10 SOW Attachment 10 - IRCA.NEXTGen WiFi AFTON.pdf
PDF 394 KB Posted
- Attached to
- Z2DA--666-21-704 -EHRM NEXT GEN WIFI Federal contract opportunity
- Solicitation number
- 36C25923R0060
About this file
This scope of work document outlines requirements for a construction project to support installation of replacement and new WiFi access points at a Veterans Affairs medical center and various clinics. The contractor will install 48 conduits, 11 mounting brackets, seal wall penetrations, install fire stopping systems, and support preparation of work areas according to infection control risk assessments. Additional requirements include installing approximately 2,564 linear feet of conduit, 4,601 linear feet of CAT6a cable, and sealing 498 penetrations. The work must be completed within 60 days of notice to proceed, with asbestos abatement and conduit work finalized before access point installation scheduled from October 3rd to 28th, 2022. The Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 19 is the contracting agency.
View the file
Other files for this federal contract opportunity
Show all 30
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SVAHCS HEALTHCARE SYSTEM
Infection Control Risk Assessment (ICRA)
Project Name: NextGen WiFi Update Project Number: N/A
Construction Location: Afton CBOC Impact to area: Entire Facility Identify areas surrounding the project area and potential impact.
o Above: N/A o Below: N/A o Adjacent Areas: N/A
Project COR: Nicole Perez Telephone: 307-675-7385
Project CPs: OIT escort, CBOC point of contact Project Start Date: 08/09/2022
Estimated Duration: 1 Day
Contractor: AT&T SUB Contractor: TekSynap Corporation
Completion Date: 08-09-2022
GC Supervisor: Telephone:
Check applicable CONSTRUCTION ACTIVITY TYPE
Check applicable
IC PATIENT RISK
GROUP
TYPE A: Inspection, non-invasive activities, minimum dust levels GROUP 1: Low Risk
X TYPE B: Small scale, short duration, moderate dust levels X GROUP 2: Medium Risk
TYPE C: Generates moderate to high levels of dust, requires greater than one work shift for completion GROUP 3: Medium/High Risk
TYPE D: Major duration and construction activities requiring consecutive work shifts GROUP 4: Highest Risk
Project Construction Class:
REQUIREMENTS (in addition to page 4)
• Will remove a maximum of two ceiling tiles at one time
• Limit patient flow through work areas - SVA staff responsibility to ensure compliance
• Damp clean after work – all horizontal surfaces, including floors - SVA staff responsibility to perform
• Contractor is responsible for using a HEPA vac if drilling into walls
• Contractor is responsible for cover items on desks/counter if they will be removing ceiling tiles/working above the area with plastic
• Contractor is responsible for dry sweeping any debris generated
• Higher risk areas (related to drilling or cable pulling), such as supply rooms, lab, med rooms/pharmacy, and procedure rooms that may need items/equipment covered CLEAN STORAGE ROOM
• SVA staff will need to assess high risk patients ie immunocompromised, cancer patients etc. and reschedule if necessary
• Notify OIT escort when work is finished
• Wear face masks per facility requirements
Infection Contol Digital Signature:
X
Project COR / CP:
X
Implementation Checklist:
[X] Reviewed construction scope [] Notified Contractor of their responsibilities relative to ICRA.
Date Meeting was held: ___________________________
Persons Present: ____________________________________________, _ [] Developed a plan and train both appropriate hospital staff as well as construction personnel relative to
ICRA including a written and signed document attesting to said training.
[] Contractor will provide daily inspections and reports on construction site relative to ICRA.
See Attachment A and b [X] COR will notify Infection Prevention relative to all potential infection control deficiencies.
[X] Multidisciplinary team has been notified and concurs with plan.
[] Multidisciplinary team will review, and document weekly or other intervals as decided by the team.
STEP 1: Using the following table, identify the Type of Construction Activity
TYPE A
Inspection and Non-Invasive Activities. Includes, but is not limited to:
• Removal of ceiling tiles for visual inspection limited to 1 tile per 50 square feet.
• Painting (but not sanding).
• Wall covering, electrical trim work, minor plumbing and activities that do not generate dust or require cutting of walls or access to ceilings other than for visual inspection.
TYPE B
Small scale, short duration activities that create minimal dust. Includes, but is not limited to:
• Installation of telephone and computer cabling.
• Access to chase spaces.
• Cutting of walls or ceiling where dust migration can be controlled.
• Chipping and sanding of tile flooring <4 sq. feet
TYPE C
Work that generates a moderate to high level of dust or requires demolition or removal of any fixed building components or assemblies. Includes, but is not limited to:
• Sanding of walls for painting or wall covering.
• Removal of floor coverings, ceiling tiles and casework.
• New wall construction.
• Minor duct work or electrical work above ceilings.
• Major cabling activities.
• Any activity that cannot be completed within a single work shift.
TYPE D
Major demolition and construction projects. Includes, but is not limited to:
• Activities that require consecutive work shifts.
• Requires heavy demolition or removal of a complete cabling system.
• New construction.
Step 1 Determination: TYPE:
Step 2: Using the following table, identify the Patient Risk Groups that will be affected.
Low Risk- Group 1
Medium Risk- Group 2
High Risk- Group 3
Highest Risk- Group 4 o Office areas o Library, o Chapel, o EMS o FMS o Ambulatory Care/ Outpatient Clinics, o Blind Rehabilitation o Audiology, Speech
Pathology o Echocardiography o Food Service Areas/Main patient hall o Laundry o Imaging (eg, Radiology, MRI, Nuclear Med) o Rehabilitation Svc o Prosthetics o Respiratory Therapy o Sleep Laboratory o Patient Access Hall o Clinical Labs o Pathology & Laboratory Svc o Echocardiography o Endoscopy o Emergency Department o Distribution o Pharmacy o Medical-Surgical Day Units o Patient Wards (eg, CLC, Medical, Surgical, Spinal Cord Injury, Psychiatry)
Areas caring for immunocompromised patients Bronchoscopy Cardiac Cath Lab Intensive Care Units (eg, CCU, MICU, PCU, SICU) Interventional Radiology SPS (Sterile Processing Service) Cardiac Catheter, Electrophysiology (EP) Laboratories Dental Clinic Dialysis unit Negative Pressure Isolation Rooms Pharmacy Admixture Areas Oncology (Radiation Therapy & Chemotherapy) Operating Rooms and PACU Procedural areas (ex. Cysto, Derm, etc.)
Step 2 Determination: RISK:
CONSTRUCTION PROJECT CLASS
Patient Risk Group TYPE A TYPE B TYPE C TYPE D
LOW Risk Group I II II III/IV
MEDIUM Risk I II III IV
HIGH Risk Group I II III/IV IV
HIGHEST Risk II III/IV III/IV IV
Step 3 Project/ Construction Class: CLASS
INFECTION CONTROL RISK ASSESSMENT – ADMINISTRATIVE ACTIONS
Applicable ICRA Administrative Action
Tightly seal construction perimeter and inspect critical barriers for integrity. Verify negative air pressure with airflow from clean (hospital/clinic/support spaces) to dirty areas (construction areas).
Construction site has proper traffic flow and warning signage. Demonstrate compliance with traffic flow patterns including demolition/construction movement.
Track dirt compliance aids are in place at the doors leading to the hospital/clinic/support spaces.
Housekeeping performed frequently to prevent accumulation and spread of dirt and fine dust including regular HEPA vacuuming and damp wiping construction perimeter barriers.
Demonstrate active means that prevents airborne particles from migrating to hospital, clinical, support care areas including: HEPA vacuums, automatic self-closing construction doors, appropriate exhaust machines, debris chutes.
Block off, seal, remove or isolate open pipes, open conduits, penetrations, barrier punctures, HVAC system air vents in work area to prevent dirt and fine dust migration.
X Surfaces in adjacent hospital, clinical, support areas frequently inspected for visible dirt or fine dust and cleaned immediately with suitable materials.
Demonstrate appropriate debris transport … covered cart, dedicated elevator, designated route, etc.
Immediate control of water leakage must be handled in an emergency fashion in occupied areas. Large leaks may necessitate drying. (<72 Hrs.).
Compliance with coverall clothing when indicated by Class Precaution.
Tools and equipment damp-wiped prior to entry and exit from sterile and invasive procedure areas.
Windows, access doors, and debris chutes are closed and secured at the end of each day.
X Areas cleaned, and trash disposed at the end of each working day.
X Pest control … No visible signs of birds, insects, rodents or other vermin.
X Compliance with the required Infection Control Activities by Class Precautions.
Conduct infection control training and education to ensure awareness of construction hazards, infection control deficiencies, and compliance with the required infection control measures.
X Conduct infection control risk assessment (ICRA).
Infection Control Activities by Class Precautions During Project Construction Upon Project Completion
C la ss I
1. Keep area free of debris & trash.
2. Immediately reinstall ceiling tiles displaced for inspections.
3. Traffic Flow: Decrease exposure of patients/staff to construction.
4. Utility Shutdowns: If necessary, schedule interruptions during low activity.
5. Pest Control: Address any visible signs of birds, insects, rodents or other vermin.
6. Vacuum/sweep and wet mop surfaces daily and as needed to control debris/dust.
7. Execute work by methods to minimize dust production & migration from construction operations.
Perform clean up and disposal in accordance with contract requirements.
C la ss
II
In a dd iti on to C la ss
I
1. Dust containment barriers secure at perimeter edges.
2. Ceiling tiles in place at adjacent areas outside barrier.
3. Water mist work surfaces to control dust while cutting.
4. Unused openings (doors, windows) properly closed and sealed with masking tape.
5. Block-off, seal, remove or isolate HVAC system air vents to prevent contamination migration.
6. Place walk-off mat at work areas to prevent tracking of construction dust into surrounding areas.
7. Provide active means to prevent airborne dust from dispersing into atmosphere. HEPA vacuums, automatic self-closing construction doors, appropriate exhaust machines, debris chutes.
a. Clean work surfaces with HEPA vacuum.
b. Remove HVAC system isolation where work is complete.
c. Mop and/or wipe work surfaces with approved disinfectant.
C la ss
II
I In a dd iti on to C la ss
II
1. Inspect adjacent areas for dust migration and correct immediately.
2. Tightly cover material transport receptacles/carts. Contain construction waste in tightly covered containers before transport.
3. Maintain negative air pressure within work site utilizing HEPA air filtered machines.
4. Disinfect tools and equipment prior to entry and exit from sterile and invasive procedure areas.
5. Complete all critical barriers, i.e. sheetrock, plywood, plastic to seal area from non-work area or implement control cube method (container with suitable cover and sealed connection to work site with HEPA vacuum for cleaning prior to exit).
a. Clean remaining impacted areas with HEPA vacuum.
b. Mop/Wipe remaining impacted areas with approved disinfectant.
c. Tightly cover material transport receptacles/carts. Contain construction waste in tightly covered containers before transport.
d. Do not remove barriers from work areas until completed project is thoroughly cleaned and inspected by the VA Safety Officer and Infection Control Practitioner.
e. Clean & remove barrier materials carefully to minimize spreading of dirt and debris associated with construction. C la ss
IV
In a dd iti on to
C la ss
II
I
1. Temporarily relocate staff/patients away from impacted areas if possible.
2. Seal holes, pipes, conduits, penetrations and barrier punctures to prevent dirt and fine dust migration.
3. All personnel entering the work site are required to wear shoe covers. Shoe covers must be removed each time the worker exits the work area.
4. d. Either construct anteroom and require all personnel to pass through this room and be HEPA vacuumed clean before leaving the work site or optionally require all personnel to wear cloth/paper coveralls that are removed each time the worker exits the work area.
Attachment A
INFECTION CONTROL RISK ASSESSMENT (ICRA) DAILY INSPECTION FORM
INSTRUCTIONS: This form is to be utilized when infection controls are impacted, or construction activities are in progress.
ICRA must be implemented upon project start and continuously enforced through project completion to provide a level of infection control comparable to that required by EPA, OSHA and the Life Safety Code. Submit completed forms to the VA Infection Control Practitioner & Project Engineer.
Project Name: Project Number:
Construction & Impact Description: Construction Locations:
Identify areas surrounding the project area and assess potential impact.
Project Start Date:
Project COTR: Project Start Date:
Project CPs: Estimated Duration:
Completion Date:
Contractor:
GC Supervisor: Telephone:
Contractor CP:
Inspection Comments/Findings: (PROVIDE DETAILED EXPLAINATION OF EXCEPTIONS/DEFICIENCIES)
Signature/Date:
Project CPs GC Safety Manager
Attachment B
INFECTION CONTROL RISK ASSESSMENT (ICRA) DAILY INSPECTION FORM
Locations
IC Measure and Class Precaution
C L
A
SS
Inspection Date
SUN
MON
TUE
WED
THR
FRI
SAT
CP
Initials
BARRIERS
1. Dust containment secure at perimeter edges II
2. Doors/Windows properly closed/sealed II
3. Inspect integrity of dust critical barriers III
4. Relocate staff/patients from impact areas IV
5. Seal openings/penetrations daily IV
6. Verify anteroom operation IV
AIR HANDLING
7. Isolate/Shutdown HVAC II
8. Seal off building air ducts/vents II
9. Negative air machines running III
10. Negative air properly exhausted III
11. Verify negative air pressure frequently III
12. Negative air machines cleaned daily III
PROJECT AREA
13. Minimize raising dust I
14. Area free of debris & trash I
15. Area free of birds, insects, rodents, vermin I
16. Wash hands frequently I
17. Wet mop daily& as needed I
18. Housekeeping performed as needed I
19. Reinstall SAT displaced for inspections I
20. Prevent dust dispersion into atmosphere II
21. Contain SAT & fiberglass as removed II
22. Water mist work surfaces as needed II
23. Wipe surfaces with disinfectant II
24. Adjacent area SAT in place II
25. HEPA vacuum frequently II
26. Sticky mats in use II
27. Debris/Trash in covered container III
28. Inspect adjacent areas for dust migration III
TRAFFIC CONTROL
29. Route flow away from construction I
30. Traffic flow/warning signs posted I
DRESS CODE
31. Workers wear head covers IV
32. Workers wear/change shoe covers IV
33. Workers wear coveralls IV
34. Vacuum self upon leaving area IV
OTHER
35. Use drills with vacuum II
36. Use saws with vacuum II
| Project Number NA: | |
| Impact to area Entire Facility: | |
| Identify areas surrounding the project area and potential impact: | |
| o Above NA: | |
| o Below NA: | |
| o Adjacent Areas NARow1: | |
| Project COR Nicole Perez: | |
| Telephone 3076757385: | |
| Project Start Date 08092022: | |
| Project CPs OIT escort CBOC point of contactRow1: | |
| Estimated Duration 1 Day: | |
| Completion Date 08092022: | |
| GC Supervisor: | |
| Telephone: | |
| Check applicableRow1: | |
| Check applicableTYPE A Inspection noninvasive activities minimum dust levels: | |
| GROUP 1 Low Risk: | |
| GROUP 2 Medium Risk: | |
| XRow1: | |
| XTYPE C Generates moderate to high levels of dust requires greater than one work shift for completion: | |
| XRow2: | |
| XTYPE D Major duration and construction activities requiring consecutive work shifts: | |
| GROUP 4 Highest Risk: | |
| Project Construction Class: | |
| REQUIREMENTS in addition to page 4: | |
| Will remove a maximum of two ceiling tiles at one time: | |
| Contractor is responsible for dry sweeping any debris generated: | |
| Notify OIT escort when work is finished: | |
| Wear face masks per facility requirements: | |
| Infection Contol Digital Signature X Project COR CP X: | |
| Date Meeting was held: | |
| TYPE C: | |
| TYPE D: | |
| Major demolition and construction projects Includes but is not limited to Activities that require consecutive work shifts Requires heavy demolition or removal of a complete cabling system New construction: | |
| Step 1 Determination TYPE: | |
| o Office areas o Library o Chapel o EMS o FMS: | |
| Step 2 Determination RISK: | |
| ApplicableRow1: | |
| ApplicableRow2: | |
| ApplicableRow3: | |
| ApplicableRow4: | |
| ApplicableRow5: | |
| XRow1_2: | |
| X: | |
| Areas cleaned and trash disposed at the end of each working day: | |
| X_2: | |
| XRow1_3: | |
| X_3: | |
| Conduct infection control risk assessment ICRA: | |
| Infection Control Activities by Class PrecautionsRow1: | |
| Infection Control Activities by Class PrecautionsRow2: | |
| Perform clean up and disposal in accordance with contract requirements: | |
| Infection Control Activities by Class PrecautionsRow3: | |
| a Clean work surfaces with HEPA vacuum b Remove HVAC system isolation where work is complete c Mop andor wipe work surfaces with approved disinfectant: | |
| In addition to Class II Row1: | |
| Project Name: | |
| Project Number: | |
| Construction Impact Description: | |
| Construction Locations: | |
| Project Start Date: | |
| Project COTR: | |
| Project Start Date_2: | |
| Estimated Duration: | |
| Project CPsRow1: | |
| Completion DateContractor: | |
| GC Supervisor_2: | |
| TelephoneContractor CP: | |
| 5 Seal openingspenetrations daily: | |
| undefined: | |
| SUN: | |
| AIR HANDLING: | |
| TUE: | |
| WED: | |
| THR: | |
| FRI: | |
| SAT: | |
| Locations IC Measure and Class PrecautionRow1: | |
| 7 IsolateShutdown HVAC: | |
| CLASS: | |
| SUNCP Initials: | |
| MONCP Initials: | |
| TUECP Initials: | |
| WEDCP Initials: | |
| THRCP Initials: | |
| FRICP Initials: | |
| SATCP Initials: | |
| II: | |
| II_2: | |
| III: | |
| IV: | |
| IV_2: | |
| IV_3: | |
| II_3: | |
| II_4: | |
| III_2: | |
| III_3: | |
| III_4: | |
| III_5: | |
| 12 Negative air machines cleaned dailyRow1: | |
| PROJECT AREA: | |
| PROJECT AREA_2: | |
| I: | |
| 14 Area free of debris trash: | |
| I_2: | |
| 15 Area free of birds insects rodents vermin: | |
| I_3: | |
| I_4: | |
| 17 Wet mop daily as needed: | |
| I_5: | |
| I_6: | |
| I_7: | |
| II_5: | |
| II_6: | |
| II_7: | |
| 23 Wipe surfaces with disinfectant: | |
| II_8: | |
| II_9: | |
| 25 HEPA vacuum frequently: | |
| II_10: | |
| 26 Sticky mats in use: | |
| II_11: | |
| III_6: | |
| III_7: | |
| 28 Inspect adjacent areas for dust migrationRow1: | |
| TRAFFIC CONTROL: | |
| I_8: | |
| I_9: | |
| 30 Traffic flowwarning signs postedRow1: | |
| DRESS CODE: | |
| DRESS CODE_2: | |
| IV_4: | |
| 32 Workers wearchange shoe covers: | |
| IV_5: | |
| IV_6: | |
| IV_7: | |
| 34 Vacuum self upon leaving areaRow1: | |
| OTHER: | |
| OTHER_2: | |
| II_12: | |
| II_13: | |
| 36 Use saws with vacuumRow1: | |
| IIRow1: | |
| 2022-08-04T15:22:30-0600 | |
| Nicole J. Perez 894253 |
| 2022-08-04T15:37:49-0600 | |
| CAROLYN MELISSA INGALLS |
File details come from the government source that posted it. Updated .