SEE ATTACHED DOCUMENTS

3/24/2020- RFQ response date is being extended to 4/3/2020 due to waiting on answers to request for information from the project owners.

4/1/2020- The purpose for this ammendment is to post the answers to the vendors' request for information and to post the revised sketches. Also, the RFQ due date will be extended to 4/6/2020 in order to give vendors adequate time to adjust their quotes based on the information posted. 

4/2/2020- The purpose for this ammendment is to post a revised copy of the answers to the request for information that was posted on 4/1/2020.

4/2/2020- The purpose for this ammendment is to extend the RFQ due date to 4/12/2020, 12pm inorder to give vendors adequate time to finalize their quotes based on the answers to RFIs.

4/2/2020- The purpose for this ammendment is to extend the RFQ due date to 4/13/2020, 12pm inorder to give vendors adequate time to finalize their quotes based on the answers to RFIs.

4/2/2020- The purpose for this ammendment is to clarify the basket is not part of the scope. 

4/7/2020- The purpose for this ammendment is to provide a clarification answer. 

4.8.2020- The purpose for this ammendment is to provide a clarification answer. 

Update #8 ·

SEE ATTACHED DOCUMENTS

3/24/2020- RFQ response date is being extended to 4/3/2020 due to waiting on answers to request for information from the project owners.

4/1/2020- The purpose for this ammendment is to post the answers to the vendors' request for information and to post the revised sketches. Also, the RFQ due date will be extended to 4/6/2020 in order to give vendors adequate time to adjust their quotes based on the information posted. 

4/2/2020- The purpose for this ammendment is to post a revised copy of the answers to the request for information that was posted on 4/1/2020.

4/2/2020- The purpose for this ammendment is to extend the RFQ due date to 4/12/2020, 12pm inorder to give vendors adequate time to finalize their quotes based on the answers to RFIs.

4/2/2020- The purpose for this ammendment is to extend the RFQ due date to 4/13/2020, 12pm inorder to give vendors adequate time to finalize their quotes based on the answers to RFIs.

4/2/2020- The purpose for this ammendment is to clarify the basket is not part of the scope. 

4/7/2020- The purpose for this ammendment is to provide a clarification answer. 

Update #7 ·

SEE ATTACHED DOCUMENTS

3/24/2020- RFQ response date is being extended to 4/3/2020 due to waiting on answers to request for information from the project owners.

4/1/2020- The purpose for this ammendment is to post the answers to the vendors' request for information and to post the revised sketches. Also, the RFQ due date will be extended to 4/6/2020 in order to give vendors adequate time to adjust their quotes based on the information posted. 

4/2/2020- The purpose for this ammendment is to post a revised copy of the answers to the request for information that was posted on 4/1/2020.

4/2/2020- The purpose for this ammendment is to extend the RFQ due date to 4/12/2020, 12pm inorder to give vendors adequate time to finalize their quotes based on the answers to RFIs.

4/2/2020- The purpose for this ammendment is to extend the RFQ due date to 4/13/2020, 12pm inorder to give vendors adequate time to finalize their quotes based on the answers to RFIs.

4/2/2020- The purpose for this ammendment is to clarify the basket is not part of the scope. 

Update #6 ·

SEE ATTACHED DOCUMENTS

3/24/2020- RFQ response date is being extended to 4/3/2020 due to waiting on answers to request for information from the project owners.

4/1/2020- The purpose for this ammendment is to post the answers to the vendors' request for information and to post the revised sketches. Also, the RFQ due date will be extended to 4/6/2020 in order to give vendors adequate time to adjust their quotes based on the information posted. 

4/2/2020- The purpose for this ammendment is to post a revised copy of the answers to the request for information that was posted on 4/1/2020.

4/2/2020- The purpose for this ammendment is to extend the RFQ due date to 4/12/2020, 12pm inorder to give vendors adequate time to finalize their quotes based on the answers to RFIs.

4/2/2020- The purpose for this ammendment is to extend the RFQ due date to 4/13/2020, 12pm inorder to give vendors adequate time to finalize their quotes based on the answers to RFIs.

Update #5 ·

SEE ATTACHED DOCUMENTS

3/24/2020- RFQ response date is being extended to 4/3/2020 due to waiting on answers to request for information from the project owners.

4/1/2020- The purpose for this ammendment is to post the answers to the vendors' request for information and to post the revised sketches. Also, the RFQ due date will be extended to 4/6/2020 in order to give vendors adequate time to adjust their quotes based on the information posted. 

4/2/2020- The purpose for this ammendment is to post a revised copy of the answers to the request for information that was posted on 4/1/2020.

4/2/2020- The purpose for this ammendment is to extend the RFQ due date to 4/12/2020, 12pm inorder to give vendors adequate time to finalize their quotes based on the answers to RFIs.

Update #4 ·

SEE ATTACHED DOCUMENTS

3/24/2020- RFQ response date is being extended to 4/3/2020 due to waiting on answers to request for information from the project owners.

4/1/2020- The purpose for this ammendment is to post the answers to the vendors' request for information and to post the revised sketches. Also, the RFQ due date will be extended to 4/6/2020 in order to give vendors adequate time to adjust their quotes based on the information posted. 

4/2/2020- The purpose for this ammendment is to post a revised copy of the answers to the request for information that was posted on 4/1/2020.

Update #3 ·

SEE ATTACHED DOCUMENTS

3/24/2020- RFQ response date is being extended to 4/3/2020 due to waiting on answers to request for information from the project owners.

4/1/2020- The purpose for this ammendment is to post the answers to the vendors' request for information and to post the revised sketches. Also, the RFQ due date will be extended to 4/6/2020 in order to give vendors adequate time to adjust their quotes based on the information posted. 

Update #2 ·

SEE ATTACHED DOCUMENTS

3/24/2020- RFQ response date is being extended to 4/3/2020 due to waiting on answers to request for information from the project owners.

Update #1 ·

SEE ATTACHED DOCUMENTS

Files

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity