Answers__to_questions..doc

DOC document 28 KB Posted

Attached to
GSU ITS PHASE V
Solicitation number
W9133L-14-R-0033
Issued by

About this file

Updated answer for certification.

View the file

Other files

File Type Posted
Amendment_07_for_14-R-0033.doc DOC document
14-R-00033_GSU_AMD_06.doc DOC document
14r-0033_revised_section_L.doc DOC document
amendment_for_14-R-0033.odt ODT document
REVISED_DOC.FOR_14-R-0033.docR.doc DOC document
Answers__to_questions..doc DOC document
W9133L-14-R-0033AMENDMENT_-0004.doc DOC document
AMEND_SECTION_B_FOR__14-R-0033.docx DOCX document
Amendment_3_of_14R0033_rev.doc DOC document
gsu_revisePWS.docx DOCX document
W9133l-14-r-0033_amendment_03.doc DOC document
GSU__answers_part_3.doc DOC document
GSU_ANSWERS__Answers_Part_2.doc DOC document
Phase_VI_W9133L_14_R_0053_Questions_PART_1.xls XLS spreadsheet
A6X-14-015_GSU_POC_List_for_Phase_6.docx DOCX document
AMENDMENT_02_FOR_14-R-0033__EXTENSION.doc DOC document
14R-0033_AMENDMENT_01.doc DOC document
W9133L-14-R-0033.docx DOCX document
GSU_ITS_Project_Phase_5_PWS_.docx DOCX document
Show all 19

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1 Answers to questions indicated Price/Cost submission shall only be in Excel format, does this indicate no narrative is expected for cost volume, just numbers?

ANSWER: You can add narrative

2. Answers to questions indicates FFP travel versus cost reimbursed, why are receipts required if contractor assumes the risk?

ANSWER: Because the government has to verified cost.

3. Phase V, 0033 – There is still uncertainty about the delivery date of 16-JUN-2015 shown in the 0033 solicitation. Page 8 of 89 shows a delivery date of June 16, 2015 for all the CLINs. There is other conflicting information in the PWS Section 1.3 that indicates a Two (2) year period of performance. This was not cleared up in the Q&A and is critical to know. Will the solicitation date be changed to align with a two year period as with the other solicitation?

ANSWER: The period of performance is for 2 years. Start day will be the date of award.

4. Phase V requires 2 Volumes (the A & B tabs identified on pages 82 and 83 do not jive with page 85 Tab C Price).

ANSWER: see revised Section L. Tab C is deleted

5. Please clarify what the government is expecting for Phase V W9133L-14-R-0033 for Tabs A,and B ANSWER. Tab A should include Technical and Management proposal, Resumes, SF 33, TAB B Should include Price and costing data.

6.WWith regards to certification once system is install it needs to be certify that it works.

Certification in Section 1.1 refers to ensuring the 4 communications systems

(WLAN, ISP, OSP, CBN) were installed properly and are operational.