This document is a set of project specifications for the Bakers Lane Shared-Use Path project (Section 20-00631-00-BT) prepared by the City of Urbana, Illinois. The project involves constructing a 10-ft-wide concrete shared-use path with 2-ft-wide earthen shoulders, located on the north side of Washington Street from Kinch Street to Bakers Lane, and along Bakers Lane from Washington Street to Main Street. The work includes reconstruction of HMA and concrete driveways, curb removal and replacement, installation of new lighting, tree removal, seeding, and other miscellaneous construction activities. The project specifications detail technical requirements, materials specifications, traffic control protocols, utility adjustments, and construction methodologies.
The project specifications include detailed provisions for insurance requirements, with contractors required to place insurance with companies having an A.M. Best Rating of A- VIII or better. Prevailing wage rates for Champaign County will be applicable, and the project has specific requirements for contractor qualifications, including certification levels for hot-mix asphalt technicians. The contract includes provisions for equipment, traffic control, pedestrian safety, utility coordination with entities like City of Urbana Utilities, Illinois American Water, and I3 Broadband, and specific technical requirements for materials such as concrete, lighting, and pavement markings. The project appears to be funded through local municipal infrastructure funding, with precise funding sources not explicitly detailed in the specifications.
View the file
Other files
Show all 25
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Bakers Lane Shared Use Path
Section No. 20-00631-00-BT
August 28, 2025
Specifications
TABLE OF CONTENTS
A. City of Urbana Special Provisions
a. General Contractual Conditions
b. Technical Provisions
B. IDOT Special Provisions
a. Index for Supplemental Specifications
b. BLR 11300 – Check Sheet for Recurring Special Provisions
c. BDE Special Provisions
C. Highway Standards and District 5 Details
SECTION A
City of Urbana Special Provisions
City of Urbana
Final Submittal 1
CITY OF URBANA
SPECIAL PROVISIONS
PART 1 – GENERAL CONTRACTUAL CONDITIONS
1.1 COORDINATION OF CONTRACT DOCUMENTS
1.2 PRE-CONSTRUCTION MEETING
1.3 GUARANTEE PERIOD
1.4 INSURANCE
1.5 CONSTRUCTION AND MAINTENANCE NOISE
1.6 PREVAILING WAGE RATES
1.7 PROSECUTION OF THE WORK AND WORKING DAYS
PART 2 - TECHNICAL PROVISIONS
2.1 LOCATION OF PROJECT
2.2 DESCRIPTION OF WORK
2.3 STATUS OF UTILITIES
2.4 STABILIZED CONSTRUCTION ENTRANCE
2.5 TREE PRUNING
2.6 MANHOLE TO BE ADJUSTED
2.7 TRAFFIC CONTROL AND PROTECTION
2.8 WASHOUT BASIN
2.9 PORTLAND CEMENT CONCRETE SIDEWALK (SPECIAL)
2.10 RECTANGULAR RAPID FLASHING BEACON ASSEMBLY (COMPLETE)
2.11 GENERAL ELECTRIC REQUIREMENTS
2.12 LUMINAIRE (SPECIAL)
2.13 LIGHT POLE, SPECIAL, 16 FT
2.14 REMOVE TEMPORARY CONCRETE BARRIER
2.15 EXPLORATION TRENCH (SPECIAL)
2.16 METER VAULTS TO BE ADJUSTED
2.17 REMOVE EXISTING SIGN POST
2.18 JUNCTION BOX TO BE ADJUSTED
2.19 CONTRACTOR DISTURBED AREAS
2.20 TOPSOIL EXCAVATION AND PLACEMENT
Final Submittal 2
PART 1 – GENERAL CONTRACTUAL CONDITIONS
1.1 Coordination of Contract Documents
The following table supplements the hierarchy of contract documents according to Article 105.05 of the Standard Specifications.
Authorized Change Orders Hold over: Addenda to Contract Documents, Special
Provisions, Plans, Recurring Special Provisions, Supplemental Specifications, and Standard Specifications.
Addenda to Contract Documents Hold over: Special Provisions, Plans, Recurring Special Provisions, Supplemental Specifications, and Standard Specifications.
Special Provisions (1) Hold over: Plans, Recurring Special Provisions, Supplemental Specifications, and Standard Specifications.
Plans (2) Hold over: Recurring Special Provisions, Supplemental Specifications, and Standard Specifications.
Notes:
(1) The term “Special Provisions” includes General Information, General Contractual Conditions, and Technical Provisions.
(2) Detail plans hold over Urbana Standard Details, and Urbana Standard Details hold over IDOT District or Highway Standards.
1.2 Pre-Construction Meeting
As soon as possible after receipt of the Notice to Proceed, the ENGINEER will schedule a Pre-construction Meeting for the project. The CONTRACTOR shall have his/her General Superintendent and Jobsite Superintendent present at the appropriate meeting to discuss all details of the project. At these meetings, the CONTRACTOR shall submit for approval information and drawings where appropriate on all major equipment and materials planned for use on the projects to the ENGINEER for approval.
Information shall be included on a minimum of the following items:
A. List of Subcontractors and Material Suppliers B. Shop Drawings C. Erosion Control Plan and Inlet Filter Systems D. Construction Staging and Access to Properties E. Traffic Control Plan F. Progress Schedule
1.3 Guarantee Period
The CONTRACTOR shall warrant all work performed for a period of one (1) year from the date of completion and acceptance by the OWNER.
Final Submittal 3
1.4 Insurance
Insurance must be placed with companies with an A.M. Best Rating of A- VIII or better.
For “Employers Liability” (part (a)(2) of Article 107.27 of the Standard Specifications), change the coverage limit to $1,000,000 for each category. Coverage will include a waiver of subrogation in favor of the City of Urbana.
Add the following requirements to “Commercial General Liability” (part (b) of Article 107.27 of the Standard Specifications):
(4) Personal and Advertising Injury Liability Limit $1,000,000.
Contractor shall name the City of Urbana and its officers and employees as additional insured (additional insured status must be provided via CG 2010 07/04 and CG 2037 07/04 for two (2) years from completion of the project), on a primary and non-contributory basis to any City of Urbana insurance or self-insured program, for liability arising out of the activities of Contractor.
Coverage will include contractual liability and a waiver of subrogation.
Add the following requirements to “Commercial Automobile Liability” (part (c) of Article 107.27 of the Standard Specifications):
Contractor shall name the City of Urbana and its officers and employees as additional insured on a primary and non-contributory basis to any City of Urbana insurance or self-insured program, for liability arising out of the activities of Contractor. Coverage will include a waiver of subrogation.
Add the following requirements to “Umbrella Liability” (part (d) of Article 107.27 of the Standard Specifications):
(1) General Aggregate Limit $5,000,000
(2) Each Occurrence Limit $5,000,000
Pollution Liability. When the services provided under this contract include any potential pollution/environmental risk or losses caused by pollution conditions, including mold and asbestos, that may arise from the Contractor’s work, Contractor shall maintain pollution liability insurance coverage at minimum limits as indicated below for itself, and its employees and agents. When a claims-made policy is renewed or replaced, the policy retroactive date must coincide with, or precede commencement of services by Contractor under this Contract. A claims-made policy that is replaced by an occurrence-based policy or not renewed must have an extended reporting period of at least two years.
Pollution Liability $1,000,000 per occurrence $2,000,000 annual aggregate
Contractor shall name the City of Urbana and its officers and employees as additional insured on a primary and non-contributory basis to any City of Urbana insurance or self-insured program, for liability arising out of the activities of Contractor. Coverage will include a waiver of subrogation.
Final Submittal 4
1.5 Construction and Maintenance Noise
The contractor shall adhere to the City of Urbana noise ordinance Section 16-7 in scheduling work windows. According to the ordinance, it is unlawful to use any construction equipment to perform any construction or maintenance work associated with this project at any time between the hours noted below where such construction equipment is operated within six hundred (600) feet of any residence, hospital, or place of worship.
8:00 pm through 7:00 am Monday through Saturday 8:00 pm Saturday through 12:00 pm (noon) Sunday 8:00 pm Sunday through 7:00 am Monday
This time regulation shall not apply to sawing contraction joints, maintenance or operation of safety and traffic control devices such as barricades, signs and lighting, or to construction of an emergency nature.
Any arrow board used for traffic control that is to remain in place overnight shall be of a non-motorized type in order to eliminate noise and comply with the City’s Ordinance.
Exception: Any machine or device or part thereof which is regulated by or becomes regulated by Federal or State of Illinois noise standards shall conform to those above standards. Such equipment shall be operated as designated above.
1.6 Prevailing Wage Rates
The current prevailing wage rates for Champaign County, Illinois are found on the Illinois Department of Labor (IDOL) website (https://labor.illinois.gov/laws-rules/conmed/current-prevailing-rates.html).
1.7 Prosecution of the Work and Working Days
Replace Article 108.03 of the Standard Specifications with the following:
The Contractor shall begin the work to be performed under the contract according to a satisfactory progress schedule or critical path schedule. If the Contractor has not submitted a satisfactory progress schedule or critical path schedule to the Engineer within five days after the execution of the contract by the Department, then the Contractor shall begin the work to be performed under the contract not later than ten days after the execution of the contract by the Department. The work shall be prosecuted in such a manner and with such a supply of materials, equipment and labor as is considered necessary to ensure its completion according to the time specified in the contract.
The Contractor shall notify the Engineer at least 24 hours in advance of either discontinuing or resuming operations.
Add the following to the end of the first paragraph of Article 108.04 of the Standard Specifications:
The charging of working days may start later than ten days after the execution and approval of the contract according to a satisfactory progress schedule or critical path schedule.
Final Submittal 5
PART 2 - TECHNICAL PROVISIONS
The following Special Provisions supplement the “Standard Specifications for Road and Bridge Construction, Adopted January 1, 2022”, the latest edition of the “Manual on Uniform Traffic Control Devices for Streets and Highways”, and the “Manual of Test Procedures for Materials” in effect on the date of invitation for bids, and the “Supplemental Specifications and Recurring Special Provisions, adopted January 1, 2025” indicated on the Check Sheet included herein, which apply to and govern the construction of the Bakers Lane Shared Use Path and in case of conflict with any part, or parts, of said Specifications, the said Special Provisions shall take precedence and shall govern.
2.1 Location of Project
The proposed shared use path is located on the north side of Washington Street in Urbana, Illinois, from Kinch Street to Bakers Lane (Smith Street), and along Bakers Lane from Washington Street to Main Street.
2.2 Description of Work
The work consists of installation of a 10-ft-wide concrete pavement path with 2-ft-wide earthen shoulders, reconstruction of HMA and concrete driveways, curb removal and replacement, installation of new lighting, tree removal, seeding, and all other miscellaneous work to construct the project as shown in the plans and described herein.
2.3 Status of Utilities
Name & Address of Utility
Type Location(s) Adjustment or
Relocation City of Urbana
706 Glover Ave.
Urbana, IL 61802
Street Lighting Vault STA 303+70 Adjustment
City of Urbana 706 Glover Ave.
Urbana, IL 61802
Sanitary Manhole STA 308+20 Adjustment
City of Urbana 706 Glover Ave.
Urbana, IL 61802
Storm Manhole
STA 500+65
STA 506+25
STA 526+70
Adjustment
City of Urbana 706 Glover Ave.
Urbana, IL 61802
Water Meter Vault
STA 303+70
STA 316+60
Adjustment
Illinois American Water 1406 Cardinal Ct.
Urbana, IL 61801
Valve Boxes
STA 305+60
STA 310+10
Adjustment
Illinois American Water 1406 Cardinal Ct.
Urbana, IL 61801
Fire Hydrant STA 305+60 Relocation
I3 Broadband 602 High Point Lane East Peoria, IL 61611
Fiber Optic Utility Vault
STA 301+10
STA 301+25
STA 306+35
STA 309+90
Adjustment
Ameren Illinois #6 Richard Mark Way
Collinsville, Illinois 62234 Gas Valve Box STA 315+80 Adjustment
Final Submittal 6
Toll Free J.U.L.I.E. Telephone Number (800) 892-0123 *= J.U.L.I.E. Member
2.4 Stabilized Construction Entrance
This work shall consist of constructing, maintaining, removing, and disposing of temporary stabilized construction entrances according to the City of Urbana “Stabilized Construction Entrance Details” and Section 280 of the Standard Specifications.
The stabilized construction entrance shall be constructed and maintained so that positive drainage is provided at all times. If it is necessary to interrupt existing drainage facilities with the stabilized construction entrance, the Contractor shall provide and maintain temporary drainage facilities within the limits of the contract. The location of the stabilized construction entrances are shown on the plans in approximate locations. The contractor shall review their operations and if changes are warranted, the contractor shall submit alternative locations for review.
Method of Measurement. This work will be measured for payment in place in square yards.
Temporary drainage facilities required for the stabilized construction entrance will not be measured for payment.
Basis of Payment. This work will be paid for at the contract unit price per square yard for STABILIZED
CONSTRUCTION ENTRANCE.
2.5 Tree Pruning
In addition to the requirements of Section 201 of the Standard Specifications, any tree limb pruning shall be performed by a professional arborist.
2.6 Manhole to be Adjusted
For manholes, adjusting rings shall be fabricated from Cretex expanded polypropylene (EPP), or approved equivalent. This work shall be considered incidental to MANHOLE TO BE ADJUSTED and shall not be paid separately.
2.7 Traffic Control and Protection
Traffic control shall be in accordance with the applicable sections of the Standard Specifications for Road and Bridge Construction, the applicable guidelines contained in the Illinois Manual on Uniform Traffic Control Devices for Streets and Highways, these Special Provisions and any special details and highway standards contained herein and in the plans.
Special attention is called to Articles 107.09 and 107.14 of the Standard Specifications, the following Highway Standards relating to Traffic Control, and the listed Supplemental Specifications and Recurring Special Provisions.
Highway Standards:
701001-02 Off-Road Operations, 2L, 2W, More than 15’ Away 701006-05 Off-Road Operations, 2L, 2W, 15’ to 24” from Pavement Edge 701501-06 Urban Lane Closure, 2L, 2W, Undivided 701502-09 Urban Lane Closure, 2L, 2W, with Bidirectional Left Turn Lane 701601-09 Urban Lane Closure, Multilane, 1W or 2W with Nontraversable Median 701701-10 Urban Lane Closure, Multilane Intersection
Final Submittal 7
701801-06 Sidewalk, Corner or Crosswalk Closure 701901-10 Traffic Control Devices
Special Provisions: LRS 3 - Work Zone Traffic Control Surveillance
Traffic: It is the intention of the City that Washington Street and Main Street be kept open to traffic at all times during the construction of this section. One-way traffic will be permitted in the immediate work areas during construction. At all other times, two-way traffic shall be maintained throughout the project.
Activities interfering with access to sidewalk and entrances along Washington Street shall be limited to the summer break period for Urbana School District 116.
During periods when material or equipment is being hauled to or from the project site all haul trucks shall have at least one (1) flashing amber light or one (1) set of dual emergency flashers, operating when within the lane closure. In addition “WORK TRUCK DO NOT FOLLOW” signs shall be displayed on the rear of all haul trucks. Displays shall be 36 inch x 18 inch (0.91 m x 0.46 m) made of Fluorescent Orange reflective material as specified in Article 1106.01. This work shall be considered as included in the contract unit prices for the construction items involved and no additional compensation will be allowed.
Parking of personal vehicles within the right-of-way will be strictly prohibited. Off-site parking and transportation arrangements shall be the responsibility of the Contractor.
The following traffic control standards shall be utilized during, but not limited to, the listed construction operations:
Advanced Notice
The City of Urbana will be responsible for notifying the public, the United States Postal Service and the emergency service agencies for road closures and changes in the traffic maintenance plans.
The contractor shall notify the City 72 hours in advanced of implementing new or adjusting existing traffic control.
Access
If a proposed patch or driveway remove/replacement interferes with access to a private or commercial driveway, the contractor shall give at least 48 hours advanced notice to the Engineer of the driveway closure. If a private home or commercial business has one (1) entrance, all attempts must be made to do only half the drive (while maintaining access) at a time. If a private home or commercial business has two (2) or more entrances, at least one (1) entrance must remain open at all times. Nearby on-street parking shall be maintained while a driveway is closed.
Changeable Message Signs
Portable changeable signs shall be erected at each location at the beginning and end of the project five
(5) days prior to the start of construction to forewarn motorists of the impending construction. This work shall be performed in accordance with Article 701 of the Standard Specifications except reference to supplying equipment to run the sign from a remote location and reference to the basis of payment shall be deleted. The signs shall remain in place and operational until such time that all traffic control devices are in place and construction has begun. The sign message will be provided by the Engineer.
Final Submittal 8
Solar Powered Arrow Boards
Arrow boards shall be used as required by the Standards and as directed by the Engineer. All arrow boards to be used on this project shall be solar powered.
Pedestrian Sidewalk Control
The Contractor shall install, maintain, and remove necessary signs and barricades needed to direct pedestrians to usable sidewalks and walkways during the construction, and as directed by the Engineer.
At each point of closure, a sufficient number of barricades shall be used to completely close the sidewalk to pedestrian movement. Where construction activities involve sidewalks on both sides of the street, the work shall be staged so that both are not out of service at the same time.
Temporary Sidewalks
The Contractor may restrict pedestrian access to the project during working hours by utilizing Highway Standard 701801. During non-working hours the Contractor shall allow for pedestrian access through the project site by constructing temporary sidewalks at locations where existing sidewalks have been removed or as directed by the Engineer. The temporary sidewalk shall consist of coarse aggregate gradation CA-6 placed at a compacted depth of five (5) inches and minimum width of four (4) feet at locations and to the satisfaction of the Engineer. This work, including furnishing and placing the materials, as well as compaction, maintenance, removal, and subsequent disposal of the material in accordance with Article 202.03 of the Standard Specifications.
Public Safety and Convenience
The Contractor shall maintain entrances and side roads along the proposed improvement. Interference with traffic movements and inconvenience to owners of abutting property and the public shall be kept to a minimum. Any delays or inconveniences caused to the Contractor by complying with these requirements shall be considered as incidental to the contract and no additional compensation will be allowed.
Method of Measurement. This work will be measured for payment as a Lump Sum for the traffic control and protection outlined in the above special provision. .
Basis of Payment. This work will be paid for at the contract unit price per lump sum for TRAFFIC
CONTROL AND PROTECTION.
2.8 Washout Basin
This work shall consist of constructing, maintaining, and removing temporary concrete truck washout basin(s) as specified herein and shown in the details in the plans.
The Contractor shall take sufficient precautions to prevent pollution of streams, lakes, reservoirs, and wetlands with fuels, oils, bitumen, calcium chloride, or other harmful materials according to Article 107.23 of the Standard Specifications.
As indicated in the project quantities, each project area specifying concrete construction requiring more than 9 cubic yards of concrete will be considered for one WASHOUT BASIN. Any location requiring less than 9 cubic yards of concrete will not be considered for payment of a WASHOUT BASIN but shall be considered part of the cost of the concrete work performed.
Final Submittal 9
General
The WASHOUT BASIN shall be constructed on the job site in accordance with the Illinois Urban Manual practice standard for Temporary Concrete Washout Facility.
The Contractor may elect to use a prefabricated portable concrete washout structure. The Contractor shall submit a plan for the prefabricated concrete washout facility to the Engineer for approval a minimum of 10 calendar days prior to the first concrete pour.
The working concrete washout facility shall be in place before any delivery of concrete to the site. The Contractor shall ensure that all concrete washout activities are limited to the designated area.
The WASHOUT BASIN shall be located no closer than 50 feet from any environmentally sensitive areas, such as storm drain inlets, open drainage facilities, bodies of water, wetlands and/or other areas indicated on the plans. Each facility is to be located away from construction traffic or access areas to prevent disturbance or tracking. Adequate signage shall be placed at the washout facility and elsewhere as necessary to clearly indicate the location of the Washout Basin to the operators of the concrete trucks.
Design
The WASHOUT BASIN shall be adequately sized to fully contain the concrete washout needs of the project. As shown in the details, the WASHOUT BASIN shall be constructed of straw bales or a wood frame and polyethylene sheeting. Straw bales or wood frames shall be used to create a berm, then lined with a single sheet of 30 mil polyethylene sheeting which is free from holes, tears, or other defects which may compromise the impermeability of the material. Sheeting shall extend over the entire basin and berm.
Maintenance
The contents of the WASHOUT BASIN shall not exceed 75% of the facility capacity. Once 75% capacity is reached, concrete placement shall be discontinued until the basin is cleaned out. Hardened concrete shall be removed and properly disposed of outside the right-of-way. Slurry shall be allowed to evaporate or shall be removed and properly disposed of outside the right-of-way.
The Contractor shall immediately replace the damaged basin liner or other washout basin components to prevent leakage of concrete waste from the WASHOUT BASIN. WASHOUT BASINS shall be inspected by the Contractor after each use. All spills shall be reported to the Engineer and cleaned up immediately. The Contractor shall remove the WASHOUT BASIN when it is no longer needed.
If a rain or snowstorm is forecasted, a non-collapsing, non-water collecting cover shall be placed over the WASHOUT BASIN and secured to prevent accumulation and overflow of precipitation.
Method of Measurement
WASHOUT BASIN will be measured AS Lump Sum regardless of number, location, size, maintenance requirements, or length of time in use. The WASHOUT BASIN shall be used throughout the duration of the project.
Basis of Payment
WASHOUT BASIN will be paid for at the contract unit price per Lump Sum for WASHOUT BASIN and will be paid in full at the completion of the concrete work.
Final Submittal 10
2.9 Portland Cement Concrete Sidewalk (Special)
This work shall consist of constructing the proposed PCC path in accordance with the applicable sections of the Standard Specifications for Road and Bridge Construction, these Special Provisions and any special details contained herein and in the plans.
General
This work shall be performed in accordance with Section 424 of the Standard Specifications, except joints shall consist of sawed grooves in the surface of the pavement in accordance with Article 420.05(c) of the Standard Specifications. Maximum spacing for contraction joints shall be 10 feet. Expansion joints shall be included at logical locations up to a maximum distance of 200 feet, as approved by the Engineer. A tooled joint shall not be used in the finishing of the concrete except under special conditions approved by the Engineer.
Method of Measurement
PORTLAND CEMENT CONCRETE SIDEWALK (SPECIAL), of the thickness specified, will be measured in square feet.
Basis of Payment
PORTLAND CEMENT CONCRETE SIDEWALK (SPECIAL), of the thickness specified, will be paid for at the contract unit price per square foot.
2.10 Rectangular Rapid Flashing Beacon Assembly (Complete)
This work shall consist of all labor, materials, tools, and equipment necessary to furnish and install the concrete foundation, pole and base, rectangular rapid flashing beacons, signage and the solar power assembly at the specified locations in the plans, in accordance with the applicable sections of the Standard Specifications for Road and Bridge Construction, these Special Provisions, and any special details contained herein and in the plans.
Materials
RECTANGULAR RAPID FLASHING BEACON ASSEMBLY (COMPLETE) shall be equipped with a pedestrian activated push button or remote transmitters, strobe warning light flash bars, and 40-watt solar panel. A JSF Technologies product or owner-approved equivalent alternative product should be utilized.
Steel support channels shall conform to Section 720 of the Standard Specifications and shall be galvanized. Concrete foundations with steel reinforcement cages and anchor bolts shall be furnished and installed according to the manufacturer’s specifications and Section 836 of the Standard Specifications.
All signage shall conform to the most recently adopted ILMUTCD.
Installation
The Contractor shall furnish and install the RECTANGULAR RAPID FLASHING BEACON ASSEMBLY (COMPLETE) at the locations shown on the plans. This item shall be mounted on steel support channels conforming to Section 720 of the Standard Specifications. Sign mounting heights and depths of burial for the support channels shall conform to the applicable IDOT Standard Specifications and details. This task shall include all programming required upon completion of the installation of the hardware in order to synchronize the multiple sign locations.
Final Submittal 11
Method of Measurement
RECTANGULAR RAPID FLASHING BEACON ASSEMBLY (COMPLETE) will be measured as one unit at each location.
Basis of Payment
RECTANGULAR RAPID FLASHING BEACON ASSEMBLY (COMPLETE) will be paid for at the contract unit price per each RECTANGULAR RAPID FLASHING BEACON ASSEMBLY (COMPLETE). Steel support channels, concrete foundations, and all other materials and equipment required for installation shall be considered incidental and shall be included in the unit price for each RECTANGULAR RAPID
FLASHING BEACON ASSEMBLY (COMPLETE).
2.11 General Electric Requirements
This work shall be performed in accordance with applicable sections in Division 800 of the Standard Specifications for Road and Bridge Construction, these Special Provisions, and any special details contained herein and in the plans
Standards of Installation
Materials shall be installed according to the manufacturer’s recommendations, the NEC, OSHA, the NESC, and AASHTO’s Standard Specifications for Structural Supports for Highway Signs, Luminaires, and Traffic Signals.
All like materials shall be from the same manufacturer. Listed and labeled materials shall be used whenever possible. The listing shall be according to UL or an approved equivalent. Upon completion of the installation, the lighting system shall be tested according to Section 800.
Safety and Protection
Safety and protection requirements shall be as follows.
Safety. Electrical systems shall not be left in an exposed or otherwise hazardous condition. All electrical boxes, cabinets, pole handholes, etc. which contain wiring, either energized or non-energized, shall be closed or shall have covers in place and be locked when possible, during nonworking hours.
Protection. Electrical raceway or duct openings shall be capped or otherwise sealed from the entrance of water and dirt. Wiring shall be protected from mechanical injury.
Equipment Grounding Conductor
All electrical systems, materials, and appurtenances shall be grounded. Good ground continuity throughout the electrical system shall be assured, even though every detail of the requirements is not specified or shown. Electrical circuits shall have a continuous insulated equipment grounding conductor.
When metallic conduit is used, it shall be bonded to the equipment grounding conductor but shall not be used as the equipment grounding conductor.
Where connections are made to painted surfaces, the paint shall be scraped to fully expose metal at the connection point. After the connection is completed, the paint system shall be repaired to the satisfaction of the Engineer.
Final Submittal 12
Bonding of all boxes and other metallic enclosures throughout the wiring system to the equipment grounding conductor shall be made using a splice and pigtail connection. Mechanical connectors shall have a serrated washer at the contact surface.
All connections to structural steel or fencing shall be made with exothermic welds. Care shall be taken not to weaken load carrying members. Where connections are made to epoxy coated reinforcing steel, the epoxy coating shall be sufficiently removed to facilitate a mechanical connection. The epoxy coating shall be repaired to the satisfaction of the Engineer. Where connections are made to insulated conductors, the connection shall be wrapped with at least four layers of electrical tape extended 6 in.
(150 mm) onto the conductor insulation.
Submittals
At the preconstruction meeting, the Contractor shall submit a written listing of manufacturers for all major electrical and mechanical items. The list of manufacturers shall be binding, except by written request from the Contractor and approval by the Engineer. The request shall include acceptable reasons and documentation for the change.
Major items shall include, but not be limited to the following:
Type of Work (discipline)
Item
All Electrical Work Electric Service Metering Emergency Standby System Ground rods Grounding connections Cable Unit Duct Splices Conduit Surge Suppression System
Lighting Pole Luminaire Foundation Steel reinforcement Breakaway Device Controllers Control Cabinet and Peripherals
ITS Controller Cabinet and Peripherals CCTV Cameras Camera Structures Ethernet Switches Detectors Detector Loop Fiber Optic Cable
Within 30 calendar days after contract execution, the Contractor shall submit, for approval, one copy each of the manufacturer’s product data (for standard products and components) and detailed shop drawings (for fabricated items). Submittals for the materials for each individual pay item shall be complete in every respect. Submittals which include multiple pay items shall have all submittal material for each
Final Submittal 13 item or group of items covered by a particular specification, grouped together and the applicable pay item identified. Various submittals shall, when taken together, form a complete coordinated package. A partial submittal will be returned without review unless prior written permission is obtained from the Engineer.
The submittal shall be properly identified by route, section, county, and contract number.
The Contractor shall have reviewed the submittal material and affixed his/her stamp of approval, with date and signature, for each individual item. In case of subcontractor submittal, both the subcontractor and the Contractor shall review, sign, and stamp their approval on the submittal.
Illegible print, incompleteness, inaccuracy, or lack of coordination will be grounds for rejection.
Items from multiple disciplines shall not be combined on a single submittal and transmittal. Items for lighting, signals, surveillance and CCTV must be in separate submittals since they may be reviewed by various personnel in various locations.
The Engineer will review the submittals for conformance with the design concept of the project according to Article 105.04 and the following. The Engineer will stamp the drawings indicating their status as “Approved”, “Approved as Noted”, “Disapproved”, or “Information Only”. Since the Engineer’s review is for conformance with the design concept only, it shall be the Contractor’s responsibility to coordinate the various items into a working system as specified. The Contractor shall not be relieved from responsibility for errors or omissions in the shop, working, or layout drawings by the Engineer’s approval thereof. The Contractor shall still be in full compliance with contract and specification requirements.
All submitted items reviewed and marked “Disapproved” or “Approved as Noted” shall be resubmitted by the Contractor in their entirety, unless otherwise indicated within the submittal comments.
Work shall not begin until the Engineer has approved the submittal. Material installed prior to approval by the Engineer, will be subject to removal and replacement at no additional cost to the Department.
Unless otherwise approved by the Engineer, all of the above items shall be submitted to the Engineer at the same time. Each item shall be properly identified by route, section, and contract number.
Certifications
When certifications are specified and are available prior to material manufacture, the certification shall be included in the submittal information. When specified and only available after manufacture, the submittal shall include a statement of intent to furnish certification. All certificates shall be complete with all appropriate test dates and data.
Maintenance Transfer and Preconstruction Inspection
General. Before performing any excavation, removal, or installation work (electrical or otherwise) at the site, the Contractor shall request a maintenance transfer and preconstruction site inspection, to be held in the presence of the Engineer and a representative of the party or parties responsible for maintenance of any lighting and/or traffic control systems which may be affected by the work. The request for the maintenance transfer and preconstruction inspection shall be made no less than seven (7) calendar days prior to the desired inspection date. The maintenance transfer and preconstruction inspection shall:
Establish the procedures for formal transfer of maintenance responsibility required for the construction period.
Final Submittal 14
Establish the approximate location and operating condition of lighting and/or traffic control systems which may be affected by the work.
Marking of Existing Cable Systems. The party responsible for maintenance of any existing lighting and/or traffic control systems at the project site will, at the Contractor's request, mark and/or stake, once per location, all underground cable routes owned or maintained by the State. A project may involve multiple "locations" where separated electrical systems are involved (i.e. different controllers). The markings shall be taken to have a horizontal tolerance of at least 304.8 mm (one (1) foot) to either side.. The request for the cable locations and marking shall be made at the same time the request for the maintenance transfer and preconstruction inspection is made. The Contractor shall exercise extreme caution where existing buried cable runs are involved. The markings of existing systems are made strictly for assistance to the Contractor and this does not relieve the Contractor of responsibility for the repair or replacement of any cable run damaged in the course of his work, as specified elsewhere herein. Note that the contractor shall be entitled to only one request for location marking of existing systems and that multiple requests may only be honored at the contractor's expense. No locates will be made after maintenance is transferred, unless it is at the contractor’s expense.
Condition of Existing Systems. The Contractor shall conduct an inventory of all existing electrical system equipment within the project limits, which may be affected by the work, making note of any parts which are found broken or missing, defective or malfunctioning. Megger and load readings shall be taken for all existing circuits which will remain in place or be modified. If a circuit is to be taken out in its entirety, then readings do not have to be taken. The inventory and test data shall be reviewed with and approved by the Engineer and a record of the inventory shall be submitted to the Engineer for the record. Without such a record, all systems transferred to the Contractor for maintenance during construction shall be returned at the end of construction in complete, fully operating condition.”
Marking Proposed Locations for Highway Lighting System
The Contractor shall mark or stake the proposed locations of all poles, cabinets, junction boxes, pull boxes, handholes, cable routes, pavement crossings, and other items pertinent to the work. A proposed location inspection by the Engineer shall be requested prior to any excavation, construction, or installation work after all proposed installation locations are marked. Any work installed without location approval is subject to corrective action at no additional cost to the Department.
Inspection of Electrical Work
Inspection of electrical work shall be according to Article 105.12 of the Standard Specifications for Road and Bridge Construction and the following.
Before any splice, tap, or electrical connection is covered in handholes, junction boxes, light poles, or other enclosures, the Contractor shall notify and make available such wiring for the Engineer’s inspection.
Maintenance and Responsibility During Construction
Lighting Operation and Maintenance Responsibility. The scope of work shall include the assumption of responsibility for the continuing operation and maintenance of the existing, proposed, temporary, sign and navigation lighting, or other lighting systems and all appurtenances affected by the work as specified elsewhere herein. Maintenance of lighting systems is specified elsewhere and will be paid for separately
The proposed lighting system must be operational prior to opening the roadway to traffic unless temporary lighting exists which is designed and installed to properly illuminate the roadway.
Final Submittal 15
Energy and Demand Charges. The payment of basic energy and demand charges by the electric utility for existing lighting which remains in service will continue as a responsibility of the owner of the utility, unless otherwise indicated. Unless otherwise indicated or required by the Engineer duplicate lighting systems (such as temporary lighting and proposed new lighting) shall not be operated simultaneously at the Owner's expense and lighting systems shall not be kept in operation during long daytime periods at the Owner's expense. Upon written authorization from the Engineer to place a proposed new lighting system in service, whether the system has passed final acceptance or not, (such as to allow temporary lighting to be removed), the Owner will accept responsibility for energy and demand charges for such lighting, effective the date of authorization. All other energy and demand payments to the utility shall be the responsibility of the Contractor until final acceptance.
Damage to Electrical Systems
Should damage occur to any existing electrical systems through the Contractor’s operations, the Engineer will designate the repairs as emergency or non-emergency in nature.
Emergency repairs shall be made by the Contractor, or as determined by the Engineer, the Department, or its agent. Non-emergency repairs shall be performed by the Contractor within six working days following discovery or notification. All repairs shall be performed in an expeditious manner to assure all electrical systems are operational as soon as possible. The repairs shall be performed at no additional cost to the Department.
Lighting. An outage will be considered an emergency when three or more lights on a circuit or three successive lights are not operational. Knocked down materials, which result in a danger to the motoring public, will be considered an emergency repair.
Temporary aerial multi-conductor cable, with grounded messenger cable, will be permitted if it does not interfere with traffic or other operations, and if the Engineer determines it does not require unacceptable modification to existing installations.
Testing
Before final inspection, the electrical work shall be tested. Tests may be made progressively as parts of the work are completed, or may be made when the work is complete. Tests shall be made in the presence of the Engineer. Items which fail to test satisfactorily shall be repaired or replaced. Tests shall include checks of control operation, system voltages, cable insulation, and ground resistance and continuity.
The forms for recording test readings will be available from the Engineer in electronic format. The Contractor shall provide the Engineer with a written report of all test data including the following:
Voltage Tests Amperage Tests Insulation Resistance Tests Continuity tests Detector Loop Tests
Lighting systems. The following tests shall be made.
(1) Voltage Measurements. Voltages in the cabinet from phase to phase and phase to neutral, at no load and at full load, shall be measured and recorded. Voltage readings at the last termination of each circuit shall be measured and recorded.
(2) Insulation Resistance. Insulation resistance to ground of each circuit at the cabinet, with all loads connected, shall be measured and recorded.
Final Submittal 16
On tests of new cable runs, the readings shall exceed 50 megohms for phase and neutral conductors with a connected load over 20 A, and shall exceed 100 megohms for conductors with a connected load of 20 A or less.
On tests of cable runs which include cables which were existing in service prior to this contract, the resistance readings shall be the same or better than the readings recorded at the maintenance transfer at the beginning of the contract. Measurements shall be taken with a megohm meter approved by the Engineer.
(3) Loads. The current of each circuit, phase main, and neutral shall be measured and recorded.
The Engineer may direct reasonable circuit rearrangement. The current readings shall be within ten percent of the connected load based on material ratings.
(4) Ground Continuity. Resistance of the system ground as taken from the farthest extension of each circuit run from the controller (i.e. check of equipment ground continuity for each circuit) shall be measured and recorded. Readings shall not exceed 2.0 ohms, regardless of the length of the circuit.
(5) Resistance of Grounding Electrodes. Resistance to ground of all grounding electrodes shall be measured and recorded. Measurements shall be made with a ground tester during dry soil conditions as approved by the Engineer. Resistance to ground shall not exceed 10 ohms.
ITS. The following test shall be made in addition to the lighting system test above.
Detector Loops. Before and after permanently securing the loop in the pavement, the resistance, inductance, resistance to ground, and quality factor for each loop and lead-in circuit shall be tested. The loop and lead-in circuit shall have an inductance between 20 and 2500 microhenries. The resistance to ground shall be a minimum of 50 megohms under any conditions of weather or moisture. The quality factor (Q) shall be 5 or greater.
All test results shall be furnished to the Engineer seven working days before the date the inspection is scheduled.
Contract Guarantee
The Contractor shall provide a written guarantee for all electrical work provided under the contract for a period of six months after the date of acceptance with the following warranties and guarantees.
(a) The manufacturer’s standard written warranty for each piece of electrical material or apparatus furnished under the contract. The warranty for light emitting diode (LED) modules, including the maintained minimum luminance, shall cover a minimum of 60 months from the date of delivery.
(b) The Contractor’s written guarantee that, for a period of six months after the date of final acceptance of the work, all necessary repairs to or replacement of said warranted material or apparatus for reasons not proven to have been caused by negligence on the part of the user or acts of a third party shall be made by the Contractor at no additional cost to the Department.
(c) The Contractor’s written guarantee for satisfactory operation of all electrical systems furnished and constructed under the contract for a period of six months after final acceptance of the work.
Final Submittal 17
The warranty for an uninterruptable power supply (UPS) shall cover a minimum of two years from date the equipment is placed in operation; however, the batteries of the UPS shall be warranted for full replacement for a minimum of five years.
Record Drawings
Alterations and additions to the electrical installation made during the execution of the work shall be neatly and plainly marked in red by the Contractor on the full-size set of record drawings kept at the Engineer’s field office for the project. These drawings shall be updated on a daily basis and shall be available for inspection by the Engineer during the course of the work. The record drawings shall include the following:
Cover Sheet Summary of Quantities, electrical items only Legends, Schedules and Notes Plan Sheet Pertinent Details Single Line Diagram Other useful information useful to locate and maintain the systems.
Any modifications to the details shall be indicated. Final quantities used shall be indicated on the Summary of Quantities. Foundation depths used shall also be listed.
As part of the record drawings, the Contractor shall inventory all materials, new or existing, on the project and record information on inventory sheets provided by the Engineer.
The inventory shall include:
Location of Equipment, including rack, chassis, slot as applicable.
Designation of Equipment Equipment manufacturer Equipment model number Equipment Version Number Equipment Configuration o Addressing, IP or other o Settings, hardware or programmed
Equipment Serial Number
When the work is complete, and seven days before the request for a final inspection, the set of contract drawings, stamped “RECORD DRAWINGS”, shall be submitted to the Engineer for review and approval and shall be stamped with the date and the signature of the Contractor’s supervising Engineer or electrician. The record drawings shall be electronically submitted in PDF format as well as hard copies for review and approval.
In addition to the record drawings, PDF copies of the final catalog cuts which have been Approved and Approved as Noted with applicable follow-up shall be submitted along with the record drawings. The PDF files shall clearly indicate either by filename or PDF table of contents the respective pay item number. Specific part or model numbers of items which have been selected shall be clearly visible. Hard copies of the catalog are not required with this submittal.
The Contractor shall provide two sets of electronically produced drawings in a moisture proof pouch to be kept on the inside door of the controller cabinet or other location approved by the Engineer. These drawings shall show the final as-built circuit orientation(s) of the project in the form of a single line diagram with all luminaires numbered and clearly identified for each circuit.
Final Submittal 18
Final documentation shall be submitted as a complete submittal package, i.e. record drawings, test results, inventory, etc. shall be submitted at the same time. Partial piecemeal submittals will be rejected without review. A total of five hard copies of the final documentation shall be submitted in addition to electronic submittal.
GPS Documentation
In addition to the specified record drawings, the Contactor shall record GPS coordinates of the following electrical components being installed, modified or being affected in other ways by this contract:
All light poles.
Handholes and vaults.
Junction Boxes Conduit roadway crossings.
Controllers.
Control Buildings.
Structures with electrical connections.
Electric Service locations.
Datum to be used shall be North American 1983.
Data shall be provided electronically and in print form. The electronic format shall be compatible with MS Excel. Latitude and Longitude shall be in decimal degrees with a minimum of 6 decimal places. Each coordinate shall have the following information:
District Description of item Designation Use Approximate station Contract Number Date Owner Latitude Longitude Comments
A spreadsheet template will be available from the Engineer for use by the Contractor.
Prior to the collection of data, the contractor shall provide a sample data collection of at least six data points of known locations to be reviewed and verified by the Engineer to be accurate within 20 feet. Upon verification, data collection can begin. Data collection can be made as construction progresses, or can be collected after all items are installed. If the data is unacceptable the contractor shall make corrections to the data collection equipment and or process and submit the data for review and approval as specified.
Data collection prior to the submittal and review of the sample data of existing data points will be unacceptable and rejected.
Accuracy. Data collected is to be mapping grade. A handheld mapping grade GPS device shall be used for the data collection. The receiver shall support differential correction and data shall have minimum 5 meter accuracy after post processing. GPS receivers integrated into cellular communication devices, recreational and automotive GPS devices are not acceptable.
Final Submittal 19
The GPS shall be the product of an established major GPS manufacturer having been in the business for a minimum of 6 years.
The Final Acceptance Documentation Checklist shall be completed and is contained elsewhere herein.
Acceptance
Acceptance of electrical work will be given at the time when the Department assumes the responsibility to protect and maintain the work according to Article 107.30 or at the time of final inspection.
When the electrical work is complete, tested, and fully operational, the Contractor shall schedule an inspection for acceptance with the Engineer no less than seven working days prior to the desired inspection date. The Contractor shall furnish the necessary labor and equipment to make the inspection.
A written record of the test readings taken by the Contractor according to Article 801.13 shall be furnished to the Engineer seven working days before the date the…