W912P521B0007 RTA TSpecs.pdf

PDF 4 MB Posted

Attached to
Center Hill Medium Voltage Cable Replacement Federal contract opportunity
Solicitation number
W912P521B0007
Issued by
Department of the Army Corps of Engineers Engineering District Nashville

About this file

This document provides details for a federal construction contract solicitation. The U.S. Army Corps of Engineers Nashville District is seeking a firm fixed price contract for medium voltage cable replacement work at the Center Hill Power Plant in Tennessee. The scope of work includes removing and replacing four generating units' 15kV cables with new MV-105 cables and terminations, installing temporary feeders, developing asbestos and oil removal plans, and performing factory and field testing. A site visit is scheduled for April 13, 2021, with requests due by the stated deadline. Questions must be submitted in writing by the specified date to the identified contracting officer.

View the file

Other files for this federal contract opportunity

Other files attached to Center Hill Medium Voltage Cable Replacement, newest first.
File Type Posted
W912P521B0007 Bid Abstract page 1.pdf PDF
W912P521B0007 Bid Abstract page 2.pdf PDF
M-401.pdf PDF
Center Hill Reference Photos - Amendment 002.pdf PDF
E-502.pdf PDF
W912P521B00070002 Amendment 2.pdf PDF
W912P521B0007 TSpecs Amendment 0002.pdf PDF
E-602.pdf PDF
W912P521B00070001 Amendment 1.pdf PDF
W912P521B0007 Site Visit SignIn.pdf PDF
W912P521B0007 RTA TPlans.pdf PDF
W912P521B0007 final.pdf PDF
Show all 12

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOLICITATION No. W912P521B0007

US Army Corps Of Engineers Nashville District

MEDIUM VOLTAGE

CABLE REPLACEMENT

Center Hill Dam Cumberland River Watershed

Technical Specifications

RTA – Certified Final

January 2021

THIS PAGE INTENTIONALLY LEFT BLANK

FOR DUPLEX PRINTING

Medium Voltage Cable Replacement Center Hill Dam W912P521B0007 RTA Cumberland River Watershed

PROJECT TABLE OF CONTENTS

DI VI SI ON 01 - GENERAL REQUI REMENTS

01 00 00 GENERAL REQUIREMENTS

01 11 00.00 26 SUMMARY OF WORK

01 22 00.00 26 MEASUREMENT AND PAYMENT PROCEDURES

01 32 01 PROJECT SCHEDULE

01 33 00 SUBMITTAL PROCEDURES

01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS

01 35 50 PROJECT SITE SECURITY AND AT/OPSEC PROCEDURES

01 42 00 SOURCES FOR REFERENCE PUBLICATIONS

01 45 00 QUALITY CONTROL

01 45 00.15 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE(RMS CM)

01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS

01 78 00 CLOSEOUT SUBMITTALS

01 78 23 OPERATIONS AND MAINTENANCE DATA

01 95 00 FORMS AND ATTACHMENTS

DI VI SI ON 02 - EXI STI NG CONDI TI ONS

02 81 13 TRANPORTATION, DISPOSAL, AND RECYCLING OF EXISTING

EQUIPMENT

02 82 14 ASBESTOS ABATEMENT

02 83 13 LEAD IN CONSTRUCTION

DI VI SI ON 03 - CONCRETE

03 60 00.01 26 CONCRETE DEMOLITION, REPAIR OF CONCRETE SURFACES, AND

MINOR EQUIPMENT FOUNDATIONS

DI VI SI ON 05 - METALS

05 50 03.01 26 METALWORK FABRICATION, MACHINE WORK, AND MISCELLANEOUS

PROVISIONS

05 50 04.01 26 METALS: MISCELLANEOUS, STANDARD ARTICLES, SHOP FABRICATED

ITEMS

DI VI SI ON 13 - SPECI AL CONSTRUCTI ON

13 48 00.01 26 SEISMIC RESTRAINT FOR MECHANICAL AND ELECTRICAL EQUIPMENT

DI VI SI ON 23 - HEATI NG, VENTI LATI NG, AND AI R CONDI TI ONI NG ( HVAC)

23 82 19.00 40 FAN COIL UNITS

DI VI SI ON 26 - ELECTRI CAL

26 05 00.00 26 BASIC ELECTRICAL MATERIALS AND METHODS

26 05 13.00 26 MEDIUM-VOLTAGE CABLE & TERMINATIONS FOR GENERATOR CABLES

AND SUPPORTS

26 05 26.00 26 GROUNDING

-- End of Project Table of Contents --

PROJECT TABLE OF CONTENTS Page 1

PROJECT TABLE OF CONTENTS Page 2

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 00 00

GENERAL REQUIREMENTS

PART 1 GENERAL

1.1 GENERAL

1.2 SITE WORKING HOURS

1.2.1 Government Project Personnel Working Hours

1.2.2 Contractor's Working Hours

1.3 Power House Crane

1.4 COORDINATION CONFERENCES

1.5 PARTNERING

1.6 REFERENCES

1.7 SUBMITTALS

1.8 PROJECT SIGNS

1.9 CONTRACTOR'S STAGING AREA

1.10 CONTRACTOR'S EQUIPMENT

1.10.1 Contractor's Planned Equipment Methods

1.10.2 Plant and Equipment List

1.10.3 Movement of Equipment by the Contractor

1.11 CRANES AND HEAVY EQUIPMENT

1.11.1 Contractor Crane Safety

1.11.2 Contractor Crane Testing

1.11.3 Contractor's Cranes and Heavy Equipment

1.12 SAFE CLEARANCE PROCEDURES

1.13 DAILY CLEANUP AND DISPOSAL

1.14 STORAGE OF EQUIPMENT AND MATERIALS

1.15 PROTECTION AND RESTORATION OF EXISTING FACILITIES

1.16 WORK BY THE GOVERNMENT CONCURRENT WITH CONTRACTOR WORK

1.17 EVALUATION OF CONTRACTOR PERFORMANCE

1.18 VETERANS EMPLOYMENT EMPHASIS FOR U.S. ARMY CORPS OF ENGINEERS

CONTRACTS

1.19 MEASUREMENT AND PAYMENT

PART 2 PRODUCTS (NOT USED)

PART 3 EXECUTION

3.1 AVAILABILITY AND USE OF UTILITY SERVICES

3.1.1 Contractor Responsibilities

3.1.2 Interruptions of Utilities

-- End of Section Table of Contents --

SECTION 01 00 00 Page 1

SECTION 01 00 00 Page 2

SECTION 01 00 00

GENERAL REQUIREMENTS

PART 1 GENERAL

1.1 GENERAL

This section comprises an explanation of the general contract requirements needed to accomplish the work in accordance with the contract specifications and drawings. Any engineering designs required by these specifications that require certification, or a stamp, from a Professional Engineer must be performed by a third party vendor.

1.2 SITE WORKING HOURS

1.2.1 Government Project Personnel Working Hours

The scheduled working hours of the Project staff are Mondays through Thursdays from 6:30 a.m. until 5:00 p.m. Fridays, Saturdays and Sundays are non-work days. All Project support required by the Contractor shall be scheduled during the Project staff working hours.

1.2.2 Contractor's Working Hours

The Contractor's normal working hours shall be between 6:30 a.m. and 5:00 p.m., Monday through Thursday. Working hours which extend past 5:00 p.m.

weekdays, on Fridays, on weekends, and Federal Holidays or which are proposed to be different from the normal duty hours listed above, shall be coordinated and approved by the Contracting Officer 14 days in advance.

1.3 Power House Crane

The Government will allow the Contractor to use the power house crane to move equipment, materials, and tools between the floor levels as needed.

The Government will operate the crane for the Contractor and assist with rigging. Items being lifted shall contain factory tested and approved lift points, defined centers of gravity, and necessary lift weights.

Crane use shall be coordinated with the Government at least 48 hours hours in advance of need. The Contractor shall ensure efficient use of the crane and adjust work sequence as needed should the crane be temporarily unavailable. The Contractor will be responsible for preparing lift plans, activity hazard analysis documents, and any other safety related items necessary for execution of lifts.

1.4 COORDINATION CONFERENCES

Routine coordination conferences will be scheduled by the Contracting Officer throughout the life of this contract. Coordination conferences will be held to discuss contract administration, Contractor quality control, phasing, scheduling, and other aspects relating to the required work. The Corps of Engineers and the Contractor will be represented at each of these meetings. Coordination conferences will be scheduled to occur when notified by the Contracting Officer.

SECTION 01 00 00 Page 3

1.5 PARTNERING

In order to most effectively accomplish the work, the Government urges the Contractor to join the Government in establishing a cohesive and professional project management team. Through this "partnering" relationship both entities would strive to draw on the strengths of each organization for the ultimate goal of assuring that the project’s intended results are achieved, within budget and on schedule. This endeavor seeks an environment that nurtures team building, cooperation and trust between the Government and the Contractor. The partnering relationship would be bilateral in make-up, and participation will be totally voluntary.

The first step in initiating the concept would be a joint project management team "partnering" conference attended by multiple officers from each organization representing management and the key jobsite staff of each entity. The initial conference would be held within the first thirty

(30) days following contract award. The Resident Engineer would chair the conference, establish its agenda and distribute minutes of the meeting. A professional facilitator acceptable to both parties would lead the participants of the session, through the steps of team building and the formation of a problem solving mechanism within the group. The conference duration would be no more than one day. Location of the conference would be offsite within a 60 mile radius of the jobsite at a facility which offers conference rooms and food service. All costs in connection with rented facilities and the facilitator would be shared equally by the Government and the Contractor. Each organization would pay other costs of its respective employees attending the conference.

Additional partnering sessions would be held no less than biannually.

Implementation of the partnering concept and philosophy would be an on-going process.

1.6 REFERENCES

The publications listed below form a part of this section to the extent referenced. The publications are referred to within the text by the basic designation only.

U.S. ARMY CORPS OF ENGINEERS (USACE)

ECB 2020-1 (2020) USACE Construction Project Signs and Use of the Army Star

EM 385-1-1 (2014) Safety and Health Requirements Manual

EP 310-1-6a (2006) Sign Standards Manual, VOL 1

ER 385-1-31 (2009) The Control of Hazardous Energy

1.7 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

SECTION 01 00 00 Page 4

Contractor's Planned Equipment Methods; G Loading Plan For Cranes And Heavy Equipment; G Plant and Equipment List; G Loading Diagram; G Lifting Diagram; G

1.8 PROJECT SIGNS

a. General. Furnish and erect within 30 days after issue of the Notice to Proceed at the location directed, a PROJECT IDENTIFICATION SIGN and a SAFETY PERFORMANCE SIGN. The signs must be lettered on one side only and conform to EP 310-1-6a , ECB 2020-1 , and to the details and colors shown on the sketches included in Section 01 95 00 FORMS AND ATTACHMENTS. The name of the project shall be as follows:

MEDIUM VOLTAGE CABLE REPLACEMENT

b. Materials. Construct the sign with a face sheet of 3/4 inch exterior grade plywood mounted on a substantial framework of treated 4-inch by 4-inch material. Screws must be commercial quality and of sizes shown.

c. Painting. The signs and posts must be given one prime coat and two finish coats of exterior oil paint before lettering. Apply letters and trim to one side only using one coat of enamel of color, style, and size shown.

d. Erection and Maintenance. Erect the signs at the designated locations. Signs must be plumb and backfill of post holes must be well tamped to properly support the signs. Maintain the signs in good condition until completion of the contract. Signs remain the property of the Contractor and must be removed from the site upon final acceptance of the contract work.

1.9 CONTRACTOR'S STAGING AREA

The Contractor will be assigned a portion of the warehouse area on the power plant side for use as a staging area. The building of structures, the erection of tents or other forms of protection will be permitted only at such places as the Government shall approve, and the sanitary conditions of the grounds in or about such structures shall at all times be maintained in a satisfactory manner. Temporary Contractor facilities provided during Construction shall be removed prior to final acceptance from the Government. As a minimum the area shall be left looking "broom clean" and at least as clean as before the structure placement.

1.10 CONTRACTOR'S EQUIPMENT

1.10.1 Contractor's Planned Equipment Methods

The proposed methods of transportation and operation of cranes and other heavy equipment shall be submitted by the Contractor to the Government and accepted by the Government before commencement of those operations.

Submittals shall include the type, size, and loadings of equipment, and the proposed transportation routes and work areas to be used on the project.

Operation of heavy equipment adjacent to existing structures shall be

SECTION 01 00 00 Page 5 avoided when possible. Testing requirements and operation of cranes and other heavy equipment shall be in accordance with Section 01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS, EM 385-1-1 , and as specified below. All cranes, rigging, lifts, operators, and other necessary means to move equipment or items shall be Contractor-furnished and shall comply with

EM 385-1-1 .

1.10.2 Plant and Equipment List

Provide a complete list of all plant and equipment, exclusive of shop equipment, to be used on the project at least 7 days prior to commencing site operations. An up to date plant and equipment list shall be submitted with the end of the month request for payment, throughout the life of the contract. The lists shall include rented equipment as well as lease purchase or sale leaseback equipment. The initial list and the revised monthly lists shall indicate dates equipment is assigned to or removed from the project, dates deadlined for repairs and returned for use, and adequate identification or description of each item of equipment including manufacturer's name (abbreviated), model number, manufacturer's serial number, year of manufacture, and Contractor's assigned serial or record number.

1.10.3 Movement of Equipment by the Contractor

All cranes, rigging, lifts, operators, and other necessary means to move equipment or items shall be Contractor-furnished as required to pursue and complete the work, and shall meet the requirements of EM 385-1-1 and Section 01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS. For mobile cranes a loading diagram may need to be submitted for review and approval showing the wheel loads and wheel spacing. The Contractor shall provide a Crane Critical Lift Plan as required in Section 01 35 26 and detailed in EM 385-1-1 , paragraph 16.H.02. The loading diagram and critical lift plan shall address large component laydown on the powerhouse floor.

1.11 CRANES AND HEAVY EQUIPMENT

1.11.1 Contractor Crane Safety

Contractor's cranes and equipment furnished for this work shall conform with all applicable OSHA requirements and referenced EM 385-1-1 in Section 00700 CONTRACT CLAUSES, Contract Clause 52.236-13 Alt I, ACCIDENT PREVENTION and Section 01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS.

Contractor shall submit a lifting diagram addressing such issues as lift, trim, maximum load, maximum wind speed, lifting radius, crane operator(s) qualifications and current medical exam, crane rigger(s) qualifications, and all other applicable information required by EM 385-1-1 and OSHA. The lifting diagram shall be submitted 30-days prior to site work.

1.11.2 Contractor Crane Testing

All Contractor cranes shall be tested in accordance with EM 385-1-1 prior to use on the project and the tests shall be witnessed by the COR.

Forty-eight hours notice of the test, excluding weekends and federal holidays, shall be given by the Contractor.

1.11.3 Contractor's Cranes and Heavy Equipment

The planned method of transportation and operation of Contractor provided cranes and other heavy equipment to be used in the performance of this

SECTION 01 00 00 Page 6 contract shall be submitted for government acceptance and coordinated with the COR. This loading plan for cranes and heavy equipment shall include the type, size, loading, and placement of outriggers of all cranes or heavy equipment and the proposed transportation routes and work areas to be used on the project. Operation of heavy equipment adjacent to existing structures shall be avoided when possible.

1.12 SAFE CLEARANCE PROCEDURES

Project personnel use A Safe Clearance System, as stated in ER 385-1-31 and amended by the Nashville District to ensure continuity of service and safety to personnel and equipment. Any work performed which requires taking the Project's operating equipment out of service will be done only after a formal clearance is obtained by the Contracting Officer with 48-hour minimum notice. Contractor personnel shall not violate clearance. Any violation of Safe Clearance Procedures will be grounds for removal of the offender(s). Up to five copies of the Nashville District Safe Clearance Procedure will be supplied to the Contractor upon request.

1.13 DAILY CLEANUP AND DISPOSAL

Work areas shall be kept reasonably neat on a daily basis. Debris resulting from the work, such as empty paint cans, packing cases, scrap lumber, oil and grease spills, and other debris shall be collected, removed, and disposed of off-site at least once per week. Government trash cans, dump boxes and other containers shall not be used. Liquid waste shall not be disposed of in existing drains.

1.14 STORAGE OF EQUIPMENT AND MATERIALS

Storage of equipment and materials will be permitted only in designated staging areas. A minimum access space of three feet shall be maintained between the Contractor's stored items and existing facility equipment.

1.15 PROTECTION AND RESTORATION OF EXISTING FACILITIES

Existing facilities shall be protected whether or not shown on the drawings. Upon completion of the work, existing facilities, not included as a portion of the work, shall be left in a condition equal to the original condition prior to the contract. Costs for repair and restoration of any facilities shall be considered to be incidental to and included in the contract price.

1.16 WORK BY THE GOVERNMENT CONCURRENT WITH CONTRACTOR WORK

The Government will limit interference with the Contractor's work to the maximum reasonable extent and the Government and Contractor shall coordinate as necessary.

1.17 EVALUATION OF CONTRACTOR PERFORMANCE

The Contractor's performance will be evaluated in accordance with FAR Part

42.15 in the areas of quality, schedule, cost control, management, utilization of small businesses, and regulatory compliance at minimum.

The evaluation will include a written narrative and rating of either exceptional, very good, satisfactory, marginal, or unsatisfactory for each area. The format for the evaluation is attached at the end of Section

01 95 00 FORMS AND ATTACHMENTS.

SECTION 01 00 00 Page 7

The Contractor's review of the evaluation shall be completed electronically at the CPARS website, http://www.cpars.gov . This website also includes guidance and the user's manual.

Upon contract award, the Contractor shall provide the Contracting Officer with the name and e-mail address of the Contractor's Representative to be registered into the system. Following initial completion by the Government, the Contractor will have sixty (60) calendar days to review, comment, and return the evaluation.

1.18 VETERANS EMPLOYMENT EMPHASIS FOR U.S. ARMY CORPS OF ENGINEERS

CONTRACTS

In addition to complying with the requirements outlined in FAR Part 22.13, FAR Provision 52.222-38, FAR Clause 52.222-35, FAR Clause 52.222-37, DFARS

222.13 and Department of Labor regulations, U.S. Army Corps of Engineers (USACE) contractors and subcontractors at all tiers are encouraged to promote the training and employment of U.S. veterans while performing under a USACE contract. While no set-aside, evaluation preference, or incentive applies to the solicitation or performance under the resultant contract, USACE contractors are encouraged to seek out highly qualified veterans to perform services under this contract. The following resources are available to assist USACE contractors in their outreach efforts:

a. U.S. Department of Labor Veterans employment: www.vets.gov/

b. Federal veteran employment information: www.fedshirevets.gov/index.aspx

c. Veterans’ Employment and Training Service (VETS):

http://www.dol.gov/vets/

d. Veterans Opportunity to Work (VOW) Program: http://benefits.va.gov/vow/

e. U.S. Army Warrior Transition Command Employment Index:

http://www.wct.army.mil/modules/employers/index.html

f. Hiring Our Heroes initiative:

www.uschamberfoundation.org/hiring-our-heroes

g. Guide to Hiring Veterans:

www.whitehouse.gov/sites/default/files/docs/white_house_business_council_ -_guide_to_hiring_veterans_0.pdf

1.19 MEASUREMENT AND PAYMENT

No separate payment will be made for the work covered under this section.

The costs thereof shall be included in the item to which the work pertains.

PART 2 PRODUCTS (NOT USED)

PART 3 EXECUTION

3.1 AVAILABILITY AND USE OF UTILITY SERVICES

3.1.1 Contractor Responsibilities

a. The Contractor shall be responsible for the availability of utilities for use on the project. Raw water is available with no charge at the site. The Contractor shall supply any other utilities

SECTION 01 00 00 Page 8 needed at his cost. The Contractor shall carefully conserve any utilities furnished without charge.

b. The Contractor, at its expense and in a workmanlike manner satisfactory to the Contracting Officer, shall install and maintain all necessary temporary connections and distribution lines. Before final acceptance of the work by the Government, the Contractor shall remove all the temporary connections, distribution lines, and associated paraphernalia.

c. The Contractor is responsible for providing drinking water facilities for all personnel associated with this contract.

3.1.2 Interruptions of Utilities

a. No utility services shall be interrupted by the Contractor to make connections, to relocate, or for any purpose without approval of the Contracting Officer.

b. Request for Permission to shut down services shall be submitted in writing to the Contracting Officer not less than seventeen (17) days prior to date of proposed interruption. The request shall give the following information:

(1) Nature of Utility (Gas, L.P. or H.P., Water, etc.)

(2) Size of line and location of shutoff.

(3) Buildings and services affected.

(4) Hours and date of shutoff.

(5) Estimated length of time services will be interrupted.

c. Services shall not be shutoff until receipt of approval of the proposed hours and date from the Contracting Officer.

d. Shutoffs which will cause interruption of Government work operations as determined by the Contracting Officer shall be accomplished during regular non-work hours or on non-work days of the Using Agency.

e. Operation of valves on water mains will be by Government personnel.

Where shutoff of water lines interrupts service to fire hydrants or fire sprinkler systems, the Contractor shall arrange his operations and have sufficient material and personnel available to complete the work without undue delay or to restore service without delay in event of emergency.

-- End of Section --

SECTION 01 00 00 Page 9

SECTION 01 00 00 Page 10

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

Section 01 11 00.00 26

SUMMARY OF WORK

PART 1 GENERAL

1.1 SUMMARY

1.2 WORK COVERED BY CONTRACT DOCUMENTS

1.2.1 Project Description

1.2.2 Location

1.3 OCCUPANCY OF PREMISES

1.4 EXISTING WORK

PART 2 PRODUCTS

PART 3 EXECUTION

SECTION 01 11 00.00 26 Page 1

SECTION 01 11 00.00 26 Page 2

Section 01 11 00.00 26

SUMMARY OF WORK

PART 1 GENERAL

1.1 SUMMARY

This Section provides a summary of the various Contract work elements and their relationship to each other. This summary describes work activities within interim construction completion date. This Section does not provide the technical detail for particular work activities, but describes work as a whole, providing overall perspective to the separate tasks and their interrelationships. Use this Section in conjuction with all the Specification Sections and the Drawings to establish the total work requirements.

1.2 WORK COVERED BY CONTRACT DOCUMENTS

1.2.1 Project Description

This section is a general summary of the required work and is not all-inclusive. The work described within these specifications include, but not necessarily be limited to the following:

a. Remove HPFF oil pipe cable system in the cable tunnel, including 1400 gallons of oil, all pipe supports, oil storage tanks, excess oil drums, oil piping, and oil pump skid.

b. Supply and install new solid dielectric feeder cables for generating Units 1-3 and Circuit #4 for the 44kV switchyard.

c. Supply and install temporary feeder cables for at minimum Circuit #4 and Unit 1, and optionally for Units 2-3.

d. Supply and install saddle-type cleat support system for new permenant feeders, including all support members and concrete anchors.

e. Supply and install water-cooling coil in cable tunnel ventilation outlet for improved cooling of tunnel.

f. Prepare and furnish O&M manuals and as-built drawings for the completed installation.

g. Provide all necessary commissioning activities and support Government commissioning activities.

1.2.2 Location

All work shall be performed at Center Hill Powerhouse.

1.3 OCCUPANCY OF PREMISES

The Center Hill Dam and Powerhouse is a working facility and daily routines require frequent operations to be conducted. In addition, other

SECTION 01 11 00.00 26 Page 3 equipment at the powerhouse must remain accessible for routine inspections, testing, and maintenance activities. Buildings will be occupied during performance of work under this Contract

Before work is started, arrange with the Contracting Officer a sequence of procedure, means of access, space for storage of materials and equipment, and use of approaches, decks, and roadways.

1.4 EXISTING WORK

In addition to "FAR 52.236-9, Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements":

a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.

b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work must be in a condition equal to or better than that which existed before new work started.

PART 2 PRODUCTS

Not Used.

PART 3 EXECUTION

Not Used.

SECTION 01 11 00.00 26 Page 4

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

Section 01 22 00.00 26

MEASUREMENT AND PAYMENT PROCEDURES

PART 1 GENERAL

1.1 PAYMENT GENERAL

1.2 MEASUREMENT GUIDELINES

1.2.1 Job Items

1.3 BASE CLINs

1.3.1 Mobilization and Demobilization, CLIN 0001

1.3.2 Remove and Dispose of Existing HPFF Oil Pipe Cable System for

Unit #1, CLIN 0002

1.3.3 Remove and Dispose of Existing HPFF Oil Pipe Cable System for

Unit #2, CLIN 0003

1.3.4 Remove and Dispose of Existing HPFF Oil Pipe Cable System for

Unit #3, CLIN 0004

1.3.5 Remove and Dispose of Existing HPFF Oil Pipe Cable System for

Circuit #4,, CLIN 0005

1.3.6 Supply and Install Temporary Feeder System for Circuit #4, CLIN 0006

1.3.7 Supply and Install Temporary Feeder System for Unit #1, CLIN

1.3.8 Remove and Dispose of Existing HPFF Oil Storage Tank and Oil

Pump Skid, CLIN 0008

1.3.9 Supply and Install New Saddle Cleats, Cleat Support

Structures, and Anchors, CLIN 0009

1.3.10 Supply and Install New 2000kcmil, Medium-Voltage Solid

Dielectric Cables for Unit #1 Feeders, including Switchyard Enclosures and Terminations, CLIN 0010

1.3.11 Supply and Install New 2000kcmil, Medium-Voltage Solid Dielectric Cables for Unit #2 Feeders, including Switchyard Enclosures and Terminations, CLIN 0011

1.3.12 Supply and Install New 2000kcmil, Medium-Voltage Solid Dielectric Cables for Unit #3 Feeders, including Switchyard Enclosures and Terminations, CLIN 0012

1.3.13 Supply and Install New 750kcmil, Medium-Voltage Solid

Dielectric Cables for Circuit #4 Feeders, including Switchyard Enclosures and Terminations, CLIN 0013

1.3.14 Provide O&M Manuals, CLIN 0014

1.3.15 Provide Commissioning Services and Training, CLIN 0015

1.3.16 Provide Final Record Drawings, CLIN 0016

1.4 OPTIONAL CLINs

1.4.1 Supply and Install Temporary Feeder System for Unit #2, CLIN

1.4.2 Supply and Install Temporary Feeder System for Unit #3, CLIN

1.4.3 Supply and Install Water Coil for Cable Tunnel Cooling System, CLIN 0019

SECTION 01 22 00.00 26 Page 1

PART 2 PRODUCTS

PART 3 EXECUTION

SECTION 01 22 00.00 26 Page 2

Section 01 22 00.00 26

MEASUREMENT AND PAYMENT PROCEDURES

PART 1 GENERAL

1.1 PAYMENT GENERAL

Payment items for the work of this contract for which payments will be made are listed in the BID SCHEDULE and described below. The contract price for each item shall constitute full compensation for furnishing all plant, labor, materials, appurtenances, and incidentals and performing all operations necessary to construct and complete the items in accordance with these specifications and the applicable drawings, including surveying performed by the Contractor

1.1 All costs for items of work, which are not specifically mentioned to be included in a particular payment item, shall be included in the listed job item most closely associated with the work involved. Payment for each item shall be considered as full compensation, notwithstanding that minor features may not be mentioned herein. Work paid for under one item will not be paid for under any other item. No separate payment will be made for the work, services, or operations required by the Contractor, as specified in DIVISION 01 - GENERAL REQUIREMENTS, to complete the project in accordance with these specifications; all costs thereof shall be considered as incidental to the work.

1.2 MEASUREMENT GUIDELINES

1.2.1 Job Items

Items measured as a "job" will be measured for payment as a complete job in the locations indicated. Unless the payment item paragraph makes a specific exception of any item, incidental items will not be measured under any other item even though there is another listing for the work or material.

1.3 BASE CLINs

1.3.1 Mobilization and Demobilization, CLIN 0001

Payment will be made on a per job basis under CLIN 0001. Payment shall be made for all costs incurred prior to arriving onsite (mobilization) or immediately after departing the work site (demobilization). These costs include, but are not limited to, all preparatory work at the contractors shop, labor costs associated with travel to and from the work site, and transportation costs..

1.3.2 Remove and Dispose of Existing HPFF Oil Pipe Cable System for Unit

#1, CLIN 0002

Payment for the removal and disposal of the oil pipe cables for Unit #1 generator leads, including existing conductors and exposed conduit will be made at the job bid price under Line Item No. 0002. Price and payment will constitute full compensation for the furnishing of all material, SECTION 01 22 00.00 26 Page 3 labor, and equipment to accomplish this work.

1.3.3 Remove and Dispose of Existing HPFF Oil Pipe Cable System for Unit

#2, CLIN 0003

Payment for the removal and disposal of the oil pipe cables for Unit #2 generator leads will be made at the job bid price under Line Item No.

0003. Price and payment will constitute full compensation for the furnishing of all material, labor and equipment to accomplish this work.

1.3.4 Remove and Dispose of Existing HPFF Oil Pipe Cable System for Unit

#3, CLIN 0004

Payment for the removal and disposal of the oil pipe cables for Unit #3 generator leads will be made at the job bid price under Line Item No.

0004. Price and payment will constitute full compensation for the furnishing of all material, labor and equipment to accomplish this work.

1.3.5 Remove and Dispose of Existing HPFF Oil Pipe Cable System for Circuit #4,, CLIN 0005

Payment for the removal and disposal of the oil pipe cables for Circuit #4 (44kV switchyard feeders) will be made at the job bid price under Line Item No. 0005. Price and payment will constitute full compensation for the furnishing of all material, labor and equipment to accomplish this work.

1.3.6 Supply and Install Temporary Feeder System for Circuit #4, CLIN 0006

Payment for the design, supply and installation of the temporary feeder system for Circuit #4 (loading of 14.4 MVA) will be made at the job bid price under Line Item No. 0006. Price and payment will constitute full compensation for the furnishing of all materials, labor and equipment to accomplish this work.

1.3.7 Supply and Install Temporary Feeder System for Unit #1, CLIN 0007

Payment for the design, supply, and installation of the temporary feeder system for Unit #1 will be made at the job bid price under Line Item No.

0007. Price and payment will constitute full compensation for the furnishing of all material and labor to perform this work.

1.3.8 Remove and Dispose of Existing HPFF Oil Storage Tank and Oil Pump Skid, CLIN 0008

Payment for the removal and disposal of 1400 gallons of HPFF oil, the 1500-gallon oil storage tank, oil pump skid, excess oil drums, oil piping, and other associated equipment will be made at the job bid price under Line Item No. 0008. Price and payment will constitute full compensation for the furnishing of all material, labor, and equipment to accomplish this work. Payment for the removal and disposal of the HPFF oil storage tank, oil pump skid, oil drums, nitrogen blanket tanks, exposed conduit, and other associated equipment will be made at the job bid price under Line Item No. 0008. Price and payment will constitute full compensation for the furnishing of all material, labor, and equipment to accomplish this work.

SECTION 01 22 00.00 26 Page 4

1.3.9 Supply and Install New Saddle Cleats, Cleat Support Structures, and Anchors, CLIN 0009

Payment for the supply and installation of the new saddle cleats, cleat support structures (including approved design), concrete anchors, and other associated equipment will be made at the job bid price under Line Item No. 0009. Price and payment will constitute full compensation for the furnishing of all material, labor and equipment to perform this work.

1.3.10 Supply and Install New 2000kcmil, Medium-Voltage Solid Dielectric Cables for Unit #1 Feeders, including Switchyard Enclosures and Terminations, CLIN 0010

Payment for the supply and installation of required length of 15kv, 2000kcmil solid dielectric cables for Unit #1, including terminations and enclosures to house terminations in switchyard will be made at the job bid price under Line Item No. 0010. Price and payment will constitute full compensation for the furnishing of all labor required to accomplish this work.

1.3.11 Supply and Install New 2000kcmil, Medium-Voltage Solid Dielectric Cables for Unit #2 Feeders, including Switchyard Enclosures and Terminations, CLIN 0011

Payment for the supply and installation of required length of 15kv, 2000kcmil solid dielectric cables for Unit #2, including terminations and enclosures to house terminations in switchyard will be made at the job bid price under Line Item No. 0011. Price and payment will constitute full compensation for the furnishing of all labor to accomplish this work.

1.3.12 Supply and Install New 2000kcmil, Medium-Voltage Solid Dielectric Cables for Unit #3 Feeders, including Switchyard Enclosures and Terminations, CLIN 0012

Payment for the commissiong services and trainingsupply and installation of required length of 15kv, 2000kcmil solid dielectric cables for Unit #3, including terminations and enclosures to house terminations in switchyard will be made at the job bid price under Line Item No. 0012. Price and payment will constitute full compensation for the furnishing of all material, labor and equipment to perform this work.

1.3.13 Supply and Install New 750kcmil, Medium-Voltage Solid Dielectric Cables for Circuit #4 Feeders, including Switchyard Enclosures and Terminations, CLIN 0013

Payment for the supply and installation of required quantity of 15kv, 750kcmil solid dielectric cables for Circuit #4, including terminations and enclosures to house terminations in switchyard will be made at the job bid price under Line Item No. 0013. Price and payment will constitute full compensation for the furnishing of all material and labor to perform this work.

1.3.14 Provide O&M Manuals, CLIN 0014

Payment for the supply of the O & M manuals will be made at the job bid price under Line Item No. 0014. Price and payment will constitute full compensation for the furnishing of all material and labor to perform this work.

SECTION 01 22 00.00 26 Page 5

1.3.15 Provide Commissioning Services and Training, CLIN 0015

Payment for the commissiong services and training will be made at the job bid price under Line Item No. 0015. Price and payment will constitute full compensation for the furnishing of all material and labor to perform this work.

1.3.16 Provide Final Record Drawings, CLIN 0016

Payment for the final record drawings will be made at the job bid price under Line Item No. 0016. Price and payment will constitute full compensation for the furnishing of all material and labor to perform this work.

1.4 OPTIONAL CLINs

1.4.1 Supply and Install Temporary Feeder System for Unit #2, CLIN 0017

Payment for the supply and installation of the temporary feeder system for Unit #2 will be made at the job bid price under Line Item No. 0017. Price and payment will constitute full compensation for the furnishing of all material and labor to perform this work. This temporary feeder may be awarded based on plant availability requirements at 60 days after Notice to Proceed.

1.4.2 Supply and Install Temporary Feeder System for Unit #3, CLIN 0018

Payment for the supply and installation of the temporary feeder system for Unit #3 will be made at the job bid price under Line Item No. 0018. Price and payment will constitute full compensation for the furnishing of all material and labor to perform this work. This temporary feeder may be awarded based on plant availability requirements at 60 days after Notice to Proceed.

1.4.3 Supply and Install Water Coil for Cable Tunnel Cooling System, CLIN

Payment for the supply and installation of the water-cooling coil for the tunnel HVAC system will be made at the job bid price under Line Item No.

0019. Price and payment will constitute full compensation for the furnishing of all material and labor to perform this work.

PROGRESS PAYMENT INVOICE

Submit requests for payment in accordance with Federal Acquisition Regulations (FAR) Subpart 32.9, entitled "PROMPT PAYMENT", and Clauses 52.232-5 and 52.232-27, entitled "Payments Under Fixed-Price Construction Contracts", and "Prompt Payment for Construction Contracts", respectively.

In addition each request shall be submitted in the number of copies and to the designated billing office as shown in the Contract.

When submitting payment requests, complete Blocks 1 through 12 of the "PROGRESS PAYMENT INVOICE" Form as directed by the Contracting Officer (provided in QCS). The completed form shall then become the cover document to which all other support data shall be attached.

One additional copy of the entire request for payment, to include the "PROGRESS PAYMENT INVOICE" cover document, shall be forwarded to a separate

SECTION 01 22 00.00 26 Page 6 address as designated by the Contracting Officer.

Submit with each pay request, a list of subcontractors that have worked during that pay period. The listing shall be broken down into weeks, identifying each subcontractor that has worked during a particular week, and indicate the total number of employees that have worked on site for each subcontractor for each week. Also indicate the total number of employees for on-site staff for each week.

ELECTRONIC SOFTWARE SYSTEM FOR SUBMITTING CERTIFIED LABO PAYROLLS AND RECORDS

The Contractor is required to use a commercially available software system to process and submit certified payrolls electronically to the Government.

The requirements for preparing, processing, and submitting certified labor payrolls are established by the requirements as stated in FAR 52.222-8 PAYROLLS AND BASIC RECORDS, and FAR 52.222-13 COMPLIANCE WITH CONSTRUCTION

WAGE RATE REQUIREMENTS AND RELATED REGULATIONS.

Provide all access, licenses, and other services required for the receipt, processing, certifying, and electronically transmitting payrolls to the Government, and storing weekly payroll and other data required to comply with Construction Wage Rate Requirements and related regulations. The payroll software system shall be capable of preserving submitted payroll documents and related records for a minimum of three years after contract completion. Provide system access to the Government for the duration of this construction contract. Government access shall include online review by the Government's contract administration office of all electronic payroll records of the Contractor.

The payroll processing software system shall also meet the following functional criteria. It shall:

a. Be compliant with appropriate Construction Wage Rate Requirement payroll provisions in applicable Federal Acquisition Regulations

b. Be able to accommodate the required number of employees and subcontractors employed under the contract,

c. Be capable of producing an MS Excel compatible spreadsheet to be uploaded into the Quality Control System (QCS), which in turn shall exported to the Resident Management System (RMS),

d. Provide demonstrated security of data storage, data entry, and data access rights,

e. Be able to produce Contractor certified electronic versions of weekly payroll data,

f. Be able to identify erroneous entries and track data/time of all versions of the Construction Wage Rate certified payrolls submitted to the Government over the life of the contract, and

g. Be capable of generating a durable record copy; that is, a CD or DVD of records in PDF format from the system database. This durable record copy shall be provided to the Government during contract closeout. All incurred costs related to the provision and use of an electronic payroll processing system shall be included in the price for the work under the contract. All costs for providing and using the electronic payroll processing system and services shall not be a separately billed or reimbursed item under the

SECTION 01 22 00.00 26 Page 7 contract.

COMPLIANCE WITH CONSTRUCTION WAGE RATE REQUIREMENTS

Contractor POC

Within 14 days after award of the contract, designate a point of contact (POC) who will be responsible for the Construction Wage Rates Requirements Program for the Contractor and all subcontractors under this contract as required by the Contract Clauses and FAR 52.222.

Responsibilities

The designated Contractor POC shall be responsible for Construction Wage Rates Requirements Program activities including, but not limited to:

a. Documentation and record keeping;

b. Submittal and accuracy of certified payrolls;

c. Submittal of required labor forms including requests for additional classifications and rates, Statements and Acknowledgement, etc.;

d. Posting of the wage determination, approved additional classifications and rates, labor and EEO posters;

e. Coordination with the Contracting Officer's Labor Program POC.

Prior to submittal to the Government, payrolls shall be reviewed for compliance to all applicable labor standards, to include, but not be limited to the following items: correct wage rates, correct overtime classification and pay, misclassification of workers for work actually performed, apprentice to journeyman ratios, and registration of apprentice. Corrective actions shall be taken as necessary to ensure Contractor compliance with applicable contract and FAR clauses.

Certification

The Contractor POC shall provide a signed certification stating the following: "I certify that the submitted items being forwarded have been reviewed in detail and are correct and in strict conformance with the Labor Standards of the contract except as otherwise stated."

PROPOSED PROJECT MODIFICATIONS

Price proposals for contract modifications shall be submitted in accordance with the requirements of the Contract Clause MODIFICATION PROPOSALS - PRICE BREAKDOWNS. If change order work impacts or delays other unchanged contract work, the costs of such impacts or delays shall be included in the proposals and separately identified. The current threshold for requiring cost or pricing data is $750,000 but is subject to change (see FAR 15.403-4(a)(1)(iii)). Any modification proposal that exceeds the cost and pricing data threshold shall meet the requirements of FAR 15.403 (see instructions for Change Orders/Modification and Claims in Table 15-2 of FAR 15.408)

PART 2 PRODUCTS

Not Used

SECTION 01 22 00.00 26 Page 8

PART 3 EXECUTION

Not Used

SECTION 01 22 00.00 26 Page 9

SECTION 01 22 00.00 26 Page 10

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 32 01

PROJECT SCHEDULE

PART 1 GENERAL

1.1 REFERENCES

1.2 SUBMITTALS

1.3 PROJECT SCHEDULER QUALIFICATIONS

PART 2 PRODUCTS

2.1 SOFTWARE

2.1.1 Government Default Software

2.1.2 Contractor Software

PART 3 EXECUTION

3.1 GENERAL REQUIREMENTS

3.2 BASIS FOR PAYMENT AND COST LOADING

3.2.1 Activity Cost Loading

3.2.2 Withholdings / Payment Rejection

3.3 PROJECT SCHEDULE DETAILED REQUIREMENTS

3.3.1 Level of Detail Required

3.3.2 Activity Durations

3.3.3 Design and Permit Activities

3.3.4 Procurement Activities

3.3.5 Closeout Activities

3.3.6 Mandatory Tasks

3.3.7 Government Activities

3.3.8 Standard Activity Coding Dictionary

3.3.8.1 Workers Per Day (WRKP)

3.3.8.2 Responsible Party Coding (RESP)

3.3.8.3 Area of Work Coding (AREA)

3.3.8.4 Modification Number (MODF)

3.3.8.5 Bid Item Coding (BIDI)

3.3.8.6 Phase of Work Coding (PHAS)

3.3.8.7 Category of Work Coding (CATW)

3.3.8.8 Feature of Work Coding (FOW)

3.3.9 Contract Milestones and Constraints

3.3.9.1 Project Start Date Milestone and Constraint

3.3.9.2 End Project Finish Milestone and Constraint

3.3.9.3 Interim Completion Dates and Constraints

3.3.9.3.1 Start Phase

3.3.9.3.2 End Phase

3.3.10 Calendars

3.3.11 Open Ended Logic

3.3.12 Default Progress Data Disallowed

3.3.13 Out-of-Sequence Progress

3.3.14 Added and Deleted Activities

SECTION 01 32 01 Page 1

3.3.15 Original Durations

3.3.16 Leads, Lags, and Start to Finish Relationships

3.3.17 Retained Logic

3.3.18 Percent Complete

3.3.19 Remaining Duration

3.3.20 Cost Loading of Closeout Activities

3.3.20.1 As-Built Drawings

3.3.20.2 O & M Manuals

3.3.21 Anticipated Adverse Weather

3.3.22 Early Completion Schedule and the Right to Finish Early

3.4 PROJECT SCHEDULE SUBMISSIONS

3.4.1 Preliminary Project Schedule Submission

3.4.2 Initial Project Schedule Submission

3.4.2.1 Design Package Schedule Submission

3.4.3 Periodic Schedule Updates

3.4.4 Re-Baseline for Exercised Options

3.5 SUBMISSION REQUIREMENTS

3.5.1 Narrative Report

3.5.2 Schedule Reports

3.5.2.1 Activity Report

3.5.2.2 Logic Report

3.5.2.3 Total Float Report

3.5.2.4 Earnings Report by CLIN

3.5.2.5 Schedule Log

3.5.3 Network Diagram

3.5.3.1 Continuous Flow

3.5.3.2 Project Milestone Dates

3.5.3.3 Critical Path

3.5.3.4 Banding

3.5.3.5 Cash Flow / Schedule Variance Control (SVC) Diagram

3.6 SCHEDULE EXPECTATIONS KICKOFF MEETING (SEKO)

3.7 PERIODIC SCHEDULE UPDATE

3.7.1 Periodic Schedule Update Meetings

3.7.2 Update Submission Following Progress Meeting

3.8 WEEKLY PROGRESS MEETINGS

3.9 REQUESTS FOR TIME EXTENSIONS

3.9.1 Justification of Delay

3.9.2 Time Impact Analysis (Prospective Analysis)

3.9.3 Forensic Schedule Analysis (Retrospective Analysis)

3.9.4 Fragmentary Network (Fragnet)

3.9.5 Time Extension

3.9.6 Impact to Early Completion Schedule

3.10 FAILURE TO ACHIEVE PROGRESS

3.10.1 Artificially Improving Progress

3.10.2 Failure to Perform

3.10.3 Recovery Schedule

3.11 OWNERSHIP OF FLOAT

3.12 TRANSFER OF SCHEDULE DATA INTO RMS/QCS

3.13 PRIMAVERA P6 MANDATORY REQUIREMENTS

SECTION 01 32 01 Page 2

SECTION 01 32 01

PROJECT SCHEDULE

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

AACE INTERNATIONAL (AACE)

AACE 29R-03 (2011) Forensic Schedule Analysis

AACE 52R-06 (2006) Time Impact Analysis - As Applied in Construction

U.S. ARMY CORPS OF ENGINEERS (USACE)

ER 1-1-11 (1995) Administration -- Progress, Schedules, and Network Analysis Systems

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Project Scheduler Qualifications; G Preliminary Project Schedule; G Initial Project Schedule; G Periodic Schedule Update; G

1.3 PROJECT SCHEDULER QUALIFICATIONS

Designate an authorized representative to be responsible for the preparation of the schedule and all required updating and production of reports. The authorized representative must have a minimum of 2-years experience scheduling construction projects similar in size and nature to this project with scheduling software that meets the requirements of this specification. Representative must have a comprehensive knowledge of CPM scheduling principles and application.

PART 2 PRODUCTS

2.1 SOFTWARE

The scheduling software utilized to produce and update the schedules required herein must be capable of meeting all requirements of this

SECTION 01 32 01 Page 3 specification.

2.1.1 Government Default Software

The Government intends to use Primavera P6 version 16.2.

2.1.2 Contractor Software

Scheduling software used by the contractor must be able to meet the requirements of this specification and be compatible with the software used by the government; Primavera P6 version 16.2

PART 3 EXECUTION

3.1 GENERAL REQUIREMENTS

Prepare for approval a Project Schedule, as specified herein. Show in the schedule the proposed sequence to perform the work and dates contemplated for starting and completing all schedule activities. The scheduling of the entire project is required. The scheduling of design and construction is the responsibility of the Contractor. Contractor management personnel must actively participate in its development. Subcontractors, Designers, and suppliers working on the project must also contribute in developing and maintaining an accurate Project Schedule. Provide a schedule that is a forward planning as well as a project monitoring tool. Use the Critical Path Method (CPM) of network calculation to generate all Project Schedules. Prepare each Project Schedule using the Precedence Diagram Method (PDM).

3.2 BASIS FOR PAYMENT AND COST LOADING

The schedule is the basis for determining contract earnings during each update period and therefore the amount of each progress payment. The aggregate value of all activities coded to a contract CLIN must equal the value of the CLIN.

3.2.1 Activity Cost Loading

Activity cost loading must be reasonable and without front-end loading.

Provide additional documentation to demonstrate reasonableness if requested by the Contracting Officer.

3.2.2 Withholdings / Payment Rejection

Failure to meet the requirements of this specification may result in the disapproval of the preliminary, initial or periodic schedule updates and subsequent rejection of payment requests until compliance is met.

In the event that the Contracting Officer directs schedule revisions and those revisions have not been included in subsequent Project Schedule revisions or updates, the Contracting Officer may withhold 10 percent of pay request amount from each payment period until such revisions to the project schedule have been made.

3.3 PROJECT SCHEDULE DETAILED REQUIREMENTS

3.3.1 Level of Detail Required

Develop the Project Schedule to the appropriate level of detail to address

SECTION 01 32 01 Page 4 major milestones and to allow for satisfactory project planning and execution. Failure to develop the Project Schedule to an appropriate level of detail will result in its…