THIS PROJECT IS ADVERTISED AS A TOTAL SMALL BUSINESS SET-ASIDE.

THIS IS A REQUEST FOR QUOTE - PLANS AND SPECIFICATIONS ARE AVAILABLE.

PROJECT NUMBER: NE FTFW FTNI TRAIL (1)

PROJECT NAME: Fort Falls Trail

PROJECT DESCRIPTION:  The project is in Fort Niobrara National Wildlife Refuge, which is approximately 5 miles east of Valentine, NE in Cherry County. The project consists of rehabilitation of the Fort Falls trailhead, including the reconstruction of the parking area with new ABA parking pad, construction of an interpretive landing, and the reconstruction of the upper portion of the trail itself. Construction improvements include clearing and grubbing, aggregate base, aggregate reconditioning, concrete pad, concrete trail, signing and striping, and other minor safety improvements.

CONSTRUCTION DURATION: September, 2020 through October, 2020

ADDITIONAL INFORMATION:

Anticipated Advertisement: July, 2020

Anticipated Bid Opening: August, 2020

Anticipated Award: September, 2020

Update #1 ·

THIS PROJECT IS ADVERTISED AS A TOTAL SMALL BUSINESS SET-ASIDE.

THIS IS A REQUEST FOR BID - PLANS AND SPECIFICATIONS ARE AVAILABLE.

PROJECT NUMBER: NE FTFW FTNI TRAIL (1)

PROJECT NAME: Fort Falls Trail

PROJECT DESCRIPTION:  The project is in Fort Niobrara National Wildlife Refuge, which is approximately 5 miles east of Valentine, NE in Cherry County. The project consists of rehabilitation of the Fort Falls trailhead, including the reconstruction of the parking area with new ABA parking pad, construction of an interpretive landing, and the reconstruction of the upper portion of the trail itself. Construction improvements include clearing and grubbing, aggregate base, aggregate reconditioning, concrete pad, concrete trail, signing and striping, and other minor safety improvements.

CONSTRUCTION DURATION: September, 2020 through October, 2020

ADDITIONAL INFORMATION:

Anticipated Advertisement: July, 2020

Anticipated Bid Opening: August, 2020

Anticipated Award: September, 2020

Files

File Type Posted
Bid Tabulation NE FTFW FTNI TRAIL(1).pdf PDF
Bid Opening Summary - Fort Falls Trail.pdf PDF
QnA 8.21.2020.pdf PDF
A001.pdf PDF
6982AF20Q000023.pdf PDF
FP-14.pdf PDF
NE FTFW FTNI Trail(1) Plans.pdf PDF

Notice history

Notice Type Posted
NE FTFW FTNI TRAIL (1) Fort Falls Trail Award Award Notice
This notice Latest solicitation Solicitation
NE FTFW FTNI TRAIL (1) Fort Falls Trail Pre-Solicitation
NE FTFW FTNI TRAIL (1) Fort Falls Trail Original Pre-Solicitation

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity