This is a Bid Proposal Form issued by the Connecticut Department of Administrative Services Construction Services for the Troop H Maintenance Facility Repairs project located at 100R Washington Street, Hartford, Connecticut (Project BI-2B-500). The scope of work includes asbestos roofing removal, selective demolition, historic masonry restoration and cleaning, concrete spall repairs, metal fabrications, single-ply roofing installation, door and window replacements, chimney reconstruction with terracotta flue liner replacement, and electrical, plumbing, and HVAC modifications. The facility is an operational military installation requiring 72-hour advance notice for work location changes and coordination around an active microwave antenna (no work within 12 feet while operational). A mandatory pre-bid meeting is scheduled for June 10, 2026 at 9:00 AM at the project site, with bids due July 7, 2026 at 10:00 AM. The contract term is 243 calendar days for substantial completion, followed by 90 calendar days for acceptance of work. The estimated project cost ranges from $2.21 million to $2.44 million.

Bidders must submit a lump-sum base bid along with a Standard Bid Bond or certified check equal to 10 percent of the bid amount, a General Contractor Bidder's Qualification Statement with resumes and reference letters, a Certificate of Authority, and Named Subcontractor Signature Pages. Bids exceeding $1 million require current DAS Prequalification Certificate and DAS Update Statement for General Building Construction (Group B), a non-waivable eligibility requirement. The project is subject to Connecticut prevailing wage requirements and does not include federal financial assistance or a Project Labor Agreement. SBE and MBE subcontractor participation goals of 5.3 percent and 1.96 percent respectively apply, with good-faith efforts required. Named subcontractors for masonry work and other classes of work exceeding $100,000 must be identified in the bid with signed statements confirming direct communication. Liquidated damages are assessed at $1,297 per calendar day beyond substantial completion and an additional $1,297 per day beyond the 90-day acceptance period. All bids must be submitted electronically through CTsource with questions due June 23, 2026 at 10:00 AM.

View the file

Other files

File Type Posted
00 41 00 DAS-CS Bid Proposal Form LOCKED 20251001.docx DOCX document
Specification Vol 1 of 1.pdf PDF
00 40 16 DAS Update Stmt Reqts 20251001.docx DOCX document
00 40 15 DAS Prequal Cert Reqts 20251001.docx DOCX document
Addendum 2.pdf PDF
Drawings Voloume 1.pdf.crdownload CRDOWNLOAD file
Specification Vol 1 of 1.pdf.crdownload CRDOWNLOAD file
00 40 14 CertOfAuthority 20231001.docx DOCX document
00 11 16 DAS-CS Invitation to Bid.pdf PDF
00 45 14 GC Bidder Qual Statement 20251001.docx DOCX document
Addendum 2.pdf.crdownload CRDOWNLOAD file
Addendum 4.pdf PDF
Addendum 3.pdf PDF
00 43 16 BidBond 20240924.docx DOCX document
2615BI2B500_Aug_3_26_solicitation_doc.pdf PDF
2615BI2B500_May_28_26_solicitation_doc.pdf PDF
Drawings Voloume 1.pdf PDF
00 45 20 Named Sub Signature Page 20251001.docx DOCX document
Addendum 1.pdf PDF
Show all 19

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION 00 41 00

BID PROPOSAL FORM

SECTION 00 41 00

BID PROPOSAL FORM

BID PROPOSAL FORM

Awarding Authority:

Connecticut Department of Administrative Services / Construction Services Office of Legal Affairs, Policy, and Procurement 450 Columbus Boulevard, Suite 1302, Hartford, CT 06103

Required DAS Prequalification Classification for Bidders:
Bidders must by Prequalified by DAS for General Building Construction (Group B) if their bid is greater than one million dollars ($1,000,000.00).
BID OPENING DATE & TIME:
See page 1 of Section 00 11 16 Invitation To Bid.

Bidder Information:

Proposal Of:

(Complete Bidder's Legal Company Name As Registered With the CT Secretary of State)

Firm Address:
,
,

(Avenue / Street)

(Town / City)

(State)

(Zip Code)

Contact Person:

(Name)

(Title)

Contact Information:

(Phone Number)

(Fax Number)

(Email Address)

Threshold Project:
Major Contractor Registration License No.:

All Bidders for Projects that exceed Threshold Limits (see below): Insert your Firm’s Major Contractor Registration License Number in the space provided above. If this Project does NOT exceed Threshold Limits, insert “Not Applicable” in the space provided above.

1.0 General Bid Proposal Information: (recent updates are in yellow highlight)

Project Title:
Troop H Maintenance Facility Repairs
Project Location:
100R Washington St., Hartford, CT, 06103
Project Number:
BI-2B-500
Prevailing Wages:
This is a Prevailing Wages Project
Project Labor Agreement:
This Project is NOT subject to a Project Labor Agreement.
Federal Financial Assistance:
This Project DOES NOT include Federal Financial Assistance.
BABA Applicability:
"Build America, Buy America Act" (BABA) requirements DO NOT apply to this Project.
Threshold Limits:(C.G.S. §29-276b)
This Project DOES NOT exceed Threshold Limits.
SBE / MBE Subcontractor Participation Goals:
SBE Subcontractors &/or Suppliers: 5.3%;

MBE Subcontractors &/or Suppliers: 1.96%

Pre-Bid Meeting:
See Sections 00 11 16 Invitation to Bid and 00 25 13 Pre-Bid Meeting.
Plans and Specifications by A/E:
Gale Associates, Inc. 703 Hebron Avenue, Glastonbury, CT

Bid Proposal Form Instructions:

· Duly Authorized Signature: A duly authorized representative of the Bidder or Bidder’s partnership, firm, corporation or business organization must sign the Bid Proposal Form.

Any Bid Proposal Form that is submitted without the signature of the bidder or its authorized representative, will be rejected (unless the bid is signed by the duly authorized representative within two (2) business days after the opening of bids, without alteration or revision to the submitted Bid Proposal Form).

· A signed and scanned Certificate (of Authority), Section 00 40 14, must be uploaded to CTsource prior to the date and time of the Bid Opening.

· Remote Electronic Notarization: In accordance with Connecticut General Statutes (C.G.S.) Section (§) 3-95b, Bidders are permitted to use Remote Electronic Notarization to perform notarial acts that are required under Connecticut law and the Procurement Documents of the Awarding Authority.

· No Facsimile Signature is permitted. All information in this Proposal is to be filled in by the Bidder.

· If an Addendum is issued that changes the Bid Proposal Form, then the Revised Bid Proposal Form (issued with the Addendum) must be uploaded instead. If you have previously responded to the bid, select “Retract & Edit Response”. You must Accept the Addendum, attach applicable documents, and re-submit your bid.

· Any Bid Proposal Form that has omitted or added items, altered the form, or contains conditional, alternative, or obscure bids will be rejected.

· See Section 00 21 13 Instructions to Bidders for additional information. See Section 00 41 10 Bid Package Submittal Requirements for a checklist of Bid Documents that must be uploaded to CTsource prior to the date and time of the Bid Opening.

· Attachment 1: Campaign Contribution Certification: All Bidders must read, complete, sign, notarize, and upload Attachment 1 with the Bid Proposal Form.

· Attachment 2: Additional Information Questions: In accordance with C.G.S. § 4b-91a, any bid of a Contractor on a contract to perform work with a value of more than $500,000 but less than $1,000,000 in response to an Invitation to Bid issued by the Commissioner of Administrative Services, shall answer the Additional Information Questions in Attachment 2 of this Bid Proposal Form.

Pursuant to C.G.S. § 4b-91a, any failure to disclose any of the information required in Attachment 2 shall disqualify a Contractor from any associated bid on a contract and shall not be considered a minor irregularity under C.G.S. § 4b-95.

· Attachment 3: Named Subcontractor DAS Prequalification Certificates and Update Statements: For projects with Named Subcontractors, all Bidders shall upload DAS Prequalification Certificates and Update Statements from each Named Subcontractor listed in Table 2.7 of this Bid Proposal Form if the subcontract is proposed to be greater than $1,000,000, and if the Class of Work is Electrical, HVAC, Masonry, Plumbing, or other DAS Prequalification Class of Work that the Awarding Authority deems necessary (including the Bidder, if the Bidder intends to self-perform).

· Attachment 4: Build America, Buy America Act (BABA) Acknowledgement: For projects subject to BABA, all Bidders must read, comply with, sign, and upload Attachment 4 with the Bid Proposal Form. For projects subject to BABA, if a specific manufacture is used in the bidding, a statement that the manufacturer will comply with BABA must be included with the submitted bid documents.

· Attachment 5: Named Subcontractor Signed Statement: For projects with Named Subcontractors, all Bidders shall upload a signed statement from each Named Subcontractor listed in Table 2.7 of this Bid Proposal Form, stating that the Named Subcontractor has communicated directly with the Bidder about the work to be performed on such contract. Bidders may use Section 00 45 20 Named Subcontractor Signature Page to obtain such signed statements. See the solicitation on CTsource for a template.

· Attachments 1, 2, 3, 4 and 5 of this Bid Proposal Form must be correctly completed (as applicable) and remain attached to the Bid Proposal Form. Failure to correctly complete and submit Attachments 1, 2, 3, 4, and 5 with the Bid Proposal Form (and all applicable documents) or within two (2) business days after the opening of bids, without alteration or revision to the submitted Bid Proposal Form, shall cause the bid to be rejected and shall not be considered a minor irregularity under C.G.S. § 4b-95.

1.0 General Bid Proposal Information (continued):

1.1
Commencement and Acceptance: (See Section 00 73 13 General Conditions, Article 4 - Commencement and Progress of Work and Article 1 - Definitions)

The Selected Bidder shall commence Work within fourteen (14) Calendar Days after receiving a

“Construction Start Date and Notice to Proceed” by the Commissioner or authorized representative

and continue for
243Calendar Days for “Substantial Completion” of the project;
and then continue
90
Calendar Days for “Acceptance” of the Work.
1.2
Liquidated Damages: (See Section 00 73 13 General Conditions, Article 8 – Damages & Article 1 - Definitions)
1.2.1
Liquidated Damages – Substantial Completion:
The Selected Bidder shall be assessed $
1,297.00per Calendar Day beyond the date established for Substantial

Completion of the Contract according to the Contract Time as defined in Article 1.28 of Section 00 73 13 General Conditions, and not otherwise excused or waived pursuant to the Contract Documents, as defined in Article 1.23 of Section 00 73 13 General Conditions.

1.2.2
Liquidated Damages – Acceptance:
The Selected Bidder shall be assessed $
1,297.00per Calendar Day beyond ninety (90) days after the date of

said Substantial Completion that the Selected Bidder fails to achieve Acceptance, as defined in Article 1.1 of Section 00 73 13 General Conditions, and not otherwise excused or waived as described above.

1.3
Bid Proposal Statements and Conditions: This Bid Proposal Form shall be submitted according to, and in compliance with, the foregoing and following statements, conditions, and/or information:
1.3.1
This Bid Proposal Form is submitted in accordance with Chapter 60 Construction And Alterations Of State Buildings, Part II Bidding And Contracts of the C.G.S., as amended, particularly C.G.S. § 4b-91(a), and pursuant to, and in compliance with, the Invitation to Bid (Section 00 11 16), the Instructions to Bidders (Section 00 21 13), the Bid Package Submittal Requirements (Section 00 41 10), and the Contract (Section 00 52 03).
1.3.2
The Bidder proposes to furnish the labor and/or materials, installed as required for the Project named and numbered on this Bid Proposal Form, submitted herein, furnishing all necessary equipment, machinery, tools, labor and other means of construction, and all materials specified in the manner and at the time prescribed strictly in accordance with the provisions of the Contract including, but not limited to, the specifications and/or drawings together with all Addenda issued by the Awarding Authority and received by the Bidder, prior to the scheduled Date and Time of the Bid Opening as stated on page 1 of the Invitation To Bid, and in conformity with requirements of the Awarding Authority and any laws or Departmental regulations of the State of Connecticut or of the United States which may affect the same, for and in consideration of the price(s) stated on this Bid Proposal Form, hereof.
1.3.3
The Bidder acknowledges that the Proposed Lump Sum Base Bid submitted on this Bid Proposal Form in Subsection 2.1.1 includes all work indicated on the drawings and/or described in the specifications, including the Allowances and Base Bid Quantities described in Section 01 20 00 Contract Considerations, and does not include the Supplemental Bids submitted on the Bid Proposal Form in Subsection 2.1.2 and described in Section 01 23 13 Supplemental Bids.
1.3.4
The Bidder acknowledges and agrees to furnish all labor and materials required for this Project, in accordance with the accompanying Plans and Specifications prepared by the Architect/Engineer listed on page 1 of this Bid Proposal Form, for the Contract Sum specified in the Proposed Lump Sum Base Bid in Subsection 2.1.1 of this Bid Proposal Form, subject to additions and deductions according to the terms of the specifications, and including the number of Addenda stated in Subsection 2.1.3 of this Bid Proposal Form.
1.4
Award:
1.4.1
All Bid Proposals shall be subject to the provisions of Section 00 21 13 Instructions to Bidders and for purpose of award, consideration shall be given only to Bid Proposals submitted by qualified and responsible Bidders.
1.4.2
The award shall be made on the lowest Lump Sum Bid as stated in Subsection 2.1.1 of this Bid Proposal Form and any or all Supplemental Bid(s) as stated in Subsection 2.1.2 of this Bid Proposal Form, taken sequentially, as applicable, provided funds are available.
1.4.3
In the event of any discrepancy between the amount written in words and the amount written in numerical figures, the amount written in words shall be controlling.

2.0 Bid Package Requirements:

2.1
Proposed Lump Sum Base Bid, Supplemental Bids, and Addenda:
2.1.1
PROPOSED LUMP SUM BASE BID:
2.1.1.1
All Bidders: Insert the Proposed Lump Sum Base Bid in the spaces provided below.
2.1.1.2
The Proposed Lump Sum Base Bid shall be shown in both numerical figures and “printed words” dollar amount. In the event of any discrepancy the “printed” words dollar amount shall govern.
2.1.1.3
The Proposed Lump Sum Base Bid shall include all work indicated on the drawings, all work described in the specifications, all Allowances, and all Base Bid Quantities (including all Defined Unit Prices for additions and deductions) for items including, but not limited to, Earth and Rock Excavation, Miscellaneous Items, Alterations Items, Environmental Remediation, and/or Hazardous Building Materials Abatement. IMPORTANT: All Bidders must review Section 01 20 00 Contract Considerations for all Base Bid Quantities and Defined Unit Prices.
2.1.1.4
The Proposed Lump Sum Base Bid shall not include Supplemental Bids.
2.1.1.5
The Proposed Lump Sum Base Bid is:

(Place Numerical Figures in the Box Above)

Dollars

(Insert “Printed Words” Dollar Amount in the Box Above)

2.1.2
SUPPLEMENTAL BIDS:
2.1.2.1
All Bidders: If Supplemental Bids are applicable to this Project, insert the Supplemental Bids in the spaces provided below. See Section 01 23 13 Supplemental Bids in Division 01 General Requirements for information regarding Supplemental Bids.
2.1.2.2
Any Supplemental Bids listed below, if accepted by the Owner, will be taken cumulatively and in numerical order as scheduled. No Supplemental Bid will be skipped or taken out of numerical order as scheduled.

Supplemental Bid No. 1: Enter information in blue boxes below:

ADD:
$

Dollars

(Insert Numerical Figures)

(Insert “Printed Words” Dollar Amount)

Supplemental Bid No. 2: NOT APPLICABLE

ADD:
$

Dollars

(Insert Numerical Figures)

(Insert “Printed Words” Dollar Amount)

Supplemental Bid No. 3: NOT APPLICABLE

ADD:
$

Dollars

(Insert Numerical Figures)

(Insert “Printed Words” Dollar Amount)

Supplemental Bid No. 4: NOT APPLICABLE

ADD:
$

Dollars

(Insert Numerical Figures)

(Insert “Printed Words” Dollar Amount)

2.1.3
NUMBER OF ADDENDA:
2.1.3.1
All Bidders: Insert the Number of Addenda issued by the Awarding Authority in the space provided below.
2.1.3.2
Failure to acknowledge the correct number of all Addenda in the box below in this Bid Proposal Form may cause rejection of the bid.
2.1.3.3
The Bidder acknowledges that their Proposed Lump Sum Base Bid Proposal includes:

Number of Addenda. If none, enter “0”.

2.0 Bid Package Requirements (continued):

2.2
Section 00 40 14 Certificate (of Authority):
2.2.1
All Bidders for bids in excess of $50,000:

· Download Section 00 40 14 Certificate (of Authority) from CTsource for the template and instructions.

· Complete, sign, and upload Section 00 40 14 Certificate (of Authority) to CTsource prior to the date and time of the Bid Opening.

2.3
Section 00 43 16 Standard Bid Bond:
2.3.1
All Bidders for bids in excess of $50,000:

· Download Section 00 43 16 Standard Bid Bond from CTsource for the template and instructions.

· Complete, sign, notarize, and upload Section 00 43 16 Standard Bid Bond (and the associated Surety Power of Attorney) to CTsource prior to the date and time of the Bid Opening.

· Failure of a Bidder to provide the Bid Bond or Certified Check prior to the date and time of the Bid Opening in the form required by the Awarding Authority shall cause rejection of the bid and shall not be considered a minor irregularity under C.G.S. 4b-95.

2.4
Section 00 45 14 General Contractor Bidder’s Qualification Statement:
2.4.1
All Bidders:

· Download Section 00 45 14 General Contractor Bidder's Qualification Statement from CTsource for the template and instructions.

· Complete, sign, notarize, and upload Section 00 45 14 General Contractor Bidder's Qualification Statement to CTsource prior to the date and time of the Bid Opening.

· INCLUDE REQUIRED ATTACHMENTS.

· Information with regards to the General Contractor's Bidder's Qualification Statement is submitted and is made part of this Bid Proposal Form.

· Failure of a Bidder to properly complete, answer any question, provide required information, INCLUDE ATTACHMENTS, sign, notarize, and upload this form to CTsource prior to the date and time of the Bid Opening shall cause rejection of the bid and shall not be considered a minor irregularity under C.G.S. §§ 4b-92 and 4b-95.

2.5
Section 00 45 15 Objective Criteria Established for Evaluating Qualifications of Bidders:
2.5.1
· All Bidders shall comply with Section 00 45 15 Objective Criteria Established for Evaluating Qualifications of Bidders.

· Note: Individual Specification Sections may contain General Contractor and/or Subcontractor Qualification requirements that exceed those in Section 00 45 15 Objective Criteria Established for Evaluating Qualifications of Bidders.

2.0 Bid Package Requirements (continued):

2.6
DAS Prequalification Requirements for Contracts and Subcontracts exceeding $1,000,000:
2.6.1
Bidder’s Prequalification Requirements:
2.6.1.1
Pursuant to C.G.S. §§ 4a-100 and 4b-91(a)(2), as amended, except as provided in C.G.S. § 4b-91(a)(3), every contract for the construction, reconstruction, alteration, remodeling, repair or demolition of any public building or any other public work by the state that is estimated to cost more than One Million Dollars ($1,000,000) shall be awarded to the lowest responsible and qualified general bidder who is prequalified pursuant to C.G.S. § 4a-100 on the basis of competitive bids in accordance with the procedures set forth in Chapter 60 of the Connecticut General Statutes, after the Awarding Authority has invited such bids by posting notice on CTsource (the State Contracting Portal).
2.6.1.2
All Bidders submitting bids exceeding $1,000,000 must upload to the solicitation on CTsource a current copy (not expired) of their Firm’s “DAS Prequalification Certificate” and “DAS Update Statement” for the applicable Class of Work on page 1 of this Bid Proposal Form prior to the date and time of the Bid Opening.

See “Required DAS Prequalification Classification for Bidders” on page 1 of this Bid Proposal Form.

.1
See Section 00 40 15 DAS Contractor Prequalification Certification Requirements and Section 00 40 16 DAS Update Statement Requirements for instructions on downloading your Firm’s “DAS Prequalification Certificate” and “DAS Update Statement”.
.2
Failure of a Bidder to properly complete, sign and upload their Firm’s “DAS Prequalification Certificate” and “DAS Update Statement” to the solicitation on CTsource prior to the date and time of the Bid Opening or to submit to the Awarding Authority within two (2) business days after the opening of bids shall cause rejection of the bid and shall not be considered a minor irregularity under C.G.S. §§ 4b-91(d) and 4b-95.
2.6.2
Subcontractor’s Prequalification Requirements:
2.6.2.1
Pursuant to C.G.S. §§ 4a-100 and 4b-91(j), as amended, no person whose Subcontract exceeds One Million Dollars ($1,000,000) in value may perform work as a Subcontractor on a project for the construction, reconstruction, alteration, remodeling repair or demolition of any public building or any other public work by the state or a municipality, which project is estimated to cost more than $1,000,000 and is paid for, in whole or in part, with state funds, unless, at the time of bid submission, the person is prequalified in accordance with C.G.S. §§ 4a-100 and C.G.S. §4b-91(j) as amended.

“Prequalified” includes the Substantial Subcontractor's prequalification classifications, aggregate work capacity ratings and single project limits.

Failure to comply with this requirement shall cause rejection of the bid and shall not be considered a minor irregularity under C.G.S. § 4b-95.

.1
A Subcontractor whose Subcontract exceeds $1,000,000 is known as a “Substantial Subcontractor”, as defined in C.G.S. §4a-100(a)(7), as amended:

“Substantial Subcontractor” means a person who performs Work with a value in excess of $1,000,000 for a Contractor pursuant to a Contract for work for the state or a municipality which is estimated to cost more than $1,000,000.

2.6.2.2
See Subsection 2.7.2 below for Named Subcontractor requirements for Subcontracts exceeding $1,000,000.

These requirements also apply to the Bidder if the Bidder is self-performing as a Named Subcontractor.

2.6.2.3
See Subsection 2.8.3 below for SBE/MBE Subcontractor requirements for Subcontracts exceeding $1,000,000.

2.0 Bid Package Requirements (continued):

2.7
Named Subcontractor Requirements:

Attachment 5: Named Subcontractor Signed Statement:

1. In accordance with C.G.S.§§ 4a-60g(d) and 4b-95(b)(3), as amended by Public Act 25-168 and effective October 1, 2025, the Bidder shall obtain a signed statement from each Named Subcontractor listed in Table 2.7 of this Bid Proposal Form, stating that the Named Subcontractor has communicated directly with the Bidder about the work to be performed on such contract. The Bidder may use Section 00 45 20 Named Subcontractor Signature Page to obtain such signed statements. See the solicitation on CTsource for a template.

2. The Bidder must upload all signed statements to the solicitation on CTsource prior to the date and time of the Bid Opening.

3. Failure of a Bidder to upload signed statements from each Named Subcontractor listed in Table 2.7 of this Bid Proposal Form to the solicitation on CTsource prior to the date and time of the Bid Opening or to submit to the Awarding Authority within two (2) business days after the opening of bids shall cause rejection of the bid and shall not be considered a minor irregularity under C.G.S. § 4b-95.

2.7.1
Named Subcontractor Requirements for Classes of Work Exceeding One Hundred Thousand Dollars ($100,000):
2.7.1.1
Named Subcontractors Requirements:
.1
In accordance with C.G.S. 4b-93, each of the following Classes of Work that is set forth in a separate section of the specifications and designated in Table 2.7 of this Bid Proposal Form, shall be a subtrade and shall be the matter of a subcontract if, in the estimate of the Awarding Authority, the Class of Work will exceed one hundred thousand dollars ($100,000):

(1) Masonry work; (2) electrical work; (3) plumbing; (4) heating, ventilating and air conditioning (HVAC) work, and

(5) other Class(es) of Work for which the Awarding Authority deems it necessary or convenient.

NOTE: Failure to properly provide all of the required information in Table 2.7 (and Attachments 3 and 5) may cause rejection of the bid.

.2
For each Class of Work checked in Table 2.7, the Awarding Authority has estimated that the Class of Work will exceed One Hundred Thousand Dollars ($100,000).
.3
For each Class of Work checked in Table 2.7, the Bidder shall complete Table 2.7 by inserting the name(s) of each Subcontractor, including circumstances where the Subcontractor is a Small Business Enterprise (SBE) or a Minority Business Enterprise (MBE), with the Proposed Dollar Value of their Subcontract; this is known as the “Named Subcontractor”.
.4
If a Bidder intends to use one or more Subcontractors to perform any portion of the Class of Work checked in Table 2.7 and the value of the subcontract is in excess of $100,000, then the Bidder shall provide the names of all Subcontractors for such Class of Work with the dollar amount of their proposed subcontracts in the second page of Table 2.7.
.5
Post-bid, in accordance with C.G.S. § 4b-95(c),the General Contractor cannot substitute a Subcontractor for one named in the Bid Proposal Form except for “Good Cause”, as determined by the Awarding Authority.
2.7.1.2
Self-Performing Bidder Requirements:
.1
In accordance with C.G.S. § 4b-95(c), for each Class of Work checked in Table 2.7, if the Bidder does not name itself or a Subcontractor for a specified Class of Work, it shall be presumed that the Bidder intends to perform with its own employees all work in such specified Class of Work. The Bidder shall be required to perform with its own employees all of the work of the specified Class of Work.
.2
All Self-Performing Bidders shall complete Table 2.7 for each specified Class of Work they will self-perform with the Proposed Dollar Value of their Work.
.3
In the event that the Bidder names a Subcontractor to perform some, but not all, of the separate section of the specifications for a particular Class of Work, then it will be presumed, in addition, that the Bidder intends to perform the balance of the Class of Work.
.4
Pursuant to C.G.S. §§ 4b-92, 4b-95(c), and 4b-95a, in the event the Bidder either lists itself or is presumed to perform with its own employees all work in a specified class, no such sub-bid by a Bidder shall be considered unless the Bidder can show to the satisfaction of the Awarding Authority, based on objective criteria established for such purpose, that it customarily performs such subtrade work and is qualified to do the character of work required by the applicable section of the specifications.
.5
Post-bid, in accordance with C.G.S. § 4b-95, the Self-Performing Bidder cannot bring in a Subcontractor for any designated subtrade work presumed to be performed by the Bidder’s own forces, except for “Good Cause”, as determined by the Awarding Authority. Subcontracting any portion of such specified Class of Work subsequently, will be considered a violation of C.G.S. § 4b-95 and subject the Bidder to disqualification under C.G.S. § 4b-95(e).

2.0 Bid Package Requirements (continued):

2.7
Named Subcontractor Requirements (continued):
2.7.2
Named Subcontractor Prequalification Requirements for Subcontracts Exceeding One Million Dollars ($1,000,000):

Attachment 3: Named Subcontractor DAS Prequalification Certificates and Update Statements:

1. All Bidders shall upload current (not expired) “DAS Prequalification Certificates” and “DAS Update Statements” as required in Attachment 3 of this Bid Proposal Form for each Named Subcontractor in Table 2.7 with a Subcontract that exceeds $1,000,000 (including the Bidder, if the Bidder will be Self-Performing the Named Subcontractor Work and the Work exceeds $1,000,000). This information shall be considered as part of the Bid Proposal Form.

2. Failure of a Bidder to upload the Named Subcontractor’s (and Self-Performing Bidder’s, if applicable) “DAS Prequalification Certificates” and “DAS Update Statements” as required in Attachment 3 of the Bid Proposal Form to the solicitation on CTsource prior to the date and time of the Bid Opening or to submit to the Awarding Authority within two (2) business days after the opening of bids shall cause rejection of the bid and shall not be considered a minor irregularity under C.G.S. § 4b-95.

2.7.2.1
Named Subcontractor Prequalification Requirements:

For each Class of Work checked in Table 2.7 of this Bid Proposal Form, if the value of a Subcontract of a Named Subcontractor is in excess of One Million Dollars ($1,000,000), then the Named Subcontractor must be “prequalified” by DAS in the specified Class of Work at the time of bid submission, pursuant to C.G.S. §§ 4a-100 and 4b-91(j), as amended, to the extent the Class of Work for the Named Subcontractor is a Prequalification Classification.

2.7.2.2
Self-Performing Bidder Prequalification Requirements:

If a Class of Work is checked in Table 2.7 of this Bid Proposal Form and if the work to be performed by the Self-Performing Bidder is in excess of One Million Dollars ($1,000,000), then the Self-Performing Bidder must be “prequalified” by DAS in the Class of Work checked in Table 2.7 at the time of bid submission, pursuant to C.G.S. §§ 4b-91(d), 4b-92 and 4b-95(c), as amended, to the extent the Class of Work for the Named Subcontractor is a Prequalification Classification.

Table 2.7: Named Subcontractors and Classes of Work:

Electrical Work: NOT APPLICABLE

Complete Subcontractor Name:

Proposed Dollar Value of Subcontract:
$

HVAC Work: NOT APPLICABLE

Complete Subcontractor Name:

Proposed Dollar Value of Subcontract:
$

Masonry Work: Enter information in blue boxes below:

Complete Subcontractor Name:

Proposed Dollar Value of Subcontract:
$

Plumbing Work: NOT APPLICABLE

Complete Subcontractor Name:

Proposed Dollar Value of Subcontract:
$

Environmental Remediation: NOT APPLICABLE

Complete Subcontractor Name:

Proposed Dollar Value of Subcontract:
$

Hazardous Materials Abatement: NOT APPLICABLE

Complete Subcontractor Name:

Proposed Dollar Value of Subcontract:
$

2.0 Bid Package Requirements (continued):

Table 2.7 (continued):

ADDITIONAL Named Subcontractors:

INSTRUCTIONS:

Enter information for subcontract amounts above One Hundred Thousand Dollars ($100,000) in the specified classes of work below. Make copies of this page if necessary.

Electrical, HVAC, Masonry, Plumbing, Environmental Remediation, and/or Hazardous Materials Abatement:

Additional Subcontract (above $100,000):

Complete Subcontractor Name:

Check ONE box:

☐ Electrical
☐ HVAC
☐ Masonry
☐ Plumbing
☐ Environmental Remediation
☐ Hazardous Materials Abatement
Proposed Dollar Value of Subcontract:
$

Electrical, HVAC, Masonry, Plumbing, Environmental Remediation, and/or Hazardous Materials Abatement:

Complete Subcontractor Name:

Check ONE box:

☐ Electrical
☐ HVAC
☐ Masonry
☐ Plumbing
☐ Environmental Remediation
☐ Hazardous Materials Abatement
Proposed Dollar Value of Subcontract:
$

Electrical, HVAC, Masonry, Plumbing, Environmental Remediation, and/or Hazardous Materials Abatement:

Complete Subcontractor Name:

Check ONE box:

☐ Electrical
☐ HVAC
☐ Masonry
☐ Plumbing
☐ Environmental Remediation
☐ Hazardous Materials Abatement
Proposed Dollar Value of Subcontract:
$

Electrical, HVAC, Masonry, Plumbing, Environmental Remediation, and/or Hazardous Materials Abatement:

Complete Subcontractor Name:

Check ONE box:

☐ Electrical
☐ HVAC
☐ Masonry
☐ Plumbing
☐ Environmental Remediation
☐ Hazardous Materials Abatement
Proposed Dollar Value of Subcontract:
$

Electrical, HVAC, Masonry, Plumbing, Environmental Remediation, and/or Hazardous Materials Abatement:

Complete Subcontractor Name:

Check ONE box:

☐ Electrical
☐ HVAC
☐ Masonry
☐ Plumbing
☐ Environmental Remediation
☐ Hazardous Materials Abatement
Proposed Dollar Value of Subcontract:
$

2.0 Bid Package Requirements (continued):

2.8
SBE/MBE Requirements:

The Contractor who is selected to perform this State project must comply with C.G.S. §§ 4a-60, 4a-60g, and 46a-68b through 46a-68f, inclusive.

This contract requires a minimum spending allocation goal of the state-funded portion of the contract be awarded to subcontractors holding current certification from DAS under the provisions of C.G.S. § 4a-60g. The contractor must demonstrate good faith effort to meet the spending allocation goals.

2.8.1
SBE and MBE Subcontractor Participation Goals For All Projects:
2.8.1.1
All Bidders shall make good faith efforts to award not less than the percentage(s) stated on page 1 of this Section 00 41 00 Bid Proposal Form to Subcontractors who are currently DAS-certified Small Business Enterprise (SBE) and/or Minority Business Enterprise (MBE) contractors, in accordance with C.G.S.§ 4a-60g.

· The MBE participation by Subcontractors does count as part of the SBE participation.

· For CHRO contract compliance requirements, see C.G.S. §§ 4a-60, 4a-60g, 46a-68b through 46a-68f, 46a-71(d), 46a-81i(d), as amended, and the Regulations of Connecticut State Agencies (R.C.S.A.) §§ 46a-68j-21 through 43.

IMPORTANT NOTE: The SBE/MBE participation goals for Subcontractors apply even if the Bidder is a DAS-certified SBE or MBE. The Bidder cannot count their status as an SBE or MBE towards the SBE or MBE participation goals for the Project.

2.8.1.2
SBE/MBE Subcontractor Participation Schedule:

The Three (3) Apparent Lowest Bidders will receive a “Subcontractor Information Request” (“Request”) from the Awarding Authority and must submit the following items within ten (10) calendar days after receiving the Request:

· a completed copy of Section 00 73 27 SBE/MBE Subcontractor Schedule, listing the DAS-certified SBE/MBE Subcontractors to be used on this project along with the dollar amounts to be paid to each;

· a copy of the current (not expired) “DAS SBE/MBE Certificate” for each Subcontracted SBE and/or MBE firm(s) listed in the “SBE/MBE Subcontractor Schedule”; and

· a copy of the current (not expired) “DAS Prequalification Certificate” and “DAS Update Statement” for each Subcontractor listed in the “SBE/MBE Subcontractor Schedule” whose Subcontract exceeds $1,000,000 and to the extent that their Class of Work is a DAS Prequalification Classification.

2.0 Bid Package Requirements (continued):

2.9
Insurance Coverages:

The General Contractor shall be required to purchase and maintain Insurance as set forth below and any other insurance required in Section 00 72 13 General Conditions (Article 35 Contractors Insurance) and Section 00 62 16 Certificates of Insurance. All insurances are to be placed with an insurance company licensed in the State of Connecticut and with a current AM Best rating of no less than A-, VII unless otherwise acceptable in writing by the Owner. Such insurance shall be written for not less than the following limits, or greater if required by law.

2.9.1
Commercial General Liability Insurance:
|X|
The Bidder shall maintain Commercial General Liability (CGL) Insurance. Policy must be on the ISO CG 20 01 04 13 form or equivalent including coverage for Bodily Injury and Property Damage, Premises-Operations, Independent Contractors' Protective, Products-Completed Operations, Contractual Liability, Personal Injury, and Broad Form Property Damage (including coverage for Explosion, Collapse and Underground hazards, when applicable to the Work to be performed). Products-Completed Operations insurance shall be maintained for the duration of the Project and shall be maintained for a minimum of three (3) years after certification by the Owner that all Work has been completed and accepted by the Owner in accordance with the Contract Documents. CGL coverage may include Special Hazards Insurance, as described below. The Contractual Liability insurance shall include coverage sufficient to meet the indemnification obligations in General Conditions Article 35.

NOTE: All selected firms are required to provide an endorsement to the CGL insurance stating that the State of Connecticut, the Awarding Authority, and their respective officers, agents, and employees shall be named as an Additional Insured on a primary and noncontributory basis. Please be advised that a blanket endorsement may not be acceptable. Only the following ISO endorsements or their equivalents are acceptable: CG 20 10 04 13 when used with CG 20 38 04 13; CG 20 37 07 04 when used with CG 20 40 12 19.

l
Each Occurrence:
$
1,000,000.00
l
General Aggregate (Per Project Location):
$
2,000,000.00
2.9.2
Special Hazards Insurance:
|_|
None is Required.
|_|
The Bidder shall maintain Special Hazards Insurance, including coverage for Explosion, Collapse and Underground damage (X-C-U).
l
Each Occurrence (minimum):
$
1,000,000.00
2.9.3
Owner’s and Contractor’s Protective Liability Insurance:
|X|
The Bidder shall maintain Owner’s and Contractor’s Protective Liability Insurance. This coverage shall be for and in the name of the State of Connecticut.
l
Bodily Injury or Death (Per Occurrence) Total:
$
1,000,000.00
l
Property Damages Total (Aggregate):
$
2,000,000.00
2.9.4
Automobile Liability Insurance:
|X|
The Bidder shall maintain Automobile Liability Insurance for the operation of all motor vehicles including those owned, non-owned and hired or used in connection with the Contract. Should the Bidder not own any automobiles, the automobile & liability requirement shall be amended to allow the Bidder to maintain only hired and non-owned liability coverage.
l
Combined Single Limit (Each Occurrence):
$
1,000,000.00
2.9.5
Umbrella Liability Insurance:
|X|
The Bidder shall maintain Umbrella Liability Insurance. The Bidder shall provide an endorsement to the Umbrella Liability policy stating that the State of Connecticut is an Additional Insured, and the Umbrella Liability policy shall provide continuous coverage to the underlying policies on a complete "Follow-Form" basis.
Contract Value:
Umbrella Limit
l
$1.00
to
$500,000.00
$
1,000,000.00
l
$500,000.01
to
$1,000,000.00
$
2,000,000.00
l
$1,000,000.01
to
$10,000,000
$
5,000,000.00
l
$10,000,000.01
to
$30,000,000
$
10,000,000.00
l
$30,000,000.01
to
$80,000,000
$
15,000,000.00
l
$80,000,000.01
to
$150,000,000
$
20,000,000.00
l
$150,000,000.01
to
$300,000,000
$
25,000,000.00

2.0 Bid Package Requirements (continued):

2.9
Insurance Coverages: (continued)
2.9.6
Workers Compensation and Employers’ Liability Insurance:
|X|
The Bidder shall maintain Workers Compensation and Employers’ Liability Insurance. When Work is on or contiguous to navigable bodies of waterways and ways adjoining, the Contractor shall include the Federal Act endorsement for the U.S. Longshoremen’s and Harbor Workers Act.
Part 1: Workers' Compensation:
Statutory Limits

Part 2: Employers' Liability:

l
Bodily Injury with Accident (Each Accident):
$
100,000.00
l
Bodily Injury by Disease (Each Employee):
$
100,000.00
l
Bodily Injury by Disease (Policy Limit):
$
500,000.00
2.9.7
Builder’s Risk Insurance:
|_|
None is Required.
|X|
The Bidder shall maintain Builder's Risk Insurance providing coverage for the entire Work at the project site, portions of the Work located away from the site but intended for use at the site, and portions of the Work in transit. Coverage shall be written on an All-Risk, Replacement Cost, and completed Value Form basis in an amount at least equal to the projected completed value of the Work. Prior to the Owner's issuance of a Notice to Proceed, the Contractor shall provide coverage for the entire Work in an amount equal to the total contract amount and any additional modifications. The Owner and its officers, agents and employees shall be listed as Loss Payee subject to the prior review of the Owner, and not as an Additional Insured for these coverages. The Builder’s Risk Insurance policy shall state it is for the benefit of and payable to the State of Connecticut. The Period of Coverage shall be the number of Calendar Days from Construction Start Date to Substantial Completion as stated in the Bid Proposal Form of the Project Manual, plus ninety (90) Calendar Days to Acceptance of the Work. The Contractor must obtain the permission of the Owner to adjust any of the requirements in this section. The Contractor shall provide Owner with certificates of insurance which show that Contractor is so insured, and Owner shall keep them on file. The insured's certificates of insurance shall include a statement as to the indemnification of Owner by the Contractor and the insurer of the Contractor. Such certificates shall be updated and provided to Owner on an annual basis.
l
Builders Risk Insurance: Deductible of $25,000
Contract Value Less Than or Equal to $5 Million:
Contract Value Greater Than $5 Million:
l
Policy Limit:
$
Value of Project
$
Value of Project
l
Limits for Windstorm, Rain, Fire, Collapse, Earth movement, Lightning, Hail, Arson, and Acts of Sabotage.
$
Value of Project
$
Value of Project
l
Limits for Soft Costs
$
Value of Project
$
5,000,000.00
l
Limits for Flood
$
Value of Project
$
10,000,000.00
l
Limits of Earthquake
$
Value of Project
$
10,000,000.00
l
Toppling of Crane
$
1,000,000.00
$
1,000,000.00
l
Theft or Destruction of Materials at Job Site
$
500,000.00
$
500,000.00
l
Mold, Mildew, Fungus, Dry Rot, Wet Rot
$
500,000.00
$
500,000.00
l
Loss of Use
$
Value of Project
$
5,000,000.00
l
Landscaping
$
100,000.00
$
100,000.00
l
Storage
$
500,000.00
$
500,000.00
l
Business Interruption and Extra Expense
$
Value of Project
$
5,000,000.00
l
Valuable Paper and Records
$
100,000.00
$
100,000.00
l
Inland Marine/Transit
$
500,000.00
$
500,000.00
l
Terrorism
$
Value of Project
$
Value of Project
2.9.8
Inland Marine/Transit Insurance (Transportation Insurance):
|_|
None is Required.
|_|
With respect to property with values in excess of $100,000 which is rigged, hauled or situated at the site pending installation, the Bidder shall maintain Inland Marine/Transit Insurance (Transportation Insurance) provided the coverage is not afforded by a Builder’s Risk policy. The Inland Marine/Transit Insurance policy shall endorse the State of Connecticut as a Loss Payee and the policy shall state it is for the benefit of and payable to the State of Connecticut.
l
Each Occurrence:
$
100,000.00
l
Annual Aggregate:
$
100,000.00

2.0 Bid Package Requirements (continued):

2.9
Insurance Coverages: (continued)
2.9.9
Contractor’s Pollution Liability Insurance (including Errors and Omissions):
|_|
None is Required.
|_|
For losses caused by pollution conditions that arise from the operations of the Contractor as described in the Scope of Services section of this Contract. The policy shall also provide for complete professional service coverage, including coverage for pollution liability that is the result of a breach of professional duties. The policy shall provide for protection against claims for third-party bodily injury, property damage, or environmental damage caused by pollution conditions including but not limited to asbestos containing material, lead and mold resulting from the activities for which the Contractor is legally liable.
l
Each Occurrence:
$
1,000,000.00
l
General Aggregate:
$
2,000,000.00
2.9.10
Subcontractors:
|X|
Contractors’ certificate(s) shall include all subcontractors as additional insureds under its policies or Contractor shall furnish to the State separate certificates and endorsements for each subcontractor. All coverage for subcontractors shall be subject to the minimum requirements identified above.
2.10
Section 00 73 63 Connecticut Department of Correction (DOC) Security Requirements:
2.10.1
All Bidders attending a Pre-Bid Meeting at a DOC Facility shall read Section 00 73 63 CT DOC Security Requirements for Contract Forces on DOC Facilities, complete and submit the DOC “Security Background Questionnaire” as directed, and obtain approval, prior to the Pre-Bid Meeting, otherwise admission to the Pre-Bid Meeting will be denied. To find and download a copy of the Security Background Questionnaire, go to the DOC website (www.ct.gov/doc), scroll down to “Publications” and click on “Forms” then “Security Background Questionnaire”. It is recommended that the approved form be brought as evidence of approval to attend the Pre-Bid Meeting.

3.0 Bid Proposal Acknowledgements:

The Bidder acknowledges and agrees to the following:

3.1
To Properly Complete and Upload to CTsource Section 00 41 00 Bid Proposal Form (all pages, including Attachments 1, 2, 3, 4 and 5) and all other Bid Documents prior to the Date and Time of the Bid Opening:
3.1.1
The Bidder acknowledges and agrees to properly complete and electronically upload to CTsource all pages of the Bid Proposal Form (including Attachments 1, 2, 3, 4 and 5), and all other Bid Documents as directed in this Section 00 41 00 Bid Proposal Form, Section 00 11 16 Invitation to Bid, Section 00 21 13 Instructions to Bidders, and Section 00 41 10 Bid Package Submittal Requirements.
3.1.2
The State may waive minor irregularities which it considers in the best interest of the State and, when applicable, are corrected by the Bidder within seven (7) Calendar Days after the date of the Bid Opening. Failure to properly complete, sign and upload any of the items marked with an asterisk (*) in Section 00 41 10 Bid Package Submittal Requirements shall cause rejection of the bid and shall not be considered a minor irregularity under C.G.S. § 4b-95.
3.1.3
If there are any delays in the receipt of other documents, then the Bid shall remain valid for the same additional number of days. For example, if the documents are submitted four (4) Calendar Days later; then the bid shall remain valid for ninety-four (94) Calendar Days.
3.1.4
Failure to submit the documents before the stated deadline may result in rejection of the bid at the sole discretion of the Awarding Authority.
3.2
To Hold Bid Price:

The Bidder acknowledges and agrees to hold the Proposed Lump Sum Base Bid in Subsection 2.1.1 of this Bid Proposal Form for ninety (90) Calendar Days after the date of the Bid Opening and any extensions caused by the Bidder’s delays in required submissions. The Bidder and the State may mutually agree to extend this period. The agreement to extend the ninety (90) Calendar Day period may occur after the expiration of the original ninety (90) Calendar Day period.

3.0 Bid Proposal Acknowledgements (continued):

3.3
To Use and Accept Allowances:

When applicable to this Project, the Bidder acknowledges and agrees to accept and use the Allowances as shown in Section 01 20 00 Contract Considerations of Division 01 General Requirements as part of the Proposed Lump Sum Base Bid listed in Subsection 2.1.1 of this Bid Proposal Form.

3.4
To Use and Accept the Following Defined Unit Prices and Supplemental Bids:
3.4.1
Defined Unit Prices:

When applicable to this Project, the Bidder acknowledges and agrees to accept and use the Defined Unit Prices, Add Unit Prices, and Deduct Unit Prices as shown in Section 01 20 00 Contract Considerations of Division 01 General Requirements in evaluating either additions to or deductions from the Work.

3.4.2
Supplemental Bid(s):

When applicable to this Project and if accepted by the Owner, the Bidder acknowledges and agrees to provide all labor, material and equipment to complete the Work in accordance with the Supplemental Bid(s) described in Section 01 23 13 Supplemental Bids of Division 01 General Requirements and provided by the Bidder in Subsection 2.1.2 of this Bid Proposal Form.

3.5
To Use the Named Subcontractors Listed in Table 2.7 and To Include Attachments 3 & 5:
3.5.1
In accordance with C.G.S.§§ 4b-95(b)(3) and 4b-96, as amended, the Bidder agrees that each of the Named Subcontractors listed in Table 2.7 of this Bid Proposal Form will be used for the Class of Work indicated, for the Proposed Total Subcontract Value dollar amount stated, unless a substitution is permitted by the Awarding Authority.
3.5.2
ATTACHMENT 3:

The Bidder agrees that for each of the Named Subcontractor(s) listed in Table 2.7 with Subcontracts greater than One Million Dollars ($1,000,000), the Bidder shall upload to the solicitation on CTsource DAS Prequalification Certificate(s) and DAS Update Statement(s) for each such Named Subcontractor (including the Bidder, if the Bidder intends to self-perform). The Bidder acknowledges that each such Named Subcontractors must be “prequalified” by DAS in the Class of Work specified in Table 2.7 of this Bid Proposal Form at the time of bid submission, pursuant to C.G.S. §§ 4a-100 and 4b-91(j), as amended, to the extent the Class of Work for the Named Subcontractor is a Prequalification Classification.

3.5.3
ATTACHMENT 5:

In accordance with C.G.S.§§ 4a-60g(d) and 4b-95(b)(3), as amended by Public Act 25-168 and effective October 1, 2025, the Bidder agrees to obtain and upload to the solicitation on CTsource a signed statement from each Named Subcontractor listed in Table 2.7 of this Bid Proposal Form, stating that the Named Subcontractor has communicated directly with the Bidder about the work to be performed on such contract.

The Bidder may use Section 00 45 20 Named Subcontractor Signature Page to obtain such signed statements. See the solicitation on CTsource for a template.

3.6
To Make Good Faith Efforts to Employ MBEs:

In accordance with C.G.S. § 4b-95(b)(2), the Bidder agrees and warrants that the Bidder has made good faith efforts to employ Minority Business Enterprises (MBEs) as Subcontractors and Suppliers of materials under such Contract.

3.7
To Submit the Standard Bid Bond or Certified Check (if required):

The Bidder acknowledges and agrees to submit Section 00 43 16 Standard Bid Bond completed for either the Standard Bid Bond or Certified Check prior to the due date and time of the Bid Opening (if required). Download Section 00 43 16 Standard Bid Bond from the solicitation on CTsource for the template and instructions.

3.8
To Accept the Current Prevailing Wage Rate Schedule:
3.8.1
The U. S. Secretary of Labor's latest decision and the State of Connecticut Department of Labor (DOL) Prevailing Wage Rate Schedule are all incorporated in the documents. The higher rate (Federal or State) for any given occupation shall prevail.
3.8.2
For Prevailing Wage Projects, at the time of bidding, the Bidder agrees to accept the current Prevailing Wage Rate Schedule, as well as the annual adjustment to the prevailing wage rate that is in effect each July 1st, as provided by DOL. See Section 00 73 44 Prevailing Wage Rates/Contractor’s Wage Certification/Payroll Certification.

3.0 Bid Proposal Acknowledgements (continued):

3.8
To Accept the Current Prevailing Wage Rate Schedule (continued):
3.8.3
For Prevailing Wage Projects on and after July 1, 2025, in accordance with C.G.S. § 31-53 as amended by Public Act 25-168, the Bidder agrees to include the C.G.S. § 31-53 prevailing wage provision in each contract, including contracts for off-site custom fabrication. For purposes of this section, "off-site custom fabrication" means the fabrication of systems that are fabricated at a site located within the state other than the location of a public works project, but are fabricated specifically for such public works project, including plumbing systems, heating systems, cooling systems, pipefitting systems, ventilation systems or exhaust duct systems. "Off-site custom fabrication" does not include components or materials that are stock shelf items or readily available.
3.8.4
Annual adjustments of prevailing wage rates will not be considered a matter for a contract amendment with the Awarding Authority.
3.9
To Comply with CHRO Requirements:

In accordance with C.G.S. § 4b-95(b)(2), the Apparent Low Bidder agrees and warrants to provide the Commission on Human Rights and Opportunities (CHRO) with such information as is requested by the Commission concerning their employment practices and procedures as they relate to the current provisions of the Connecticut General Statutes governing Contract requirements within fifteen (15) calendar days after receipt of the “Letter of Intent” from the Awarding Authority.

3.10
To Ensure Executive Order No. 11246 for Equal Employment Opportunity & Non-Segregated Facilities Has Been Met:

The Apparent Low Bidder acknowledges and agrees to ensure that Executive Order No. 11246 for Equal Employment Opportunity & Non-Segregated Facilities has been met for their firm and their Subcontractors.

The Apparent Low Bidder also agrees to certify (if required) to the compliance of non-segregated facilities.

3.11
To Obtain and Maintain Required Insurance Coverages:

The Bidder acknowledges and agrees to obtain and maintain the required Insurance Coverages and submit the Firm’s “Certificate of Liability Insurance Acord® form” within fifteen (15) calendar days after receipt of the “Letter of Intent” from the Awarding Authority, as discussed in Section 00 62 16 Certificate of Insurance and Article 35, “Contractors Insurance” in Section 00 73 13 General Conditions.

3.12
To Comply With Security Requirements for CT Department of Correction (DOC) Facilities:

When…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .