Final-15027-20-001A Supply New Code Stamped Pressure Vessel for the W19 Dryer SOW.pdf

PDF 338 KB Posted

Attached to
PRESSURE VESSEL
Solicitation number
FA9101-20-Q-0026
Issued by

View the file

Other files

File Type Posted
4.8.2020 Ammendment.docx DOCX document
4.7.2020 RFI Clarification.docx DOCX document
4.2.2020-FA9101-20-Q-0026- ANSWER TO CLARIFICATION RFIs.docx DOCX document
FA9101-20-Q-0026 Final answers to RFI.2.docx DOCX document
VCT01619.01 W19 Dryer_Page_2.jpg JPG image
FA9101-20-Q-0026 Final answers to RFI.docx DOCX document
VCT01619.01 W19 Dryer_Page_1.jpg JPG image
VCT01619.01 W19 Dryer_Page_3.jpg JPG image
FA9101-20-Q-0026 Pressure Vessel Combined Synopsis Solicitation.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

15027-20-001A

SOW NO. 15027-20-001A

5 March 2020

STATEMENT OF WORK

SUPPLY NEW CODE STAMPED PRESSURE VESSEL

FOR THE W19 DRYER

ARNOLD ENGINEERING DEVELOPMENT COMPLEX

ARNOLD AIR FORCE BASE, TENNESSEE 37389-9998

NOT SENSITIVE

IRA-4990

IRA-4990 Page - 1

Table of Contents

1. SCOPE

1.1 Scope

1.2 Background

2. APPLICABLE DOCUMENTS

2.1 Government Documents

2.2 Non-Government Documents

3. REQUIREMENTS

Appendix A - Sketch SKVU6479 W19 Dryer Vessel

Appendix B - Submittal Procedure

Appendix C - Nozzle Loads

IRA-4990 Page - 2

1. SCOPE

1.1 Scope: Work consists of providing a new ASME code stamped pressure vessel for the W19 Dryer to replace the existing vessel.

1.2 Background: The existing non-stamped vessel is of multi-layered type with an 8” 1500# Weld Neck Flange at the top and a 6” 1500# Weld Neck Flange at the bottom. An ASME code stamped vessel is required to replace the vessel.

2. APPLICABLE DOCUMENTS

2.1 Government Documents:

A. NAS Sketch SKVU6479 W19 Dryer Vessel (Appendix A)

2.2 Non-Government Documents:

A. American Society of Mechanical Engineers:

1. ASME SEC VIII-1-19 Boiler and Pressure Vessel Code – Pressure Vessels.

2. ASME SEC IX-19 Qualification Standard for Welding and Brazing Procedures, Welders, Brazers, and Welding and Brazing Operators Welding and Brazing Qualifications.

B. Other referenced documents shall be the latest edition at the time of the contract award.

3. REQUIREMENTS

3.1 Vessel design, construction, fabrication, inspection and testing shall be in accordance with ASME BPVC Section VIII Division 1, ASME BPVC Section IX.

3.2 Dimensional requirements for the vessel shall be in accordance with NAS Sketch SKVU6479 in Appendix A.

3.3 Vessel shall have an 8” 1500# Weld Neck Ring Joint Flange at the top end and a 6” 1500# Weld Neck Ring Joint Flange on the bottom end. Flanges shall conform to ASME B16.5, except Long Weld Neck flanges and Studding Outlets suitable for mating to ASME B16.5 are acceptable. Nozzles shall not project beyond the vessel inside surface, and the use of “paste-on” type neck-to-head connections are prohibited for the 6” NPS and 8” NPS nozzles. In addition to pressure loads, nozzles shall be designed for the piping mechanical loads defined in Appendix C, and the local head stresses from these loads shall be evaluated using WRC 107 or equivalent. The local head stresses shall be maintained within the limits defined by published pressure vessel engineering practices that are consistent with code

IRA-4990 Page - 3 requirements.

3.4 The total length from top flange face to bottom flange face of the vessel shall be 23 feet, 7 inches plus or minus one inch, unless a greater distance is required to meet the volume requirement in paragraph 3.5.

3.5 The total volume shall be a minimum of 300 ft3.

3.6 The vessel shall come with required lifting lugs or other components for installation and removal. Lifting components will be required to lift the vessel from horizontal to vertical position for installation and vice versa for removal, with a 100% impact factor.

3.7 Material shall be carbon or low alloy steel.

3.8 The vessel shall be mono-wall construction.

3.9 The vessel shall have hemispherical heads to allow for installation into cradle on SKU6479 page 2.

3.10 Vessel will be designed to be suitable for wind and seismic loads per ASCE-7.

Vessel will be installed outdoors in Middle Tennessee weather.

3.11 Performance Parameters:

A. Design Pressure: 2750 psig – Full Vacuum.

B. Design Temperature: Min -20 F Max 360 F.

C. Vertical Installation

D. Service Type: Desiccant Air Dryer

E. Desiccant Weight: 17,500 lbs.

F. Interior Corrosion Allowance : 1/16”

G. Allow for future hydro-tests while in vertical position.

3.12 Corrosion prevention shall be per manufacturer’s standard finish. Exterior surfaces shall be painted. The buyer will define the exterior paint color after contract award.

Submit coating surface preparation and identify coating material specifications to Buyer with bid. All coating shall be applied per the coating manufacturer’s recommendations.

3.13 Vessel shall be ASME code stamped and registered with that National Board.

Submit code certification to Buyer.

3.14 Vessel shall be painted before delivery.

IRA-4990 Page - 4

3.15 Submittals:

A. Seller shall provide fabrication drawing(s) in AutoCAD format according to Appendix B – Submittal Procedure.

B. Seller shall submit a Bid Sketch denoting main vessel dimensions and all materials of construction with bid.

C. Seller shall provide design code calculations.

D. Seller shall provide material test reports.

E. Seller shall provide Weld Procedure Specifications (WPS) and Procedure Qualification Records (PQR).

F. Seller shall provide all NDE inspection records.

G. If Post Weld Heat Treat is performed Seller shall provide all related information/records.

H. Seller shall provide all Pressure Test Records.

I. Seller shall provide paint material specifications.

J. Seller shall provide ASME Form U-1 associated with the vessel.

K. Seller shall provide final As-Built Drawing(s) of Record. The drawing(s) shall define the vessel empty weight, volume, and center-of-gravity location.

L. Submittal Table:

Submittal

Para. Ref. Description Date Due

1 Para 3.12 Corrosion Control Coating System with Bid

2 Para 3.15.A AutoCAD Fabrication Drawing Prior to fabrication

3 Para 3.15 B Bid Sketch with Materials of Construction

With Bid

IRA-4990 Page - 5

4 Para 3.15 C Design Code Calculations Prior to fabrication

5 Para 3.15 D Material Test Reports With delivery

6 Para 3.15 E WPS/PQR’s Prior to fabrication

7 Para 3.15 F NDE inspection records With delivery

8 Para 3.15 H Pressure Test Records With delivery

9 Para 3.15 I Paint Material Specifications Prior to fabrication

10 Para 3.15 J ASME Certification Form U-1 With delivery

11 Para 3.15 K Final As-Built Drawing(s) With delivery

12 Para 3.15 G Post Weld Heat Treatment Records

With delivery

3.16 Transportation and packaging

A. The Seller shall be responsible for all transportation of the vessel to Arnold AFB including necessary cribbing, tie downs, and weather protection to ensure safe transportation.

B. The Buyer will unload the vessel. The Buyer will provide required crane support and rigger crew to unload the vessel in the VKF Plant Yard for installation.

3.17 Acceptance: Buyer will accept upon:

A. The Buyer reserves the right to visit the site midway through fabrication to inspect vessel progress; the Seller shall coordinate with the Buyer a planned site visit.

IRA-4990 Page - 6

B. The Buyer reserves the right to witness the pressure test; the Seller shall notify the Buyer two weeks prior to the expected pressure test date.

C. Receipt and approval of submittals.

D. Inspection and acceptance upon receipt of vessel (TRIR).

IRA-4990 Appendix A - 1

APPENDIX A

NAS SKETCH SKVU6479 W19 VESSEL

IRA-4990 Appendix A - 1

APPENDIX A

NAS SKETCH SKVU6479 W19 VESSEL

END OF APPENDIX A

IRA-4990 B - 1

APPENDIX B

SUBMITTAL PROCEDURE

PART 1 GENERAL

1.1 DESCRIPTION OF REQUIREMENTS. This section specifies procedural requirements for non-administrative submittals, including but not limited to shop drawings, product data, manufacturer’s certificate, design data, calculations, and verifications, manufacturer’s instructions, manufacturer’s field service reports, samples, operation and maintenance manuals, and other miscellaneous work-related submittals. These submittals are required to amplify, expand, and coordinate other information contained in the contract. This section describes the type and content of submittals that may be required for this work. The required submittals are included in the Statement of Work or Specification.

Non-work-related submittals are addressed elsewhere in the contract rather than in the specification and may include items such as: contract progress schedule, permits, payment applications, performance and payment bonds, insurance certificates, and progress reports.

The Contracting Officer may request submittals in addition to those specified when deemed necessary to adequately describe the work covered in the respective sections of the Specification or Statement of Work.

1.2 SUBMITTAL PROCEDURE

A. Definition: For the purposes of this section, the term “Contractor” denotes the prime Contractor.

B. Listing: At the end of this section is a summarized listing of item submittals requiring approval for the work. The listing is included for the convenience of users of the contract documents. The listing may not be all inclusive and additional item submittals may be required. Within 14 calendar days after receiving contract award, Contractor shall submit a copy of the summarized submittal listing with calendar dates assigned to each item submittal indicating when submittal will be received by the Government. If contract requires a pre-construction conference, Contractor may submit completed submittal listing at the conference.

C. Risk: Do not proceed with the part of the work covered by an item submittal including purchasing, fabricating, and delivering until approval is received.

Machinery, equipment, material, and articles that do not have the required approval shall be installed or used at the risk of subsequent rejection. Any fabrication or other work performed in advance of the receipt of accepted item submittals and approvals shall be entirely at the Contractor’s risk and expense.

IRA-4990 B - 2

D. Transmittal Timing: Coordinate the preparation and processing of item submittals with the performance of the work. Prepare and transmit each item submittal to the Contracting Officer sufficiently in advance of the performance of related work and other applicable activities. Transmit related item submittals for the same unit of work so that processing will not be delayed by the Government's need to review submittals concurrently for coordination. No delay damages or time extensions will be allowed for time lost in late submittals.

E. Content: Each submittal shall be complete and in sufficient detail to allow ready determination of compliance with contract requirements. All submittals which are generic and list more information than is specifically required shall be marked to identify required information. Complete AF Form 3000 and attach as cover sheet for each submittal. Contractor may include multiple item numbers on an AF Form 3000.

F. Language: All item submittals shall be written in English, including documents, notes on drawings, sketches, and/or samples, calculations, manuals, and all other instances of written text and communication.

G. Units: All item submittals shall be marked or show dimensions and values in the same units as specified in the contract documents.

H. Review Time: Allow sufficient time so that contract performance will not be delayed as a result of the time required to properly process submittals, including time for re-submittals, if necessary. Allow 14 calendar days for initial Government processing of each submittal. No extension of time will be authorized because of the Contractor's failure to transmit submittals to the Government sufficiently in advance of the work.

I. Contractor Certification: All submittals shall be carefully reviewed by an authorized representative of the Contractor prior to submission to the Government. Each submittal shall be dated, signed, and certified by the Contractor as being correct and in strict conformance with the contract documents. No consideration for review by the Government of any Contractor’s submittal will be made for any items which have not been so certified by the Contractor. All noncertified submittals will be returned to the Contractor without action taken by the Government, and any delays caused thereby shall be the total responsibility of the Contractor.

J. Deviations: Should any item submittals required by the contract documents show deviations from the contract requirement, the Contractor shall make specific mention of such deviations in the letter of transmittal, including stating cost effects, and product and system limitations which may adversely affect the work, in order that if acceptable, suitable action may be taken for proper adjustment of the contract; otherwise the Contractor will not be relieved of the responsibility for executing the work in accordance

IRA-4990 B - 3

with the contract documents and the approved submittals. Contractor shall clearly mark the proposed variation in all documentation and specifically point out deviations from contract requirements in transmittal letters. Failure to point out deviations may result in the Government requiring rejection and removal of such work at no additional cost to the Government. Deviations from contract requirements require Government approval and will only be considered when advantageous to the Government. When proposing deviations, deliver written request to the Contracting Officer, with documentation of the nature and features of the deviation and why the deviation is desirable and beneficial to the Government. If lower cost is a benefit, include an estimate of the cost savings. In addition to documentation required for deviation, include the submittal information required for the item. Allow an additional 14 calendar days beyond normal submittal review period for consideration by the Government of submittals with deviations.

K. Approved Submittals: The part of the work covered by the approved item submittal may proceed provided it complies with the requirements of the contract documents. Final acceptance will depend upon that compliance.

The term “Approved” shall only indicate that there is no exception taken to the submittal. Approval of the item submittal shall not be construed as a complete check, and indicates only that the general method or other information appears to meet the contract requirements. Approval does not relieve the Contractor of the responsibility for any error which may exist.

After item submittals have been approved by the Contracting Officer, no resubmittal for the purpose of substituting materials or equipment, or changes to any other information will be considered unless accompanied by an explanation of why a substitution or change is necessary.

L. Disapproved Submittals: Contractor shall correct disapproved item submittals and resubmit for approval within timeframe noted. If no date is given, Contractor shall submit corrected submittal within 14 calendar days.

If the Contractor considers any correction or notation on the returned submittal to constitute a change to the contract drawings, specification, or statement of work the Contractor shall notify the Contracting Officer.

M. Responsibility: The Government’s review of Contractor submittals shall not relieve the Contractor of the entire responsibility for the correctness of details and dimensions and conformance to the specifications. The Contractor shall assume all responsibility and risk for any mistakes and/or costs due to any errors in submittals.

N. Inconsistencies: If a conflict or inconsistency arises between an approved item submittal and the contract documents, the contract documents shall govern.

IRA-4990 B - 4

1.3 SPECIFIC SUBMITTAL DESCRIPTIONS AND REQUIREMENTS: Submittal requirements for individual units of work are specified in the applicable specification section or Statement of Work (SOW). Except as otherwise indicated in the individual specification sections or SOW, comply with the following requirements for each type of submittal.

A. Shop Drawings: These are technical drawings and data specially prepared for this contract including fabrication and installation drawings, setting and seaming diagrams, and coordination drawings (for use on-site). Shop drawings include drawings, diagrams and schedules specifically prepared to illustrate some portion of the work, diagrams and instructions from a manufacturer or fabricator for use in producing the product and as aids to the Contractor for integrating the product or system into the project, or drawings prepared by or for the Contractor to show how multiple systems and interdisciplinary work will be coordinated. Information required on shop drawings includes dimensions, identification of specific products and materials which are included in the work, compliance with specified standards, and notations of coordination requirements with other work.

Provide special notations of dimensions that have been established by field measurements. Highlight, encircle, or otherwise indicate deviations from the contract documents on the shop drawings. Furnish one hard copy and one electronic copy in AutoCAD 2007 through 2015 drawing file format (.dwg).

The only permissible text font is ROMANS. Custom fonts and shapes are prohibited. The minimum allowable font size shall be 0.125-inch. The maximum allowable font size shall be 0.25-inch.

B. Product Data: This data includes standard printed information on manufactured products that has not been specially prepared for this contract, including manufacturers' product specifications illustrating size, physical appearance and other characteristics of materials, installation instructions, standard color charts, catalog cuts, illustrations, schedules, standard wiring diagrams, standard product operating and maintenance manuals, and samples of warranty language when the contract requires extended product warranties. General information required specifically as product data includes manufacturers' standard printed recommendations for application and use, compliance with recognized standards of trade associations and testing agencies, the application of their labels and seals (if any), special notation of dimensions which have been verified by way of field measurement, and special coordination requirements for interfacing the material, product, or system with other work. Furnish three hard copies and one electronic copy.

C. Samples: These are physical examples of work, including, swatches showing color, texture, and pattern, color-range sets, and units of work to be used for independent inspection and testing. Samples include fabricated or unfabricated physical examples of materials, equipment or workmanship that illustrate functional and aesthetic characteristics of a material or product

IRA-4990 B - 5

and establish standards by which the work can be judged, color samples from the manufacturer’s standard line (or custom color samples if specified) to be used in selecting or approving colors for the project, and field samples and mock-ups constructed on the project site to establish standards by which the ensuring work can be judged. This includes assemblies or portions of assemblies which are to be incorporated into the project and those which will be removed at conclusion of the work. Submit samples for the Contracting Officer's visual review of general kind, color, pattern, and texture for a final check of the coordination of these characteristics with other related elements of the work and for quality control comparison of these characteristics between the final sample submittal and the actual work as it is delivered and installed. Submit one each.

D. Design Data: Design data includes design calculations, mix designs, analyses or other data pertaining to a part of work. Refer to individual sections of the specification or statement of work for required quantities, formats, and signatures or certifications required. Furnish three hard copies and one electronic copy.

E. Test Plans and Reports: Test plans shall include planned testing, including a description of the test, equipment and supplies needed, and step-by-step notation of test activities and tasks. Test reports include reports signed by an authorized official of a testing laboratory that a material, product or system identical to the material, product or system to be provided has been tested in accordance with the specified requirements. Testing shall have been within three years of date of contract award for the project. Reports also include findings of tests required to be performed by the Contractor on an actual portion of the work or prototype prepared for the project before shipment to the job site, findings of tests made at the job site or on a sample taken from the job site, investigation reports, daily logs and checklists, and final acceptance test and operational test procedures. Furnish three hard copies and one electronic copy of each such report required.

F. Certificates: These include statements printed on the manufacturer’s letterhead and signed by the responsible officials of the manufacturer of a product, system or material attesting that the product, system or material meets specification requirements. Certificates include documentation required of the Contractor, or of a manufacturer, supplier, installer or subcontractor through the Contractor, to further demonstrate the quality of orderly progressions of a portion of the work by documenting procedures, acceptability of methods or personnel qualifications. Examples include confined space entry permits, and text of posted operating instructions.

Certificates shall be dated after award of the project contract and clearly name the project. Furnish three hard copies and one electronic copy of each certificate required.

IRA-4990 B - 6

G. Manufacturer’s Instructions: Preprinted material describing installation of a product, system or material, including special notices and Material Safety Data sheets concerning impedances, hazards and safety precautions.

Furnish three hard copies and one electronic copy.

H. Manufacturer’s Field Reports: Documentation of the testing and verification actions taken by a manufacturer’s representative at the job site, in the vicinity of the job site, or on a sample taken from the job site, on a portion of the work, during or after installation, to confirm compliance with the manufacturer’s standards or instructions. The documentation shall be signed by an authorized official of a testing laboratory or agency and shall state the test results, and indicate whether the material, product, or system has passed or failed the test. Furnish three hard copies and one electronic copy.

I. Operation and Maintenance Data: Data furnished by the manufacturer, or the system provider, to the equipment operating and maintenance personnel, including manufacturer’s help and product line documentation necessary to maintain and install the equipment, and needed by operating and maintenance personnel for the safe and efficient operation, maintenance, and repair of the item. The data is intended to be incorporated in an operations and maintenance manual or control system. Furnish two hard copies and one electronic copy.

J. Final Design Drawings and Documentation: Final design documentation including drawings, specifications, estimates, and other required deliverables. Electronic documentation submitted shall include every associated component file of drawings and other documentation, including raster images, jpeg, tiff, Excel, and any related items required to view, modify, or manipulate the electronic files. Furnish a CD-ROM of all final design documentation, and drawings in AutoCAD 2007 through 2015 drawing file format (.dwg), to the Contracting Officer for approval prior to applying for final payment. The drawings shall be fully editable using AutoCAD software. In addition, drawings shall be delivered to clearly show the location and arrangement of all materials and equipment. The only permissible text font is ROMANS. Custom fonts are shape files are prohibited. The minimum allowable font size shall be 0.125-inch. The maximum allowable font size shall be 0.25-inch.

K. Record (As-Built) Drawings: Record drawings showing final configuration of work accomplished. Show all changes, additions, and deviations from the original contract drawings and documentation. If no changes occur, furnish certification to that effect. Drawings shall be redlined electronic drawings, unless waived by the Government, and shall accurately show as-built conditions during the progress of the job. Furnish drawings on a CD-ROM, in AutoCAD 2007 through 2015 format, including every associated component file of the drawings, including raster images, jpeg, tiff, Excel, and

IRA-4990 B - 7

any related items required to view, modify, or manipulate the electronic files.

Submit to the Contracting Officer for approval prior to applying for final payment.

L. Miscellaneous Submittals: These are work-related, non-administrative submittals that do not fit in the previous categories, including the following:

1. Maintenance agreements. Furnish one hard copy and one electronic copy.

2. Survey data and reports. Furnish one hard copy and one electronic copy.

3. Project photographs. Furnish both hard copies and digital files.

4. Keys and other security protection devices.

5. Maintenance tools, spare parts, and overrun or maintenance stock.

Refer to individual sections of the specification for required quantities of spare parts, extra and overrun stock, maintenance tools and devices, keys, and similar physical units to be submitted.

6. Qualification certificates. Furnish one hard copy and one electronic copy.

7. Employee training certificates and documentation showing successful completion of training.

8. Documentation of percentage of recovered material content used during contract.

9. Contractor safety and work plans and schedules.

10. Warranties.

IRA-4990 B - 8

APPENDIX C

NOZZLE LOADS