CONSTRUCTION PROJECT - Bldg 356, 357, 358 & 360
Award Notice Posted
- Solicitation number
- W912GY-17-R-0017
- Agency
-
ACC Warren
Army Contracting Command, Department of Defense
- Awarded
- to Herman Construction Group, Inc.
- Set-aside
- Competitive 8(a)
Opportunity facts
- Contract number
- W912GY-18-C-0010 Federal contract award
- NAICS code
- 236210 Industrial Building Construction
- PSC
- Not on record
- Place of performance
- Sierra Army Depot, CA, California, United States
Notice details come from SAM.gov. Updated .
Notice text
7 versions
Update #7 · Latest ·
Awarded Vendors: HERMAN CONSTRUCTION GROUP, INC.. Contract Award Dollar Amount: 7,668,100.00. Contract Award Date: 2018-06-22.
Update #6 ·
*****ONLY PERFORMANCE AND PAYMENT BONDS ARE REQUIRED FOR THIS SOLICITATION. BID BONDS ARE NOT REQUIRED.*****
*****ALL QUESTIONS NEED TO BE SUBMITTED BY 5PM EST ON AUGUST 7, 2017. NO FURTHER QUESTIONS WILL BE ANSWERED AFTER THIS DATE*****
Army Contract Command - Warren (ACC-WRN) is soliciting for repairs to Buildings 356, 357, 358, and 360 at SIAD, using a firm fixed price C-Type contract. This action will be an 8(a) set-aside, and competed among all capable 8(a) construction companies. Repairs to these buildings are needed over the next year.
There are many tasks that must be completed for the buildings to be fully repaired. Some of those tasks include: remove and retain termination bar, remove and retain of gutters and all downspouts, repair roof along edge of the gutters, re-install roof termination bar, remove all siding material and replace with new siding, install moisture barrier to exterior of the building, remove wood bumper system from perimeter of the buildings, remove existing windows and replace with new vinyl windows, install j-channel and trim accessories as needed around doors, Install fanfold insulation, provide and install vinyl trim accessories, apply sealant calking as needed, Install a tooled expansion joint, fill joints with exterior grade flexible joint fill product, dispose of waste, remove and replace old damaged concrete ramps, remove and replace existing sliding cargo doors, in addition to other ancillary tasks associated with each of these repairs.
The Contractor shall provide all labor, materials, equipment, and supervision necessary to complete the work within the Statements of Work (SOW). All work shall be done in a professional workman-like manner and to industrial standards.
Primary Point of Contact.:
Janeca Y Clark
janeca.y.clark.civ@mail.mil
Phone: 5862823546
Contracting Office Address:
6501 EAST 11 MILE ROAD
Warren, Michigan 48397-5000
United States
.
Update #5 ·
Added: Jul 18, 2017 2:55 pm
Modified: Aug 25, 2017 11:11 amTrack Changes
*****ONLY PERFORMANCE AND PAYMENT BONDS ARE REQUIRED FOR THIS SOLICITATION. BID BONDS ARE NOT REQUIRED.*****
*****ALL QUESTIONS NEED TO BE SUBMITTED BY 5PM EST ON AUGUST 7, 2017. NO FURTHER QUESTIONS WILL BE ANSWERED AFTER THIS DATE*****
Army Contract Command - Warren (ACC-WRN) is soliciting for repairs to Buildings 356, 357, 358, and 360 at SIAD, using a firm fixed price C-Type contract. This action will be an 8(a) set-aside, and competed among all capable 8(a) construction companies. Repairs to these buildings are needed over the next year.
There are many tasks that must be completed for the buildings to be fully repaired. Some of those tasks include: remove and retain termination bar, remove and retain of gutters and all downspouts, repair roof along edge of the gutters, re-install roof termination bar, remove all siding material and replace with new siding, install moisture barrier to exterior of the building, remove wood bumper system from perimeter of the buildings, remove existing windows and replace with new vinyl windows, install j-channel and trim accessories as needed around doors, Install fanfold insulation, provide and install vinyl trim accessories, apply sealant calking as needed, Install a tooled expansion joint, fill joints with exterior grade flexible joint fill product, dispose of waste, remove and replace old damaged concrete ramps, remove and replace existing sliding cargo doors, in addition to other ancillary tasks associated with each of these repairs.
The Contractor shall provide all labor, materials, equipment, and supervision necessary to complete the work within the Statements of Work (SOW). All work shall be done in a professional workman-like manner and to industrial standards.
Primary Point of Contact.:
Janeca Y Clark
janeca.y.clark.civ@mail.mil
Phone: 5862823546
Contracting Office Address:
6501 EAST 11 MILE ROAD
Warren, Michigan 48397-5000
United States
Update #4 ·
*****ALL QUESTIONS NEED TO BE SUBMITTED BY 5PM EST ON AUGUST 7, 2017. NO FURTHER QUESTIONS WILL BE ANSWERED AFTER THIS DATE*****
Army Contract Command - Warren (ACC-WRN) is soliciting for repairs to Buildings 356, 357, 358, and 360 at SIAD, using a firm fixed price C-Type contract. This action will be an 8(a) set-aside, and competed among all capable 8(a) construction companies. Repairs to these buildings are needed over the next year.
There are many tasks that must be completed for the buildings to be fully repaired. Some of those tasks include: remove and retain termination bar, remove and retain of gutters and all downspouts, repair roof along edge of the gutters, re-install roof termination bar, remove all siding material and replace with new siding, install moisture barrier to exterior of the building, remove wood bumper system from perimeter of the buildings, remove existing windows and replace with new vinyl windows, install j-channel and trim accessories as needed around doors, Install fanfold insulation, provide and install vinyl trim accessories, apply sealant calking as needed, Install a tooled expansion joint, fill joints with exterior grade flexible joint fill product, dispose of waste, remove and replace old damaged concrete ramps, remove and replace existing sliding cargo doors, in addition to other ancillary tasks associated with each of these repairs.
The Contractor shall provide all labor, materials, equipment, and supervision necessary to complete the work within the Statements of Work (SOW). All work shall be done in a professional workman-like manner and to industrial standards.
Primary Point of Contact.:
Janeca Y Clark
janeca.y.clark.civ@mail.mil
Phone: 5862823546
Contracting Office Address:
6501 EAST 11 MILE ROAD
Warren, Michigan 48397-5000
United States
.
Update #3 ·
Added: Jul 18, 2017 2:55 pm
Modified: Aug 01, 2017 11:42 amTrack Changes
*****ALL QUESTIONS NEED TO BE SUBMITTED BY 5PM EST ON AUGUST 7, 2017. NO FURTHER QUESTIONS WILL BE ANSWERED AFTER THIS DATE*****
Army Contract Command - Warren (ACC-WRN) is soliciting for repairs to Buildings 356, 357, 358, and 360 at SIAD, using a firm fixed price C-Type contract. This action will be an 8(a) set-aside, and competed among all capable 8(a) construction companies. Repairs to these buildings are needed over the next year.
There are many tasks that must be completed for the buildings to be fully repaired. Some of those tasks include: remove and retain termination bar, remove and retain of gutters and all downspouts, repair roof along edge of the gutters, re-install roof termination bar, remove all siding material and replace with new siding, install moisture barrier to exterior of the building, remove wood bumper system from perimeter of the buildings, remove existing windows and replace with new vinyl windows, install j-channel and trim accessories as needed around doors, Install fanfold insulation, provide and install vinyl trim accessories, apply sealant calking as needed, Install a tooled expansion joint, fill joints with exterior grade flexible joint fill product, dispose of waste, remove and replace old damaged concrete ramps, remove and replace existing sliding cargo doors, in addition to other ancillary tasks associated with each of these repairs.
The Contractor shall provide all labor, materials, equipment, and supervision necessary to complete the work within the Statements of Work (SOW). All work shall be done in a professional workman-like manner and to industrial standards.
Primary Point of Contact.:
Janeca Y Clark
janeca.y.clark.civ@mail.mil
Phone: 5862823546
Contracting Office Address:
6501 EAST 11 MILE ROAD
Warren, Michigan 48397-5000
United States
Update #2 ·
Army Contract Command - Warren (ACC-WRN) is soliciting for repairs to Buildings 356, 357, 358, and 360 at SIAD, using a firm fixed price C-Type contract. This action will be an 8(a) set-aside, and competed among all capable 8(a) construction companies. Repairs to these buildings are needed over the next year.
There are many tasks that must be completed for the buildings to be fully repaired. Some of those tasks include: remove and retain termination bar, remove and retain of gutters and all downspouts, repair roof along edge of the gutters, re-install roof termination bar, remove all siding material and replace with new siding, install moisture barrier to exterior of the building, remove wood bumper system from perimeter of the buildings, remove existing windows and replace with new vinyl windows, install j-channel and trim accessories as needed around doors, Install fanfold insulation, provide and install vinyl trim accessories, apply sealant calking as needed, Install a tooled expansion joint, fill joints with exterior grade flexible joint fill product, dispose of waste, remove and replace old damaged concrete ramps, remove and replace existing sliding cargo doors, in addition to other ancillary tasks associated with each of these repairs.
The Contractor shall provide all labor, materials, equipment, and supervision necessary to complete the work within the Statements of Work (SOW). All work shall be done in a professional workman-like manner and to industrial standards.
Primary Point of Contact.:
Janeca Y Clark
janeca.y.clark.civ@mail.mil
Phone: 5862823546
Contracting Office Address:
6501 EAST 11 MILE ROAD
Warren, Michigan 48397-5000
United States
.
Update #1 ·
Added: Jul 18, 2017 2:55 pm
Army Contract Command - Warren (ACC-WRN) is soliciting for repairs to Buildings 356, 357, 358, and 360 at SIAD, using a firm fixed price C-Type contract. This action will be an 8(a) set-aside, and competed among all capable 8(a) construction companies. Repairs to these buildings are needed over the next year.
There are many tasks that must be completed for the buildings to be fully repaired. Some of those tasks include: remove and retain termination bar, remove and retain of gutters and all downspouts, repair roof along edge of the gutters, re-install roof termination bar, remove all siding material and replace with new siding, install moisture barrier to exterior of the building, remove wood bumper system from perimeter of the buildings, remove existing windows and replace with new vinyl windows, install j-channel and trim accessories as needed around doors, Install fanfold insulation, provide and install vinyl trim accessories, apply sealant calking as needed, Install a tooled expansion joint, fill joints with exterior grade flexible joint fill product, dispose of waste, remove and replace old damaged concrete ramps, remove and replace existing sliding cargo doors, in addition to other ancillary tasks associated with each of these repairs.
The Contractor shall provide all labor, materials, equipment, and supervision necessary to complete the work within the Statements of Work (SOW). All work shall be done in a professional workman-like manner and to industrial standards.
Primary Point of Contact.:
Janeca Y Clark
janeca.y.clark.civ@mail.mil
Phone: 5862823546
Contracting Office Address:
6501 EAST 11 MILE ROAD
Warren, Michigan 48397-5000
United States
Files
| File | Type | Posted |
|---|---|---|
| Revised-Epoxy_Broadcast_Floor_Coating_system.doc | DOC document | |
| W912GY-17-R-0017_0002.pdf | ||
| SOW_Bldg_358_.docx | DOCX document | |
| SOW_Bldg_360_.docx | DOCX document | |
| Construction_Q&A_-_Group_B.docx | DOCX document | |
| W912GY-17-R-0017_0001.pdf | ||
| Service_Entrance_Conductors_Warehouse_2017-02-16.pdf | ||
| SOW_Bldg_356_.docx | DOCX document | |
| SOW_Bldg_357.docx | DOCX document | |
| Bldg_356_Electrical_22Mar17.pdf | ||
| Construction_QA.docx | DOCX document | |
| BUILDING_356_Post_and_Truss_Repair.pdf | ||
| Bldg_360_Lighting_-_2017-03-15.pdf | ||
| End-wall_brace_detail.pdf | ||
| Wall_Pipe_Bracing_over_roll-up_doors..pdf | ||
| Epoxy_Broadcast_Floor_Coating_system.doc | DOC document | |
| Bldg_356_Lighting_22Mar17.pdf | ||
| Bldg_358__Lift_Tables_drawing.pdf | ||
| Drawings_Bldg_357_Lift_table_location.pdf | ||
| SOW_Bldg_357.pdf | ||
| SOW_Bldg_358_.pdf | ||
| SOW_Bldg_356_.pdf | ||
| SOW_Bldg_360_.pdf | ||
| Wage_Determination_-_Construction_(SIAD).pdf | ||
| W912GY-17-R-0017.pdf |
Show all 25
Notice history
| Notice | Type | Posted |
|---|---|---|
| This notice | Award Notice | |
| SIAD Construction Project - Group B (356, 357, 358, 360) | Award Notice | |
| SIAD Construction Project - Group B | Award Notice |
On GovTribe
Work this opportunity
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity