Lock & Dam 7 Upper Guidewall Crib Grouting
Award Notice Posted
- Solicitation number
- W912ES-15-B-0011
- Agency
-
ENDIST St Paul
US Army Corps of Engineers, Department of Defense
- Awarded
- to J.f. Brennan Company, Inc.
- Set-aside
- No set-aside
Opportunity facts
- Contract number
- W912ES-15-C-0008 Federal contract award
- NAICS code
- 238110 Poured Concrete Foundation and Structure Contractors
- PSC
- Not on record
- Place of performance
- Lock & Dam 7 La Crescent, Minnesota 55947, United States
Notice details come from SAM.gov. Updated .
Notice text
7 versions
Update #7 · Latest ·
Added: Jun 11, 2015 12:24 am Modified: Sep 01, 2015 4:03 pmTrack Changes
Bid Abstract Posted
Amendment 4 Posted
Amendment 3 Posted
Amendment 2 Posted
Amendment 1 Posted
Solicitation Posted
The Lock and Dam 7 upper guidew all crib repair project is located upstream of La Crescent, Minnesota and consists of stabilizing the pile
foundation w ith low density cellular concrete. The upper guide w all is founded on timber piles and a rock filled crib. Voids have been
created in the rock filled crib due to rock w ash out and settlement. The contractor shall provide all plant labor and material to complete the
contract requirements. This contract involves placing and sealing concrete forms along the upper guidew all foundation and placing low
density cellular concrete to fill the voids in the rock filled crib as w ell as spaces betw een the existing crib rock. This w ork w ill be
accomplished during the non-navigation season, w hich is generally betw een December and mid March. The project magnitude in terms of
estimated price is betw een $1,000,000 and $5,000,000. The NAICS code for the proposed project is 238110 w ith a small business size
standard of $15 million.
Update #6 ·
Added: Jun 11, 2015 12:24 am Modified: Aug 20, 2015 7:16 pmTrack Changes
Amendment 4 Posted
Amendment 3 Posted
Amendment 2 Posted
Amendment 1 Posted
Solicitation Posted
The Lock and Dam 7 upper guidew all crib repair project is located upstream of La Crescent, Minnesota and consists of stabilizing the pile
foundation w ith low density cellular concrete. The upper guide w all is founded on timber piles and a rock filled crib. Voids have been
created in the rock filled crib due to rock w ash out and settlement. The contractor shall provide all plant labor and material to complete the
contract requirements. This contract involves placing and sealing concrete forms along the upper guidew all foundation and placing low
density cellular concrete to fill the voids in the rock filled crib as w ell as spaces betw een the existing crib rock. This w ork w ill be
accomplished during the non-navigation season, w hich is generally betw een December and mid March. The project magnitude in terms of
estimated price is betw een $1,000,000 and $5,000,000. The NAICS code for the proposed project is 238110 w ith a small business size
standard of $15 million.
Update #5 ·
Added: Jun 11, 2015 12:24 am Modified: Aug 19, 2015 4:34 pmTrack Changes
Amendment 3 Posted
Amendment 2 Posted
Amendment 1 Posted
Solicitation Posted
The Lock and Dam 7 upper guidew all crib repair project is located upstream of La Crescent, Minnesota and consists of stabilizing the pile
foundation w ith low density cellular concrete. The upper guide w all is founded on timber piles and a rock filled crib. Voids have been
created in the rock filled crib due to rock w ash out and settlement. The contractor shall provide all plant labor and material to complete the
contract requirements. This contract involves placing and sealing concrete forms along the upper guidew all foundation and placing low
density cellular concrete to fill the voids in the rock filled crib as w ell as spaces betw een the existing crib rock. This w ork w ill be
accomplished during the non-navigation season, w hich is generally betw een December and mid March. The project magnitude in terms of
estimated price is betw een $1,000,000 and $5,000,000. The NAICS code for the proposed project is 238110 w ith a small business size
standard of $15 million.
Update #4 ·
Added: Jun 11, 2015 12:24 am Modified: Aug 12, 2015 1:58 pmTrack Changes
Amendment 2 Posted
Amendment 1 Posted
Solicitation Posted
The Lock and Dam 7 upper guidew all crib repair project is located upstream of La Crescent, Minnesota and consists of stabilizing the pile
foundation w ith low density cellular concrete. The upper guide w all is founded on timber piles and a rock filled crib. Voids have been
created in the rock filled crib due to rock w ash out and settlement. The contractor shall provide all plant labor and material to complete the
contract requirements. This contract involves placing and sealing concrete forms along the upper guidew all foundation and placing low
density cellular concrete to fill the voids in the rock filled crib as w ell as spaces betw een the existing crib rock. This w ork w ill be
accomplished during the non-navigation season, w hich is generally betw een December and mid March. The project magnitude in terms of
estimated price is betw een $1,000,000 and $5,000,000. The NAICS code for the proposed project is 238110 w ith a small business size
standard of $15 million.
Update #3 ·
Added: Jun 11, 2015 12:24 am Modified: Jul 30, 2015 8:18 pmTrack Changes
Amendment 1 Posted
Solicitation Posted
The Lock and Dam 7 upper guidew all crib repair project is located upstream of La Crescent, Minnesota and consists of stabilizing the pile
foundation w ith low density cellular concrete. The upper guide w all is founded on timber piles and a rock filled crib. Voids have been
created in the rock filled crib due to rock w ash out and settlement. The contractor shall provide all plant labor and material to complete the
contract requirements. This contract involves placing and sealing concrete forms along the upper guidew all foundation and placing low
density cellular concrete to fill the voids in the rock filled crib as w ell as spaces betw een the existing crib rock. This w ork w ill be
accomplished during the non-navigation season, w hich is generally betw een December and mid March. The project magnitude in terms of
estimated price is betw een $1,000,000 and $5,000,000. The NAICS code for the proposed project is 238110 w ith a small business size
standard of $15 million.
Update #2 ·
Added: Jun 11, 2015 12:24 am Modified: Jul 16, 2015 6:55 pmTrack Changes
The Lock and Dam 7 upper guidew all crib repair project is located upstream of La Crescent, Minnesota and consists of stabilizing the pile
foundation w ith low density cellular concrete. The upper guide w all is founded on timber piles and a rock filled crib. Voids have been
created in the rock filled crib due to rock w ash out and settlement. The contractor shall provide all plant labor and material to complete the
contract requirements. This contract involves placing and sealing concrete forms along the upper guidew all foundation and placing low
density cellular concrete to fill the voids in the rock filled crib as w ell as spaces betw een the existing crib rock. This w ork w ill be
accomplished during the non-navigation season, w hich is generally betw een December and mid March. The project magnitude in terms of
estimated price is betw een $1,000,000 and $5,000,000. The NAICS code for the proposed project is 238110 w ith a small business size
standard of $15 million.
Update #1 ·
Added: Jun 11, 2015 12:24 am
The Lock and Dam 7 upper guidewall crib grouting project is located upstream of La Crescent, Minnesota and consists of stabilizing the pile foundation with a flowable grout. The upper guide wall is founded on timber piles and a rock filled crib. Voids have been created in the rock filled crib due to rock wash out and settlement. These voids and the spaces between the rock also need to be filled with grout. The contractor shall provide all plant labor and material to complete the contract requirements. This contract involves placing and sealing concrete forms around the upper guidewall foundation and placing flowable grout to entirely fill the voids in the rock filled crib. This work will be accomplished during the non-navigation season, which is generally between December and mid March.
The project magnitude in terms of estimated price is between $1,000,000 and $5,000,000. The appropriate NAICS code for the proposed project is 238110 with a small business size standard of $15 million.