18-1091_RFP_ Attch 16_Appendix 14- Table of Deliverables- ToD.pdf

PDF 145 KB Posted

Attached to
Demolish Space Launch Complex-2 Bldgs 1619, 1624, 1632 Federal contract opportunity
Solicitation number
FA461021R0008
Issued by
Department of the Air Force Space Command

About this file

This document outlines the requirements for a federal contract solicitation to demolish buildings at Vandenberg Space Force Base in California. The contractor will demolish Space Launch Complex-2 Buildings 1619, 1624, and 1632 and relocate electrical service for Building 1632. The solicitation is a total small business set-aside for firms with average annual revenue under $15 million. The contract will be a firm-fixed-price award made to the lowest price technically acceptable offer. Proposals are due by August 17, 2021. The pre-proposal site visit will take place on July 21 and interested parties must RSVP by July 19. Questions about the solicitation must be submitted by July 28. The contractor will be responsible for all demolition and electrical work in accordance with contract requirements, and will submit regular progress and status reports.

View the file

Other files for this federal contract opportunity

Other files attached to Demolish Space Launch Complex-2 Bldgs 1619, 1624, 1632, newest first.
File Type Posted
Solicitation - FA461021R0008 Amend 02 20210823.pdf PDF
18-1091_RFP_ Attch 26_Asbestos Report B-1632 SolAmend02.pdf PDF
Solicitation- FA461021R0008 RFI_revised 20210823.pdf PDF
18-1091_RFP_ Attch 23_Building Plans B-1624-Amend01.pdf PDF
18-1091_RFP_ Attch 17_Asbestos Report B-1619-Amend01.pdf PDF
18-1091_RFP_ Attch 22_Building Plans B-1619 Part 3-Amend01.pdf PDF
18-1091_RFP_ Attch 18_Asbestos Report B-1624-Amend01.pdf PDF
18-1091_RFP_ Attch 25_Initial Year Seed Mix List for Restoration-Amend01.pdf PDF
18-1091_RFP_ Attch 24_Basic Seed Mix List - Dec 2016-Amend01.pdf PDF
18-1091_RFP_ Attch 20_Building Plans B-1619 Part 1-Amend01.pdf PDF
18-1091_RFP_ Attch 21_Building Plans B-1619 Part 2-Amend01.pdf PDF
18-1091_RFP_ Attch 19_Site Building Photos-Amend01.pdf PDF
Solicitation- FA461021R0008 RFI Responses 20210817.pdf PDF
Solicitation - FA461021R0008 Amend 01 20210816.pdf PDF
18-1091_RFP_ Attch 13_Appendix 11- CQC Specs_01 44 00_202103 Update 20210804.pdf PDF
Site Visit Notes -Demolish Space Launch Complex-2 Buildings 1619 1624 1632 20210726.pdf PDF
Site Visit Sign-In Sheet 20210721.pdf PDF
18-1091_RFP_ Attch 4_Appendix 2- Demo Area B1619.pdf PDF
18-1091_RFP_ Attch 14_Appendix 12- Env Specs_01 57 20_202103.pdf PDF
18-1091_RFP_ Attch 5_Appendix 3- Utility CC Loc B1619.pdf PDF
18-1091_RFP_ Attch 11_Appendix 9- VSFB Electl GL 4_30_2020.pdf PDF
18-1091_RFP_FA461021R0008.pdf PDF
18-1091_RFP_ Attch 2_Wage Determinations.pdf PDF
18-1091_RFP_ Attch 6_Appendix 4- Demo Area B1624.pdf PDF
18-1091_RFP_ Attch 8_Appendix 6- Demo Area B1632.pdf PDF
18-1091_RFP_ Attch 9_Appendix 7- Utility CC Loc B1632.pdf PDF
18-1091_RFP_ Attch 15_Appendix 13- AutoCAD Proj File List Comptr Files.pdf PDF
18-1091_RFP_ Attch 1_Demo SLC-2 B1619 1624 1632_PWS_20210430.pdf PDF
18-1091_RFP_ Attch 3_Appendix 1- Demo SLC-2 PWS_Site Map.pdf PDF
18-1091_RFP_ Attch 12_Appendix 10- Gen Reqmts Spec_01 00 00.pdf PDF
18-1091_RFP_ Attch 13_Appendix 11- CQC Specs_01 44 00_202103.pdf PDF
18-1091_RFP_ Attch 7_Appendix 5- Utility CC Loc B1624.pdf PDF
18-1091_RFP_ Attch 10_Appendix 8- Elect Service Line for Radar.pdf PDF
Show all 33

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SLC-2 Demo PWS

Appendix 14 - Page 1 of 2

XUMU181091 Demolish Space Launch Complex-2 (SLC-2), Bldgs 1619, 1624, 1632

Appendix 14 - Table of Deliverables

TABLE OF DELIVERABLES

Document Title

Copies Per

Addressee

Delivery Date C u st o m er

B a se P

O C

E le ct ro n ic

H ar d C o p y ct ro d C o ct ro d C o

Project Management Plan (PMP) 1 0 1 0 1 0 Within 14 calendar days after Award

Quality Control Plan (QCP) 0 0 1 0 1 0 At least 30 calendar days before on-site construction begins

Accident Prevention Plan (APP) 1 0 1 1 1 0 At least 30 calendar days before on-site construction begins

Demolition Plan 1 0 1 0 1 0 At least 30 calendar days before demolition begins

Kick-Off Meeting 10 calendar days after Award

Charrette The Day of or the Day After the Kick-Off

Meeting

Progress Meetings Once a week

Meeting Minutes 1 0 1 0 1 0 3 business days after each meeting

Monthly Status Report 1 0 1 0 1 0 15th of each month

Progress Schedule (AF 3064 or approved equivalent) 1 0 1 0 1 0

Baseline form shall be submitted 10 calendar days after award or at the Kick-Off Meeting, whichever is later. Updated form shall be submitted on or about the 1st of each month

Progress Report (AF 3065 or approved equivalent) 1 0 1 0 1 0

Baseline form shall be submitted 10 calendar days after award or at the Kick-Off Meeting, whichever is later. Updated form shall be submitted on or about the 1st of each month

65% Design 1 0 2 2 1 0

Within 60 calendar days after the Design

Charrette. Hard copies for all design phases shall be half size (17”x22”) (ANSI Size C)

The Government will provide review comments within 30 calendar days of 65% Design Submittal

65% Design Review Conference Within 7 calendar days of receipt of Gov.

comments on the 65% Design

100% Design, with Signed & Sealed

Drawings & Specifications 1 1 2 2 1 0

14 calendar days after receipt of Government

Review Comments from the 65% Design

SLC-2 Demo PWS

Appendix 14 - Page 2 of 2

TABLE OF DELIVERABLES

Document Title

Copies Per

Addressee

Delivery Date

C u st o m er

B a se P ct ro d C o ct ro d C o ct ro d C o

The Government will provide final comments within 14 calendar days of 100% Design Submittal

Material Approval (AF Form 3000) 1 0 1 0 1 0 At least 30 calendar days prior to requirement

Incidental Design Documents / Shop

Drawings (AF Form 3000) 1 0 1 0 1 0 At least 30 calendar days prior to requirement

Production or Delivery Problem Report 1 0 1 0 1 0 Same day as issue or occurrence

Pre-Final Inspection Report 1 0 1 0 1 0 5 calendar days before Final Inspection

Daily Logs (AF Form 1477 or approved equivalent) 1 0 1 0 1 0

Within 1 work day after each day work is performed on-site

Record Drawings 1 0 1 2 1 0 14 calendar days after Final Inspection

Interim Transfer & Acceptance of Military

Real Property (DD Form 1354) 0 0 1 1 1 0

At least 28 calendar days prior to final inspection

Final Transfer & Acceptance of Military

Real Property (DD Form 1354) 0 0 1 1 1 0 Upon acceptance of record drawings

Final Inspection Report 1 0 1 0 1 0 5 calendar days after Final Inspection

Contract Closeout Book 1 0 1 1 1 0 10 calendar days after Final Inspection