Questions and Answers 9 May 25.pdf

PDF 105 KB Posted

Attached to
GAOA Forest Wide Toilet Replacement and Installation
Solicitation number
1240LU25B0003
Issued by

About this file

This document is a Questions and Answers (Q&A) file for Solicitation 1240LU25B0003, a GAOA Forest Wide SST (Vault Toilet) Replacement project for the Beaverhead-Deerlodge National Forest (BDNF) at various locations. The Q&A addresses four key contractor inquiries: (1) USFS will flag approximate vault toilet and aggregate path locations, with contractors responsible for following manufacturer installation instructions, (2) no soil or subgrade testing is required, (3) no as-built documentation is needed, and (4) old vaults must be cleaned before dismantling and removal, as specified in the General Notes Sheet 2 in the project plans. The document is dated 5/9/2025 and provides critical clarification for potential contractors on project installation and preparation requirements.

View the file

Other files

File Type Posted
Bid Tabulation_1240LU25B0003.pdf PDF
Updated GPS Coordinates.xlsx XLSX spreadsheet
Questions and Answers 13 May 25.pdf PDF
Questions and Answers 2 May 25.pdf PDF
GPS Coordinates.xlsx XLSX spreadsheet
QuestionsAnswers_4.24.2025.pdf PDF
Attach 3 DrawingsPlans.zip ZIP file
SF1442_Amend001_1240LU25B0003.pdf PDF
1240LU25B0003.pdf PDF
Attachment 1 Schedule of Items.docx DOCX document
Attachment 2 FSSS.pdf PDF
Attachment 4 Wage Determination.pdf PDF
Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation 1240LU25B0003 GAOA Forest Wide SST Replacement BDNF, various locations

Questions and Answers

5/9/2025

1. Per page 2 of drawings the locations of vault toilets will be flagged or stake by USFS.

Can you please confirm no additional surveying is required?

No additional surveying required. USFS will flag approximate locations for installs. It will be contractors’ responsibility to make sure manufacturer installation instructions are followed. Additionally, approximate locations for aggregate paths will be flagged and dimensions of typical section shall be followed.

2. Is there any soil or subgrade testing required? No

3. Are there any requirements for as-built documentation? No. Contractor will need to use toilet model specified or approved equal.

4. Do old vaults need cleaning before dismantling and removal off Forest?

Yes, see General Notes Sheet 2 in the Plans. Outhouse Pumping “Contractor is responsible….”