Engineer makes no written objection prior to the giving of the Notice of Award will be deemed acceptable to Owner and Engineer subject to subsequent revocation of such acceptance as provided in
Paragraph 7.07 of the General Conditions.
ARTICLE 12�PREPARATION OF BID
12.01 The Bid Form is included with the Bidding Documents is for Reference. Bidders shall complete the electronic bid form within PennBid (�Prepare Your Submission� tab)..
12.02 A Bid by a corporation must be executed in the corporate name by a corporate officer (whose title must appear under the signature), accompanied by evidence of authority to sign. The corporate address and state of incorporation must be shown.
12.03 A Bid by a partnership must be executed in the partnership name and signed by a partner (whose title must appear under the signature), accompanied by evidence of authority to sign. The official address of the partnership must be shown.
12.04 A Bid by a limited liability company must be executed in the name of the firm by a member or other authorized person and accompanied by evidence of authority to sign. The state of formation of the firm and the official address of the firm must be shown.
12.05 A Bid by an individual must show the Bidder�s name and official address.
Rev. June 26, 2026 00 21 00 - 7 Instructions to Bidders
12.06 A Bid by a joint venture must be executed by an authorized representative of each joint venturer in the manner indicated on the Bid Form. The joint venture must have been formally established prior to submittal of a Bid, and the official address of the joint venture must be shown.
12.07 All names must be printed in ink below the signatures.
12.08 The Bid must contain an acknowledgment of receipt of all Addenda, the numbers of which must be filled in on the Bid Form.
12.09 Postal and e-mail addresses and telephone number for communications regarding the Bid must be shown.
12.10 The Bid must contain evidence of Bidder�s authority to do business in the state where the Project is located, or Bidder must certify in writing that it will obtain such authority within the time for acceptance of Bids and attach such certification to the Bid.
12.11 If Bidder is required to be licensed to submit a Bid or perform the Work in the state where the
Project is located, the Bid must contain evidence of Bidder�s licensure, or Bidder must certify in writing that it will obtain such licensure within the time for acceptance of Bids and attach such certification to the Bid. Bidder�s state contractor license number, if any, must also be shown on the Bid Form.
ARTICLE 13�BASIS OF BID
13.01 Lump Sum
A. Bidders must submit a Bid on a lump sum basis as set forth in the Bid Form.
ARTICLE 14�SUBMITTAL OF BID
14.01 Bids shall be submitted online via the PennBid Program (https://pennbid.bonfirehub.com) by the date and time indicated in the Invitation for Bids along with the Bid security and the other documents required to be submitted as identified herein..
14.02 A Bid must be received no later than the date and time prescribed and at the place indicated in the Advertisement or invitation to bid.
14.03 Bids received after the date and time, or not submitted in the designated manner, will not be accepted.
ARTICLE 15�MODIFICATION AND WITHDRAWAL OF BID
15.01 A Bid may be withdrawn, altered or modified at any time within PennBid prior to the due date and time identified in the Invitation for Bids. If within 24 hours after Bids are opened any Bidder files a duly signed written notice with Owner and promptly thereafter demonstrates to the reasonable satisfaction of Owner that there was a material and substantial mistake in the
Rev. June 26, 2026 00 21 00 - 8 Instructions to Bidders preparation of its Bid, the Bidder may withdraw its Bid, and the Bid security will be returned.
Thereafter, if the Work is rebid, the Bidder will be disqualified from further bidding on the Work.
ARTICLE 16�OPENING OF BIDS
16.01 Bids will be opened privately.
ARTICLE 17�BIDS TO REMAIN SUBJECT TO ACCEPTANCE
17.01 All Bids will remain subject to acceptance for the period of time stated in the Bid Form, but Owner may, in its sole discretion, release any Bid and return the Bid security prior to the end of this period.
ARTICLE 18�EVALUATION OF BIDS AND AWARD OF CONTRACT
18.01 Owner reserves the right to reject any or all Bids, including without limitation, nonconforming, nonresponsive, unbalanced, or conditional Bids. Owner also reserves the right to waive all minor
Bid informalities not involving price, time, or changes in the Work.
18.02 Owner will reject the Bid of any Bidder that Owner finds, after reasonable inquiry and evaluation, to not be responsible.
18.03 If Bidder purports to add terms or conditions to its Bid, takes exception to any provision of the
Bidding Documents, or attempts to alter the contents of the Contract Documents for purposes of the Bid, whether in the Bid itself or in a separate communication to Owner or Engineer, then
Owner will reject the Bid as nonresponsive.
18.04 If Owner awards the contract for the Work, such award will be to the responsible Bidder whose
Bid is in the best interests of the project.
18.05 Evaluation of Bids
A. In evaluating Bids, Owner will consider whether the Bids comply with the prescribed requirements, and such alternates, unit prices, and other data, as may be requested in the
Bid Form or prior to the Notice of Award.
B. For determination of the apparent low Bidder(s) when sectional bids are submitted, Bids will be compared on the basis of the aggregate of the Bids for separate sections and the Bids for combined sections that result in the lowest total amount for all of the Work.
C. For the determination of the apparent low Bidder when unit price bids are submitted, Bids will be compared on the basis of the total of the products of the estimated quantity of each item and unit price Bid for that item, together with any lump sum items.
D. For the determination of the apparent low Bidder when cost-plus-fee bids are submitted, Bids will be compared on the basis of the Guaranteed Maximum Price set forth by Bidder on the Bid Form.
18.06 In evaluating whether a Bidder is responsible, Owner will consider the qualifications of the Bidder and may consider the qualifications and experience of Subcontractors and Suppliers proposed for
Rev. June 26, 2026 00 21 00 - 9 Instructions to Bidders those portions of the Work for which the identity of Subcontractors and Suppliers must be submitted as provided in the Bidding Documents.
18.07 Owner may conduct such investigations as Owner deems necessary to establish the responsibility, qualifications, and financial ability of Bidders and any proposed Subcontractors or Suppliers.
ARTICLE 19�BONDS AND INSURANCE
19.01 Article 6 of the General Conditions, as may be modified by the Supplementary Conditions, sets forth Owner�s requirements as to performance and payment bonds, other required bonds (if any), and insurance. When the Successful Bidder delivers the executed Agreement to Owner, it must be accompanied by required bonds and insurance documentation.
19.02 Article 8, Bid Security, of these Instructions, addresses any requirements for providing bid bonds as part of the bidding process.
ARTICLE 20�SIGNING OF AGREEMENT
20.01 When Owner issues a Notice of Award to the Successful Bidder, it will be accompanied by the unexecuted counterparts of the Agreement along with the other Contract Documents as identified in the Agreement. Within 15 days thereafter, Successful Bidder must execute and deliver the required number of counterparts of the Agreement and any bonds and insurance documentation required to be delivered by the Contract Documents to Owner. Within 10 days thereafter, Owner will deliver one fully executed counterpart of the Agreement to Successful
Bidder, together with printed and electronic copies of the Contract Documents as stated in
Paragraph 2.02 of the General Conditions.
ARTICLE 21�SALES AND USE TAXES
21.01 Owner is exempt from Pennsylvania state sales and use taxes on materials and equipment to be incorporated in the Work. (Exemption No. 75586711). Said taxes must not be included in the Bid.
Refer to Paragraph SC-7.10 of the Supplementary Conditions for additional information.
Rev. June 26, 2026 00 41 00 - 1 Bid Form for Construction Contract
Section 00 41 00
Bid Form for Construction Contract
The terms used in this Bid with initial capital letters have the meanings stated in the Instructions to
Bidders, the General Conditions, and the Supplementary Conditions.
ARTICLE 1�OWNER AND BIDDER
1.01 This Bid is submitted to: Robert Daniels, Brandywine Conservancy and Museum of Art
1.02 The undersigned Bidder proposes and agrees, if this Bid is accepted, to enter into an Agreement with Owner in the form included in the Bidding Documents to perform all Work as specified or indicated in the Bidding Documents for the prices and within the times indicated in this Bid and in accordance with the other terms and conditions of the Bidding Documents.
ARTICLE 2�ATTACHMENTS TO THIS BID
2.01 The following documents are submitted with and made a condition of this Bid:
A. Required Bid security;
B. List of Proposed Subcontractors;
C. List of Proposed Suppliers;
D. Evidence of authority to do business in the state of the Project; or a written covenant to obtain such authority within the time for acceptance of Bids;
E. Contractor�s license number as evidence of Bidder�s State Contractor�s License or a covenant by Bidder to obtain said license within the time for acceptance of Bids;
F. Required Bidder Qualification Statement with supporting data; and
ARTICLE 3�BASIS OF BID�LUMP SUM BID AND UNIT PRICES
3.01 Lump Sum Bids
A. Bidder will complete the Work in accordance with the Contract Documents for the following lump sum (stipulated) price(s), together with any Unit Prices indicated in Paragraph 3.02:
1. Lump Sum Price (Single Lump Sum)
Lump Sum Bid Price $
ARTICLE 4�TIME OF COMPLETION
4.01 Bidder agrees that the Work will be substantially complete and will be completed and ready for final payment in accordance with Paragraph 15.06 of the General Conditions on or before the dates or within the number of calendar days indicated in the Agreement.
Rev. June 26, 2026 00 41 00 - 2 Bid Form for Construction Contract
4.02 Bidder agrees that the Work will be substantially complete on or before October 15, 2026, and will be completed and ready for final payment in accordance with Paragraph 15.06 of the General
Conditions on or before December 31, 2026.
4.03 Bidder accepts the provisions of the Agreement as to liquidated damages.
ARTICLE 5�BIDDER�S ACKNOWLEDGEMENTS: ACCEPTANCE PERIOD, INSTRUCTIONS, AND RECEIPT OF
ADDENDA
5.01 Bid Acceptance Period
A. This Bid will remain subject to acceptance for 60 days after the Bid opening, or for such longer period of time that Bidder may agree to in writing upon request of Owner.
5.02 Instructions to Bidders
A. Bidder accepts all of the terms and conditions of the Instructions to Bidders, including without limitation those dealing with the disposition of Bid security.
5.03 Receipt of Addenda
A. Bidder hereby acknowledges receipt of the following Addenda: [Add rows as needed. Bidder is to complete table.]
Addendum Number Addendum Date
ARTICLE 6�BIDDER�S REPRESENTATIONS AND CERTIFICATIONS
6.01 Bidder�s Representations
A. In submitting this Bid, Bidder represents the following:
1. Bidder has examined and carefully studied the Bidding Documents, including Addenda.
2. Bidder has visited the Site, conducted a thorough visual examination of the Site and adjacent areas, and become familiar with the general, local, and Site conditions that may affect cost, progress, and performance of the Work.
3. Bidder is familiar with all Laws and Regulations that may affect cost, progress, and performance of the Work.
4. Bidder has carefully studied the reports of explorations and tests of subsurface conditions at or adjacent to the Site and the drawings of physical conditions relating to existing surface or subsurface structures at the Site that have been identified in the
Supplementary Conditions, with respect to the Technical Data in such reports and drawings.
5. Bidder has carefully studied the reports and drawings relating to Hazardous
Environmental Conditions, if any, at or adjacent to the Site that have been identified in the Supplementary Conditions, with respect to Technical Data in such reports and drawings.
Rev. June 26, 2026 00 41 00 - 3 Bid Form for Construction Contract
6. Bidder has considered the information known to Bidder itself; information commonly known to contractors doing business in the locality of the Site; information and observations obtained from visits to the Site; the Bidding Documents; and the Technical
Data identified in the Supplementary Conditions or by definition, with respect to the effect of such information, observations, and Technical Data on (a) the cost, progress, and performance of the Work; (b) the means, methods, techniques, sequences, and procedures of construction to be employed by Bidder, if selected as Contractor; and
(c) Bidder�s (Contractor�s) safety precautions and programs.
7. Based on the information and observations referred to in the preceding paragraph, Bidder agrees that no further examinations, investigations, explorations, tests, studies, or data are necessary for the performance of the Work at the Contract Price, within the Contract
Times, and in accordance with the other terms and conditions of the Contract.
8. Bidder is aware of the general nature of work to be performed by Owner and others at the Site that relates to the Work as indicated in the Bidding Documents.
9. Bidder has given Engineer written notice of all conflicts, errors, ambiguities, or discrepancies that Bidder has discovered in the Bidding Documents, and of discrepancies between Site conditions and the Contract Documents, and the written resolution thereof by Engineer is acceptable to Contractor.
10. The Bidding Documents are generally sufficient to indicate and convey understanding of all terms and conditions for performance and furnishing of the Work.
11. The submission of this Bid constitutes an incontrovertible representation by Bidder that without exception the Bid and all prices in the Bid are premised upon performing and furnishing the Work required by the Bidding Documents.
6.02 Bidder�s Certifications
A. The Bidder certifies the following:
1. This Bid is genuine and not made in the interest of or on behalf of any undisclosed individual or entity and is not submitted in conformity with any collusive agreement or rules of any group, association, organization, or corporation.
2. Bidder has not directly or indirectly induced or solicited any other Bidder to submit a false or sham Bid.
3. Bidder has not solicited or induced any individual or entity to refrain from bidding.
4. Bidder has not engaged in corrupt, fraudulent, collusive, or coercive practices in competing for the Contract. For the purposes of this Paragraph 8.02.A:
a. Corrupt practice means the offering, giving, receiving, or soliciting of anything of value likely to influence the action of a public official in the bidding process.
b. Fraudulent practice means an intentional misrepresentation of facts made (a) to influence the bidding process to the detriment of Owner, (b) to establish bid prices at artificial non-competitive levels, or (c) to deprive Owner of the benefits of free and open competition.
Rev. June 26, 2026 00 41 00 - 4 Bid Form for Construction Contract
c. Collusive practice means a scheme or arrangement between two or more Bidders, with or without the knowledge of Owner, a purpose of which is to establish bid prices at artificial, non-competitive levels.
d. Coercive practice means harming or threatening to harm, directly or indirectly, persons or their property to influence their participation in the bidding process or affect the execution of the Contract.
Rev. June 26, 2026 00 41 00 - 5 Bid Form for Construction Contract
BIDDER hereby submits this Bid as set forth above:
Bidder:
(typed or printed name of organization)
By:
(individual�s signature)
Name:
(typed or printed)
Title:
(typed or printed)
Date:
(typed or printed)
If Bidder is a corporation, a partnership, or a joint venture, attach evidence of authority to sign.
Attest:
(individual�s signature)
Name:
(typed or printed)
Title:
(typed or printed)
Date:
(typed or printed)
Address for giving notices:
Bidder�s Contact:
Name:
(typed or printed)
Title:
(typed or printed)
Phone:
Email:
Address:
Bidder�s Contractor License No.: (if applicable)
Rev. June 26, 2026 00 41 00 - 1 Bid Bond
Confidential
SECTION 00 41 00
Bid Bond
Contractor Surety
Name: Name:
Address (principal place of business): Address (principal place of business):
Owner Contract
Name: Brandywine Conservancy and Museum of Art Project (name and location):
Mailing address (principal place of business): Hoffman�s Mill Dam Removal, Chadds Ford, PA
1 Hoffman�s Mill Road
PO Box 141
Chadds Ford, PA 19317
Bid Due Date: July 20, 2026
Bond
Bond Amount:
Date of Bond:
Surety and Bidder, intending to be legally bound hereby, subject to the terms set forth in this Bid Bond, do each cause this Bid Bond to be duly executed by an authorized officer, agent, or representative.
Bidder Surety
(Full formal name of Bidder) (Full formal name of Surety) (corporate seal)
By: By:
(Signature) (Signature) (Attach Power of Attorney)
Name: Name:
(Printed or typed) (Printed or typed)
Title: Title:
Attest: Attest:
(Signature) (Signature)
Name: Name:
(Printed or typed) (Printed or typed)
Title: Title:
Notes: (1) Note: Addresses are to be used for giving any required notice. (2) Provide execution by any additional parties, such as joint venturers, if necessary.
Rev. June 26, 2026 00 41 00 - 2 Bid Bond
Confidential
1. Bidder and Surety, jointly and severally, bind themselves, their heirs, executors, administrators, successors, and assigns to pay to Owner upon default of Bidder any difference between the total amount of Bidder�s Bid and the total amount of the Bid of the next lowest, responsible Bidder that submitted a responsive Bid, as determined by Owner, for the work required by the Contract Documents, provided that:
1.1. If there is no such next Bidder, and Owner does not abandon the Project, then Bidder and Surety shall pay to Owner the bond amount set forth on the face of this Bond, and
1.2. In no event will Bidder�s and Surety�s obligation hereunder exceed the bond amount set forth on the face of this Bond.
1.3. Recovery under the terms of this Bond will be Owner�s sole and exclusive remedy upon default of Bidder.
2. Default of Bidder occurs upon the failure of Bidder to deliver within the time required by the Bidding Documents
(or any extension thereof agreed to in writing by Owner) the executed Agreement required by the Bidding
Documents and any performance and payment bonds required by the Bidding Documents.
3. This obligation will be null and void if:
3.1. Owner accepts Bidder�s Bid and Bidder delivers within the time required by the Bidding Documents (or any extension thereof agreed to in writing by Owner) the executed Agreement required by the Bidding
Documents and any performance and payment bonds required by the Bidding Documents, or
3.2. All Bids are rejected by Owner, or
3.3. Owner fails to issue a Notice of Award to Bidder within the time specified in the Bidding Documents (or any extension thereof agreed to in writing by Bidder and, if applicable, consented to by Surety when required by Paragraph 5 hereof).
4. Payment under this Bond will be due and payable upon default of Bidder and within 30 calendar days after receipt by Bidder and Surety of written notice of default from Owner, which notice will be given with reasonable promptness, identifying this Bond and the Project and including a statement of the amount due.
5. Surety waives notice of any and all defenses based on or arising out of any time extension to issue Notice of
Award agreed to in writing by Owner and Bidder, provided that the total time for issuing Notice of Award including extensions will not in the aggregate exceed 120 days from Bid due date without Surety�s written consent.
6. No suit or action will be commenced under this Bond prior to 30 calendar days after the notice of default required in Paragraph 4 above is received by Bidder and Surety, and in no case later than one year after the Bid due date.
7. Any suit or action under this Bond must be commenced only in a court of competent jurisdiction located in the state in which the Project is located.
8. Notices required hereunder must be in writing and sent to Bidder and Surety at their respective addresses shown on the face of this Bond. Such notices may be sent by personal delivery, commercial courier, or by United
States Postal Service registered or certified mail, return receipt requested, postage pre-paid, and will be deemed to be effective upon receipt by the party concerned.
9. Surety shall cause to be attached to this Bond a current and effective Power of Attorney evidencing the authority of the officer, agent, or representative who executed this Bond on behalf of Surety to execute, seal, and deliver such Bond and bind the Surety thereby.
10. This Bond is intended to conform to all applicable statutory requirements. Any applicable requirement of any applicable statute that has been omitted from this Bond will be deemed to be included herein as if set forth at length. If any provision of this Bond conflicts with any applicable statute, then the provision of said statute governs and the remainder of this Bond that is not in conflict therewith continues in full force and effect.
Rev. June 26, 2026 00 41 00 - 3 Bid Bond
Confidential
11. The term �Bid� as used herein includes a Bid, offer, or proposal as applicable.
Rev. June 26, 2026 00 52 13 - 1 Agreement
SECTION 00 52 13
AGREEMENT
This Contract is by and between Brandywine Conservancy and Museum of Art (Owner) and
(Contractor).
Owner and Contractor hereby agree as follows:
ARTICLE 1 - THE WORK
1.01 Work
A. Work includes all labor, materials, equipment, services, and documentation necessary to construct the Project defined herein. The Work may include related services such as testing, start-up, and commissioning, all as required by the Contract Documents.
B. The Contractor shall complete all Work as specified or indicated in the Contract Documents.
The Project is generally described as follows:
1. Hoffman�s Mill Dam Removal which includes the removal of Hoffman�s Mill Dam, a rockfill run-of-river dam located across the Brandywine Creek in Chadds Ford and
Pennsbury Townships, Pennsylvania.
2. The Site of the Work includes property, easements, and designated work areas described in greater detail in the Contract Documents but generally located across the
Brandywine Creek immediately upstream of the Route 1 bridge, in Chadds Ford and
Pennsbury Townships, Pennsylvania.
ARTICLE 2 - CONTRACT DOCUMENTS
2.01 Intent of Contract Documents
A. It is the intent of the Contract Documents to describe a functionally complete project. The
Contract Documents do not indicate or describe all of the Work required to complete the
Project. Additional details required for the correct installation of selected products are to be provided by the Contractor and coordinated with the Owner and Engineer. This Contract supersedes prior negotiations, representations, and agreements, whether written or oral.
The Contract Documents are complementary; what is required by one part of the Contract
Documents is as binding as if required by other parts of the Contract Documents.
B. During the performance of the Work and until final payment, Contractor and Owner shall submit all matters in question concerning the requirements of the Contract Documents, or relating to the acceptability of the Work under the Contract Documents to the Engineer.
Engineer will be the initial interpreter of the requirements of the Contract Documents, and judge of the acceptability of the Work thereunder.
C. Engineer will render a written clarification, interpretation, or decision on the issue submitted, or initiate a modification to the Contract Documents.
Rev. June 26, 2026 00 52 13 - 2 Agreement
D. Contractor, and its subcontractors and suppliers, shall not have or acquire any title to or ownership rights to any of the Drawings, Specifications, or other documents (including copies or electronic media editions) prepared by Engineer or its consultants.
2.02 Contract Documents Defined
A. The Contract Documents consist of the following documents:
1. This Contract.
2. Bid Bond
3. Performance bond.
4. Payment bond.
5. Maintenance Bond
6. Specifications listed in the Table of Contents.
7. Drawings as listed on the Drawing Sheet Index.
8. The following which may be delivered or issued on or after the Effective Date of the
Contract:
a. Work Change Directives (EJCDC C-940).
b. Change Orders (EJCDC C-941).
c. Field Orders.
ARTICLE 3 - ENGINEER
3.01 Engineer
A. The Engineer for this Project is Ramboll Americas Engineering Solutions, Inc., 751 Arbor
Way, Suite 200, Blue Bell, Pennsylvania 19422
ARTICLE 4 - CONTRACT TIMES
4.01 Contract Times
A. The Work will be substantially completed on or before October 15, 2026, and completed and ready for final payment on or before December 31, 2026.
4.02 Liquidated Damages
A. Contractor and Owner recognize that time is of the essence in the performance of the
Contract, and that Owner will incur damages if Contractor does not complete the Work according to the requirements of Paragraph 4.01. Because such damages for delay would be difficult and costly to determine, Owner and Contractor agree that as liquidated damages for delay (but not as a penalty) Contractor shall pay Owner $2,000 for each day that expires after the Contract Time for substantial completion.
4.03 Delays in Contractor�s Progress
A. If Owner, Engineer, or anyone for whom Owner is responsible, delays, disrupts, or interferes with the performance or progress of the Work, then Contractor shall be entitled to an
Rev. June 26, 2026 00 52 13 - 3 Agreement equitable adjustment in the Contract Times and Contract Price. Contractor�s entitlement to an adjustment of the Contract Times is conditioned on such adjustment being essential to
Contractor�s ability to complete the Work within the Contract Times.
B. Contractor shall not be entitled to an adjustment in Contract Price or Contract Times for delay, disruption, or interference caused by or within the control of Contractor or their subcontractors or suppliers.
C. If Contractor�s performance or progress is delayed, disrupted, or interfered with by unanticipated causes not the fault of and beyond the control of Owner, Contractor, and those for which they are responsible, then Contractor shall be entitled to an equitable adjustment in Contract Times.
D. Contractor shall not be entitled to an adjustment in Contract Price or Contract Times for any delay, disruption, or interference if such delay is concurrent with a delay, disruption, or interference caused by or within the control of Contractor or Contractor�s subcontractors or suppliers.
4.04 Progress Schedules
A. Contractor shall develop a progress schedule and submit to the Engineer for review and comment before starting Work on the Site. The Contractor shall modify the schedule in accordance with the comments provided by the Engineer.
B. The Contractor shall update and submit the progress schedule to the Engineer each month.
The Owner may withhold payment if the Contractor fails to submit the schedule.
ARTICLE 5 - CONTRACT PRICE
5.01 Payment
A. Owner shall pay Contractor the total Contract Price for completion of the Work in accordance with the Contract Documents. Payment of the Contract Price shall be made in accordance with Article 14 (Progress Payments), including retainage and final payment provisions.
ARTICLE 6 - BONDS AND INSURANCE
6.01 Bonds
A. Before starting Work, Contractor shall furnish a performance bond, a payment bond, a bid bond, and a maintenance bond from surety companies that are duly licensed or authorized to issue bonds in the required amounts in the jurisdiction in which the Project is located. The performance bond and labor and material payment bond shall be in an amount equal to the
Contract Price, and the bid bond and maintenance bond shall be in an amount equal to 10 percent of the Contract Price, as security for the faithful performance and payment of all of
Contractor�s obligations under the Contract. These bonds shall remain in effect until the completion of the correction period specified in Paragraph 7.12 but, in any case, not less than one year after the date when final payment becomes due.
6.02 Insurance
A. Before starting Work, Contractor shall furnish evidence of insurance from companies that are duly licensed or authorized in the jurisdiction in which the Project is located with a
Rev. June 26, 2026 00 52 13 - 4 Agreement minimum AM Best rating of A-VII or better.
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .