Site Visit Notes -Demolish Space Launch Complex-2 Buildings 1619 1624 1632 20210726.pdf
PDF 227 KB Posted
- Attached to
- Demolish Space Launch Complex-2 Bldgs 1619, 1624, 1632 Federal contract opportunity
- Solicitation number
- FA461021R0008
About this file
This document contains a site visit notes report and related federal contract opportunity solicitation. The site visit notes document a mandatory pre-proposal site visit held on July 21, 2021 at Vandenberg Space Force Base in California for Solicitation Number FA461021R0008. The solicitation is for a firm-fixed price demolition contract awarded on a lowest price technically acceptable basis. The contractor shall demolish Space Launch Complex-2 Buildings 1619, 1624, and 1632 and relocate electrical service for Building 1632. The work supports the 30th Civil Engineering Squadron at Vandenberg Space Force Base. The total small business set-aside contract value is unavailable. The solicitation is available on SAM.gov. Proposals are due by August 17, 2021. The site visit provided an opportunity for offerors to view existing conditions and ask questions.
View the file
Other files for this federal contract opportunity
Show all 33
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEPARTMENT OF THE AIR FORCE
UNITED STATES SPACE FORCE
SPACE LAUNCH DELTA 30
21 JUL 2021
MEMORANDUM FOR RECORD
SUBJECT: XUMU 18-1091; REPAIR Demolish Space Launch Complex-2 (SLC-2) Buildings 1619, 1624, 1632
1. On 21 July 2021, A site visit was conducted at SLC 2 Vandenberg Space Force Base. During the site visit, the following events occurred:
a. All Offerors met at the Vandengberg SFB Visitor Center to process passes. Aditionally CO Jeffrey
Grelck 30 CONS/PKA, Space Launch Delta 30 Planning Manager Wendi Rupp SLD 30/XP and
Project Manager David Rutledge 30 CES/CENME were in attendance.
b. An Offeror posed a question: “Can 1 electronic response submission fufill the solicitation requirement or does it have to be 2 hard copies?” CO Grelck responded: “It is ok to submit just 1 electronic response to the solicitation.”
c. All depeparted the Visitor Center at approximately 10:30 AM PST via caravan.
d. Arrival at Buidling 1619 at approximately 10:45am PST. Offerors briefed on procedures to include photographs being allowed, and personal flashlights or phone lighting being necessary inside the building which was dark. Review of Building 1619 completed at approximately 11:25 AM PST.
e. Arrival at Buidling 1624 at approximately 10:50 AM PST. Review of Building 1624 completed at approximately 11:50 AM PST.
f. Arrival at Buidling 1624 at approximately 10:50 AM PST. Offeror question was asked: “Will the shack that is not pictured in the site map soliciation need to be removed?” CO Grelck responded: “Yes, it is within the limit lines, however an RFI will need to be submitted for an official answer.”
g. Review of Building 1624 completed at approximately 11:50 AM PST.
h. All attendees caravanned to Building 1632, and the review was completed and the site visit was concluded at aprroximetely 12:20 PM PST.
MONICA ALDERETTE
CONTRACT SPECIALIST
| 2021-07-26T15:52:21-0700 | |
| ALDERETTE.DELIA.M.1175506205 |