26-0069 Attachment J- Davis Aerospace Tech High School.PDF
PDF 157 KB Posted
- Solicitation number
- RFP-DET-250000002601-3
- Issued by
- Wayne County, Detroit City, Michigan
About this file
This document is a detailed project schedule and timeline for the Davis Aerospace Technical High School construction project, involving the Detroit Public Schools (DPS). The project encompasses a comprehensive renovation and construction effort, starting on August 12, 2024, and scheduled for completion by October 21, 2026. Key phases include design development (August 2024 - January 2025), construction documents (January - June 2025), procurement (May 2025 - August 2026), and construction activities spanning demolition, structural work, interior fit-out, electrical and mechanical equipment installation, and final sitework. Critical milestones include the start of construction on October 1, 2025, substantial completion on August 21, 2026, and the first day of school on August 24, 2026.
The project schedule breaks down intricate details across multiple work streams, including demolition, structure, interior fit-out, electrical and mechanical equipment installation, and final sitework. The timeline includes specific activities such as MEP cut and cap, salvage items, selective demolition, temporary lighting, rough framing, masonry walls, structural steel framing, MEP rough-in, drywall installation, painting, ceiling work, equipment installation, and final commissioning. The project involves complex logistical planning with precise durations for each construction phase, demonstrating a methodical approach to renovating and preparing the Davis Aerospace Technical High School for educational operations.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Activity ID Activity Name Original Duration
Remaining Duration
Start Finish
Davis Aerospace Technical High SchoolDavis Aerospace Technical High School 556 354 12-Aug-24 A 21-Oct-26
MilestonesMilestones 226 226 01-Oct-25 24-Aug-26
A1000 Start of Construction 0 0 01-Oct-25
A1010 Substantial Completion 0 0 21-Aug-26*
CON-1380 First Day of School 0 0 24-Aug-26
Design PhaseDesign Phase 206 4 12-Aug-24 A 04-Jun-25
Design DevelopmentDesign Development 109 0 12-Aug-24 A 23-Jan-25 A
DD-1000 DD Drawings 1 0 12-Aug-24 A 31-Dec-24 A
DD-1010 DD Estimate 1 0 01-Jan-25 A 16-Jan-25 A
DD-1020 DD Estimate Reconciliation 1 0 17-Jan-25 A 23-Jan-25 A
Construction DocumentsConstruction Documents 93 4 24-Jan-25 A 04-Jun-25
CD-1000 CD Drawings 1 0 24-Jan-25 A 08-May-25 A
CD-1010 CD Estimate 15 2 09-May-25 A 02-Jun-25
CD-1020 Constructability Review 7 0 09-May-25 A 28-May-25 A
CD-1030 CD Estimate Reconciliation 2 2 03-Jun-25 04-Jun-25
ProcurementProcurement 313 299 09-May-25 A 04-Aug-26
Bid and AwardBid and Award 46 32 09-May-25 A 15-Jul-25
BA-1000 Bid Documents 1 0 09-May-25 A 22-May-25 A
BA-1010 DPS Review Bid Documents 4 7 23-May-25 A 09-Jun-25
BA-1020 Bidding Period 15 15 10-Jun-25 30-Jun-25
BA-1030 Bid Review 10 10 01-Jul-25 15-Jul-25
GMPGMP 67 67 16-Jul-25 17-Oct-25
GMP-1000 Prepare GMP 15 15 16-Jul-25 05-Aug-25
GMP-1010 Submit GMP 2 2 06-Aug-25 07-Aug-25
GMP-1020 DPS GMP Approval 30 30 08-Aug-25 19-Sep-25
GMP-1030 Issue Subcontracts 20 20 22-Sep-25 17-Oct-25
SubmittalsSubmittals 135 135 04-Jun-25 17-Dec-25
LL-1000 Recieve Environmental Report 0 0 04-Jun-25
LL-1100 FAA Crane Permit 90 90 05-Jun-25 10-Oct-25
LL-1010 Permits - City of Detroit 55 55 10-Jun-25 26-Aug-25
LL-1020 Electrical Submittals 10 10 20-Oct-25 31-Oct-25
LL-1120 Elevator Submittals 20 20 20-Oct-25 17-Nov-25
LL-1030 HVAC Submittals 10 10 03-Nov-25 17-Nov-25
LL-1040 Kitchen Equipment Submittals 10 10 18-Nov-25 03-Dec-25
LL-1050 Roof Submittals 10 10 04-Dec-25 17-Dec-25
Long Lead ItemsLong Lead Items 190 190 03-Nov-25 04-Aug-26
LL-1090 Electrical Gear 190 190 03-Nov-25 04-Aug-26
LL-1060 Boilers 50 50 18-Nov-25 30-Jan-26
LL-1080 RTU's 120 120 18-Nov-25 08-May-26
LL-1110 Elevator Hydraulic Power Unit 100 100 18-Nov-25 10-Apr-26
LL-1070 Kitchen Equipment 110 110 04-Dec-25 08-May-26
LL-1130 DTE Transformer 0 0 03-Aug-26*
ConstructionConstruction 284 284 19-Sep-25 15-Aug-26
Oct N D Jan F Mar Apr M Jun Jul A S Oct N D Jan F Mar Apr M Jun Jul A S Oct N D Jan F Mar Apr 2025 2026 2027
Start of Construction
Substantial Completion
First Day of School
DD Drawings
DD Estimate
DD Estimate Reconciliation
CD Drawings
CD Estimate
Constructability Review
CD Estimate Reconciliation
Bid Documents
DPS Review Bid Documents
Bidding Period
Bid Review
Prepare GMP
Submit GMP
DPS GMP Approval
Issue Subcontracts
Recieve Environmental Report
FAA Crane Permit
Permits - City of Detroit
Electrical Submittals
Elevator Submittals
HVAC Submittals
Kitchen Equipment Submittals
Roof Submittals
Electrical Gear
Boilers
RTU's
Elevator Hydraulic Power Unit
Kitchen Equipment
DTE Transformer
Finish Date: 21-Oct-26
Data Date: 30-May-25
Run Date: 02-Jun-25 17:22
DAVIS-1
Remaining Level of Effort
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Summary Milestones
Critical Milestones
Milestone
Davis Aerospace Technical High School
Remaining Duration
Start Finish
DemolitionDemolition 95 95 19-Sep-25 07-Jan-26
CON-1390 MEP Cut & Cap - Make Safe 5 5 19-Sep-25 24-Sep-25
CON-1020 Salvage Items 5 5 25-Sep-25 30-Sep-25
CON-1000 Selective Demolition 30 30 01-Oct-25 04-Nov-25
CON-1050 MEP Demolition 30 30 01-Oct-25 04-Nov-25
A1020 Air Side Fencing 10 10 01-Oct-25 11-Oct-25
CON-1430 Escalator / Baggage Conveyor / Dumbwaiter 15 15 01-Oct-25 17-Oct-25
CON-1060 Lower Roof Demolition 5 5 05-Nov-25 10-Nov-25
CON-1410 Upper Roof Demolition 5 5 02-Jan-26 07-Jan-26
StructureStructure 90 90 18-Oct-25 30-Jan-26
CON-1010 Temporary Lighting 10 10 18-Oct-25 29-Oct-25
CON-1030 Rough Framing 30 30 22-Oct-25 25-Nov-25
CON-1040 Masonry Walls and Infills 30 30 05-Nov-25 09-Dec-25
CON-1080 Structural Steel Framing 20 20 10-Dec-25 01-Jan-26
CON-1070 Lower Roof Installation 8 8 18-Dec-25 26-Dec-25
CON-1090 Floor Infills / Slab on Grade 5 5 08-Jan-26 13-Jan-26
CON-1400 Upper Roof Installation 15 15 14-Jan-26 30-Jan-26
Interior Fit OutInterior Fit Out 214 214 10-Dec-25 15-Aug-26
CON-1110 Overhead MEP Rough In 30 30 10-Dec-25 13-Jan-26
CON-1100 In Wall MEP Rough In 20 20 14-Jan-26 05-Feb-26
CON-1140 Install Drywall 20 20 06-Feb-26 28-Feb-26
CON-1160 Mud / Tape / Sand 20 20 12-Feb-26 06-Mar-26
CON-1170 Prime and 1st Coat Paint 10 10 07-Mar-26 18-Mar-26
CON-1180 Suspended Ceiling Tracks 20 20 19-Mar-26 10-Apr-26
CON-1120 MEP Bathroom Finishes 25 25 19-Mar-26 16-Apr-26
CON-1200 Casework Installation 5 5 19-Mar-26 24-Mar-26
CON-1230 MEP Devices (Lights/Diffusers/Ducts) 15 15 25-Mar-26 10-Apr-26
CON-1150 Elevator Upgrades 35 35 11-Apr-26 21-May-26
CON-1250 In Wall Devices 10 10 11-Apr-26 22-Apr-26
CON-1260 Final Fire Alarm / Sprinkler Devices 5 5 11-Apr-26 16-Apr-26
CON-1270 Flooring 30 30 11-Apr-26 15-May-26
CON-1220 Toilet Accessories 5 5 17-Apr-26 22-Apr-26
CON-1190 Kitchen Equipment 20 20 09-May-26 01-Jun-26
CON-1280 Second Coat of Paint 10 10 02-Jun-26 12-Jun-26
CON-1290 Ceiling Tile 15 15 13-Jun-26 30-Jun-26
CON-1300 Door Installation 5 5 01-Jul-26 06-Jul-26
CON-1310 Construction Clean 2 2 04-Jul-26 06-Jul-26
CON-1320 Internal Punch List 2 2 07-Jul-26 08-Jul-26
CON-1340 A/E Punch List 2 2 09-Jul-26 10-Jul-26
CON-1350 Sub Remedy Punch List 10 10 09-Jul-26 20-Jul-26
CON-1360 Final Clean 5 5 21-Jul-26 25-Jul-26
CON-1370 A/E Owner Sign Off 1 1 27-Jul-26 27-Jul-26
CON-1330 School Furniture Move In 10 10 28-Jul-26 07-Aug-26
Electrical and Mechanical EquipmentElectrical and Mechanical Equipment 169 169 31-Jan-26 15-Aug-26
Oct N D Jan F Mar Apr M Jun Jul A S Oct N D Jan F Mar Apr M Jun Jul A S Oct N D Jan F Mar Apr 2025 2026 2027
MEP Cut & Cap - Make Safe
Salvage Items
Selective Demolition
MEP Demolition
Air Side Fencing
Escalator / Baggage Conveyor / Dumbwaiter
Lower Roof Demolition
Upper Roof Demolition
Temporary Lighting
Rough Framing
Masonry Walls and Infills
Structural Steel Framing
Lower Roof Installation
Floor Infills / Slab on Grade
Upper Roof Installation
Overhead MEP Rough In
In Wall MEP Rough In
Install Drywall
Mud / Tape / Sand
Prime and 1st Coat Paint
Suspended Ceiling Tracks
MEP Bathroom Finishes
Casework Installation
MEP Devices (Lights/Diffusers/Ducts)
Elevator Upgrades
In Wall Devices
Final Fire Alarm / Sprinkler Devices
Flooring
Toilet Accessories
Kitchen Equipment
Second Coat of Paint
Ceiling Tile
Door Installation
Construction Clean
Internal Punch List
A/E Punch List
Sub Remedy Punch List
Final Clean
A/E Owner Sign Off
School Furniture Move In
Finish Date: 21-Oct-26
Data Date: 30-May-25
Run Date: 02-Jun-25 17:22
DAVIS-1
Remaining Level of Effort
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Summary Milestones
Critical Milestones
Remaining Duration
Start Finish
CON-1210 Install Boilers 10 10 31-Jan-26 11-Feb-26
CON-1130 Install RTU's 10 10 09-May-26 20-May-26
CON-1420 Install Electrical Gear 10 10 05-Aug-26 15-Aug-26
Final SiteworkFinal Sitework 48 48 17-Jun-26 11-Aug-26
SITE-1010 Site Preparation 15 15 17-Jun-26* 03-Jul-26
SITE-1020 Sealing, Pavement, and Patching 20 20 04-Jul-26 27-Jul-26
SITE-1030 New Concrete 15 15 04-Jul-26 21-Jul-26
SITE-1040 Parking Lot Gate 15 15 22-Jul-26 07-Aug-26
SITE-1050 Stripping 2 2 08-Aug-26 10-Aug-26
SITE-1060 Clean Up 1 1 11-Aug-26 11-Aug-26
CloseoutCloseout 92 92 07-Jul-26 21-Oct-26
CL-1010 Test and Balance 5 5 07-Jul-26 11-Jul-26
CL-1000 Commissioning 15 15 17-Aug-26 02-Sep-26
CL-1020 Final Inspections 5 5 17-Aug-26 21-Aug-26
CL-1030 Project Closeout 42 42 03-Sep-26 21-Oct-26
Oct N D Jan F Mar Apr M Jun Jul A S Oct N D Jan F Mar Apr M Jun Jul A S Oct N D Jan F Mar Apr 2025 2026 2027
Install Boilers
Install RTU's
Install Electrical Gear
Site Preparation
Sealing, Pavement, and Patching
New Concrete
Parking Lot Gate
Stripping
Clean Up
Test and Balance
Commissioning
Final Inspections
Project Closeout
Finish Date: 21-Oct-26
Data Date: 30-May-25
Run Date: 02-Jun-25 17:22
DAVIS-1
Remaining Level of Effort
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Summary Milestones
Critical Milestones