Amendment 1 + Attachment 9 Drawings - 12912819Q0012

View the file

Other files

Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES

1 3

2. AMENDMENT/MODIFICATION NUMBER

A0001

3. EFFECTIVE DATE

04/19/2019

4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE

USDA FOREST SERVICE

PACIFIC SOUTHWEST REGION

1323 CLUB DRIVE

VALLEJO, CA 94592-1110

SAME AS ITEM 6.

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NUMBER

12912819Q0012

9B. DATED (SEE ITEM 11)

04/03/2019

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not is required to sign this document and return 1 copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Amendment A0001 is for the purpose of providing additional Drawings.

Incorporated as Attachment 9. Replacement pages 11 and 25 of 42 are attached.

The offer due date/time is unchanged. Offers are due NLT Monday, May 6, 2019, 3pm/1500 PST.

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

Jeremy Bedner, Contracting Officer

15B. CONTRACTOR/OFFEROR 15C. DATE SIGNED 16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

16C. DATE SIGNED

04/19/2019 (Signature of person authorized to sign)

Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243

Replacement Page 11 of 42 A0001

RFQ 12912819Q0012

UNAUTHORIZED ROUTE DECOMMISSIONING

CLEVELAND NATIONAL FOREST

US FOREST SERVICE

B1. LIST DRAWINGS – included as ATTACHMENT 2

The following Drawings shall be included in this contract:

B2. LIST OF ADDITIONAL DRAWINGS – included as ATTACHMENT 9

C. LIST OF MAPS – included as ATTACHMENT 3

SEQUENCE DESCRIPTION

1 Steel Pipe Fencing Design 2 Removable Steel Pipe Fencing/Swing Gates 3 Forest Service Gate Fabrication, Details A-B 4 Forest Service Gate Fabrication, Details C-D 5 Forest Service Gate Fabrication, Details E-F 6 Forest Service Gate Installation Details 7 Horse Gate 8 Site 17S08

SEQUENCE DESCRIPTION

9 16S12 Helispot Restoration Site 10 17S12 Dam Breach Site 11 17S12 Road Stream Intersection Repair 12 UND330 Morena Channel Reconstruction 13 UND566 Pullout 14 13S10-16.8-R2

MAPS

Bear Valley Buckman Springs El Cajon Mountain Elsinore Peak Hauser Wilderness Indian Flats Japatul Valley Road Kitchen Creek Central Sheephead Kitchen Creek North Wooded Hill Kitchen Creek South

Replacement Page 25 of 42 A0001

RFQ 12912819Q0012

UNAUTHORIZED ROUTE DECOMMISSIONING

CLEVELAND NATIONAL FOREST

US FOREST SERVICE

SECTION E

CONTRACT DOCUMENTS, EXHIBITS, AND ATTACHMENTS

NUMBER

TITLE PAGES

1 Specifications

2 Drawings – refer to Section B1

3 Maps

4 Tables – Work Summary

5 Restoration / Decommissioning Methods

6 Fire Plan

SCA Wage Determination no. 2015-5636 revision no. 10 dated 12/26/2018 – San Diego County

SCA Wage Determination no. 2015-5629 revision no. 9 dated 12/26/2018 – Riverside County

9 Additional Drawings – Refer to Section B2

AutoCAD SHX Text ~ 9.0%9.0%

AutoCAD SHX Text Remove vegetation and rocks for channel restoration, scatter slash for a natural appearance, utilize rocks as riprap stabilization for diversion channel fill. Remove berm, restore channel alignment as staked ~ 125 ft./25 CY at ~ 9.0% grade, connect to upstream (US) and down stream (DS) existing profile, match existing US and DS cross section. Block diversion channel: place excavated material in diversion channel at its inlet, raise inlet elevation approx. 3 ft. Excavation and embankment compaction: adjust the moisture content of the material to a moisture content suitable for compaction. Fill the interstices around rock with earth or other fine material as practical. Operate hauling and spreading equipment uniformly over the full width of each layer until there is no visible evidence of further consolidation, make at least three complete passes. Alternatively, compact the complete surface with a bucket of a medimum excavator using a minimum of three blows. Overlap compaction by ½ width of bucket.

AutoCAD SHX Text Existing channel profile

AutoCAD SHX Text Restored channel profile

AutoCAD SHX Text Location: 11S 518076 3640592 UTM (-116.806708 32.903381)

AutoCAD SHX Text Block diversion channel here

AutoCAD SHX Text Stock pond

AutoCAD SHX Text Original channel

AutoCAD SHX Text Restore original alignment

AutoCAD SHX Text Diversion channel

AutoCAD SHX Text O

AutoCAD SHX Text 10O

AutoCAD SHX Text 20O

AutoCAD SHX Text

FT.

SF-30 A1
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
Amendment A0001 is for the purpose of providing additional Drawings.
Incorporated as Attachment 9. Replacement pages 11 and 25 of 42 are attached.
replacement pages 11, 25
Amendment 1 Attachment 9 DRAWINGS B2 9-14
9 16S12 Helispot Restoration Site
10 17S12 Dam Breach Site
11 17S12 Road Stream Intersection Repair
12 UND330 Morena Channel Reconstruction
13 UND566 Pullout
14 13S10-16.8-R2
Sheets and Views