3-Application for Payment.pdf.pdf

PDF 740 KB Posted

Attached to
Sidewalk Replacement and Repair - South (WORCS 2)
Solicitation number
IFB-26-00297
Issued by
Hillsborough County, Florida

About this file

This is an Application for Payment form used by Hillsborough County, Florida for construction projects. The document serves as the primary instrument for contractors to request payment for work completed on county construction contracts. The form is designed to capture project-specific information including the project name, application number, contract identification numbers, period covered, and contractor identification. The application process requires contractors to document the value of work in place, stored materials, total earned amounts, retainage deductions, previous payments, and the current payment due. The form must be accompanied by a detailed Schedule of Values providing line-item information, and attachments for documenting any payment disputes or disputes regarding subcontractor and supplier payments.

The Application for Payment requires certification by the contractor that all amounts are accurate, work complies with contract documents, title is clear for stored materials, and previous payments have been properly distributed to subcontractors and suppliers. Hillsborough County staff including the Project Manager, Resident Engineer, Inspector, and Section Manager (if applicable) must review and approve the application based on on-site observations and verification that work progress aligns with contract requirements. The form includes provisions for retainage calculations, change order documentation, and detailed accounting of all financial transactions. Two attachments accompany standard applications: Attachment 1 documents any disputes regarding previous payment applications, while Attachment 2 identifies disputes related to current payment allocations to subcontractors, material suppliers, and other contributors.

View the file

Other files

File Type Posted
5-Subcontractors Statement of Satisfaction.pdf.pdf PDF
16-Attachment B- Sidewalk Spec R3.pdf PDF
25-Payment Bond 07.02.25.pdf PDF
23-Agreement - Construction - Term Contract.doc.pdf PDF
26-IFB-26-00297 Addendum 1.pdf PDF
24-Performance Bond 07.02.25.pdf PDF
6-Consent of Surety to Final Payment.pdf.pdf PDF
12-Contractors Affidavit for Payment of Debts and Claims 02.18.2026.pdf PDF
14-Subcontractor Letter of Intent .pdf PDF
11-SBE Subcontractors Material Suppliers List SBE-1 Form.pdf PDF
21-Attachment E- Insurance Requirements.pdf PDF
9-Substitute W9 Form.pdf.pdf PDF
1-Drug Free Workplace Form.doc.doc DOC document
4-Consent of Surety-Change Order.pdf.pdf PDF
8-Insurance Certificate.doc.doc DOC document
22-1. IFB-26-00297 Terms and Conditions.pdf PDF
15-Attachment A- Construction Sign 2026.pdf PDF
2-Allowance Authorization Release Form.pdf.pdf PDF
27-IFB-26-00297 Preliminary Bid Tabulation.pdf PDF
10-Direct Deposit Authorization Form 5.15.2025.pdf.pdf PDF
20-Attachment D- Project Maps South.pdf PDF
17-Attachment C- Supplemental Specifications.pdf PDF
19-Bid Bond.pdf PDF
13-SBE-2 Goal Participation Tutorial.mp4 MP4 file
18-AFFIDAVIT OF COMPLIANCE - Denying Doing Business with a Foreign Country of Concern 02.26.2026.pdf PDF
7-Change Order Form.pdf.pdf PDF
Show all 26

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

HILLSBOROUGH COUNTY

APPLICATION FOR PAYMENT

(SECTION I) PAGE ONE OF PAGE(S)

PROJECT: APPLICATION NO.:

APPLICATION DATE:

CIP NO.: BID NO.: FOR PERIOD FROM:

TO:

CONTRACTOR:

CHANGE ORDER SUMMARY CONTRACT STATUS

ORIGINAL CONTRACT SUM $

NET CHANGE BY CHANGE ORDERS

(COLUMN 3 MINUS COLUMN 4) $

CONTRACT SUM TO DATE $

1 2 3 4

NO.

DATE APPROVED BY

COUNTY ADDITIVE DEDUCTIVE

VALUE OF WORK IN PLACE $

VALUE OF STORED MATERIALS $

TOTAL EARNED $

RETAINAGE AT % $

TOTAL EARNED LESS RETAINAGE $

LESS PREVIOUS PAYMENTS $

LESS $

CURRENT PAYMENT DUE $ TOTALS

(SECTION II) CERTIFICATION BY CONTRACTOR

The undersigned Contractor certifies:

1) All amounts and items shown on this application are correct.

2) Any work performed or materials supplied have been done in accordance with the contract documents.

3) That the contractor has clear title to any materials or equipment for which the contractor is requesting payment as stored materials.

4) All amounts paid by the County to the Contractor in previous progress payments have been applied by the Contractor and its subcontractors to promptly pay, in proportionate amounts, all subcontractors, suppliers, and others who have contributed work or materials listed in the Schedule of Values of the previous Payment Applications, except as indicated on Attachment 1, which is incorporated herein, consisting of _____ page(s).

5) The Contractor will apply any sums paid by the County from this Application for Payment to subcontractors, material, suppliers, and others who have contributed work or materials included in the line items referenced in the attached Schedule of Values (less retainage, if applicable) except as indicated on Attachment 2, which is incorporated herein, consisting of ____ page(s).

CONTRACTOR:

BY:

(Title) (Date)

ATTEST:

State of __________ County of__________

Sworn to (or affirmed) and subscribed before me, by means of_ ___ ____physical presence or ____online notarization, this ____ day of ___________, 20___, by ________________________________________.

Notary Public:

My Commission Expires:

SEAL)

Personally Known OR Produced Identification Type of Identification Produced ______________________

Revised 04.20.2020

(SECTION III) CERTIFICATION BY HILLSBOROUGH COUNTY AND REPRESENTATIVES

Based on on-site observations and the data comprising this Application for Payment, the undersigned certifies that the Work has progressed to the point indicated herein and to the best of my knowledge, information and belief is in accordance with the Contract Documents and that the CONTRACTOR is entitled to payment of the amount certified herein.

Hillsborough County INSPECTOR: DATE Hillsborough County RESIDENT ENGINEER: DATE Hillsborough County PROJECT MANAGER: DATE Hillsborough County SECTION MANAGER*: DATE

(*applicable if Project Manager is a temporary employee, consultant, or 50% of payment application; otherwise N/A)

COUNTY REPRESENTATIVE:

PROFESSIONAL CONSULTANT:

BY: DATE

(See Instructions on Back)

HILLSBOROUGH COUNTY'S CONSTRUCTION APPLICATION

FOR PAYMENT INSTRUCTION

The purpose of this form is to facilitate the summary information for Hillsborough County's Construction Application for Payment. This form will be completed by the Contractor each time payment is requested for a project. This Application for Payment will be accompanied by a Schedule of Values (which provides line-item detail information for the project), Attachment 1, and Attachment 2.

SECTION I: This section will be completed by the Contractor. The Contractor will provide the information as indicated on the form.

SECTION II: This section will be completed by the Contractor. In this section, the Contractor will provide certification about the information provided in Section I. The certification will be provided in accordance with the construction Contract Documents.

SECTION III: This section will be completed to provide approval by Hillsborough County staff and/or its representative(s). Under the approval section by Hillsborough County staff:

signature/approval by a County Project Manager will always be provided. However, the signature for the Resident Engineer or the Inspector will only be provided if the County is responsible for these functions. When the County is not responsible for these functions, the approval will indicate "N/A".

Under the approval section by Hillsborough County's Representative: signature/approval will be provided by a Construction Manager when applicable. Additionally, signature/approval may also be provided by a Professional when applicable. When there is no Construction Manager or Professional responsible for such activities then the approval will indicate "N/A".

PAGE ONE OF PAGE(S)

PROJECT: ATTACHMENT 1

CIP NO: BID NO: APPLICATION NO.:

APPLICATION DATE:

CONTRACTOR: FOR PERIOD FROM:

TO:

Name of Entity Relationship

Amount in Dispute

Application for Payment No. or corresponding line item reference to Schedule of Values Explanation

-or-

This page [ ] is [ ] is not applicable.

Contractor Signature

PAGE ONE OF PAGE(S)

PROJECT: ATTACHMENT 2

CIP NO: BID NO: APPLICATION NO.:

APPLICATION DATE:

CONTRACTOR: FOR PERIOD FROM:

TO:

Name of Entity Relationship

Amount in Dispute

Corresponding line item reference to Schedule of Values Explanation

-or-

This page [ ] is [ ] is not applicable.

Contractor Signature

HILLSBOROUGH COUNTY, FLORIDA

APPLICATION FOR PAYMENT PAGE OF PAGES

SCHEDULE OF VALUES

PROJECT NO. APPLICATION NO.

PROJECT: APPLICATION DATE:

BID NO. FOR PERIOD FROM:

CONTRACTOR: TO:

A B C D E F G H I J K L M N O P

Item No. Description Of Work Unit Price

CONTRACT SUM TO DATE WORK IN PLACE STORED MATERIALS

Comp

CONTRACT AAR APPLICATIONS CHANGE ORDER APPLICATIONS

Quantity Value Quantity Value Quantity Value No. Quantity Value No. Quantity Value

PAGE TOTALS:

CUMULATIVE TOTALS:

CHANGE ORDER SUMMARY
CONTRACT STATUS
DEDUCTIVE
VALUE OF WORK IN PLACE $
TOTALS
Entity
Relationship
Dispute
Application for
Payment No. or
corresponding line
item reference to
Schedule of Values
Explanation
Entity
Dispute
Schedule of Values
Explanation
ADDITIVE
FOR PAYMENT INSTRUCTION