Lemon Dam High Pressure Gate Modification

Awarded Award Notice Posted

Solicitation number
R16PS00929
Agency
Bureau of Reclamation Department of the Interior
Awarded
to Gracon LLC
Set-aside
Total Small Business

Opportunity facts

Contract number
R16PC00116 Federal contract award
NAICS code
237990 Other Heavy and Civil Engineering Construction
PSC
Not on record
Place of performance
Lemon Dam, 15 miles from Durango, CO Durango, Colorado 81301, United States

Notice details come from SAM.gov. Updated .

Notice text

7 versions

Update #7 · Latest ·

Added: Apr 28, 2016 10:30 am Modified: Jul 19, 2016 6:44 pmTrack Changes See attachments for Amendment 4

See attachments for Amendment 3

See attachments for Amendment 2



This amendment required to post the full solicitation package (see attached documents)

R16PS00929 Lemon Dam High Pressure Gate ModificatioSYNOPSIS

R16PS00929 Lemon Dam High Pressure Gate Modification


The Bureau of Reclamation, Upper Colorado Region, has a requirement to replace the gate seats and perform coating repairs to the guard gates and appurtenant features of the Lemon Dam outlet works. Lemon Dam is located on the Florida River approximately 16 miles Northeast of Durango, Colorado in La Plata County.


A. The work will begin after summer reservoir releases have been complete. This ranges from 9/1/2016 to 9/30/2017. All work as described in this solicitation shall be completed 16 months after notice to proceed
B. Fabricate and provide a steel intake bulkhead gate.
C. Remove, refurbish, the four trashracks that are located in the intake structure below the water surface of the reservoir. Reinstall the trashracks after the bulkhead has been removed. Refurbishment of the trashracks also referred to trashracks repair and trashracks coating the Section B is optional and is at the discretion of the CO. If the CO elects not to repair and coat the trashracks, the trashracks will remain below the surface of the reservoir and will not be exposed to the atmosphere.
D. Isolate the main outlet works by setting the contractor provided bulkhead in the intake structure, and drain the inlet tunnel.
E. Water will be released through the bulkhead to maintain river flow. There will be two hoses plumbed through the bulkhead that connect into a 12-inch hose. The 12-inch will run the length of the upstream tunnel which is approximately 1000 -feet. There will be a regulating valve adjacent to the high pressure gates that will control the releases of water through the tunnel. There will be times such as during the set-up an disassembly of the hose system that releases cannot be made through the bulkhead; releases will be made by pumping no less than 3 cubic feet per second into the stilling basin to maintain constant releases from the reservoir to the Florida River.
F. The tunnel wyes upstream of the 4 - 2'- 3" x 2'- 3" High Pressure Gates. Water flow in the tunnel will be diverted to flow through gates 1 and 3 when work is being performed on gates 2 and 4, and the water will be diverted to flow through gates 2 and 4 when work is being performed on gates 1 and 3.
G. Modify and repair 4 - 2'- 3" x 2'- 3" High Pressure Gates and hoists. This includes but is not limited to:
1. Furnishing and installing new composite self-lubricating high-pressure gate leaf seats and new bronze frame seats.
2. Performing surface preparation and applying coatings on the four high-pressure gate leaves and hoists.
3. Performing surface preparation and applying coatings on the four high-pressure gates.
4. Installing new hydraulic valves, pipe, and fittings at each hoist.
H. Test the four high pressure gates under the equivalent pressure of lake head. This will be performed without charging the tunnel between the bulkhead and the high pressure gates. Pressure can be placed upstream side of the gates by installing an expansion bulkhead downstream of the wye.
I. Close the High Pressure gates and fill the intake tunnel, and remove the bulkhead for the intake structure.
J. Perform operational tests on all four high pressure gates.
It is anticipated the contract will be a fixed price construction contract. This is a total small business set aside. The North American Industry Classification System Code (NAICS) is 237990 Other Heavy and Civil Engineering Construction with a small business size standard of $33.5M. The estimated magnitude of the requirement in terms of physical characteristics and estimated range is between $1,000,000 and $5,000,000.


Anticipated award is for a contract with an estimated 16 month duration. Request for Proposal No. R16PS00929, using procedures prescribed by FAR Part 36 - Construction Architect-Engineer Contracts in conjunction with FAR Part 15 - Contracting by Negotiation, will be posted shortly after transmission of this synopsis.


All responsible sources may submit a proposal which shall be considered by the agency. An electronic copy of the solicitation will be available within the next few weeks at Federal Business Opportunities www.fbo.gov or directly at FedConnect https://www.fedconnect.net/FedConnect/Default.htm. Once logged into the "FedBizOpps" web-site, type in the Solicitation Number "R16PS00929" in the Keyword/Solicitation # field.


A site visit will be held. The date and details will be provided in Section L of the solicitation and on the website https://www.fbo.gov/


Submit all questions in writing to mcouvrette@usbr.gov. Only questions submitted in writing will be addressed during the site visit and subsequent amendment. Prospective offerors must be registered and must maintain an active registration in the System for Award Management database found at http://www.sam.gov.


The Bureau of Reclamation, Upper Colorado Region, has a requirement to construct an


approximate 74-acre foot regulating reservoir and appurtenant structures. The work is


located on Orchard Mesa, approximately 5 miles southwest of Grand Junction, Colorado


in Mesa County.


A. The work will begin after summer reservoir releases have been complete. This


ranges from 9/1/2016 to 9/30/2017. All work as described in this solicitation shall


be completed 16 months after notice to proceed


B. Fabricate and provide a steel intake bulkhead gate.


C. Remove, refurbish, the four trashracks that are located in the intake structure


below the water surface of the reservoir. Reinstall the trashracks after the


bulkhead has been removed. Refurbishment of the trashracks also referred to


trashracks repair and trashracks coating the Section B is optional and is at the


discretion of the CO. If the CO elects not to repair and coat the trashracks, the


trashracks will remain below the surface of the reservoir and will not be exposed


to the atmosphere.


D. Isolate the main outlet works by setting the contractor provided bulkhead in the


intake structure, and drain the inlet tunnel.


E. Water will be released through the bulkhead to maintain river flow. There will be


two hoses plumbed through the bulkhead that connect into a 12-inch hose. The


12-inch will run the length of the upstream tunnel which is approximately 1000 -


feet. There will be a regulating valve adjacent to the high pressure gates that will


control the releases of water through the tunnel. There will be times such as


during the set-up an disassembly of the hose system that releases cannot be made


through the bulkhead; releases will be made by pumping no less than 3 cubic feet


per second into the stilling basin to maintain constant releases from the reservoir


to the Florida River.


F. The tunnel wyes upstream of the 4 - 2'- 3" x 2'- 3" High Pressure Gates. Water


flow in the tunnel will be diverted to flow through gates 1 and 3 when work is


being performed on gates 2 and 4, and the water will be diverted to flow through


gates 2 and 4 when work is being performed on gates 1 and 3.


G. Modify and repair 4 - 2'- 3" x 2'- 3" High Pressure Gates and hoists. This


includes but is not limited to:


1. Furnishing and installing new composite self-lubricating high-pressure gate leaf


seats and new bronze frame seats.


2. Performing surface preparation and applying coatings on the four high-pressure


gate leaves and hoists.


3. Performing surface preparation and applying coatings on the four high-pressure


gates.


4. Installing new hydraulic valves, pipe, and fittings at each hoist.


H. Test the four high pressure gates under the equivalent pressure of lake head. This


will be performed without charging the tunnel between the bulkhead and the high


pressure gates. Pressure can be placed upstream side of the gates by installing an


expansion bulkhead downstream of the wye.


I. Close the High Pressure gates and fill the intake tunnel, and remove the bulkhead


for the intake structure.


J. Perform operational tests on all four high pressure gates.


It is anticipated the contract will be a fixed price construction contract. This is a total


small business set aside. The North American Industry Classification System Code


(NAICS) is 237990 Other Heavy and Civil Engineering Construction with a small


business size standard of $33.5M. The estimated magnitude of the requirement in terms


of physical characteristics and estimated range is between $1,000,000 and $5,000,000.


Anticipated award is for a contract with an estimated 16 month duration. Request for


Proposal No. R16PS00929, using procedures prescribed by FAR Part 36 - Construction


Architect-Engineer Contracts in conjunction with FAR Part 15 - Contracting by


Negotiation, will be posted shortly after transmission of this synopsis.


All responsible sources may submit a proposal which shall be considered by the agency.


An electronic copy of the solicitation will be available within the next few weeks at


Federal Business Opportunities www.fbo.gov or directly at FedConnect


https://www.fedconnect.net/FedConnect/Default.htm. Once logged into the


"FedBizOpps" web-site, type in the Solicitation Number "R16PS00929" in the


Keyword/Solicitation # field.


A site visit will be held. The date and details will be provided in Section L of the


solicitation and on the website https://www.fbo.gov/


Submit all questions in writing to mcouvrette@usbr.gov. Only questions submitted in


writing will be addressed during the site visit and subsequent amendment. Prospective


offerors must be registered and must maintain an active registration in the System for


Award Management database found at http://www.sam.gov.



Update #6 ·

Added: Apr 28, 2016 10:30 am Modified: Jul 19, 2016 2:11 pmTrack Changes See attachments for Amendment 3

See attachments for Amendment 2



This amendment required to post the full solicitation package (see attached documents)

R16PS00929 Lemon Dam High Pressure Gate ModificatioSYNOPSIS

R16PS00929 Lemon Dam High Pressure Gate Modification


The Bureau of Reclamation, Upper Colorado Region, has a requirement to replace the gate seats and perform coating repairs to the guard gates and appurtenant features of the Lemon Dam outlet works. Lemon Dam is located on the Florida River approximately 16 miles Northeast of Durango, Colorado in La Plata County.


A. The work will begin after summer reservoir releases have been complete. This ranges from 9/1/2016 to 9/30/2017. All work as described in this solicitation shall be completed 16 months after notice to proceed
B. Fabricate and provide a steel intake bulkhead gate.
C. Remove, refurbish, the four trashracks that are located in the intake structure below the water surface of the reservoir. Reinstall the trashracks after the bulkhead has been removed. Refurbishment of the trashracks also referred to trashracks repair and trashracks coating the Section B is optional and is at the discretion of the CO. If the CO elects not to repair and coat the trashracks, the trashracks will remain below the surface of the reservoir and will not be exposed to the atmosphere.
D. Isolate the main outlet works by setting the contractor provided bulkhead in the intake structure, and drain the inlet tunnel.
E. Water will be released through the bulkhead to maintain river flow. There will be two hoses plumbed through the bulkhead that connect into a 12-inch hose. The 12-inch will run the length of the upstream tunnel which is approximately 1000 -feet. There will be a regulating valve adjacent to the high pressure gates that will control the releases of water through the tunnel. There will be times such as during the set-up an disassembly of the hose system that releases cannot be made through the bulkhead; releases will be made by pumping no less than 3 cubic feet per second into the stilling basin to maintain constant releases from the reservoir to the Florida River.
F. The tunnel wyes upstream of the 4 - 2'- 3" x 2'- 3" High Pressure Gates. Water flow in the tunnel will be diverted to flow through gates 1 and 3 when work is being performed on gates 2 and 4, and the water will be diverted to flow through gates 2 and 4 when work is being performed on gates 1 and 3.
G. Modify and repair 4 - 2'- 3" x 2'- 3" High Pressure Gates and hoists. This includes but is not limited to:
1. Furnishing and installing new composite self-lubricating high-pressure gate leaf seats and new bronze frame seats.
2. Performing surface preparation and applying coatings on the four high-pressure gate leaves and hoists.
3. Performing surface preparation and applying coatings on the four high-pressure gates.
4. Installing new hydraulic valves, pipe, and fittings at each hoist.
H. Test the four high pressure gates under the equivalent pressure of lake head. This will be performed without charging the tunnel between the bulkhead and the high pressure gates. Pressure can be placed upstream side of the gates by installing an expansion bulkhead downstream of the wye.
I. Close the High Pressure gates and fill the intake tunnel, and remove the bulkhead for the intake structure.
J. Perform operational tests on all four high pressure gates.
It is anticipated the contract will be a fixed price construction contract. This is a total small business set aside. The North American Industry Classification System Code (NAICS) is 237990 Other Heavy and Civil Engineering Construction with a small business size standard of $33.5M. The estimated magnitude of the requirement in terms of physical characteristics and estimated range is between $1,000,000 and $5,000,000.


Anticipated award is for a contract with an estimated 16 month duration. Request for Proposal No. R16PS00929, using procedures prescribed by FAR Part 36 - Construction Architect-Engineer Contracts in conjunction with FAR Part 15 - Contracting by Negotiation, will be posted shortly after transmission of this synopsis.


All responsible sources may submit a proposal which shall be considered by the agency. An electronic copy of the solicitation will be available within the next few weeks at Federal Business Opportunities www.fbo.gov or directly at FedConnect https://www.fedconnect.net/FedConnect/Default.htm. Once logged into the "FedBizOpps" web-site, type in the Solicitation Number "R16PS00929" in the Keyword/Solicitation # field.


A site visit will be held. The date and details will be provided in Section L of the solicitation and on the website https://www.fbo.gov/


Submit all questions in writing to mcouvrette@usbr.gov. Only questions submitted in writing will be addressed during the site visit and subsequent amendment. Prospective offerors must be registered and must maintain an active registration in the System for Award Management database found at http://www.sam.gov.


The Bureau of Reclamation, Upper Colorado Region, has a requirement to construct an


approximate 74-acre foot regulating reservoir and appurtenant structures. The work is


located on Orchard Mesa, approximately 5 miles southwest of Grand Junction, Colorado


in Mesa County.


A. The work will begin after summer reservoir releases have been complete. This


ranges from 9/1/2016 to 9/30/2017. All work as described in this solicitation shall


be completed 16 months after notice to proceed


B. Fabricate and provide a steel intake bulkhead gate.


C. Remove, refurbish, the four trashracks that are located in the intake structure


below the water surface of the reservoir. Reinstall the trashracks after the


bulkhead has been removed. Refurbishment of the trashracks also referred to


trashracks repair and trashracks coating the Section B is optional and is at the


discretion of the CO. If the CO elects not to repair and coat the trashracks, the


trashracks will remain below the surface of the reservoir and will not be exposed


to the atmosphere.


D. Isolate the main outlet works by setting the contractor provided bulkhead in the


intake structure, and drain the inlet tunnel.


E. Water will be released through the bulkhead to maintain river flow. There will be


two hoses plumbed through the bulkhead that connect into a 12-inch hose. The


12-inch will run the length of the upstream tunnel which is approximately 1000 -


feet. There will be a regulating valve adjacent to the high pressure gates that will


control the releases of water through the tunnel. There will be times such as


during the set-up an disassembly of the hose system that releases cannot be made


through the bulkhead; releases will be made by pumping no less than 3 cubic feet


per second into the stilling basin to maintain constant releases from the reservoir


to the Florida River.


F. The tunnel wyes upstream of the 4 - 2'- 3" x 2'- 3" High Pressure Gates. Water


flow in the tunnel will be diverted to flow through gates 1 and 3 when work is


being performed on gates 2 and 4, and the water will be diverted to flow through


gates 2 and 4 when work is being performed on gates 1 and 3.


G. Modify and repair 4 - 2'- 3" x 2'- 3" High Pressure Gates and hoists. This


includes but is not limited to:


1. Furnishing and installing new composite self-lubricating high-pressure gate leaf


seats and new bronze frame seats.


2. Performing surface preparation and applying coatings on the four high-pressure


gate leaves and hoists.


3. Performing surface preparation and applying coatings on the four high-pressure


gates.


4. Installing new hydraulic valves, pipe, and fittings at each hoist.


H. Test the four high pressure gates under the equivalent pressure of lake head. This


will be performed without charging the tunnel between the bulkhead and the high


pressure gates. Pressure can be placed upstream side of the gates by installing an


expansion bulkhead downstream of the wye.


I. Close the High Pressure gates and fill the intake tunnel, and remove the bulkhead


for the intake structure.


J. Perform operational tests on all four high pressure gates.


It is anticipated the contract will be a fixed price construction contract. This is a total


small business set aside. The North American Industry Classification System Code


(NAICS) is 237990 Other Heavy and Civil Engineering Construction with a small


business size standard of $33.5M. The estimated magnitude of the requirement in terms


of physical characteristics and estimated range is between $1,000,000 and $5,000,000.


Anticipated award is for a contract with an estimated 16 month duration. Request for


Proposal No. R16PS00929, using procedures prescribed by FAR Part 36 - Construction


Architect-Engineer Contracts in conjunction with FAR Part 15 - Contracting by


Negotiation, will be posted shortly after transmission of this synopsis.


All responsible sources may submit a proposal which shall be considered by the agency.


An electronic copy of the solicitation will be available within the next few weeks at


Federal Business Opportunities www.fbo.gov or directly at FedConnect


https://www.fedconnect.net/FedConnect/Default.htm. Once logged into the


"FedBizOpps" web-site, type in the Solicitation Number "R16PS00929" in the


Keyword/Solicitation # field.


A site visit will be held. The date and details will be provided in Section L of the


solicitation and on the website https://www.fbo.gov/


Submit all questions in writing to mcouvrette@usbr.gov. Only questions submitted in


writing will be addressed during the site visit and subsequent amendment. Prospective


offerors must be registered and must maintain an active registration in the System for


Award Management database found at http://www.sam.gov.



Update #5 ·

Added: Apr 28, 2016 10:30 am Modified: Jul 08, 2016 4:07 pmTrack Changes See attachments for Amendment 2



This amendment required to post the full solicitation package (see attached documents)

R16PS00929 Lemon Dam High Pressure Gate ModificatioSYNOPSIS

R16PS00929 Lemon Dam High Pressure Gate Modification


The Bureau of Reclamation, Upper Colorado Region, has a requirement to replace the gate seats and perform coating repairs to the guard gates and appurtenant features of the Lemon Dam outlet works. Lemon Dam is located on the Florida River approximately 16 miles Northeast of Durango, Colorado in La Plata County.


A. The work will begin after summer reservoir releases have been complete. This ranges from 9/1/2016 to 9/30/2017. All work as described in this solicitation shall be completed 16 months after notice to proceed
B. Fabricate and provide a steel intake bulkhead gate.
C. Remove, refurbish, the four trashracks that are located in the intake structure below the water surface of the reservoir. Reinstall the trashracks after the bulkhead has been removed. Refurbishment of the trashracks also referred to trashracks repair and trashracks coating the Section B is optional and is at the discretion of the CO. If the CO elects not to repair and coat the trashracks, the trashracks will remain below the surface of the reservoir and will not be exposed to the atmosphere.
D. Isolate the main outlet works by setting the contractor provided bulkhead in the intake structure, and drain the inlet tunnel.
E. Water will be released through the bulkhead to maintain river flow. There will be two hoses plumbed through the bulkhead that connect into a 12-inch hose. The 12-inch will run the length of the upstream tunnel which is approximately 1000 -feet. There will be a regulating valve adjacent to the high pressure gates that will control the releases of water through the tunnel. There will be times such as during the set-up an disassembly of the hose system that releases cannot be made through the bulkhead; releases will be made by pumping no less than 3 cubic feet per second into the stilling basin to maintain constant releases from the reservoir to the Florida River.
F. The tunnel wyes upstream of the 4 - 2'- 3" x 2'- 3" High Pressure Gates. Water flow in the tunnel will be diverted to flow through gates 1 and 3 when work is being performed on gates 2 and 4, and the water will be diverted to flow through gates 2 and 4 when work is being performed on gates 1 and 3.
G. Modify and repair 4 - 2'- 3" x 2'- 3" High Pressure Gates and hoists. This includes but is not limited to:
1. Furnishing and installing new composite self-lubricating high-pressure gate leaf seats and new bronze frame seats.
2. Performing surface preparation and applying coatings on the four high-pressure gate leaves and hoists.
3. Performing surface preparation and applying coatings on the four high-pressure gates.
4. Installing new hydraulic valves, pipe, and fittings at each hoist.
H. Test the four high pressure gates under the equivalent pressure of lake head. This will be performed without charging the tunnel between the bulkhead and the high pressure gates. Pressure can be placed upstream side of the gates by installing an expansion bulkhead downstream of the wye.
I. Close the High Pressure gates and fill the intake tunnel, and remove the bulkhead for the intake structure.
J. Perform operational tests on all four high pressure gates.
It is anticipated the contract will be a fixed price construction contract. This is a total small business set aside. The North American Industry Classification System Code (NAICS) is 237990 Other Heavy and Civil Engineering Construction with a small business size standard of $33.5M. The estimated magnitude of the requirement in terms of physical characteristics and estimated range is between $1,000,000 and $5,000,000.


Anticipated award is for a contract with an estimated 16 month duration. Request for Proposal No. R16PS00929, using procedures prescribed by FAR Part 36 - Construction Architect-Engineer Contracts in conjunction with FAR Part 15 - Contracting by Negotiation, will be posted shortly after transmission of this synopsis.


All responsible sources may submit a proposal which shall be considered by the agency. An electronic copy of the solicitation will be available within the next few weeks at Federal Business Opportunities www.fbo.gov or directly at FedConnect https://www.fedconnect.net/FedConnect/Default.htm. Once logged into the "FedBizOpps" web-site, type in the Solicitation Number "R16PS00929" in the Keyword/Solicitation # field.


A site visit will be held. The date and details will be provided in Section L of the solicitation and on the website https://www.fbo.gov/


Submit all questions in writing to mcouvrette@usbr.gov. Only questions submitted in writing will be addressed during the site visit and subsequent amendment. Prospective offerors must be registered and must maintain an active registration in the System for Award Management database found at http://www.sam.gov.


The Bureau of Reclamation, Upper Colorado Region, has a requirement to construct an


approximate 74-acre foot regulating reservoir and appurtenant structures. The work is


located on Orchard Mesa, approximately 5 miles southwest of Grand Junction, Colorado


in Mesa County.


A. The work will begin after summer reservoir releases have been complete. This


ranges from 9/1/2016 to 9/30/2017. All work as described in this solicitation shall


be completed 16 months after notice to proceed


B. Fabricate and provide a steel intake bulkhead gate.


C. Remove, refurbish, the four trashracks that are located in the intake structure


below the water surface of the reservoir. Reinstall the trashracks after the


bulkhead has been removed. Refurbishment of the trashracks also referred to


trashracks repair and trashracks coating the Section B is optional and is at the


discretion of the CO. If the CO elects not to repair and coat the trashracks, the


trashracks will remain below the surface of the reservoir and will not be exposed


to the atmosphere.


D. Isolate the main outlet works by setting the contractor provided bulkhead in the


intake structure, and drain the inlet tunnel.


E. Water will be released through the bulkhead to maintain river flow. There will be


two hoses plumbed through the bulkhead that connect into a 12-inch hose. The


12-inch will run the length of the upstream tunnel which is approximately 1000 -


feet. There will be a regulating valve adjacent to the high pressure gates that will


control the releases of water through the tunnel. There will be times such as


during the set-up an disassembly of the hose system that releases cannot be made


through the bulkhead; releases will be made by pumping no less than 3 cubic feet


per second into the stilling basin to maintain constant releases from the reservoir


to the Florida River.


F. The tunnel wyes upstream of the 4 - 2'- 3" x 2'- 3" High Pressure Gates. Water


flow in the tunnel will be diverted to flow through gates 1 and 3 when work is


being performed on gates 2 and 4, and the water will be diverted to flow through


gates 2 and 4 when work is being performed on gates 1 and 3.


G. Modify and repair 4 - 2'- 3" x 2'- 3" High Pressure Gates and hoists. This


includes but is not limited to:


1. Furnishing and installing new composite self-lubricating high-pressure gate leaf


seats and new bronze frame seats.


2. Performing surface preparation and applying coatings on the four high-pressure


gate leaves and hoists.


3. Performing surface preparation and applying coatings on the four high-pressure


gates.


4. Installing new hydraulic valves, pipe, and fittings at each hoist.


H. Test the four high pressure gates under the equivalent pressure of lake head. This


will be performed without charging the tunnel between the bulkhead and the high


pressure gates. Pressure can be placed upstream side of the gates by installing an


expansion bulkhead downstream of the wye.


I. Close the High Pressure gates and fill the intake tunnel, and remove the bulkhead


for the intake structure.


J. Perform operational tests on all four high pressure gates.


It is anticipated the contract will be a fixed price construction contract. This is a total


small business set aside. The North American Industry Classification System Code


(NAICS) is 237990 Other Heavy and Civil Engineering Construction with a small


business size standard of $33.5M. The estimated magnitude of the requirement in terms


of physical characteristics and estimated range is between $1,000,000 and $5,000,000.


Anticipated award is for a contract with an estimated 16 month duration. Request for


Proposal No. R16PS00929, using procedures prescribed by FAR Part 36 - Construction


Architect-Engineer Contracts in conjunction with FAR Part 15 - Contracting by


Negotiation, will be posted shortly after transmission of this synopsis.


All responsible sources may submit a proposal which shall be considered by the agency.


An electronic copy of the solicitation will be available within the next few weeks at


Federal Business Opportunities www.fbo.gov or directly at FedConnect


https://www.fedconnect.net/FedConnect/Default.htm. Once logged into the


"FedBizOpps" web-site, type in the Solicitation Number "R16PS00929" in the


Keyword/Solicitation # field.


A site visit will be held. The date and details will be provided in Section L of the


solicitation and on the website https://www.fbo.gov/


Submit all questions in writing to mcouvrette@usbr.gov. Only questions submitted in


writing will be addressed during the site visit and subsequent amendment. Prospective


offerors must be registered and must maintain an active registration in the System for


Award Management database found at http://www.sam.gov.



Update #4 ·

Added: Jul 05, 2016 3:05 pm Amendment 001
The purpose of this amendment is to:
1. Update the specification and rawings.
2. Update the question and answer due date.

Update #3 ·

Added: Apr 28, 2016 10:30 am Modified: Jun 23, 2016 2:15 pmTrack Changes This amendment required to post the full solicitation package (see attached documents)

R16PS00929 Lemon Dam High Pressure Gate ModificatioSYNOPSIS

R16PS00929 Lemon Dam High Pressure Gate Modification


The Bureau of Reclamation, Upper Colorado Region, has a requirement to replace the gate seats and perform coating repairs to the guard gates and appurtenant features of the Lemon Dam outlet works. Lemon Dam is located on the Florida River approximately 16 miles Northeast of Durango, Colorado in La Plata County.


A. The work will begin after summer reservoir releases have been complete. This ranges from 9/1/2016 to 9/30/2017. All work as described in this solicitation shall be completed 16 months after notice to proceed
B. Fabricate and provide a steel intake bulkhead gate.
C. Remove, refurbish, the four trashracks that are located in the intake structure below the water surface of the reservoir. Reinstall the trashracks after the bulkhead has been removed. Refurbishment of the trashracks also referred to trashracks repair and trashracks coating the Section B is optional and is at the discretion of the CO. If the CO elects not to repair and coat the trashracks, the trashracks will remain below the surface of the reservoir and will not be exposed to the atmosphere.
D. Isolate the main outlet works by setting the contractor provided bulkhead in the intake structure, and drain the inlet tunnel.
E. Water will be released through the bulkhead to maintain river flow. There will be two hoses plumbed through the bulkhead that connect into a 12-inch hose. The 12-inch will run the length of the upstream tunnel which is approximately 1000 -feet. There will be a regulating valve adjacent to the high pressure gates that will control the releases of water through the tunnel. There will be times such as during the set-up an disassembly of the hose system that releases cannot be made through the bulkhead; releases will be made by pumping no less than 3 cubic feet per second into the stilling basin to maintain constant releases from the reservoir to the Florida River.
F. The tunnel wyes upstream of the 4 - 2'- 3" x 2'- 3" High Pressure Gates. Water flow in the tunnel will be diverted to flow through gates 1 and 3 when work is being performed on gates 2 and 4, and the water will be diverted to flow through gates 2 and 4 when work is being performed on gates 1 and 3.
G. Modify and repair 4 - 2'- 3" x 2'- 3" High Pressure Gates and hoists. This includes but is not limited to:
1. Furnishing and installing new composite self-lubricating high-pressure gate leaf seats and new bronze frame seats.
2. Performing surface preparation and applying coatings on the four high-pressure gate leaves and hoists.
3. Performing surface preparation and applying coatings on the four high-pressure gates.
4. Installing new hydraulic valves, pipe, and fittings at each hoist.
H. Test the four high pressure gates under the equivalent pressure of lake head. This will be performed without charging the tunnel between the bulkhead and the high pressure gates. Pressure can be placed upstream side of the gates by installing an expansion bulkhead downstream of the wye.
I. Close the High Pressure gates and fill the intake tunnel, and remove the bulkhead for the intake structure.
J. Perform operational tests on all four high pressure gates.
It is anticipated the contract will be a fixed price construction contract. This is a total small business set aside. The North American Industry Classification System Code (NAICS) is 237990 Other Heavy and Civil Engineering Construction with a small business size standard of $33.5M. The estimated magnitude of the requirement in terms of physical characteristics and estimated range is between $1,000,000 and $5,000,000.


Anticipated award is for a contract with an estimated 16 month duration. Request for Proposal No. R16PS00929, using procedures prescribed by FAR Part 36 - Construction Architect-Engineer Contracts in conjunction with FAR Part 15 - Contracting by Negotiation, will be posted shortly after transmission of this synopsis.


All responsible sources may submit a proposal which shall be considered by the agency. An electronic copy of the solicitation will be available within the next few weeks at Federal Business Opportunities www.fbo.gov or directly at FedConnect https://www.fedconnect.net/FedConnect/Default.htm. Once logged into the "FedBizOpps" web-site, type in the Solicitation Number "R16PS00929" in the Keyword/Solicitation # field.


A site visit will be held. The date and details will be provided in Section L of the solicitation and on the website https://www.fbo.gov/


Submit all questions in writing to mcouvrette@usbr.gov. Only questions submitted in writing will be addressed during the site visit and subsequent amendment. Prospective offerors must be registered and must maintain an active registration in the System for Award Management database found at http://www.sam.gov.


The Bureau of Reclamation, Upper Colorado Region, has a requirement to construct an


approximate 74-acre foot regulating reservoir and appurtenant structures. The work is


located on Orchard Mesa, approximately 5 miles southwest of Grand Junction, Colorado


in Mesa County.


A. The work will begin after summer reservoir releases have been complete. This


ranges from 9/1/2016 to 9/30/2017. All work as described in this solicitation shall


be completed 16 months after notice to proceed


B. Fabricate and provide a steel intake bulkhead gate.


C. Remove, refurbish, the four trashracks that are located in the intake structure


below the water surface of the reservoir. Reinstall the trashracks after the


bulkhead has been removed. Refurbishment of the trashracks also referred to


trashracks repair and trashracks coating the Section B is optional and is at the


discretion of the CO. If the CO elects not to repair and coat the trashracks, the


trashracks will remain below the surface of the reservoir and will not be exposed


to the atmosphere.


D. Isolate the main outlet works by setting the contractor provided bulkhead in the


intake structure, and drain the inlet tunnel.


E. Water will be released through the bulkhead to maintain river flow. There will be


two hoses plumbed through the bulkhead that connect into a 12-inch hose. The


12-inch will run the length of the upstream tunnel which is approximately 1000 -


feet. There will be a regulating valve adjacent to the high pressure gates that will


control the releases of water through the tunnel. There will be times such as


during the set-up an disassembly of the hose system that releases cannot be made


through the bulkhead; releases will be made by pumping no less than 3 cubic feet


per second into the stilling basin to maintain constant releases from the reservoir


to the Florida River.


F. The tunnel wyes upstream of the 4 - 2'- 3" x 2'- 3" High Pressure Gates. Water


flow in the tunnel will be diverted to flow through gates 1 and 3 when work is


being performed on gates 2 and 4, and the water will be diverted to flow through


gates 2 and 4 when work is being performed on gates 1 and 3.


G. Modify and repair 4 - 2'- 3" x 2'- 3" High Pressure Gates and hoists. This


includes but is not limited to:


1. Furnishing and installing new composite self-lubricating high-pressure gate leaf


seats and new bronze frame seats.


2. Performing surface preparation and applying coatings on the four high-pressure


gate leaves and hoists.


3. Performing surface preparation and applying coatings on the four high-pressure


gates.


4. Installing new hydraulic valves, pipe, and fittings at each hoist.


H. Test the four high pressure gates under the equivalent pressure of lake head. This


will be performed without charging the tunnel between the bulkhead and the high


pressure gates. Pressure can be placed upstream side of the gates by installing an


expansion bulkhead downstream of the wye.


I. Close the High Pressure gates and fill the intake tunnel, and remove the bulkhead


for the intake structure.


J. Perform operational tests on all four high pressure gates.


It is anticipated the contract will be a fixed price construction contract. This is a total


small business set aside. The North American Industry Classification System Code


(NAICS) is 237990 Other Heavy and Civil Engineering Construction with a small


business size standard of $33.5M. The estimated magnitude of the requirement in terms


of physical characteristics and estimated range is between $1,000,000 and $5,000,000.


Anticipated award is for a contract with an estimated 16 month duration. Request for


Proposal No. R16PS00929, using procedures prescribed by FAR Part 36 - Construction


Architect-Engineer Contracts in conjunction with FAR Part 15 - Contracting by


Negotiation, will be posted shortly after transmission of this synopsis.


All responsible sources may submit a proposal which shall be considered by the agency.


An electronic copy of the solicitation will be available within the next few weeks at


Federal Business Opportunities www.fbo.gov or directly at FedConnect


https://www.fedconnect.net/FedConnect/Default.htm. Once logged into the


"FedBizOpps" web-site, type in the Solicitation Number "R16PS00929" in the


Keyword/Solicitation # field.


A site visit will be held. The date and details will be provided in Section L of the


solicitation and on the website https://www.fbo.gov/


Submit all questions in writing to mcouvrette@usbr.gov. Only questions submitted in


writing will be addressed during the site visit and subsequent amendment. Prospective


offerors must be registered and must maintain an active registration in the System for


Award Management database found at http://www.sam.gov.



Update #2 ·

Added: Apr 28, 2016 10:30 am Modified: Jun 07, 2016 5:12 pmTrack Changes R16PS00929 Lemon Dam High Pressure Gate ModificatioSYNOPSIS

R16PS00929 Lemon Dam High Pressure Gate Modification


The Bureau of Reclamation, Upper Colorado Region, has a requirement to replace the gate seats and perform coating repairs to the guard gates and appurtenant features of the Lemon Dam outlet works. Lemon Dam is located on the Florida River approximately 16 miles Northeast of Durango, Colorado in La Plata County.


A. The work will begin after summer reservoir releases have been complete. This ranges from 9/1/2016 to 9/30/2017. All work as described in this solicitation shall be completed 16 months after notice to proceed
B. Fabricate and provide a steel intake bulkhead gate.
C. Remove, refurbish, the four trashracks that are located in the intake structure below the water surface of the reservoir. Reinstall the trashracks after the bulkhead has been removed. Refurbishment of the trashracks also referred to trashracks repair and trashracks coating the Section B is optional and is at the discretion of the CO. If the CO elects not to repair and coat the trashracks, the trashracks will remain below the surface of the reservoir and will not be exposed to the atmosphere.
D. Isolate the main outlet works by setting the contractor provided bulkhead in the intake structure, and drain the inlet tunnel.
E. Water will be released through the bulkhead to maintain river flow. There will be two hoses plumbed through the bulkhead that connect into a 12-inch hose. The 12-inch will run the length of the upstream tunnel which is approximately 1000 -feet. There will be a regulating valve adjacent to the high pressure gates that will control the releases of water through the tunnel. There will be times such as during the set-up an disassembly of the hose system that releases cannot be made through the bulkhead; releases will be made by pumping no less than 3 cubic feet per second into the stilling basin to maintain constant releases from the reservoir to the Florida River.
F. The tunnel wyes upstream of the 4 - 2'- 3" x 2'- 3" High Pressure Gates. Water flow in the tunnel will be diverted to flow through gates 1 and 3 when work is being performed on gates 2 and 4, and the water will be diverted to flow through gates 2 and 4 when work is being performed on gates 1 and 3.
G. Modify and repair 4 - 2'- 3" x 2'- 3" High Pressure Gates and hoists. This includes but is not limited to:
1. Furnishing and installing new composite self-lubricating high-pressure gate leaf seats and new bronze frame seats.
2. Performing surface preparation and applying coatings on the four high-pressure gate leaves and hoists.
3. Performing surface preparation and applying coatings on the four high-pressure gates.
4. Installing new hydraulic valves, pipe, and fittings at each hoist.
H. Test the four high pressure gates under the equivalent pressure of lake head. This will be performed without charging the tunnel between the bulkhead and the high pressure gates. Pressure can be placed upstream side of the gates by installing an expansion bulkhead downstream of the wye.
I. Close the High Pressure gates and fill the intake tunnel, and remove the bulkhead for the intake structure.
J. Perform operational tests on all four high pressure gates.
It is anticipated the contract will be a fixed price construction contract. This is a total small business set aside. The North American Industry Classification System Code (NAICS) is 237990 Other Heavy and Civil Engineering Construction with a small business size standard of $33.5M. The estimated magnitude of the requirement in terms of physical characteristics and estimated range is between $1,000,000 and $5,000,000.


Anticipated award is for a contract with an estimated 16 month duration. Request for Proposal No. R16PS00929, using procedures prescribed by FAR Part 36 - Construction Architect-Engineer Contracts in conjunction with FAR Part 15 - Contracting by Negotiation, will be posted shortly after transmission of this synopsis.


All responsible sources may submit a proposal which shall be considered by the agency. An electronic copy of the solicitation will be available within the next few weeks at Federal Business Opportunities www.fbo.gov or directly at FedConnect https://www.fedconnect.net/FedConnect/Default.htm. Once logged into the "FedBizOpps" web-site, type in the Solicitation Number "R16PS00929" in the Keyword/Solicitation # field.


A site visit will be held. The date and details will be provided in Section L of the solicitation and on the website https://www.fbo.gov/


Submit all questions in writing to mcouvrette@usbr.gov. Only questions submitted in writing will be addressed during the site visit and subsequent amendment. Prospective offerors must be registered and must maintain an active registration in the System for Award Management database found at http://www.sam.gov.


The Bureau of Reclamation, Upper Colorado Region, has a requirement to construct an


approximate 74-acre foot regulating reservoir and appurtenant structures. The work is


located on Orchard Mesa, approximately 5 miles southwest of Grand Junction, Colorado


in Mesa County.


A. The work will begin after summer reservoir releases have been complete. This


ranges from 9/1/2016 to 9/30/2017. All work as described in this solicitation shall


be completed 16 months after notice to proceed


B. Fabricate and provide a steel intake bulkhead gate.


C. Remove, refurbish, the four trashracks that are located in the intake structure


below the water surface of the reservoir. Reinstall the trashracks after the


bulkhead has been removed. Refurbishment of the trashracks also referred to


trashracks repair and trashracks coating the Section B is optional and is at the


discretion of the CO. If the CO elects not to repair and coat the trashracks, the


trashracks will remain below the surface of the reservoir and will not be exposed


to the atmosphere.


D. Isolate the main outlet works by setting the contractor provided bulkhead in the


intake structure, and drain the inlet tunnel.


E. Water will be released through the bulkhead to maintain river flow. There will be


two hoses plumbed through the bulkhead that connect into a 12-inch hose. The


12-inch will run the length of the upstream tunnel which is approximately 1000 -


feet. There will be a regulating valve adjacent to the high pressure gates that will


control the releases of water through the tunnel. There will be times such as


during the set-up an disassembly of the hose system that releases cannot be made


through the bulkhead; releases will be made by pumping no less than 3 cubic feet


per second into the stilling basin to maintain constant releases from the reservoir


to the Florida River.


F. The tunnel wyes upstream of the 4 - 2'- 3" x 2'- 3" High Pressure Gates. Water


flow in the tunnel will be diverted to flow through gates 1 and 3 when work is


being performed on gates 2 and 4, and the water will be diverted to flow through


gates 2 and 4 when work is being performed on gates 1 and 3.


G. Modify and repair 4 - 2'- 3" x 2'- 3" High Pressure Gates and hoists. This


includes but is not limited to:


1. Furnishing and installing new composite self-lubricating high-pressure gate leaf


seats and new bronze frame seats.


2. Performing surface preparation and applying coatings on the four high-pressure


gate leaves and hoists.


3. Performing surface preparation and applying coatings on the four high-pressure


gates.


4. Installing new hydraulic valves, pipe, and fittings at each hoist.


H. Test the four high pressure gates under the equivalent pressure of lake head. This


will be performed without charging the tunnel between the bulkhead and the high


pressure gates. Pressure can be placed upstream side of the gates by installing an


expansion bulkhead downstream of the wye.


I. Close the High Pressure gates and fill the intake tunnel, and remove the bulkhead


for the intake structure.


J. Perform operational tests on all four high pressure gates.


It is anticipated the contract will be a fixed price construction contract. This is a total


small business set aside. The North American Industry Classification System Code


(NAICS) is 237990 Other Heavy and Civil Engineering Construction with a small


business size standard of $33.5M. The estimated magnitude of the requirement in terms


of physical characteristics and estimated range is between $1,000,000 and $5,000,000.


Anticipated award is for a contract with an estimated 16 month duration. Request for


Proposal No. R16PS00929, using procedures prescribed by FAR Part 36 - Construction


Architect-Engineer Contracts in conjunction with FAR Part 15 - Contracting by


Negotiation, will be posted shortly after transmission of this synopsis.


All responsible sources may submit a proposal which shall be considered by the agency.


An electronic copy of the solicitation will be available within the next few weeks at


Federal Business Opportunities www.fbo.gov or directly at FedConnect


https://www.fedconnect.net/FedConnect/Default.htm. Once logged into the


"FedBizOpps" web-site, type in the Solicitation Number "R16PS00929" in the


Keyword/Solicitation # field.


A site visit will be held. The date and details will be provided in Section L of the


solicitation and on the website https://www.fbo.gov/


Submit all questions in writing to mcouvrette@usbr.gov. Only questions submitted in


writing will be addressed during the site visit and subsequent amendment. Prospective


offerors must be registered and must maintain an active registration in the System for


Award Management database found at http://www.sam.gov.



Update #1 ·

Added: Apr 28, 2016 10:30 am The Bureau of Reclamation, Upper Colorado Region, has a requirement to construct an approximate 74-acre foot regulating reservoir and appurtenant structures. The work is located on Orchard Mesa, approximately 5 miles southwest of Grand Junction, Colorado in Mesa County.

Attachments

Files attached to this notice, newest first
File Type Posted
Amendment_004_SF_30.pdf PDF
PRICE_SCHEDULE_for_Amendment_4.docx DOCX document
SF_30_Amendment_003.pdf PDF
519-D-93.pdf PDF
519-D-94.pdf PDF
Solicitation_Questions_and_Answers_7.19.2016.docx DOCX document
TrashRackPhotos.pdf PDF
site_visit_sign_in_sheet_7.6.16.pdf PDF
Solicitation_Questions_(1).docx DOCX document
Sol_R16PS00929_Amd_000002_SF_30.pdf PDF
Tab_14_-Lemon_DamR16PS00929_Solicitation_Vol_I_7.7.16.docx DOCX document
Lemon_Dam_High_Pressure_Gate_Modification_Amendment_001_SF_30.pdf PDF
Tab_14_-Lemon_DamR16PS00929_Solicitation_Vol_I_7.5.16.pdf PDF
SpecificationLemonDam_revised_7.5.16.pdf PDF
Summary_of_changes_Ammendment_001.pdf PDF
Tab_13_-R16PS00929_1442.pdf PDF
Tab_13_-_ATT_1_Wage_Determination_R16PS00929.pdf PDF
Tab_13_-Att_2_Specification_Lemon_Dam_High_Pressure_Gate_Modification_R16PS00929.pdf PDF
Tab_14_-Lemon_DamR16PS00929_Solicitation_Vol_I.pdf PDF
Tab_14_-_Attachment_4_Subcontract_Worksheet_R16PS00929.docx DOCX document
Tab_14_-_Attachment_3_Performance_Questionnaire_R16PS00929.docx DOCX document
Tab_09_-_Synopsis_Lemon_Dam_High_Pressure_Gate_Modification_(4).docx DOCX document
Tab_09_-_Synopsis_Lemon_Dam_High_Pressure_Gate_Modification.docx DOCX document
Show all 23

On GovTribe

Work this opportunity on GovTribe

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity