Questions and Answers 13 May 25.pdf

PDF 91 KB Posted

Attached to
GAOA Forest Wide Toilet Replacement and Installation
Solicitation number
1240LU25B0003
Issued by

About this file

This document is a Questions and Answers document for Solicitation 1240LU25B0003, a GAOA Forest Wide SST (Self-Serve Toilet) Replacement project for the Beaverhead-Deerlodge National Forest (BDNF) at various locations. The Q&A provides critical project details including site accessibility, performance timeline, and construction guidelines. Key points include: the project has an 883-calendar day performance period, work can be conducted simultaneously at multiple sites, most sites are only accessible during summer months, and contractors are permitted to temporarily close the immediate area around the self-serve toilets during construction. The document clarifies that temporary porta potties are not required, site access is generally feasible with potential minor clearing needed, and toilets must be installed according to manufacturer recommendations.

View the file

Other files

File Type Posted
Bid Tabulation_1240LU25B0003.pdf PDF
Updated GPS Coordinates.xlsx XLSX spreadsheet
Questions and Answers 9 May 25.pdf PDF
Questions and Answers 2 May 25.pdf PDF
GPS Coordinates.xlsx XLSX spreadsheet
QuestionsAnswers_4.24.2025.pdf PDF
Attach 3 DrawingsPlans.zip ZIP file
SF1442_Amend001_1240LU25B0003.pdf PDF
1240LU25B0003.pdf PDF
Attachment 1 Schedule of Items.docx DOCX document
Attachment 2 FSSS.pdf PDF
Attachment 4 Wage Determination.pdf PDF
Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation 1240LU25B0003 GAOA Forest Wide SST Replacement BDNF, various locations

Questions and Answers

5/13/2025

1. After reviewing the GPS Coordinates Excel file provided on April 29 and Attachment 3 (Drawing Plans), clarification is needed: Is the South Boulder Dispersed Site (1 vault) shown on Sheet 18 of the plan set the same as the West Forks Campground listed in the Excel file?

The map on sheet 3 is incorrect as well as the lat/long. South Boulder Dispersed Site is part of this project, West Fork Campground is part of another project. Emily, can you issue a new Lat/long table for clarification?

2. Regarding site access, are there any restrictions we should be aware of (e.g., crossing private property, limitations related to bridges including GVWR or dimensional restrictions, etc.)?

To my knowledge, we do not have those restrictions.

3. The period of performance is listed as 883 calendar days after Notice to Proceed. Will the contractor be required to perform work during a specific time of year, such as only during summer months and not during winter?

Most sites are only accessible during summer. No seasonal requirement.

4. Will the contractor be restricted to working at one location at a time, or is work at multiple sites simultaneously permitted?

Working at multiple sites simultaneously is allowed.

5. Will the contractor be allowed to temporarily shut down public access to a site during construction activities?

The area immediately around the SST will be allowed to be closed during construction.

6. Is the contractor required to provide temporary porta potties for public use during construction?

No.

7. Will compaction or density testing be required as part of backfilling or site grading?

Toilets will need to be installed per manufacturer recommendations. See sheet 4 notes for more information.

Solicitation 1240LU25B0003 GAOA Forest Wide SST Replacement BDNF, various locations

8. Are each of the sites accessible for bringing in the new vault toilets on trailers and unloading from the trailers directly into the vault pits?

Yes. Toilets are generally accessible. Some clearing and grubbing might be required for site prep/access (see schedule of items).