This document outlines bid specifications for a federal contract to decommission wastewater facilities. The project involves decommissioning sanitary sewer collection systems, lagoon demolition, land application of biosolids and liquids according to approved plans, and optional soil excavation and disposal if required. Bid items include lump sum pricing for collection system decommissioning, lagoon demolition and land application. An optional item involves soil excavation and disposal on a per cubic yard basis. Contractors must adhere to provided closure plans, drawings, and DEQ requirements, and obtain necessary DEQ notifications and approvals. The related federal opportunity notice indicates the solicitation for this Dale Water-Wastewater System Decommission project will be posted on January 15, 2020. Work is estimated to begin on May 15, 2020. The project is located in Oregon and set aside 100% for small businesses. The contracting agency is the USDA Forest Service with a NAICS code of 238910 and size standard of $16.5 million.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Final Amendment 03.pdf | ||
| Schedule of Items.xlsx | XLSX spreadsheet | |
| Final Amendment 02.pdf | ||
| Final Amendment 01.pdf | ||
| FinalDaleSolicitation.pdf | ||
| FireProtectionandSuppressionr6_fS_6300_52.rtf | RTF text file | |
| dale.JPG | JPG image | |
| FINAL Dale Work Center Demolition Drawings.pdf | ||
| FINAL CLOSURE PLAN.pdf | ||
| 11847 Asbestos Report 1993.pdf | ||
| FINAL SPECIFICATIONSDaleWaterWastewaterDemo.pdf | ||
| 1980 Original Lagoon Installatoin Specs.pdf | ||
| FINAL DALE WATER-WASTEWATER PROJECT SITE MAP.pdf | ||
| DALE WATER-WASTEWATER PROJECT SITE MAP.pdf |
Show all 14
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
USDA FOREST SERVICE PROJECT SPECIFICATIONS
Dale Water-Wastewater Decommissioning Project p. 1/2 Definition of Bid Items
LAGOON DECOMMISSIONING
1. PART 1 - GENERAL
1.01 DESCRIPTION
A. The intent of this section is to explain the requirements of the lagoon decommissioning section of this contract.
B. Contractor is responsible for adhering to Project Drawings, Closure Plan, and DEQ requirements.
2. PART 2 – WASTEWATER FACILITIES DECOMMISSIONING
2.01 BID ITEM 4.0 SANITARY SEWER COLLECTION AND PUMPING SYTEM
A. Prior to demolition of the sanitary sewer lagoons the sewer collection system and pumping system shall be decommissioned. Refer to Section 2.1 and Appendix B of the Closure Plan as well as Project Drawings.
B. Measurement shall be made as a lump sum quantity for the preparation for completing this work, including equipment delivery to and from the site, temporary utility connections, worker and public safety protections and other incidentals necessary to begin and complete this project.
C. Payment shall be made at the contract lump sum price for this bid item.
2.02 BID ITEM NO. 5.0 LAGOON DEMOLITION/LAND APPLICATION
A. This bid item consists of all demolition and land application items necessary for decommissioning of the lagoon treatment and disposal system.
1. Land application of liquids and biosolids must be performed using the approved 2012 Biosolids Management Plan (BSMP) and Recycled Water Use Plan (RWUP). Refer to Sections 2, 3, and 4 of the Closure Plan.
a. Volume summary of biosolids and liquids are shown on Table 1 (Page 8 of Closure Plan)
b. Reporting and recordkeeping requirements for land application must be followed per DEQ WPCF permit (Page 13 of Closure Plan), including, but not limited to, daily site logs.
c. Monitoring and Sampling of land application must meet DEQ WPCF permit, Section 3.6 and Section 4.4 of Closure Plan.
d. Location of approved land application site, approved application rates and equipment, and schedule are listed in Section 4 of the Closure Plan
2. Lagoon Demolition must be performed after land application process is completed. Refer to Section 2.2 of the Closure Plan and Project Drawings.
a. This bid item includes all necessary excavation, backfill, compaction, and grading to restore the contours to a free-draining solid surface that blends with the surrounding contours.
USDA FOREST SERVICE PROJECT SPECIFICATIONS
Dale Water-Wastewater Decommissioning Project p. 2/2 Definition of Bid Items
B. Measurement shall be made as a lump sum quantity for the materials, labor, equipment, tools, and incidentals required to complete this item.
C. Payment shall be made at the contract lump sum price for this bid item.
3. PART 3 – OPTIONAL BID ITEMS
3.01 OPTIONAL BID ITEM NO. 6.0 – EXCAVATE & DISPOSE OF SOIL BELOW LINER
A. This bid item includes the removal of additional soil under the lagoon liners, if required by DEQ. DEQ must be notified 7 days prior to removal of lagoon liners. This pay item includes but is not limited to:
1. Soil sampling in accordance with Section 2.2 of the Closure Plan. For bidding purposes (only), assume 3 soil samples, each analyzed for TCLP at a certified laboratory. If different samples are required by DEQ, this line item can be renegotiated at the time of award to adjust for laboratory costs.
2. Excavation, transport, and proper disposal of contaminated soil. For bidding purposes (only), assume the material is non-hazardous and may be disposed of at the closest city (lined) landfill. If sample results dictate that a different disposal method must be used, the contract will be modified to adjust for the change in hauling and landfill costs.
3. Backfill, compaction, and grading to restore the contours to a free-draining solid surface that blends with the surrounding contours.
B. Measurement shall be made as a per cubic yard quantity for the materials, labor, equipment, tools, and incidentals required to complete this item. Measurement will be loose cubic yard per measurement.
C. Payment shall be made at the contract per cubic yard price for this bid item.
END OF SECTION
| 1. Part 1 - GENERAL |
| 1.01 DESCRIPTION |
| A. The intent of this section is to explain the requirements of the lagoon decommissioning section of this contract. |
| B. Contractor is responsible for adhering to Project Drawings, Closure Plan, and DEQ requirements. |
| 2. Part 2 – WASTEWATER FACILITIES DECOMMISSIONING |
| 2.01 Bid Item 4.0 SANITARY SEWER COLLECTION AND PUMPING SYTEM |
| A. Prior to demolition of the sanitary sewer lagoons the sewer collection system and pumping system shall be decommissioned. Refer to Section 2.1 and Appendix B of the Closure Plan as well as Project Drawings. |
| B. Measurement shall be made as a lump sum quantity for the preparation for completing this work, including equipment delivery to and from the site, temporary utility connections, worker and public safety protections and other incidentals necessary to... |
| C. Payment shall be made at the contract lump sum price for this bid item. |
| 2.02 BID ITEM NO. 5.0 LAGOON DEMOLITION/LAND APPLICATION |
| A. This bid item consists of all demolition and land application items necessary for decommissioning of the lagoon treatment and disposal system. |
| 1. Land application of liquids and biosolids must be performed using the approved 2012 Biosolids Management Plan (BSMP) and Recycled Water Use Plan (RWUP). Refer to Sections 2, 3, and 4 of the Closure Plan. |
| a. Volume summary of biosolids and liquids are shown on Table 1 (Page 8 of Closure Plan) |
| b. Reporting and recordkeeping requirements for land application must be followed per DEQ WPCF permit (Page 13 of Closure Plan), including, but not limited to, daily site logs. |
| c. Monitoring and Sampling of land application must meet DEQ WPCF permit, Section 3.6 and Section 4.4 of Closure Plan. |
| d. Location of approved land application site, approved application rates and equipment, and schedule are listed in Section 4 of the Closure Plan |
| 2. Lagoon Demolition must be performed after land application process is completed. Refer to Section 2.2 of the Closure Plan and Project Drawings. |
| a. This bid item includes all necessary excavation, backfill, compaction, and grading to restore the contours to a free-draining solid surface that blends with the surrounding contours. |
| B. Measurement shall be made as a lump sum quantity for the materials, labor, equipment, tools, and incidentals required to complete this item. |
| C. Payment shall be made at the contract lump sum price for this bid item. |
| 3. Part 3 – optional bid items |
| 3.01 optional BID ITEM NO. 6.0 – EXCAVATE & DISPOSE OF SOIL BELOW LINER |
| A. This bid item includes the removal of additional soil under the lagoon liners, if required by DEQ. DEQ must be notified 7 days prior to removal of lagoon liners. This pay item includes but is not limited to: |
| 1. Soil sampling in accordance with Section 2.2 of the Closure Plan. For bidding purposes (only), assume 3 soil samples, each analyzed for TCLP at a certified laboratory. If different samples are required by DEQ, this line item can be renegotiated a... |
| 2. Excavation, transport, and proper disposal of contaminated soil. For bidding purposes (only), assume the material is non-hazardous and may be disposed of at the closest city (lined) landfill. If sample results dictate that a different disposal me... |
| 3. Backfill, compaction, and grading to restore the contours to a free-draining solid surface that blends with the surrounding contours. |
| B. Measurement shall be made as a per cubic yard quantity for the materials, labor, equipment, tools, and incidentals required to complete this item. Measurement will be loose cubic yard per measurement. |
| C. Payment shall be made at the contract per cubic yard price for this bid item. |