00 45 20 Named Sub Signature Page 20251001.docx

DOCX document 83 KB Posted

Attached to
Invitation to Bid for Construction Services
Solicitation number
2615BI2B500
Issued by
Hartford County, Connecticut

About this file

This is a Named Subcontractor Signature Page document issued by the State of Connecticut Department of Administrative Services (CT DAS) for the Troop H Maintenance Facility Repairs project located at 100R Washington Street, Hartford, Connecticut (Project Number BI-2B-500). The document establishes requirements for bidders and named subcontractors in accordance with Connecticut General Statutes Sections 4a-60g(d) and 4b-95(b)(3), as amended by Public Act 25-168 and effective October 1, 2025. The document applies to projects where named subcontractors are utilized and requires each named subcontractor listed in Table 2.7 of the Bid Proposal Form to provide a signed statement confirming direct communication with the bidder regarding the work to be performed.

Bidders must obtain signed statements from all named subcontractors and upload them to CTsource prior to the bid opening date and time. Failure to provide these signed statements before the bid opening or within two business days thereafter will result in automatic bid rejection and shall not be considered a minor irregularity. Each named subcontractor must sign the statement, confirming they have communicated directly with the general contractor (bidder) about the project work, and provide their title, name, date, and firm name. The document serves as a standard form for all Connecticut DAS projects and was revised as of October 1, 2025.

View the file

Other files

File Type Posted
Addendum 3.pdf PDF
Addendum 2.pdf.crdownload CRDOWNLOAD file
Addendum 4.pdf PDF
Specification Vol 1 of 1.pdf PDF
00 40 15 DAS Prequal Cert Reqts 20251001.docx DOCX document
00 40 16 DAS Update Stmt Reqts 20251001.docx DOCX document
Addendum 1.pdf PDF
00 41 00 DAS-CS Bid Proposal Form REVISED.docx DOCX document
Drawings Voloume 1.pdf PDF
Addendum 2.pdf PDF
00 45 14 GC Bidder Qual Statement 20251001.docx DOCX document
00 41 00 DAS-CS Bid Proposal Form LOCKED 20251001.docx DOCX document
00 40 14 CertOfAuthority 20231001.docx DOCX document
Specification Vol 1 of 1.pdf.crdownload CRDOWNLOAD file
Drawings Voloume 1.pdf.crdownload CRDOWNLOAD file
2615BI2B500_May_28_26_solicitation_doc.pdf PDF
00 11 16 DAS-CS Invitation to Bid.pdf PDF
00 43 16 BidBond 20240924.docx DOCX document
2615BI2B500_Aug_3_26_solicitation_doc.pdf PDF
Show all 19

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION 00 45 20

NAMED SUBCONTRACTOR SIGNATURE PAGE

SECTION 00 45 20

NAMED SUBCONTRACTOR SIGNATURE PAGE

Named Subcontractor Signature Page

NAMED SUBCONTRACTOR(S) SIGNATURES:

In accordance with Connecticut General Statutes (C.G.S.) Sections (§§) 4a-60g(d) and 4b-95(b)(3), as amended by Public Act 25-168 and effective October 1, 2025, the Bidder shall provide a signed statement from each Named Subcontractor stating that the Named Subcontractor has communicated directly with the Bidder about the work to be performed on such contract.

See Table 2.7 of Section 00 41 00 Bid Proposal Form for applicability.

GENERAL INSTRUCTIONS:

INSTRUCTIONS TO BIDDERS: IF APPLICABLE TO THE PROJECT:

1. The Bidder must obtain and provide a signed statement from each Named Subcontractor listed in Table 2.7 of Section 00 41 00 Bid Proposal Form for the Project listed below.

2. The Bidder must upload all signed statements from all Named Subcontractors to the solicitation on CTsource prior to the date and time of the Bid Opening.

3. Failure of a Bidder to upload signed statements from each Named Subcontractor listed in Table 2.7 of this Project’s Bid Proposal Form to the solicitation on CTsource prior to the date and time of the Bid Opening or to submit signed statements within two (2) business days after the Bid Opening shall cause rejection of the bid and shall not be considered a minor irregularity under C.G.S. § 4b-95.

INSTRUCTIONS TO EACH NAMED SUBCONTRACTOR:

1. The Named Subcontractor must enter the firm name of the Bidder with whom they communicated about the Project listed below.

2. The Named Subcontractor must sign below, and enter their title, name, date, and firm name. By signing below, the Named Subcontractor is indicating that they have communicated directly with the Bidder about the work to be performed on the project listed below.

Project Title:
Troop H Maintenance Facility Repairs
Project Number:
BI-2B-500

Firm Name of Bidder (General Contractor):

(Print Bidder/General Contractor’s Firm Name)

Signature of Named Subcontractor:

(Duly Authorized Signature)

(Title)

(Print Name)

(Date)

(Print Named Subcontractor’s Firm Name)

End of Section 00 45 20 Named Subcontractor Signature Page

CT DAS 5000 (Rev. 10.01.2025)
PROJECT NO. BI-2B-500
CT DAS 5000 (Rev. 10.01.2025)
STANDARD FORM FOR ALL PROJECTS

File details come from the government source that posted it. Updated .