Notice text

3 versions

Update #3 · Latest ·

Bid Tabs

Update #2 ·

Strawberry Sheep Creek connector is a 31.9 mile route that connects US-6 to US-40 through the Uinta-Wasatch-Cache National Forest (USFS) in both, Utah and Wasatch Counties, and includes Sheep Creek – Rays Valley Road (FR70051), Unicorn Ridge – Indian Creek Road (FR70042), and West Side Strawberry Road (FR70131).

 

The base Schedule A consists of road widening, reconstruction, asphalt surfacing, drainage, and safety improvements to the unpaved 12.24 miles of Unicorn Ridge-Indian Creek Road (FR70042) between the intersections with Sheep Creek – Rays Valley Road (FR70051) and West Side Strawberry Road (FR70131). Major work elements for Schedule A include widening the roadway to a consistent width and vertical and horizontal alignment changes to correct roadway geometry and improve safety.  Construction will generally include cut slopes, embankment, rockery/rock embankment slope treatments, reinforced soil slopes, aggregate base course, and paving. Improvements include clearing roadside vegetation, stabilization of shoulders, drainage improvements, pavement markings, and updating signing.  Select pullouts and access road intersections will also be rehabilitated.   

 

Significant Quantities of Schedule A:

 

 

Item

 

Unit

Estimated Quantity

Clearing and Grubbing

ACRE

90

Embankment

CUYD

23,000

Reinforcement Geosynthetic

SQYD

34,000

RipRap

CUYD

540

Rock Embankment

CUYD

2,750

Rockery

SQFT

8,460

Aggregate Base

TON

58,000

Hot-Asphalt Concrete Pavement

TON

36,000

Culverts

LNFT

3,700

Structural Plate Culvert

LNFT

125

Concrete Curb

LNFT

5,100

Seeding and Mulching

ACRE

50

 

Option X consists of 7.00 miles of pavement preservation of Sheep Creek – Rays Valley Road (FR70051) from US-6 to the intersection with Unicorn Ridge – Indian Creek Road (FR70042) (start of Schedule A). Construction will generally include ditch reconditioning, patching, crack sealing, and chip sealing the existing pavement surface. Additional improvements include pavement markings and updating signing. 

 

Significant Quantities of Option X:

 

 

Item

 

Unit

Estimated Quantity

Ditch Reconditioning

Mile

6

Subexcavation

CUYD

300

Pavement Patching

SQYD

4,500

Emulsified Asphalt

TON

175

Chip Seal

SQYD

101,600

 

Option Y consists of road rehabilitation of West Side Strawberry Road (FR70131) from the intersection with Unicorn Ridge – Indian Creek Road (FR70042) (end of Schedule A) extending 3.75 miles towards the North. Construction will generally include ditch reconditioning, partial pulverizing and asphalt overlay, and chip seal.  Additional improvements include pavement markings and updating signing. 

 

Significant Quantities of Option Y:

 

 

Item

 

Unit

Estimated Quantity

Subexcavation

CUYD

800

Full Depth Reclamation

SQYD

28,900

Hot-Asphalt Concrete Pavement

TON

5,400

Emulsified Asphalt

TON

45

Chip Seal

SQYD

26,100

 

 

 

MISCELLANEOUS:  Road closures to public traffic are allowed in Schedule A, Unicorn Ridge-Indian Creek Road (FR70042), during a large portion of the construction activities.  Access through the closure to USFS permit holders will be required at all times.   

 

Due to weather restrictions, on-site construction typically cannot occur until May with a winter shutdown required between 2020 and 2021 construction seasons.

 

 

Anticipated Schedule:

 

Advertise: September 2019

Award:  November 2019

Notice to Proceed:  May 2020

 

The anticipated cost range is between $15 million and $20 million.

 

This solicitation will be a full and open competition. 

Update #1 ·

THIS IS NOT AN INVITATION TO BID, PLANS AND SPECIFICATIONS ARE CURRENTLY NOT AVAILABLE.

 

Strawberry Sheep Creek connector is a 31.9 mile route that connects US-6 to US-40 through the Uinta-Wasatch-Cache National Forest (USFS) in both, Utah and Wasatch Counties, and includes Sheep Creek – Rays Valley Road (FR70051), Unicorn Ridge – Indian Creek Road (FR70042), and West Side Strawberry Road (FR70131).

 

The base Schedule A consists of road widening, reconstruction, asphalt surfacing, drainage, and safety improvements to the unpaved 12.24 miles of Unicorn Ridge-Indian Creek Road (FR70042) between the intersections with Sheep Creek – Rays Valley Road (FR70051) and West Side Strawberry Road (FR70131). Major work elements for Schedule A include widening the roadway to a consistent width and vertical and horizontal alignment changes to correct roadway geometry and improve safety.  Construction will generally include cut slopes, embankment, rockery/rock embankment slope treatments, reinforced soil slopes, aggregate base course, and paving. Improvements include clearing roadside vegetation, stabilization of shoulders, drainage improvements, pavement markings, and updating signing.  Select pullouts and access road intersections will also be rehabilitated.   

 

Significant Quantities of Schedule A:

 

 

Item

 

Unit

Estimated Quantity

Clearing and Grubbing

ACRE

90

Embankment

CUYD

23,000

Reinforcement Geosynthetic

SQYD

34,000

RipRap

CUYD

540

Rock Embankment

CUYD

2,750

Rockery

SQFT

8,460

Aggregate Base

TON

58,000

Hot-Asphalt Concrete Pavement

TON

36,000

Culverts

LNFT

3,700

Structural Plate Culvert

LNFT

125

Concrete Curb

LNFT

5,100

Seeding and Mulching

ACRE

50

 

Option X consists of 7.00 miles of pavement preservation of Sheep Creek – Rays Valley Road (FR70051) from US-6 to the intersection with Unicorn Ridge – Indian Creek Road (FR70042) (start of Schedule A). Construction will generally include ditch reconditioning, patching, crack sealing, and chip sealing the existing pavement surface. Additional improvements include pavement markings and updating signing. 

 

Significant Quantities of Option X:

 

 

Item

 

Unit

Estimated Quantity

Ditch Reconditioning

Mile

6

Subexcavation

CUYD

300

Pavement Patching

SQYD

4,500

Emulsified Asphalt

TON

175

Chip Seal

SQYD

101,600

 

Option Y consists of road rehabilitation of West Side Strawberry Road (FR70131) from the intersection with Unicorn Ridge – Indian Creek Road (FR70042) (end of Schedule A) extending 3.75 miles towards the North. Construction will generally include ditch reconditioning, partial pulverizing and asphalt overlay, and chip seal.  Additional improvements include pavement markings and updating signing. 

 

Significant Quantities of Option Y:

 

 

Item

 

Unit

Estimated Quantity

Subexcavation

CUYD

800

Full Depth Reclamation

SQYD

28,900

Hot-Asphalt Concrete Pavement

TON

5,400

Emulsified Asphalt

TON

45

Chip Seal

SQYD

26,100

 

 

 

MISCELLANEOUS:  Road closures to public traffic are allowed in Schedule A, Unicorn Ridge-Indian Creek Road (FR70042), during a large portion of the construction activities.  Access through the closure to USFS permit holders will be required at all times.   

 

Due to weather restrictions, on-site construction typically cannot occur until May with a winter shutdown required between 2020 and 2021 construction seasons.

 

 

Anticipated Schedule:

 

Advertise: September 2019

Award:  November 2019

Notice to Proceed:  May 2020

 

The anticipated cost range is between $15 million and $20 million.

 

This solicitation will be a full and open competition. 

Files

Show all 23

Notice history

Notice Type Posted
UT FLAP 70131(1), Strawberry Sheep Creek Award Award Notice
UT FLAP 70131(1), Strawberry Sheep Creek Latest solicitation Solicitation
This notice Original Solicitation

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity