This is an Official Bid Results document for a Utah State Division of Purchasing Invitation for Bid (IFB) conducted by the Division of Wildlife Resources, USWFS, and BLM for the Atchee Ridge Fuel Break Bullhog project (BD27-103). The project involves wildlife habitat improvement and wildland fire hazard reduction through mechanical removal and shredding of standing live and dead pinyon and juniper trees, saplings, and brush across 260.4 acres on Indian Spring and Augisi Ridges, Book Cliffs, and Spring Ridge. The work must be completed by November 30th, 2026, with the contract term extending from the time of award through project completion. No mandatory site visit was held prior to bidding, though potential bidders were strongly encouraged to inspect the site and satisfy themselves regarding all general and local conditions affecting cost and performance. Participation in this solicitation was limited to prequalified contractors only.
Four responsive bids were received from England Construction, Hall's HammerTime Construction LLC, Razr Bak Restoration, and Wilkinson Construction Company, with total project costs of $180,978.00, $119,138.21, $153,636.00, and $207,278.40 respectively. Pricing was calculated on a per-acre basis, ranging from $457.52 to $796.00 per acre. Hall's HammerTime Construction LLC submitted the lowest bid at $119,138.21; however, this contractor voluntarily withdrew from the project due to other currently active jobs with the State. The contract was anticipated to result in a single award to the lowest cost responsive and responsible vendor, with the selected vendor required to guarantee its pricing through project completion.
View the file
Other files
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet 1
| England Construction | Hall's HammerTime Construction LLC | Razr Bak Restoration | Wilkinson Construction Company | |||
| Total Cost | $180,978.00 | $119,138.21 | $153,636.00 | $207,278.40 | ||
| Items | QTY | Unit |
of
| Measurement | Unit |
| Price | Total |
| Cost | Unit |
| Price | Total |
| Cost | Unit |
| Price | Total |
| Cost | Unit |
| Price | Total |
Cost
| $180,978.00 | $119,138.21 | $153,636.00 | $207,278.40 | |||||||
| Price per acre | 260.4 | Acres | $695.00 | $180,978.00 | $457.52 | $119,138.21 | $590.00 | $153,636.00 | $796.00 | $207,278.40 |
| **The lowest bidder willingly withdrew from the project due to other currently active jobs with the State.** |