26-0069 Attachment K- Addendum 1.PDF
PDF 153 KB Posted
- Solicitation number
- RFP-DET-250000002601-3
- Issued by
- Wayne County, Detroit City, Michigan
About this file
This document is Addendum No. 1 for a Request for Proposals (RFP) issued by Detroit Public Schools Community District for the Davis Aerospace Technical High School Project. The addendum, dated June 26, 2025, modifies the original RFP to address project timeline acceleration, with a goal of completing the project by August 2026. The addendum requests all trade partners to provide an add alternate for overtime work based on a revised project schedule, with the expectation that successful bidders will submit a detailed breakdown of cost impacts related to labor, equipment, and other relevant expenses.
The addendum specifically calls for alternate cost proposals that account for the additional efforts required to complete the project between the original completion schedule and the new August 2026 completion timeline. Bidders are instructed to incorporate these modifications into their proposals and are expected to demonstrate full understanding of the supplemental information provided. The document emphasizes that the alternate costs should directly reflect the extended work period and associated additional resource requirements.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
June 26, 2025
To: All Respondents
Re: Detroit Public Schools Community District – Davis Aerospace Technical High School Project
Subject: Addendum No. 1
This Addendum shall be considered part of the Request for Proposals for the above-mentioned Project, as though it had been issued at the same time and shall be incorporated integrally therewith. Where provisions of the following supplementary information differ from that of the Original RFP Documents, this Addendum shall govern.
Respondents are hereby notified that they shall make any and all necessary adjustments to their Proposals as a result of this Addendum. It shall be construed that each Respondent’s Proposal is submitted with full knowledge of all modifications as supplemental information contained herein.
The Request for Proposal is modified and clarified, as follows:
In an effort to complete the project by August 2026, we are requesting all trades Partners to provide an add alternate for overtime work based on the attached revised schedule. Please note that successful bidders will be requested to provide a detailed breakdown of any cost impacts related to labor, equipment, and/or other relevant costs. The Alternate cost should arrive from added efforts between the original completion schedule and August 2026 completion schedule.
END OF ADDENDUM 01