This document is a Questions & Answers (Q&A) file for a Forest Wide Toilet Replacement project solicitation number 1240LU25B0003, dated 4.24.2025. The Q&A addresses six key inquiries from potential bidders regarding the project, including site accessibility, documentation, and project logistics. Key details include: bidders are welcome to visit project sites (if accessible due to snow), no formal site tour is planned, the immediate area around toilets can be closed during removal and replacement, and partial monthly progress payments will be available. The project involves replacing vault toilets across recreation sites, with new structures using precast concrete and specific site details referenced in accompanying project plans.

View the file

Other files

File Type Posted
Bid Tabulation_1240LU25B0003.pdf PDF
Updated GPS Coordinates.xlsx XLSX spreadsheet
Questions and Answers 13 May 25.pdf PDF
Questions and Answers 9 May 25.pdf PDF
Questions and Answers 2 May 25.pdf PDF
GPS Coordinates.xlsx XLSX spreadsheet
Attach 3 DrawingsPlans.zip ZIP file
SF1442_Amend001_1240LU25B0003.pdf PDF
1240LU25B0003.pdf PDF
Attachment 1 Schedule of Items.docx DOCX document
Attachment 2 FSSS.pdf PDF
Attachment 4 Wage Determination.pdf PDF
Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1240LU25B0003

Questions & Answers - BDNF Forest Wide Toilet Replacement

4.24.2025

1. In section C2 it refers to a map of sites being available, but I didn't find it in any of the attachments. Is there a map available? Are there photos available of the current toilets in place to be removed? Refer to plans, vicinity and site maps found within this document. Photos of toilets being removed are not available, however a brief description is found on plans.

2. With the size of the project will there be site tour? These sites are in recreation sites across the Forest. Bidders are welcome to visit sites (if accessible due to snow), however no formal site tour will be planned. Refer to project maps in plans.

3. Will the campgrounds (or the immediate area encompassing the toilet) be closed to the public during the removal/replacement of the toilets? Immediate area around the toilet can be closed during removal and replacement.

4. Will partial payments be an option? Yes, partial progress payments can be made monthly.

5. Are the current existing in place vault toilets the Aspen model for Missoula Concrete as well? or another model such as CXT, Romtech etc or built on site timber frame? See plans and response to question 1.

6. Are they sitting on pre-cast concrete slabs or framed/poured on-site during installation slabs? New structures are precast concrete (see plans). Descriptions of existing structures are found in the plans.