01 SOW- Attachment 01 - Access Point Work per device - 11-23-22.pdf
PDF 112 KB Posted
- Attached to
- Z2DA--666-21-704 -EHRM NEXT GEN WIFI Federal contract opportunity
- Solicitation number
- 36C25923R0060
About this file
This scope of work document outlines the products and services required to support the installation of replacement and new WiFi access points at the Sheridan VA Medical Center campus and other locations in Wyoming. The contractor shall provide conduit, raceways, cable pathways, firestopping, and infection control measures to facilitate the installation of approximately 48 access points by the separate AT&T contractor. Specific requirements include installing conduit runs, mounting brackets, sealing penetrations, and pulling category 6A cabling. The contractor must also restore work areas and address any asbestos or other hazards encountered. All work must be completed within 60 days of the notice to proceed and coordinated with the AT&T contractor's scheduled installation from October 3rd to 28th, 2022. Submissions including product data and installation details are required prior to starting work.
View the file
Other files for this federal contract opportunity
Show all 30
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Bldg Fl AP No. No. of Cable runs
Conduit Required
AP
Bracket
ICRA Class required
53 9
1 B AP03 1 Yes I
AP03 is additional and requires a new conduit path from AP to Wiring Closet. Provide 3/4" conduit, 4 11/16" Dual Gang Box for path plus provide and pull new Cat6a cabling. Paint conduit to match ceiling color.
Provide cable service loop. Add 8' of extra cable for future move. Ceiling is hard pan -concrete and plaster. Follow infection control as per IRCA
2 B AP01 1 Yes I
Provide new conduit path and cabling from AP01 to Wiring Closet. Provide 3/4", 4 11/16" Dual Gang Box for path plus pull new Cat6a. Provide service loop with enough cable length for future move to B2, room 102. Ceiling hard pan - plaster. Follow infection control as per IRCA.
2 1 AP05 1 Yes 1 I
3 B AP02 1 Yes I
5 B AP06 1 Yes I
Provide new conduit path and cabling from AP06 to Wiring Closet. Provide 3/4" conduit, 4 11/16" Dual Gang Box for path plus pull new Cat6a. Ceiling is Hard pan -plaster. Provide enough cable length for future move to Bldg 5, room 114A. Follow infection control as per IRCA.
Comments
Provide new conduit path and cabling from AP05 to Wiring Closet. Provide 3/4" conduit thru attic for path plus pull new Cat6a. Provide service loop with enough cable length for future move to B2, room 102. Provide and install horizontal Bracket for AP and wire mold equivalent to 3/4" conduit size from ceiling to bracket. Ceiling is a metal pan historic ceiling. Submit details for VA approval on installation to minimize damage to ceiling and path to horizontal bracket.
Provide new conduit path and cabling from AP02 to Wiring Closet. Provide 3/4" conduit for path plus pull new Cat6a. Submit details for VA approval on conduit path such as snaking in conduit thru floor joists or cutting and finishing ceiling. Provide service loop plus and additional 10' for a future move. Ceiling is hard pan dry wall. Follow infection control as per IRCA.
Total
5 B AP07 1 Yes I
Provide new conduit path and cabling from AP07 to Wiring Closet. Provide 3/4" conduit, 4 11/16" Dual Gang Box for path plus pull new Cat6a. Ceiling is Hard pan -plaster. Provide enough cable length for future move to Bldg 5, room 114A. Follow infection control as per IRCA.
5 B AP08 1 Yes I
Provide new conduit path and cabling from AP08 to Wiring Closet. Provide 3/4" conduit, 4 11/16" Dual Gang Box for path plus pull new Cat6a. Ceiling is Hard pan -plaster. Provide enough cable length for future move to Bldg 5, room 114A. Follow infection control as per IRCA.
5 1 AP11 1 No I
Provide new Cat 6a and J-hooks pathway from AP to Wiring Closet. J-hooks must attach to deck or wall. Attaching to ceiling grid or other utilities will not be allowed.
Ceiling is suspended. Provide enough cable length for future move to Bldg 5, room 114A. Follow infection control as per IRCA.
5 2 AP10 1 No I
5 2 AP11 1 No I
5 2 AP12 1 No I
5 2 AP13 1 No I
7 B AP16 1 Yes 1 I
Provide new conduit path and cabling from AP16 to Data Closet 001. Provide 3/4" conduit plus pull new Cat6a. Provide and install a Horizontal mounting bracket -wall for AP. Submit details for VA approval on path to horizontal bracket and any modification needed. Provide service loop . Add 6' of extra cable for future move.
Ceiling is hard pan plaster or drywall. Follow infection control as per IRCA.
Provide new Cat 6a and J-hooks pathway from AP to Wiring Closet. J-hooks must attach to deck or wall. Attaching to ceiling grid or other utilities will not be allowed. Ceiling is suspended.
Provide enough cable length for future move to Bldg 5, room 114A. Follow infection control as per IRCA.
Provide new Cat 6a and J-hooks pathway from AP to Wiring Closet. J-hooks must attach to deck or wall. Attaching to ceiling grid or other utilities will not be allowed. Ceiling is suspended.
Provide enough cable length for future move to Bldg 5, room 114A. Follow infection control as per IRCA.
Provide new Cat 6a and J-hooks pathway from AP to Wiring Closet. J-hooks must attach to deck or wall. Attaching to ceiling grid or other utilities will not be allowed. Ceiling is suspended.
Provide enough cable length for future move to Bldg 5, room 114A. Follow infection control as per IRCA.
Provide new Cat 6a and J-hooks pathway from AP to Wiring Closet. J-hooks must attach to deck or wall. Attaching to ceiling grid or other utilities will not be allowed. Ceiling is suspended.
Provide enough cable length for future move to Bldg 5, room 114A. Follow infection control as per IRCA.
7 B AP17 1 Yes 1 I
Provide new conduit path and cabling from AP17 to Data Closet 001. Provide 3/4" conduit plus pull new Cat6a. Provide and install a Horizontal mounting bracket -wall for AP. Submit details for VA approval on path to horizontal bracket and any modification needed. Provide service loop. Add 6' of extra cable for future move.
Ceiling is hard pan plaster or daywall. Follow infection control as per IRCA.
7 B AP20 1 Yes I
Provide new conduit path and cabling from AP20 to Data Closet 001. Provide 3/4" conduit, 4 11/16" Dual Gang Box for path plus pull new Cat6a. Ceiling is Hard pan -plaster or dry wall. Provide service loop. Follow infection control as per IRCA.
7 B AP21 1 Yes I
Provide new conduit path and cabling from AP21 to Data Closet 001. Provide 3/4" conduit, 4 11/16" Dual Gang Box for path plus pull new Cat6a. Ceiling is Hard pan -plaster or dry wall. Paint conduit to match ceiling color. Provide service loop. Add 6' of extra cable for future move. Follow infection control as per IRCA.
8 B AP12 1 Yes I
Provide new conduit path and cabling from AP12 to Switch Closet 001. Provide 3/4" conduit, 4 11/16" Dual Gang Box for path plus pull new Cat6a. Ceiling is Hard pan -plaster or dry wall. Provide service loop plus an addtional 6' of cable for future move.
Follow infection control as per IRCA.
8 B AP13 1 Yes I
Provide new conduit path and cabling from AP13 to Switch Closet. Provide 3/4" conduit, 4 11/16" Dual Gang Box for path plus pull new Cat6a. Ceiling is Hard pan -plaster or dry wall. Provide service loop plus an addtional 6' of cable for future move.
Follow infection control as per IRCA.
8 AP14 1 Yes I
Provide new conduit path and cabling from AP14 to Data Closet 001. Provide 3/4" conduit, 4 11/16" Dual Gang Box for path plus pull new Cat6a. Ceiling is Hard pan -plaster or dry wall. Provide service loop plus an addtional 6' of cable for future move.
Follow infection control as per IRCA.
8 B AP15 1 Yes I
Provide new conduit path and cabling from AP15 to Switch Closet. Provide 3/4" conduit, 4 11/16" Dual Gang Box for path plus pull new Cat6a. Ceiling is Hard pan -plaster or dry wall. Provide service loop plus an addtional 6' of cable for future move.
Follow infection control as per IRCA.
8 B AP16 1 Yes I
Provide new conduit path and cabling from AP16 to Switch Closet. Provide 3/4" conduit, 4 11/16" Dual Gang Box for path plus pull new Cat6a. Ceiling is Hard pan -plaster or dry wall. Provide service loop plus an addtional 6' of cable for future move.
Follow infection control as per IRCA.
9 1 AP06 1 Yes I
Provide new conduit path and cabling from AP06 to Switch Closet. Provide 3/4" conduit, 4 11/16" Dual Gang Box for path plus pull new Cat6a. Paint conduit to match ceiling color. Ceiling is Hard pan - plaster or dry wall. Provide service loop plus an addtional 6' of cable for future move. Follow infection control as per IRCA.
11 B AP01 1 Yes I
Provide new conduit path and cabling from AP01 new location to Switch Closet.
Provide 3/4" conduit, 4 11/16" Dual Gang Box for path plus pull new Cat6a. Ceiling is Hard pan - plaster or dry wall. Provide service loop plus additional cable length for future move to B11, room 109. Follow infection control as per IRCA.
11 B AP02 1 Yes I
Provide new conduit path and cabling from AP02 new location to Switch Closet.
Provide 3/4" conduit, 4 11/16" Dual Gang Box for path plus pull new Cat6a. Ceiling is Hard pan - plaster or dry wall. Provide service loop plus additional cable length for future move to B11, room 109. Follow infection control as per IRCA.
11 1 AP03 1 Yes I
Provide extend existing conduit path and install new Cat6A cabling from AP03 new location to Switch Closet. Provide 3/4" conduit, 4 11/16" Dual Gang Box for path plus pull new Cat6a. Ceiling is Hard pan - plaster or dry wall. Provide service loop plus additional cable length for future move to B11, room 109. Follow infection control as per IRCA.
11 1 AP05 1 Yes I
Provide extend existing conduit path and install new Cat6A cabling from AP05 new location to Switch Closet. Provide 3/4" conduit, 4 11/16" Dual Gang Box for path plus pull new Cat6a. Ceiling is Hard pan - plaster or dry wall. Provide service loop. Follow infection control as per IRCA.
31 1 AP04 1 Yes 1 I
Provide new conduit path and cabling from AP04 to Wiring Closet. Provide 3/4" conduit for path plus pull new Cat6a. Provide and install a Horizontal mounting bracket -wall for AP. Submit details for VA approval on path to horizontal bracket and any modification needed. Provide service loop. Follow infection control as per IRCA.
31 AP05 1 Yes I
Provide new conduit path and cabling from AP05 to Wiring Closet. Provide 3/4" conduit, 4 11/16" Dual Gang Box for path plus pull new Cat6a. . Provide service loop.
Ceiling is hard pan concrete. Follow infection control as per IRCA.
32 1 AP03 1 Yes I
Provide new 3/4" conduit path and cabling from AP05 to Switch Closet. On finished ceiling provide wire mold equivalent to 3/4" conduit, 4 11/16" Dual Gang Box for path plus pull new Cat6a. Ceiling is Hard pan - Tile glued to drywall. Provide service loop. Follow infection control as per IRCA.
35 B AP05 1 Yes I
Provide new conduit path and cabling from AP05 to Switch Closet. Provide 3/4" conduit, 4 11/16" Dual Gang Box for path plus pull new Cat6a. Ceiling is Hard pan -plaster. Provide 15' service loop. Follow infection control as per IRCA.
36 1 AP01 1 Yes 1 I
Provide new conduit path and cabling from AP01 to Wiring Closet. Provide 3/4" conduit for path plus pull new Cat6a. Provide and install a Horizontal mounting bracket -wall for AP. Submit details for VA approval on path to horizontal bracket and any modification needed to bracket. Provide service loop. Ceiling is hard pan-plaster and wood. Follow infection control as per IRCA.
36 1 AP02 1 Yes 1 I
Provide new conduit path and cabling from AP02 to Wiring Closet. Provide 3/4" conduit for path plus pull new Cat6a. Provide and install a Horizontal mounting bracket -wall for AP. Submit details for VA approval on path to horizontal bracket and any modification needed to bracket. Provide service loop. Ceiling is hard pan-plaster and wood. Follow infection control as per IRCA.
36 1 AP03 1 Yes 1 I
Provide new conduit path and cabling from AP03 to Wiring Closet. Provide 3/4" conduit for path plus pull new Cat6a. Provide and install a Horizontal mounting bracket -wall for AP. Submit details for VA approval on path to horizontal bracket and any modification needed to bracket. Provide service loop plus add addtional length for a future move to B36 room 102. Ceiling is hard pan-plaster and wood.
Follow infection control as per IRCA.
55 1 AP01 1 Yes I
Provide new conduit path and cabling from AP01 to Wiring Closet located in B36.
Provide 3/4" conduit for path to gang box in the SW lower corner of B55 plus pull new Cat6a to the Wiring Closet in B36 thru the existing 1" buried conduit system.
Provide and install a 4 11/16" Dual Gang box for AP. Provide service loop plus additional cable length for a future move to B36 room 102. Ceiling is hard pan-plaster and wood. Follow infection control as per IRCA.
61 1 AP08 1 No I
Provide new Cat 6a and J-hooks pathway from AP to Wiring Closet. J-hooks must attach to deck or wall. Attaching to ceiling grid or other utilities will not be allowed.
Ceiling is suspended. Provide enough cable length for future move to new racks within the wiring closet i.e. 30' of loop. Follow infection control as per IRCA. Note:
Work will require working in autormium ceiling witch is 16' high. Walking planks will have to be temporarly extended, fall protection used and other safety protection used as required.
61 AP09 1 No I
Provide new Cat 6a and J-hooks pathway from AP to Wiring Closet. J-hooks must attach to deck or wall. Attaching to ceiling grid or other utilities will not be allowed.
Ceiling is suspended. Provide enough cable length for future move to new racks within the wiring closet i.e. 30' of loop. Follow infection control as per IRCA. Note:
Work will require working in autormium ceiling witch is 16' high. Walking planks will have to be temporarly extended, fall protection used and other safety protection used as required
90 1 AP01 1 Yes 1 I
Provide new conduit path and cabling from AP01 to Wiring Closet. Provide 3/4" conduit, 4 11/16" Dual Gang Box for path plus pull new Cat6a. Provide and install a Horizontal mounting bracket -wall for AP. Submit details for VA approval on path to horizontal bracket and any modification needed to bracket. Provide service loop and additional 10' of cable length for future move. Ceiling is hard pan concrete. Follow infection control as per IRCA.
AftonCBOC 1 AP01 1 No 1 See SOW
Provide new Cat 6a and J-hooks pathway from AP to Wiring Closet. J-hooks must attach to deck or wall. Attaching to ceiling grid or other utilities will not be allowed.
Provide enough 8' servoce loop. Follow infection control as per IRCA. Submit details for VA approval on path to horizontal bracket and any modification needed to bracket.
AftonCBOC 1 AP02 1 Yes See SOW
Provide new conduit path and new Cat6A cabling from AP to Wiring Closet. Provide 3/4" conduit for path. Provide 8' service loop. Follow infection control as per IRCA.
Seal all pentrations,and use fire stop systems thru attic penetrations.
AftonCBOC 1 AP03 1 Yes See SOW
Provide new conduit path and new Cat6A cabling from AP to Wiring Closet. Provide 3/4" conduit for path. Provide 8' service loop. Follow infection control as per IRCA.
Seal all pentrations,and use fire stop systems thru attic penetrations.
AftonCBOC 1 AP04 1 Yes See SOW
Provide new conduit path and new Cat6A cabling from AP to Wiring Closet. Provide 3/4" conduit for path. Provide 8' service loop. Follow infection control as per IRCA.
Seal all pentrations,and use fire stop systems thru attic penetrations.
AftonCBOC 1 AP05 1 Yes See SOW
Provide new conduit path and new Cat6A cabling from AP to Wiring Closet. Provide 3/4" conduit for path. Provide 8' service loop. Follow infection control as per IRCA.
Seal all pentrations,and use fire stop systems thru attic penetrations.
RivertonCBOC 1 AP01 1 Yes See SOW
Provide new conduit path and new Cat6A cabling from AP to Wiring Closet. Provide 3/4" conduit for path. Provide 8' service loop. Follow infection control as per IRCA.
Seal all pentrations,and use fire stop systems thru attic penetrations.
RivertonCBOC 1 AP02 1 Yes See SOW
Provide new conduit path and new Cat6A cabling from AP to Wiring Closet. Provide 3/4" conduit for path. Provide 8' service loop. Follow infection control as per IRCA.
Seal all pentrations,and use fire stop systems thru attic penetrations.
RivertonCBOC 1 AP03 1 Yes See SOW
Provide new conduit path and new Cat6A cabling from AP to Wiring Closet. Provide 3/4" conduit for path. Provide 8' service loop. Follow infection control as per IRCA.
Seal all pentrations,and use fire stop systems thru attic penetrations.
RivertonCBOC 1 AP04 1 Yes See SOW
Provide new conduit path and new Cat6A cabling from AP to Wiring Closet. Provide 3/4" conduit for path. Provide 8' service loop. Follow infection control as per IRCA.
Seal all pentrations,and use fire stop systems thru attic penetrations.
RivertonCBOC 1 AP06 1 Yes See SOW
Provide new conduit path and new Cat6A cabling from AP to Wiring Closet. Provide 3/4" conduit for path. Provide 8' service loop. Follow infection control as per IRCA.
Seal all pentrations,and use fire stop systems thru attic penetrations.
RivertonCBOC 1 AP07 1 Yes See SOW
Provide new conduit path and new Cat6A cabling from AP to Wiring Closet. Provide 3/4" conduit for path. Provide 8' service loop. Follow infection control as per IRCA.
Seal all pentrations,and use fire stop systems thru attic penetrations.
RivertonCBOC 1 AP08 1 Yes See SOW
Provide new conduit path and new Cat6A cabling from AP to Wiring Closet. Provide 3/4" conduit for path. Provide 8' service loop. Follow infection control as per IRCA.
Seal all pentrations,and use fire stop systems thru attic penetrations.
RivertonCBOC 1 AP09 1 Yes See SOW
Provide new conduit path and new Cat6A cabling from AP to Wiring Closet. Provide 3/4" conduit for path. Provide 8' service loop. Follow infection control as per IRCA.
Seal all pentrations,and use fire stop systems thru attic penetrations.
Rock Springs CBOC 1 AP01 1 Yes See SOW
Provide new conduit path and new Cat6A cabling from AP to Wiring Closet. Provide 3/4" conduit for path. Provide 8' service loop. Follow infection control as per IRCA.
Seal all pentrations,and use fire stop systems thru attic penetrations.
Worland PCTOC 1 AP01 1 Yes See SOW
Provide new conduit path and new Cat6A cabling from AP to Wiring Closet. Provide 3/4" conduit for path. Provide 8' service loop. Follow infection control as per IRCA.
Seal all pentrations,and use fire stop systems thru attic penetrations.
Worland PCTOC 1 AP02 1 Yes See SOW
Provide new conduit path and new Cat6A cabling from AP to Wiring Closet. Provide 3/4" conduit for path. Provide 8' service loop. Follow infection control as per IRCA.
Seal all pentrations,and use fire stop systems thru attic penetrations.