Revised_30_Oct_Cost_Estimate_Workbook_Attachment_2.xlsx

XLSX spreadsheet 55 KB Posted

Attached to
Formerly Utilized Sites Remedial Action Program (FUSRAP)
Solicitation number
W912P9-16-R-0002
Issued by

About this file

Revised 30 Oct Cost Estimate Workbook Attachment 2 in Excel is hereby posted.

View the file

Other files

File Type Posted
Site_Visit_Attendee_Sheet.pdf PDF
W912P9-16-R-0002-0004.pdf PDF
Question_and_Answers_5 _48 _203 _ _213_-_221.docx DOCX document
Question_and_Answers.docx DOCX document
Appendix_A_PPQ_Coversheet.pdf PDF
W912P9-16-R-0002-0002.pdf PDF
W912P9-16-R-0002-0001.pdf PDF
Attachment_4_PPQ.pdf PDF
Attachment_4_PPQ_Cover_Page.pdf PDF
D4_Frost_Ave_Sampling.docx DOCX document
SAG_for_SLS_-_October_2000.pdf PDF
FUSRAP_St__Louis_QAPP_Sep_2015r2_apdf.pdf PDF
Question_and_Answers_Posting_4_November_2015.docx DOCX document
D2_SLDS_FUSRAP_Compound.docx DOCX document
Revised_30_Oct_Cost_Estimate_Workbook_Attachment_2.pdf PDF
D1_SLAPS_FUSRAP_Compound.docx DOCX document
D3_Ballfields_Excavation.docx DOCX document
Question_and_Answers_for_Posting.docx DOCX document
W912P9-16-R-0002.pdf PDF
Show all 19

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Title

SAMPLE PROJECT
WORSHEETS
FORMERLY UTILIZED SITES REMEDIAL ACTION PROGRAM (FUSRAP)
ST. LOUIS SITES SINGLE AWARD TASK ORDER CONTRACT (SATOC)

Summary

SUMARY TOTAL

TASKDESCRIPTIONCOSTLaborMaterialEquipmentSubcontractODC
01.01.01Proj. Managt NORCO$$$$$$
01.01.02Proj. Managt. SLDS$$$$$$
01.02.01Home Off. NORCO$$$$$$
01.02.02Home Off. SLDS$$$$$$
01.03.01Const. Supp. NORCO$$$$$$
01.03.02Const. Supp. SLDS$$$$$$
01.04.01EDC NORCO$$$$$$
01.04.02EDC SLDS$$$$$$
01.05.01Rad Support NORCO$$$$$$
01.05.02Rad Support SLDS$$$$$$
02.06.01IA-9 Ballfields Phase 3$$$$$$
02.07.02PDI Samp Frost Ave$$$$$$
TOTAL$$$$$$
*Summary Costs should be transferred to the Cost Realism Table

Pro Management

WORKSHEET
01.01.00 TASK 1 - - Project Management Support (General Conditions)
Scope: Provide the overall project management staff, administration, data and compliance, reporting, and supporting
field site operations for the FUSRAP North County site project offices and general site activities.
Assumptions:
01.01.01 Project Management Support North County Site (NORCO)
Direct Labor
CodeJob DescriptionHourly RateHoursLabor Cost
Example: Travel.Project Manager000
Project Superintendent000
"000
0
Total Task Hours

Total Field Office Direct Labor Costs 0

Fringe on Direct Labor 0% 0

Field Over head 0% 0

Total Direct Labor Cost 0

Other Direct Costs0
Example: TravelSubcontracting

Subcontracting Total Cost 0

Materials

Material Total Cost 0

Equipment
Equipment Total Cost0

Total ODC Costs 0

SUBTOTAL Direct Cost and ODC 0

G&A 0% 0

Total Task Total without Fee 0

WORKSHEET
01.01.00 TASK 1 - General Conditions - Project Management Support
Scope: Provide the overall project management staff, administration, data and compliance, reporting, and supporting
field site operations for the FUSRAP North County site project offices and general site activities.
Assumptions:
01.01.02 Project Management Support St. Louis Downtown Site (SLDS)
Direct Labor
CodeJob DescriptionHourly RateHoursLabor Cost
Example: Travel.Project Manager000
Project Superintendent000
"000
0
Total Task Hours

Total Field Office Direct Labor Costs 0

Fringe on Direct Labor 0% 0

Field Over head 0% 0

Total Direct Labor Cost 0

Other Direct Costs0
Example: TravelSubcontracting

Subcontracting Total Cost 0

Materials

Material Total Cost 0

Equipment
Equipment Total Cost0

Total ODC Costs 0

SUBTOTAL Direct Cost and ODC 0

G&A 0% 0

Total Task Total without Fee 0

Home Supp

WORKSHEET
01.02.00 TASK 2 - - Home Office Support General Conditions
Scope: Provide Home office support effort in selected management, technical and services areas for which
full time project assigned positons are not required.

Assumptions:

01.02.01 Home Office Support (NORCO)
Direct Labor
CodeJob DescriptionHourly RateHoursLabor Cost
"000
"000
"000
0
Total Task Hours

Total Home Office Direct Labor Costs 0

Fringe on Home Office Labor 0% 0

Home Over head 0% 0

Total Direct Labor Cost 0

Other Direct Costs0
Subcontracting

Subcontracting Total Cost 0

Materials

Material Total Cost 0

Equipment
Equipment Total Cost0

Total ODC Costs 0

SUBTOTAL Direct Cost and ODC 0

G&A 0% 0

Total Task Total without Fee 0

WORKSHEET
01.02.00 TASK 2 - - Home Office Support General Conditions
Scope: Provide Home office support effort in selected management, technical and services areas for which
full time project assigned positions are not required.

Assumptions:

01.02.02 Home Office Support St. Louis Downtown Site (SLDS)
Direct Labor
CodeJob DescriptionHourly RateHoursLabor Cost
"000
"000
"000
0
Total Task Hours

Total Field Office Direct Labor Costs 0

Fringe on Direct Labor 0% 0

Field Over head 0% 0

Total Direct Labor Cost 0

Other Direct Costs0
Subcontracting

Subcontracting Total Cost 0

Materials

Material Total Cost 0

Equipment
Equipment Total Cost0

Total ODC Costs 0

SUBTOTAL Direct Cost and ODC 0

G&A 0% 0

Total Task Total without Fee 0

Con Supp

WORKSHEET
01.03.00 TASK 3 - General Conditons - Construction Support
Scope: Provide supplies necessary to maintain the NORCO office compound. Maintenance includes general site
support, craft trailer, loadout facility, site erosion control, site security, mowing, air monitoring.

Assumptions:

01.03.01 Construction Support NORCO
Direct Labor
CodeJob DescriptionHourly RateHoursLabor Cost
"000
"000
"000
0
Total Task Hours

Total Home Office Direct Labor Costs 0

Fringe on Home Office Labor 0% 0

Home Over head 0% 0

Total Direct Labor Cost 0

Other Direct Costs0
Subcontracting

Subcontracting Total Cost 0

Materials

Material Total Cost 0

Equipment
Equipment Total Cost0

Total ODC Costs 0

SUBTOTAL Direct Cost and ODC 0

G&A 0% 0

Total Task Total without Fee 0

WORKSHEET
01.03.00 TASK 3 - General Conditions - Construction Support
Scope: Provide supplies necessary to maintain the NORCO office compound. Maintenance includes general site
support, craft trailer, loadout facility, site erosion control, site security, mowing, air monitoring.

Assumptions:

01.03.02 Construction Support SLDS
Direct Labor
CodeJob DescriptionHourly RateHoursLabor Cost
"000
"000
"000
0
Total Task Hours

Total Field Office Direct Labor Costs 0

Fringe on Direct Labor 0% 0

Field Over head 0% 0

Total Direct Labor Cost 0

Other Direct Costs0
Subcontracting

Subcontracting Total Cost 0

Materials

Material Total Cost 0

Equipment
Equipment Total Cost0

Total ODC Costs 0

SUBTOTAL Direct Cost and ODC 0

G&A 0% 0

Total Task Total without Fee 0

EDC

WORKSHEET
01.04.00 TASK4 - Engineering During Construction
Scope: Provide field engineering, remedial design, preferential pathway assessments, prepare written
documentation of remedial efforts, prepare scope of work

Government Assumptions: Period of Performance 1 Nov 2015- 31 Oct 2016

01.04.01 Engineering During Construction NORCO
Direct Labor
CodeJob DescriptionHourly RateHoursLabor Cost
"000
"000
"000
0
Total Task Hours

Total Home Office Direct Labor Costs 0

Fringe on Home Office Labor 0% 0

Home Over head 0% 0

Total Direct Labor Cost 0

Other Direct Costs0
Example: TravelSubcontracting

Subcontracting Total Cost 0

Materials

Material Total Cost 0

Equipment
Equipment Total Cost0

Total ODC Costs 0

SUBTOTAL Direct Cost and ODC 0

G&A 0% 0

Total Task Total without Fee 0

WORKSHEET
01.04.00 TASK 4 - Engineering During Construction
Scope: Provide field engineering, remedial design, preferential pathway assessments, prepare written
documentation of remedial efforts, prepare scope of work

Government Assumptions: Period of Performance 1 Nov 2015- 31 Oct 2016

01.04.02 Engineering During Construction SLDS
Direct Labor
CodeJob DescriptionHourly RateHoursLabor Cost
"000
"000
"000
0
Total Task Hours

Total Field Office Direct Labor Costs 0

Fringe on Direct Labor 0% 0

Field Over head 0% 0

Total Direct Labor Cost 0

Other Direct Costs0
Example: TravelSubcontracting

Subcontracting Total Cost 0

Materials

Material Total Cost 0

Equipment
Equipment Total Cost0

Total ODC Costs 0

SUBTOTAL Direct Cost and ODC 0

G&A 0% 0

Total Task Total without Fee 0

Rad Supp

WORKSHEET
01.05.00 TASK 5 - Radiological Support (General Conditions)
Scope: Provide service to oversee radiological work and ensure compliance with regulatory requirements.
conduct radiological surveys, provide and maintain respiratory protective equipment

Government Assumptions: Period of Performance 1 Nov 2015- 31 Oct 2016

01.05.01 Rad Support NORCO
Direct Labor
CodeJob DescriptionHourly RateHoursLabor Cost
"000
"000
"000
0
Total Task Hours

Total Home Office Direct Labor Costs 0

Fringe on Home Office Labor 0% 0

Home Over head 0% 0

Total Direct Labor Cost 0

Other Direct Costs0
Subcontracting

Subcontracting Total Cost 0

Materials

Material Total Cost 0

Equipment
Equipment Total Cost0

Total ODC Costs 0

SUBTOTAL Direct Cost and ODC 0

G&A 0% 0

Total Task Total without Fee 0

WORKSHEET
01.05.00 TASK 5 - Radiological Support (General Conditions)
Scope: Provide service to oversee radiological work and ensure compliance with regulatory requirements.
conduct radiological surveys, provide and maintain respiratory protective equipment

Government Assumptions: Period of Performance 1 Nov 2015- 31 Oct 2016

01.05.02 Rad Support SLDS
Direct Labor
CodeJob DescriptionHourly RateHoursLabor Cost
"000
"000
"000
0
Total Task Hours

Total Field Office Direct Labor Costs 0

Fringe on Direct Labor 0% 0

Field Over head 0% 0

Total Direct Labor Cost 0

Other Direct Costs0
Subcontracting

Subcontracting Total Cost 0

Materials

Material Total Cost 0

Equipment
Equipment Total Cost0

Total ODC Costs 0

SUBTOTAL Direct Cost and ODC 0

G&A 0% 0

Total Task Total without Fee 0

Ballfield

WORKSHEET
02.06.01 TASK 06- IA-9 Ballfields Phase 3 Remedial Action (RA)
Scope -Provide necessary labor, equipment and materials to excavate app. 9,500 (BCY) of contaminated soils.
Work should include site mobilization and setup of controlled area. The utilities has been cleared and haul roads has been
established. The contaminated material should be hauled to load out rail spur 1 mile from remediation area.
Backfill with clean stockpile of existing material on site. Restore approximately 5 acres of disturbed area with
seed and mulch.
Assumptions:
`
02.06.01Remedial Action Ballfield Phase 3A
Direct Labor
CodeJob DescriptionHourly RateHoursLabor Cost
"000
"000
"000
0
Total Task Hours

Total Field Office Direct Labor Costs 0

Fringe on Direct Labor 0% 0

Field Over head 0% 0

Total Direct Labor Cost 0

Other Direct Costs0
Subcontracting

Subcontracting Total Cost 0

Materials

Material Total Cost 0

Equipment
Equipment Total Cost0

Total ODC Costs 0

SUBTOTAL Direct Cost and ODC 0

G&A 0% 0

Total Task Total without Fee 0

RD Design1

WORKSHEET
02.07.01 TASK 7- PDI sampling of Frost Avenue
Scope Based on the criteria total 128 sample locations will be used, Assume all samples will be taken to a depth of 6 feet
below ground surface(bgs), • Collection of samples will begin below any cover material

Assumptions:

02.07.01 TASK 7- PDI sampling of Frost Avenue
Direct Labor
CodeJob DescriptionHourly RateHoursLabor Cost
"000
"000
"000
0
Total Task Hours

Total Field Office Direct Labor Costs 0

Fringe on Direct Labor 0% 0

Field Over head 0% 0

Total Direct Labor Cost 0

Other Direct Costs0
Example: TravelSubcontracting

Subcontracting Total Cost 0

Materials

Material Total Cost 0

Equipment
Equipment Total Cost0

Total ODC Costs 0

SUBTOTAL Direct Cost and ODC 0

G&A 0% 0

Total Task Total without Fee 0