AZ FLAP SR181(1) Chiricahua Access Road
Pre-Solicitation Posted
This opportunity was awarded. See the award notice from , or the latest solicitation from .
- Solicitation number
- 6982AF24B000001
- Agency
-
Federal Highway Administration
Department of Transportation
- Responses due
- Not on record
- Set-aside
- No set-aside
Opportunity facts
- NAICS code
- 237310 Highway, Street, and Bridge Construction
- Place of performance
- Willcox, Arizona 85643, United States
Notice details come from SAM.gov. Updated .
About this opportunity
This pre-solicitation notice involves pulverization and paving of approximately 3 miles of existing asphalt roadway leading to Chiricahua National Monument in Cochise County, Arizona. The Department of Transportation Federal Highway Administration seeks to procure minor roadway widening, drainage improvements, guardrail installation, and associated construction services. Key requirements include construction phasing, temporary traffic control, and timely project completion to minimize disruptions. The anticipated advertisement date is late November 2023, with an estimated price range of $5-10 million.
There is no set-aside designation. Significant quantities include 11,500 tons of asphalt, 5,750 tons of aggregate base, and 11,000 cubic yards of excavation. Construction is anticipated from March 2024 to August 2024. Key numerical details involve 3 miles of roadway improvements, 400 linear feet of guardrail installation, and 900 linear feet of culverts.
Notice text
THIS IS NOT AN INVITATION FOR BID - PLANS AND SPECIFICATIONS ARE NOT AVAILABLE.
Project Number: AZ FLAP SR181(1)
Project Name: Chiricahua Access Road
This project consists of pulverization and paving of approximately 3 miles of existing asphalt paved roadway leading to Chiricahua National Monument within Cochise County, Arizona. Some minor widening is also proposed. Work also includes drainage improvements and guardrail installation.
SIGNIFICANT QUANTITIES:
11,500 tons of asphalt concrete pavement,
5,750 tons of aggregate base,
6,000 cubic yards of subexcavation,
11,000 cubic yards of roadway excavation,
400 linear feet of guardrail,
100 cubic yards of riprap, and
900 linear feet of metal pipe culverts.
MISCELLANEOUS: Construction phasing, temporary traffic control, and timely completion of construction will be crucial to minimize disruptions to Chiricahua National Monument visitors and residents throughout construction and achieve customer satisfaction.
The andticipated advertisement date is late November 2023 with construction anticipated from March 2024 to August 2024. The estimated price range is between $5,000,000.00 and $10,000,000.00.
Notice history
| Notice | Type | Posted |
|---|---|---|
| AZ FLAP SR181(1) Chiricahua Access Road | Award Notice | |
| AZ FLAP SR181(1) Chiricahua Access Road | Solicitation | |
| This notice | Pre-Solicitation |
Similar open opportunities
| Opportunity | Agency | Set-aside | Responses due |
|---|---|---|---|
| AZ BL COLO 7528(1) Burro Creek Road | Federal Highway Administration | Total Small Business | |
| UT NP ARCH 100(2) Bridges on Delicate Arch Road | Federal Highway Administration | No set-aside | |
| CO-rocky MTN arsnl NWR-patch hill road | — | No set-aside |
On GovTribe
Work this opportunity
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity