This document outlines requirements for a construction project to build a watercraft aquatic nuisance species decontamination facility at Vallecito Reservoir. The project involves cleaning construction equipment to prevent the spread of invasive species, inspecting any pumping equipment used at the reservoir, and temporarily providing portable toilets if the existing restroom is demolished in October. The contractor must restore any areas used for construction purposes. The related federal contract opportunity is solicitation number 140R4022R0023 to build the watercraft ANS decontamination facility at Vallecito Reservoir, issued by the Department of the Interior Bureau of Reclamation.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Watercraft ANS Decontamination Facility at Vallecito Reservoir .
Use of Site 01 14 10 - 1
SECTION 01 14 10
USE OF SITE
PART 1 GENERAL
1.01 MEASUREMENT AND PAYMENT
A. Cost:
1. Include in prices offered in the Price Schedule for other items of work.
1.02 REFERENCE STANDARDS
A. Bureau of Reclamation (USBR)
1. Cleaning Manual-2012 Inspection and Cleaning Manual for
Equipment and Vehicles to Prevent the Spread of Invasive Species (Technical memorandum No. 86-68220-07-05) 2012 Edition Available online at:
http://www.usbr.gov/mussels/prevention
1.03 SUBMITTALS
A. Submit the following in accordance with Section 01 33 00 - Submittals.
B. RSN 01 14 10-1, Land Use and Landscape Rehabilitation Plan:
1. For each Contractor use site on Government land.
a. Show use location and extent of impact. Uses include but are not limited to the following:
1) Buildings and service areas including offices, shops, warehouses, storage areas, fuel and oil storage areas, and fabrication yards.
2) Parking areas, temporary roads, and haul routes.
3) First-aid and medical facilities.
4) Areas for processing, storing, and disposing of waste materials from construction operations.
5) Temporary fences.
1.04 PROJECT CONDITIONS
A. Government land as shown on Drawing No. 191-417-2 may be used for required construction facilities.
http://www.usbr.gov/mussels/prevention
01 14 10 - 2
B. When private land is used for construction facilities, or other construction purposes, make necessary arrangements associated with use of private land.
C. Location, construction, operation, maintenance, and removal of construction facilities on Government land will be subject to approval of COR.
D. Do not interfere with work of other contractors or the Government in vicinity, or with reservations made by the Government for use of such land.
E. Housing for construction personnel will not be permitted on Government land, except housing for guards or watchmen as may be approved by COR.
1.05 INTERUPTION OF SERVICE
A. If the existing restroom is demolished in the month of October, the Contractor shall provide and maintain four portable toilets for public until October 31, 2022.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
3.01 CLEANING
A. Construction equipment:
1. Before bringing on site, clean construction equipment to remove dirt, vegetation, and other organic material to prevent introduction of noxious weeds, and invasive plant and animal species.
2. Contractor cleaning procedures shall result in equipment being cleaned as well or better than the procedures described in Cleaning Manual.
3. COR will inspect construction equipment following procedures described in Cleaning Manual before allowing equipment onsite.
3.02 CLEANING FOR AQUATIC NUISANCE SPECIES
A. Any equipment used for pumping, including suction lines, pumps and discharge hoses, shall be inspected and, if needed, decontaminated prior to use at Vallecito Reservoir.
B. The contractor shall notify the COR at least 3-working days before needing pumping equipment inspected.
C. The COR will arrange inspection of pumping equipment with Colorado Parks and Wildlife staff at Vallecito Reservoir
01 14 10 - 3
3.03 RESTORATION
A. Restore Contractor use areas to pre-construction condition.
B. After completion of work, regrade and scarify Government land used for construction purposes and not required for completed installation so that surfaces blend with natural terrain and are in a condition that will facilitate revegetation, provide proper drainage, and prevent erosion.
END OF SECTION