Attachment__4_-_Insurance.pdf
PDF 198 KB Posted
- Attached to
- PIJAO Utilities and Exterior Works
- Solicitation number
- 19AQMM19R0147
About this file
Attachment #4 - Insurance
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attachment__2.2_-_New_Drawings.zip | ZIP file | |
| SF30_19AQMM19R0147_0001.pdf | ||
| Section_B-M_19AQMM19R0147_00001_with_track_changes.pdf | ||
| 19AQMM19R0147_0001_Questions_&_Answers.pdf | ||
| Section_B-M_19AQMM19R0147_00001_without_track_changes.pdf | ||
| Attachment__3_-_Bid_Chart_0001.xlsx | XLSX spreadsheet | |
| Attachment__2.1_-_Drawings_(AutoCAD).zip | ZIP file | |
| Attachment__8_-_Past_Performance_Questionnaire_(PPQ).docx | DOCX document | |
| 19AQMM19R0147_B-M.pdf | ||
| Attachment__3_-_Bid_Chart.xlsx | XLSX spreadsheet | |
| Attachment__1_-_19AQMM19R0147_Specifications.pdf | ||
| Attachment__2_-_Drawings.zip | ZIP file | |
| Attachment__5_-_Submittal_Register.pdf | ||
| 19AQMM19R0147.pdf | ||
| Attachment__6_-_Firm_and_Project_Information.pdf | ||
| Attachment__7_-_Offeror_Experience.docx | DOCX document |
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ATTACHMENT 4 ‐ INSURANCE FOR CONSTRUCTION CONTRACTS
Performance Policy (Póliza de Cumplimiento): Submitted after the contractor is signed and prior to the notice to proceed in a sum equal to 30% of the value of the contract and valid for the duration of the contract and a further two months, Payment Policy (Póliza de Pago de Salarios y Prestaciones Sociales): Submitted after the contract is signed and prior to the notice to proceed in a sum equal to 20% of the value of the contract, and valid for the duration of the contract and a further three years for the salaries and social benefits of the workers.
Liability Policy ( Póliza de Responsabilidad Civil Contractual): submitted after the contract is signed and prior to the notice to proceed in a sum equal to 30% of the value of the contract, and valid for the duration of the contract and a further two months covering contractual and Third Party Civil Liability, Stability Policy (Póliza de Estabilidad): Submitted when the acceptance of work is signed in a sum equal to 30% of the value of the contract, and valid for three years from the date of the handover of the work/ substantial completion.
Elements Quality Policy ( Póliza de Calidad de Elementos): Submitted when the acceptance of work is signed in a sum equal to 30% of the value of the contract, and valid for one year from the date of the handover of the work/ substantial completion.
Correct Equipment Functioning Policy (Póliza de correcto funcionamiento de los equipos): Submitted when the acceptance of work is signed in a sum equal to 30% of the value of the contract, and valid for one year from the date of the handover of the work/ substantial completion