About this opportunity
This solicitation seeks proposals to replace two generator switchgear lineups at the Jones Bluff Powerhouse in Selma, Alabama. The Department of the Army Corps of Engineers Engineering District Mobile will procure the removal of existing 15kV switchgear and installation of new government furnished equipment. The contractor must coordinate plenum system fabrication, replace cables and conductors, modify bus equipment, install surge arrestors and capacitors, perform testing, and create as-built drawings. Proposals are due by various dates outlined in amendments, with the latest due date of August 13, 2019. Evaluation will consider technical approach, past performance, and price.
This procurement is set aside solely for small business concerns under NAICS code 335313, with a size standard of 500 employees. The place of performance is the Jones Bluff Powerhouse located at 1627 W Highland Ave, Selma, AL 36701. Key details include removing and replacing two generator switchgear lineups by specified dates in 2019, with quantities of specific equipment replacements outlined in the technical specifications.
Notice text
The solicitation package will be available for download on or about 22 May 2019. The scope of
work consists of:
a. Remove existing 15KV generator switchgear lineups for units 1-2 and station service breaker no. 1, and for units 3-4 and station service breaker no. 2.
b. Install two government furnished new 15KV generator switchgear lineups. One containing generator breakers for units 1 and 2 (breakers 710 & 720) and station service breaker no. 1 (breaker 812), and the
second containing generator breakers for units 3 and 4 (breakers 730 & 740) and station service no. 2 (breaker 822).
c. Replace all the cables from removed equipment and install new conductors to new equipment.
d. Replace, as necessary, the existing non-segregated bus from the generators and GSU in order to connect to the new 15KV switchgear, to include all connectors and fasteners.
e. Coordinate with the switchgear manufacturer to Design and Fabricate,as necessary, and Install balance of the plenum system for each of the new switchgear to vent the exhaust to a safe area.
f. Replace the existing surge arrestors and capacitors in the new government furnished equipment with new surge arrestors and capacitors.
g. Perform necessary commissioning and testing.
h. Remove a section of the synchronous condensing pipe and re-install the pipe with flanges.
i. Remove the switchgear room door and associated hardware and frame to facilitate installation of the switchgear. Contractor shall retain doors for re-use for an in-kind restoration of the entryways to
original condition.
The contractor shall be responsible for field verifying existing drawings and creating as-built
drawings.
Work will be performed at Jones Bluff Powerhouse, Selma, AL.
This procurement is 100% set aside for small business concerns. The NAICS code is 335313.
The size standard for which is a concern, including its affiliates whose number of employees does not exceed 335313.
The solicitation will not be provided in a printed paper format however, the Government reserves the right to revert to paper medium when it is determined to be in the Government's best interest.
Therefore, it is the offeror's responsibility to check the website for solicitation posting and any
changes to this solicitation. Those registering are responsible for the accuracy of the information
provided.
Files
Show all 12
On GovTribe
Work this opportunity
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity