This document contains questions and answers regarding Solicitation 140P2023R0150 to replace the dilapidated visitor center facility at Little Bighorn Battlefield National Monument. The National Park Service seeks to install impact resistant drywall at the walls in the exhibit area and at the information desk. For the metal plate wall panels, the manufacturer's standard 1/8-inch thick aluminum material with warranty is acceptable, despite the project plans calling for 12-gauge prefinished rainscreen material. The contracting officer extended the proposal due date to November 14 at 5pm Mountain Time and stated they are unable to grant any further extensions but remaining questions may be submitted until the due date.

View the file

Other files

File Type Posted
B09_Amendment_6_Questions_and_Answers_0006.docx DOCX document
B09_Amendment_6_Specification_Attachment_0006.pdf PDF
Sol_140P2023R0150_Amd_0006.pdf PDF
B09_Amendment_6_SF30_11-14-23_0006.pdf PDF
Sol_140P2023R0150_Amd_0005.pdf PDF
B09_Amendment_5_SF30_11-7-23_0005.pdf PDF
Sol_140P2023R0150_Amd_0004.pdf PDF
B09_Amendment_4_SF30_11-5-23_0004.pdf PDF
B09_Amendment_4_Questions_and_Answers_0004.pdf PDF
B09_Amendment_3_Questions_and_Answers_0003.pdf PDF
Sol_140P2023R0150_Amd_0003.pdf PDF
B09_Amendment_3_SF30_11-3-23_0003.pdf PDF
Sol_140P2023R0150_Amd_0002.pdf PDF
B09_Amendment_02_SF30_10-27-23_0002.pdf PDF
B09_Amendment_02_Questions_and_Answers_10-27-23_0002.pdf PDF
Sol_140P2023R0150_Amd_0001.pdf PDF
B09_Amendment_1_Spec_Clarifications_10-20-23_0001.docx DOCX document
B09_Amendment_01_SF30_10-20-23_0001.pdf PDF
B11_Preproposal_Conference_Sign_In_Sheet_10-10-23.xlsx XLSX spreadsheet
B08_Attch_2_Drawings.pdf PDF
B08_Attch_9_General_Ref.doc DOC document
B08_Attch_5_Geotech_Rpt_2-8-23.pdf PDF
B08_Attch_3_Wage_Det_MT20230056_9-29-23.pdf PDF
B08_Attch_1_Specifications.pdf PDF
B11_PreProposal_Conference_Slides_LIBI_241430_10-10-23.pptx PPTX presentation
B08_Attch_6_Prjt_Exp_Quest.docx DOCX document
B08_Attch_7_Past_Perf_Quest.docx DOCX document
B08_LIBI_241430_140P2023R0150_SF1442_and_Clauses_10-10-23.pdf PDF
B08_Attch_12_Construction_Contract_Administration.docx DOCX document
B08_Attch_10_LmtOnSubconRpt.xlsx XLSX spreadsheet
B08_Attch_4_HAZMAT_Rpt_1-10-23.pdf PDF
B08_Attch_11_ContractPriceSchedule.xlsx XLSX spreadsheet
B08_Attch_13_CO_Statement_on_Brand_Name_Items.docx DOCX document
Sol_140P2023R0150.pdf PDF
B08_Attch_8_Bid_Bond.pdf PDF
Show all 35

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Replace Dilapidated Visitor Center Facility

Little Bighorn Battlefield National Monument

(LIBI 241430)

Solicitation 140P2023R0150

Amendment 5 Questions and Answers

November 7, 2023

61. We noticed in the specs for the gypsum board that Impact Resistant sheet rock was called out for. However, after reviewing the plans I did not see a note or description that called out where this board might be located. Can you please confirm the location, if any, of where the Impact

Resistant drywall should be installed?

RESPONSE: The impact resistant sheet rock is located at the walls in the exhibit area and at the info desk.

62. Spec Section – 074213.16 – Metal Plate Wall Panels, Section 2.4 calls out material requirements to be provided by the mfr (BOK‐Modern). Material thickness of the panel is to be 12 gauge.

Plan Details: the project plan details for MP1 call out for a 12 ga prefinished rainscreen material.

Issue: BOK‐Modern standard rainscreen product (Enfold Façade) is a 1/8” thick aluminum product. While they (BOK‐Modern) can provide a 12 ga material, they do not offer it in a rainscreen application as this type of panel runs the risk of rusting even when powder coated and cannot be warrantied. BOK‐Modern will only do the aluminum material at the rain screen system. QUESTION TO OWNER/DESIGN TEAM: Is the mfr’s standard aluminum material acceptable for the MP‐1 rainscreen application. If not, how is the manufacturer warranty issue to be addressed?

RESPONSE: The manufacturer’s standard aluminum material of 1/8” thickness with the warranty is acceptable.

63. Contracting Officer’s Statement: Amendment 4 extended the proposal due date to Tuesday, November 14 at 5pm MT. After a careful consideration of several factors, I am unable to extend further beyond this date. If you have further solicitation questions, you may submit them to myself timothy_burger@nps.gov and daryl_hawkins@nps.gov up until proposals are due, however, we cannot guarantee they will be answered in enough time prior to the 14th. Thank you for your understanding on this matter and for your hard work in putting your proposals together.