Bid Tabulation NE FTFW FTNI TRAIL(1).pdf

PDF 640 KB Posted

Attached to
NE FTFW FTNI TRAIL (1) Fort Falls Trail
Solicitation number
6982AF20Q000023
Issued by

View the file

Other files

File Type Posted
Bid Opening Summary - Fort Falls Trail.pdf PDF
QnA 8.21.2020.pdf PDF
A001.pdf PDF
NE FTFW FTNI Trail(1) Plans.pdf PDF
6982AF20Q000023.pdf PDF
FP-14.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Tabulation of Bids Report Date: 09/01/20

1 out of 7Source Selection Information - See FAR 2.101 & 3.104

Project No: NE FTFW FTNI TRAIL(1)

Project Name: Fort Falls Trail

Schedule: A

Schedule Type: Base

Solcitation No: 6982AF20Q000023

Division: Central Federal Lands

State: NE County: Cherry

Federal Land: Opened at: Lakewood, CO

Opened by: Leslie Karsten

Date: 08/27/20

I certify that this Bid Tabulation accurately reflects the offers received for this solicitation.

Signed: _______________________________

Title: _______________________________

Date: _______________________________

Contract Awarded to: ____________________ Award Date: ____________________

Contractor Comment Bid Amount Responsive

Kovilic Construction Company, Inc. Under SAT no bid bond $240,290.00 3721 N. Carnation Street Franklin Park, IL 60131

Wynne Contracting, LLC Under Simplified Acquisition Threshold, no bid bond required

$253,393.20 11274 US Highway 26 Bayard, NE 69334

Construction Solutions Group, LLC $311,910.00 5512 Elk Valley Estates Dr St. Louis, MO 63128

Engineer's Estimate $230,000.00

Contract Specialist

09/01/20

2 out of 7Source Selection Information - See FAR 2.101 & 3.104

Project No: NE FTFW FTNI TRAIL(1)

Project Name: Fort Falls Trail

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0010 15101-0000 MOBILIZATION

Kovilic Construction Company, Inc. Lump Sum $30,000.00 Wynne Contracting, LLC Lump Sum $43,662.37 Construction Solutions Group, LLC Lump Sum $95,000.00 Engineer's Estimate ALL LPSM Lump Sum $49,139.00

A0020 15206-0000 SLOPE, REFERENCE, AND CLEARING AND GRUBBING STAKE

Kovilic Construction Company, Inc. $40,000.00 $3,600.00 Wynne Contracting, LLC $4,974.40 $447.70 Construction Solutions Group, LLC $12,000.00 $1,080.00 Engineer's Estimate 0.09 MILE $17,000.00 $1,530.00

A0030 15215-7000 SURVEY AND STAKING, PARKING AREA

Kovilic Construction Company, Inc. $5,000.00 $10,000.00 Wynne Contracting, LLC $161.52 $323.04 Construction Solutions Group, LLC $3,500.00 $7,000.00 Engineer's Estimate 2 EACH $3,000.00 $6,000.00

A0040 15236-2000 SURVEY CONTROL, GRADE FINISHING

Kovilic Construction Company, Inc. $20,000.00 $3,600.00 Wynne Contracting, LLC $3,422.40 $616.03 Construction Solutions Group, LLC $12,000.00 $2,160.00 Engineer's Estimate 0.18 MILE $15,000.00 $2,700.00

A0050 15301-0000 CONTRACTOR QUALITY CONTROL

Kovilic Construction Company, Inc. Lump Sum $15,000.00 Wynne Contracting, LLC Lump Sum $71,840.00 Construction Solutions Group, LLC Lump Sum $31,000.00 Engineer's Estimate ALL LPSM Lump Sum $5,000.00

A0060 15401-0000 CONTRACTOR TESTING

Kovilic Construction Company, Inc. Lump Sum $15,000.00 Wynne Contracting, LLC Lump Sum $15,200.00 Construction Solutions Group, LLC Lump Sum $16,500.00 Engineer's Estimate ALL LPSM Lump Sum $5,000.00

3 out of 7Source Selection Information - See FAR 2.101 & 3.104

Project No: NE FTFW FTNI TRAIL(1)

Project Name: Fort Falls Trail

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0070 15501-0000 CONSTRUCTION SCHEDULE

Kovilic Construction Company, Inc. Lump Sum $2,500.00 Wynne Contracting, LLC Lump Sum $4,000.00 Construction Solutions Group, LLC Lump Sum $12,500.00 Engineer's Estimate ALL LPSM Lump Sum $10,000.00

A0080 15705-1400 SOIL EROSION CONTROL, FIBER ROLL

Kovilic Construction Company, Inc. $30.00 $12,900.00 Wynne Contracting, LLC $9.30 $3,999.00 Construction Solutions Group, LLC $10.00 $4,300.00 Engineer's Estimate 430 LNFT $6.00 $2,580.00

A0090 15802-0000 WATERING FOR DUST CONTROL

Kovilic Construction Company, Inc. Lump Sum $10,000.00 Wynne Contracting, LLC Lump Sum $3,440.00 Construction Solutions Group, LLC Lump Sum $10,000.00 Engineer's Estimate ALL LPSM Lump Sum $10,000.00

A0100 20103-0000 CLEARING AND GRUBBING

Kovilic Construction Company, Inc. $10.00 $5,000.00 Wynne Contracting, LLC $2.57 $1,285.00 Construction Solutions Group, LLC $30.00 $15,000.00 Engineer's Estimate 500 SQYD $6.00 $3,000.00

A0110 20301-2400 REMOVAL OF SIGN

Kovilic Construction Company, Inc. $300.00 $300.00 Wynne Contracting, LLC $40.62 $40.62 Construction Solutions Group, LLC $350.00 $350.00 Engineer's Estimate 1 EACH $150.00 $150.00

A0120 20302-0700 REMOVAL OF FENCE

Kovilic Construction Company, Inc. $10.00 $1,700.00 Wynne Contracting, LLC $2.10 $357.00 Construction Solutions Group, LLC $10.00 $1,700.00 Engineer's Estimate 170 LNFT $6.00 $1,020.00

4 out of 7Source Selection Information - See FAR 2.101 & 3.104

Project No: NE FTFW FTNI TRAIL(1)

Project Name: Fort Falls Trail

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0130 20303-0300 REMOVAL OF CONCRETE

Kovilic Construction Company, Inc. $36.00 $1,800.00 Wynne Contracting, LLC $10.02 $501.00 Construction Solutions Group, LLC $40.00 $2,000.00 Engineer's Estimate 50 SQYD $125.00 $6,250.00

A0140 20303-1900 REMOVAL OF PAVEMENT, ASPHALT, 3-INCH DEPTH

Kovilic Construction Company, Inc. $23.00 $3,220.00 Wynne Contracting, LLC $15.11 $2,115.40 Construction Solutions Group, LLC $80.00 $11,200.00 Engineer's Estimate 140 SQYD $15.00 $2,100.00

A0150 20401-0000 ROADWAY EXCAVATION

Kovilic Construction Company, Inc. $100.00 $10,000.00 Wynne Contracting, LLC $40.56 $4,056.00 Construction Solutions Group, LLC $40.00 $4,000.00 Engineer's Estimate 100 CUYD $40.00 $4,000.00

A0160 30202-2000 ROADWAY AGGREGATE, METHOD 2

Kovilic Construction Company, Inc. $110.00 $17,600.00 Wynne Contracting, LLC $103.74 $16,598.40 Construction Solutions Group, LLC $55.00 $8,800.00 Engineer's Estimate 160 TON $135.00 $21,600.00

A0170 50101-0600 MINOR CONCRETE PAVEMENT, REINFORCED, 6-INCH DEPTH

Kovilic Construction Company, Inc. $125.00 $13,750.00 Wynne Contracting, LLC $155.21 $17,073.10 Construction Solutions Group, LLC $90.00 $9,900.00 Engineer's Estimate 110 SQYD $135.00 $14,850.00

A0180 60915-1000 WHEELSTOP, CONCRETE

Kovilic Construction Company, Inc. $500.00 $500.00 Wynne Contracting, LLC $239.44 $239.44 Construction Solutions Group, LLC $500.00 $500.00 Engineer's Estimate 1 EACH $250.00 $250.00

5 out of 7Source Selection Information - See FAR 2.101 & 3.104

Project No: NE FTFW FTNI TRAIL(1)

Project Name: Fort Falls Trail

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0190 61501-0100 SIDEWALK, CONCRETE

Kovilic Construction Company, Inc. $110.00 $9,900.00 Wynne Contracting, LLC $117.78 $10,600.20 Construction Solutions Group, LLC $75.00 $6,750.00 Engineer's Estimate 90 SQYD $130.00 $11,700.00

A0200 61901-2400 FENCE, SPLIT RAIL, 2 RAIL (WOOD)

Kovilic Construction Company, Inc. $25.00 $10,000.00 Wynne Contracting, LLC $17.04 $6,816.00 Construction Solutions Group, LLC $13.00 $5,200.00 Engineer's Estimate 400 LNFT $40.00 $16,000.00

A0210 62201-0200 DUMP TRUCK, 8 CUBIC YARD MINIMUM CAPACITY

Kovilic Construction Company, Inc. $130.00 $1,300.00 Wynne Contracting, LLC $152.00 $1,520.00 Construction Solutions Group, LLC $150.00 $1,500.00 Engineer's Estimate 10 HOUR $110.00 $1,100.00

A0220 62201-0550 BACKHOE LOADER, 6 CUBIC FOOT MINIMUM RATED CAPACITY BUCKET, 24-INCH WIDTH

Kovilic Construction Company, Inc. $240.00 $2,400.00 Wynne Contracting, LLC $278.78 $2,787.80 Construction Solutions Group, LLC $150.00 $1,500.00 Engineer's Estimate 10 HOUR $110.00 $1,100.00

A0230 62201-0950 WHEEL LOADER, 3 CUBIC YARD MINIMUM RATED CAPACITY

Kovilic Construction Company, Inc. $220.00 $2,200.00 Wynne Contracting, LLC $458.46 $4,584.60 Construction Solutions Group, LLC $150.00 $1,500.00 Engineer's Estimate 10 HOUR $160.00 $1,600.00

A0240 62201-3350 HYDRAULIC EXCAVATOR, 1 CUBIC YARD MINIMUM CAPACITY

Kovilic Construction Company, Inc. $280.00 $2,800.00 Wynne Contracting, LLC $431.34 $4,313.40 Construction Solutions Group, LLC $150.00 $1,500.00 Engineer's Estimate 10 HOUR $170.00 $1,700.00

6 out of 7Source Selection Information - See FAR 2.101 & 3.104

Project No: NE FTFW FTNI TRAIL(1)

Project Name: Fort Falls Trail

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0250 62301-0000 GENERAL LABOR

Kovilic Construction Company, Inc. $110.00 $4,400.00 Wynne Contracting, LLC $28.80 $1,152.00 Construction Solutions Group, LLC $30.00 $1,200.00 Engineer's Estimate 40 HOUR $40.00 $1,600.00

A0260 62302-1000 SPECIAL LABOR, HIRED TECHNICAL SERVICES

Kovilic Construction Company, Inc. $175.00 $3,500.00 Wynne Contracting, LLC $144.00 $2,880.00 Construction Solutions Group, LLC $200.00 $4,000.00 Engineer's Estimate 20 HOUR $150.00 $3,000.00

A0270 62302-1100 SPECIAL LABOR, HIRED SURVEY SERVICES

Kovilic Construction Company, Inc. $175.00 $3,500.00 Wynne Contracting, LLC $217.60 $4,352.00 Construction Solutions Group, LLC $125.00 $2,500.00 Engineer's Estimate 20 HOUR $160.00 $3,200.00

A0280 62405-0300 PLACING CONSERVED TOPSOIL, 4-INCH DEPTH

Kovilic Construction Company, Inc. $11.00 $4,510.00 Wynne Contracting, LLC $4.51 $1,849.10 Construction Solutions Group, LLC $5.00 $2,050.00 Engineer's Estimate 410 SQYD $12.00 $4,920.00

A0290 62511-1000 SEEDING, DRY METHOD

Kovilic Construction Company, Inc. $6.00 $2,460.00 Wynne Contracting, LLC $9.76 $4,001.60 Construction Solutions Group, LLC $8.00 $3,280.00 Engineer's Estimate 410 SQYD $3.10 $1,271.00

A0300 63301-0000 SIGN SYSTEM

Kovilic Construction Company, Inc. $750.00 $1,500.00 Wynne Contracting, LLC $800.00 $1,600.00 Construction Solutions Group, LLC $500.00 $1,000.00 Engineer's Estimate 2 EACH $700.00 $1,400.00

7 out of 7Source Selection Information - See FAR 2.101 & 3.104

Project No: NE FTFW FTNI TRAIL(1)

Project Name: Fort Falls Trail

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0310 63401-0300 PAVEMENT MARKINGS, TYPE B, SOLID

Kovilic Construction Company, Inc. $20.00 $4,600.00 Wynne Contracting, LLC $8.00 $1,840.00 Construction Solutions Group, LLC $8.00 $1,840.00 Engineer's Estimate 230 LNFT $3.00 $690.00

A0320 63405-0850 PAVEMENT MARKINGS, TYPE B, ACCESSIBILITY SYMBOL

Kovilic Construction Company, Inc. $750.00 $750.00 Wynne Contracting, LLC $800.00 $800.00 Construction Solutions Group, LLC $600.00 $600.00 Engineer's Estimate 1 EACH $550.00 $550.00

A0330 63501-0000 TEMPORARY TRAFFIC CONTROL

Kovilic Construction Company, Inc. Lump Sum $10,000.00 Wynne Contracting, LLC Lump Sum $960.00 Construction Solutions Group, LLC Lump Sum $2,500.00 Engineer's Estimate ALL LPSM Lump Sum $5,000.00

A0340 64603-2100 FIXTURE, STAIRWAY (REINFORCING STEEL)

Kovilic Construction Company, Inc. $20,000.00 $20,000.00 Wynne Contracting, LLC $17,542.40 $17,542.40 Construction Solutions Group, LLC $42,000.00 $42,000.00 Engineer's Estimate 1 EACH $30,000.00 $30,000.00

Total Schedule - All Items

Kovilic Construction Company, Inc. $240,290.00 Wynne Contracting, LLC $253,393.20 Construction Solutions Group, LLC $311,910.00 Engineer's Estimate $230,000.00