Questions and Answers during Advertisement for NE FTFW FTNI TRAIL(1) Fort Falls Trail
August 21, 2020
Questions Answers 1 What are the plans for weather days should we have an early winter? Would the CO anticipate work to resume and finish in Spring 2021 if weather completely shuts the contractor down?
See Section 108.03, 108.04, and 108.05 of the SCR’s and FP-14.