RFP 3-8-2010.pdf
PDF 29 MB Posted
- Attached to
- Buffalo CDF 4 Repair
- Solicitation number
- W912P4-10-R-0005
About this file
Request For Proposal
View the file
Other files
| File | Type | Posted |
|---|---|---|
| CDF-4 Ques.docx | DOCX document | |
| Responses to Questions From Bidders doc.docx | DOCX document | |
| CHANGES TO SPECIFICATIONS FOR BUFFALO CDF 4REPAIR | — | |
| Bid opening date will be postponed until April 14.docx | DOCX document | |
| CHANGES TO SPECIFICATIONS FOR BUFFALO CDF 4REPAIR.docx | DOCX document | |
| Questions.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FY10 Buffalo CDF-4 Dike Repair, Buffalo, NY
Estimated Construction Cost is between $1,000,000 and $5,000,000
This project is set-aside 100% for Small Business. The NAICS code for this project is 237990, which has a Small Business Size standard of $33.5 Million.
Site visit for this project will be held on 03/25/10 at 9:30 AM, Buffalo District Office, 1776 Niagara Street, Buffalo, NY 14207.
Solicitation is Subject to availabilityof funds.
A Bid Bond will be required.
WALTER KAMAD 716.879.4134
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS
NEGOTIATED
08-Mar-2010
(RFP)
(IFB)
X
CALL:
B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
See Item 7
2. TYPE OF SOLICITATION
SEALED BID
3. DATE ISSUED
9. FOR INFORMATION A. NAME
SOLICITATION
NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)
Prescribed by GSA FAR (48 CFR) 53.236-1(e)
11. The Contractor shall begin performance within _______ 10 calendar days and complete it within ________ 150 calendar days after receiving award, X notice to proceed. This performance period is X mandatory, negotiable. (See _________________________ Sec. 01 35 13
12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
X YES NO
13. ADDITIONAL SOLICITATION REQUIREMENTS:
A. Sealed offers in original and __________ 2 copies to perform the work required are due at the place specified in Item 8 by ___________ local time ______________ 07 Apr 2010 (date).
If this is a sealed bid solicitation, offers must be publicly opened at that time.
shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
B. An offer guarantee X is, is not required.
C. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
D. Offers providing less than _______ 60 calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NO.
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
4. CONTRACT NO.
7. ISSUED BY CODE
DEPARTMENT OF THE ARMY
USACE, BUFFALO
1776 NIAGARA STREET
BUFFALO NY 14207-3199
W912P4
PAGE OF PAGES
1 OF
CODE
(Title, identifying no., date):
12B. CALENDAR DAYS
03:00 PM (hour) Sealed envelopes containing offers
5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.
8. ADDRESS OFFER TO (If Other Than Item 7)
716-879-4353 FAX: TEL: 716-879-4134 TEL: FAX:
W912P4-10-R-0005 27
20B. SIGNATURE
(REV. 4-85)STANDARD FORM 1442 BACK
TO SIGN
NSN 7540-01-155-3212
SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)
CODE FACILITY CODE
17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.
the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)
AMOUNTS SEE SCHEDULE OF PRICES
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE
20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN
OFFER (Type or print)
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM
(4 copies unless otherwise specified)
CODE
(Insert any number equal to or greater than
20C. OFFER DATE
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY
(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)
See Item 14
(Include only if different than Item 14)16. REMITTANCE ADDRESS
30B. SIGNATURE
29. AWARD (Contractor is not required to sign this document.)
document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .
gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.
30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)
30C. DATE
(Type or print)
TEL: EMAIL:
31B. UNITED STATES OF AMERICA 31C. AWARD DATE
BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this28. NEGOTIATED AGREEMENT
(M ust be fully completed by offeror)OFFER
W912P4-10-R-0005
Section 00010 - Solicitation Contract Form
SECTION 00010
SOLICITATION, OFFER, AND AWARD (SF 1442) AND BIDDING SCHEDULE
CONFINED DISPOSAL FACILITY 4 REPAIR
BUFFALO HARBOR
BUFFALO, NEW YORK
BIDDING SCHEDULE “A”
Bid on Bidding Schedule “A” will be based upon the preparation of a grouting placement plan, constructing a grout test section, furnishing and placing grout, perform post-grouting coring, and welding sheet pile interlocks.
(See Sections 01 35 13, SPECIAL PROJECT PROCEDURES and 31 32 23.00 02, DIKE
REPAIRS)
Item Estimated Unit Estimated No. Quantity Unit Price Amount
1 Mobilization / Demobilization LS $ ______ $ _________
2. Temporary Field Office LS $ ______ $ _________
3. Site Preparation LS $ ______ $ _________
4. Record As-built Drawings LS $ ______ $ _________
5. Grout Test Section LS $ ______ $ _________
6. Grouting Area A 640 LF $ ______ $ _________
7. Grouting Area B 25 LF $ ______ $ _________
8. Post Grouting Cores 35 EA $ ______ $ _________
9. Welding Sheet Pile Interlocks 430 EA $ ______ $ _________
Total Estimated Amount (Items 1 - 9) $ _________________
Section 00100 - Bidding Schedule/Instructions to Bidders
SECTION 001000 INDEX
SECTION 00100 - INSTRUCTIONS, CONDITIONS, AND NOTICES TO OFFERERS
1.0 INTRODUCTION
1.1 SCOPE
You are invited to submit a proposal in response to Request for Proposal (RFP) “W912P4-10-R-0005”. The U.S. Army Corps of Engineers, Buffalo District, intends to conduct this acquisition by use of a Competitive Source Selection Procedure, in accordance with the provisions set forth in this RFP.
Award of a firm-fixed price construction contract is anticipated. Award will be made to the offeror submitting a proposal that is determined to be the lowest price technically acceptable (LPTA).
1.2 CLAUSES
1.2.1 Clauses and provisions from the Federal Acquisition Regulation (FAR) and supplements thereto are incorporated in this document by reference and in full text. Those incorporated by reference have the same force and effect as if they were given in full text.
1.3.2 Clauses and provisions in this document may not appear in consecutive order.
1.3 REMOVAL OF SECTIONS AT TIME OF AWARD
Sections 00100, 00110, 00120, 00600 and all exhibits will be physically removed as a result of an award, but will be deemed to be incorporated by reference in that award.
1.4 DISPOSITION OF UNSUCCESSFUL PROPOSALS
In compliance with FAR Subpart 4.8, the Government will retain one copy of all unsuccessful proposals. The Government will destroy extra copies of unsuccessful proposals. No destruction certificate will be provided.
1.5 BONDING REQUIREMENTS
Performance and Payment bonds will be required in the amount of 100% of the contract award value. A bid bond is required per clause 52.228-1. The amount of the guarantee shall be 3 million dollars or 20% of the bid price, whichever is less. Offerors shall provide a letter from their bonding company to stat that the company, upon contract award, will be bonded in that amount.
1.6 FORMAL COMMUNICATION, OFFEROR EXPLANATIONS
Any explanation desired by an offeror regarding the meaning or interpretation of the solicitation, for proposals, drawings, specifications, etc. must be requested in writing and with sufficient time allowed for a reply to reach offerors before the submission of their proposals. All questions and requests for information (RFIs) must be received NOT LATER THAN 31 March 2010. Questions and RFIs may be submitted to:
walter.kamad@usace.army.mil and cc kenneth.e.mackay@usace.army.mil.
Acknowledgement of each amendment by the offeror must be made in the space provided on the SF 1442, or by returning a signed copy of the amendment by the time set for receipt of proposals.
1.7 AMENDMENTS PRIOR TO DATE SET FOR RECEIPT OF PROPOSALS
The right is reserved, as the interest of the Government may require, to revise or amend the solicitation, specifications and/or drawings, prior to and/or after the date set for receipt of proposals. Such changes, if any, will be announced by an amendment or amendments to this Request for Proposal. All information relating to this RFP, including pertinent changes/amendments and other information applicable prior to the date set for receipt of proposals will be posted on FedBizOpps.
1.8 HAND CARRIED PROPOSALS/INVITATIONS
Proposals can be hand carried to the USACE Buffalo District located at 1776 Niagara St, Buffalo, NY 14207. Hand carried proposals must be received in the Contracting Office prior to the time established for receipt of proposals. Offerors are cautioned that they will be required to enter a Federal Government facility and should allow time to accomplish this.
1.9 WAGE DETERMINATION
Davis Bacon Wage Rates are applicable to this project and shall be included in the contract.
1.10 PROPOSAL EXPENSES AND PRE-CONTRACT COSTS
This RFP does not commit the Government to pay costs incurred in preparation and submission of initial and subsequent proposals or for other costs incurred prior to award of a formal contract.
mailto:walter.kamad@usace.army.mil�
SECTION 00110 - PROPOSAL PREPARATION INSTRUCTIONS TO OFFERERS
1.0 GENERAL INSTRUCTIONS
1.1 PROPOSAL PREPARATION INSTRUCTIONS
1.1.1 These instructions prescribe the format of proposals, and describe the approach for the development and presentation of the proposal data. They are designed to ensure the submission of necessary information to provide for the understanding and comprehensive evaluation of proposals. Carefully review this section prior to commencing proposal preparation. All solicitation amendments must be acknowledged in accordance with Section 00100, FAR Provision 52.215-1, and Instructions to Offerors.
1.1.2 Offerors are cautioned to strictly comply with all instructions within this solicitation to ensure submission of a complete proposal. Failure to furnish a complete proposal, at the time of proposal submission, may result in the proposal being unacceptable to the Government and eliminated from consideration for award.
1.1.3 After compiling all required information, submit the information in accordance with the “Proposal Due Date Schedule” paragraph and return the original and specified number of copies to the issuing office listed in Block 8 of the SF 1442.
Mark the front of the envelope/box with the following: “PROPOSAL for W911XK-10-R-0005 - DO NOT OPEN - Competitive Acquisition”.
1.2 PROPOSAL CONTENT
Prospective offerors shall submit the following volumes in two separate packages in accordance with instructions contained herein:
1. Volume 1, Technical Capability and Past Performance, in original and five (5) copies
2. Volume 2, Business Proposal, in original and one (1) copy
Offerors are cautioned to carefully review the proposal requirements for these volumes and ensure a complete proposal is submitted.
1.3 PROPOSAL DUE DATE SCHEDULE
The entire proposal (Volumes 1 and 2) are due by the date and time set for the receipt of proposals shown in Block 13 of the SF 1442.
1.4 PROPOSAL FORMAT
1.4.1 Purpose: These instructions prescribe the format of proposals, and describe the approach for the development and presentation of the proposed data. The proposal shall include all of the information requested in the specific instructions.
Failure to include all information requested may adversely affect the evaluation.
A proposal that is orderly and sufficiently documented will be easy for the Government to understand and will enable the Government to perform a thorough and fair evaluation.
1.4.2 Offerors are cautioned to submit enough information to enable the evaluation committee to fully ascertain each offeror’s capability to perform all of the requirements contemplated by this solicitation. All commitments made in the proposal may become a part of the resultant contract. The data submitted with each proposal should be complete and concise, but not overly elaborate.
Excessive reliance on promotional brochures is discouraged.
1.4.3 The number for pages per volume may not exceed 25 pages. The specific information as listed in the note below will be excluded from the total number of pages.
NOTE: The items that are excluded from the page count are the Proposal Cover;
the Table of Contents; and Title or Index Page.
1.4.4 Each page should be numbered consecutively within each section. The page size of the offeror’s proposal shall not exceed an 8-1/2 inch by 11-inch sheet of paper.
Please refer to Section 00700, FAR 52.204-4 for printing/duplicating instructions.
NOTE: Double sided copies are considered as two pages. Proposals that exceed the specified page limit will have only those first pages that are within the required limits evaluated. All information appearing thereafter will not be evaluated.
1.4.5 Proposal type size for text documents shall not be smaller than Microsoft Word
Times New Roman 10 point font; normal proportional spacing and page size shall be no larger than normal letter size paper (8 ½” x 11”). Type size for graphics, charts, diagrams and tables, shall be of an appropriate font and size for the application, and must be clearly readable without magnification assistance to the normal eye. Text lines shall be no less than single-space. To the maximum extent practicable, proposal submission shall be double sided.
1.4.6 Binding: Elaborate format and binding are neither necessary nor desirable. All binders shall be capable of lying flat when opened. The cover and spine of each binder shall clearly identify the offeror’s name, Volume number, RFP number, RFP title and copy number, (e.g. copy 2 of 5). The original for each volume shall be clearly identified on the cover and the spine. All binders shall allow for easy removal and replacement of pages.
1.4.7 Indexing: Each binder shall contain a “Table of Contents” for that volume. The
“Table of Contents” shall identify major areas, paragraphs and subparagraphs by number and title as well as by page number and volume locations. Tab indexing shall be used to identify Sections as appropriate.
2.0 PROPOSAL VOLUME CONTENTS
2.1 VOLUME 1 - OFFEROR TECHNICAL INFORMATION
Volume 1 is obtained for the purpose of evaluating Technical Acceptability. The following information shall be included in Volume 1:
a. Resume of Grouting Engineer
b. Resume of Grouting Superintendent
c. Listing/Description of at least 3 projects in the past 5 years performing similar grouting projects indicating fulfillment of the experience requirement for this work with the Grout Placement Plan. Projects should be similar in technical nature and dollar magnitude. Include point of contact (name, phone number, and email address) for the customer, dollar amount, and location for each project.
2.2 VOLUME 2 - PRICE/BUSINESS INFORMATION
Offerors shall provide the following information in Volume 2:
a. Completed Bid Schedule
b. Bid Bond
c. Complete in its entirety the “Offeror” portion of the Standard Form (SF) 1442.
An official having the authority to contractually bind your company must sign the SF 1442 in accordance with FAR 4.102. One copy of the SF 1442 is required to have an original signature.
d. Representation and Certification as required by Section 00600. If ORCA has been completed by the offeror, please indicate such. A complete printout of the ORCA certifications is not required.
SECTION 00120 - PROPOSAL EVALUATION AND BASIS FOR AWARD
1.0 GENERAL INFORMATION
1.1 The solicitation will result in the award of one firm-fixed price construction contract.
Award will be made on the basis of the lowest evaluated price of proposals meeting or exceeding the acceptability standards for non-cost factors.
1.2 The source selection process will be conducted in accordance with FAR Part 15.3, Source
Selection procedures.
1.3 The Contracting Officer will conduct proposal compliance review after closing for determination of basic proposal adequacy prior to providing the proposals to the evaluators. Failure to provide a complete proposal, both volumes, may result in the proposal being removed from further consideration for award.
1.4 Offerors must ensure that no pricing information is displayed in any volume except the
Business Proposal.
1.5 The Government intends to evaluate proposals and award a contract without discussions with offerors (except clarifications as described in FAR 15.306(a)). The Government reserves the right to conduct discussions if the Contracting Officer later determines them to be necessary. If the Contracting Officer determines that the number of proposals that would otherwise be in the competitive range exceeds the number at which an efficient competition can be conducted, the Contracting Officer may limit the number of proposals in the competitive range to the greatest number that will permit an efficient competition among the most highly rated proposals.
1.6 ENFORCEABILITY OF PROPOSAL: The proposal must set forth full, accurate and complete information as required by this solicitation. The Government will rely on such information in the award of a contract. By submission of the offer, the offeror agrees that all items proposed (if applicable e.g., key personnel, subcontractors, etc.) will be utilized for the duration of the contract and any substitutions will require prior Contracting Officer's approval.
2.0 EVALUATION FACTORS FOR AWARD (LOW COST, TECHNICALLY
ACCEPTABLE)
Award of the contract resulting from this solicitation will be made to the responsible offeror whose proposal is technically acceptable, in full compliance to all other requirements set forth in the solicitation, and the lowest cost or price. The Government reserves the right to judge which proposals show the required capability.
2.1 Technical Acceptability Evaluation
The Government will evaluate each proposal for technical acceptability. In order to be technically acceptable, an offer must be technically acceptable in each of the following sub-factors:
a. Grouting Engineer
b. Grouting Superintendent
c. Experience
The standards for technically acceptable for each subfactor are as follows:
a. Grouting Engineer
The Contractor shall provide a qualified Grouting Engineer to perform the design of the grouting program and prepare the Grout Placement Plan for this contract. The Grouting Engineer shall have a minimum of 10-years experience in the design of grouting projects and shall be a registered professional engineer.
b. Grouting Superintendent
The Contractor shall provide a qualified Grouting Superintendent, experienced in using the materials and equipment proposed for this work. The Grouting Superintendent shall have a minimum of 10-years experience in grouting projects. The Grouting Superintendent shall be present during all drilling and grouting. This individual shall be responsible for the oversight of all drilling and grouting operations, mix formulations and the preparation of grouting records for each boring and series of borings.
c. Experience
The Contractor performing the grouting shall have experience grouting on a scale comparable to this work on a minimum of 3 projects in the past 5 years, and shall have demonstrated proficiency with the materials and equipment to be used in this work.
2.2 Contractor Selection
At the completion of the technical evaluations, each firm shall be rated either technically acceptable or unacceptable. At this point, the lowest priced technically acceptable proposal, in full compliance to all other requirements set forth in the solicitation, will be determined to represent the best value to the Government.
Section 00600 - Representations & Certifications
CLAUSES INCORPORATED BY FULL TEXT
52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (FEB 2009)
(a)(1) The North American Industry Classification System (NAICS) code for this acquisition is [237990].
(2) The small business size standard is [33.5 Million].
(3) The small business size standard for a concern which submits an offer in its own name, other than on a construction or service contract, but which proposes to furnish a product which it did not itself manufacture, is 500 employees.
(b)(1) If the clause at 52.204-7, Central Contractor Registration, is included in this solicitation, paragraph (d) of this provision applies.
(2) If the clause at 52.204-7 is not included in this solicitation, and the offeror is currently registered in CCR, and has completed the ORCA electronically, the offeror may choose to use paragraph (d) of this provision instead of completing the corresponding individual representations and certifications in the solicitation. The offeror shall indicate which option applies by checking one of the following boxes:
(__) Paragraph (d) applies.
(__) Paragraph (d) does not apply and the offeror has completed the individual representations and certifications in the solicitation.
(c)(1) The following representations or certifications in ORCA are applicable to this solicitation as indicated:
(i) 52.203-2, Certificate of Independent Price Determination. This provision applies to solicitations when a firm-fixed-price contract or fixed-price contract with economic price adjustment is contemplated, unless--
(A) The acquisition is to be made under the simplified acquisition procedures in Part 13;
(B) The solicitation is a request for technical proposals under two-step sealed bidding procedures; or
(C) The solicitation is for utility services for which rates are set by law or regulation.
(ii) 52.203-11, Certification and Disclosure Regarding Payments to Influence Certain Federal Transactions. This provision applies to solicitations expected to exceed $100,000.
(iii) 52.204-3, Taxpayer Identification. This provision applies to solicitations that do not include the clause at 52.204-7, Central Contractor Registration.
(iv) 52.204-5, Women-Owned Business (Other Than Small Business).This provision applies to solicitations that--
(A) Are not set aside for small business concerns;
(B) Exceed the simplified acquisition threshold; and
(C) Are for contracts that will be performed in the United States or its outlying areas.
(v) 52.209-5, Certification Regarding Responsibility Matters. This provision applies to solicitations where the contract value is expected to exceed the simplified acquisition threshold.
(vi) 52.214-14, Place of Performance--Sealed Bidding. This provision applies to invitations for bids except those in which the place of performance is specified by the Government.
(vii) 52.215-6, Place of Performance. This provision applies to solicitations unless the place of performance is specified by the Government.
(viii) 52.219-1, Small Business Program Representations (Basic & Alternate I). This provision applies to solicitations when the contract will be performed in the United States or its outlying areas.
(A) The basic provision applies when the solicitations are issued by other than DoD, NASA, and the Coast Guard.
(B) The provision with its Alternate I applies to solicitations issued by DoD, NASA, or the Coast Guard.
(ix) 52.219-2, Equal Low Bids. This provision applies to solicitations when contracting by sealed bidding and the contract will be performed in the United States or its outlying areas.
(x) 52.222-22, Previous Contracts and Compliance Reports. This provision applies to solicitations that include the clause at 52.222-26, Equal Opportunity.
(xi) 52.222-25, Affirmative Action Compliance. This provision applies to solicitations, other than those for construction, when the solicitation includes the clause at 52.222-26, Equal Opportunity.
(xii) 52.222-38, Compliance with Veterans' Employment Reporting Requirements. This provision applies to solicitations when it is anticipated the contract award will exceed the simplified acquisition threshold and the contract is not for acquisition of commercial items.
(xiii) 52.223-1, Biobased Product Certification. This provision applies to solicitations that require the delivery or specify the use of USDA-designated items; or include the clause at 52.223-2, Affirmative Procurement of Biobased Products Under Service and Construction Contracts.
(xiv) 52.223-4, Recovered Material Certification. This provision applies to solicitations that are for, or specify the use of, EPA-designated items.
(xv) 52.225-2, Buy American Act Certificate. This provision applies to solicitations containing the clause at 52.225- 1.
(xvi) 52.225-4, Buy American Act--Free Trade Agreements—Israeli Trade Act Certificate. (Basic, Alternate I, and Alternate II) This provision applies to solicitations containing the clause at 52.225-3.
(A) If the acquisition value is less than $25,000, the basic provision applies.
(B) If the acquisition value is $25,000 or more but is less than $50,000, the provision with its Alternate I applies.
(C) If the acquisition value is $50,000 or more but is less than $67,826, the provision with its Alternate II applies.
(xvii) 52.225-6, Trade Agreements Certificate. This provision applies to solicitations containing the clause at 52.225-5.
(xviii) 52.225-20, Prohibition on Conducting Restricted Business Operations in Sudan--Certification.
(xix) 52.226-2, Historically Black College or University and Minority Institution Representation. This provision applies to--
(A) Solicitations for research, studies, supplies, or services of the type normally acquired from higher educational institutions; and
(B) For DoD, NASA, and Coast Guard acquisitions, solicitations that contain the clause at 52.219-23, Notice of Price Evaluation Adjustment for Small Disadvantaged Business Concerns.
(2) The following certifications are applicable as indicated by the Contracting Officer:
(Contracting Officer check as appropriate.)
----(i) 52.219-19, Small Business Concern Representation for the Small Business Competitiveness Demonstration Program.
------(ii) 52.219-21, Small Business Size Representation for Targeted Industry Categories Under the Small Business Competitiveness Demonstration Program.
------(iii) 52.219-22, Small Disadvantaged Business Status.
------(A) Basic.
------(B) Alternate I.
------(iv) 52.222-18, Certification Regarding Knowledge of Child Labor for Listed End Products.
------(v) 52.222-48, Exemption from Application of the Service Contract Act to Contracts for Maintenance, Calibration, or Repair of Certain Equipment Certification.
------(vi) 52.222-52 Exemption from Application of the Service Contract Act to Contracts for Certain Services-- Certification.
------(vii) 52.223-9, with its Alternate I, Estimate of Percentage of Recovered Material Content for EPA-Designated Products (Alternate I only).
------(viii) 52.223-13, Certification of Toxic Chemical Release Reporting.
------(ix) 52.227-6, Royalty Information.
------ (A) Basic.
------ (B) Alternate I.
------(x) 52.227-15, Representation of Limited Rights Data and Restricted Computer Software.
(d) The offeror has completed the annual representations and certifications electronically via the Online Representations and Certifications Application (ORCA) website at http://orca.bpn.gov. After reviewing the ORCA database information, the offeror verifies by submission of the offer that the representations and certifications currently posted electronically that apply to this solicitation as indicated in paragraph (c) of this provision have been entered or updated within the last 12 months, are current, accurate, complete, and applicable to this solicitation (including the business size standard applicable to the NAICS code referenced for this solicitation), as of the date of this offer and are incorporated in this offer by reference (see FAR 4.1201); except for the changes identified below (offeror to insert changes, identifyingchange by clause number, title, date). These amended representation(s) and/or certification(s) are also incorporated in this offer and are current, accurate, and complete as of the date of this offer.
FAR Clause Title Date Change
Any changes provided by the offeror are applicable to this solicitation only, and do not result in an update to the representations and certifications posted on ORCA.
(End of Provision)
Section 00700 - Contract Clauses
CLAUSES INCORPORATED BY REFERENCE
52.203-3 Gratuities APR 1984 52.203-5 Covenant Against Contingent Fees APR 1984 52.203-7 Anti-Kickback Procedures JUL 1995 52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or
Improper Activity
JAN 1997
52.203-10 Price Or Fee Adjustment For Illegal Or Improper Activity JAN 1997 52.203-12 Limitation On Payments To Influence Certain Federal
Transactions
SEP 2007
52.204-7 Central Contractor Registration APR 2008 52.204-9 Personal Identity Verification of Contractor Personnel SEP 2007 52.209-6 Protecting the Government's Interest When Subcontracting
With Contractors Debarred, Suspended, or Proposed for Debarment
SEP 2006
52.215-2 Audit and Records--Negotiation MAR 2009 52.215-11 Price Reduction for Defective Cost or Pricing Data--
Modifications
OCT 1997
52.215-13 Subcontractor Cost or Pricing Data--Modifications OCT 1997 52.215-21 Requirements for Cost or Pricing Data or Information Other
Than Cost or Pricing Data--Modifications
OCT 1997
52.219-8 Utilization of Small Business Concerns MAY 2004 52.219-14 Limitations On Subcontracting DEC 1996 52.222-3 Convict Labor JUN 2003 52.222-4 Contract Work Hours and Safety Standards Act - Overtime
Compensation
JUL 2005
52.222-6 Davis Bacon Act JUL 2005 52.222-7 Withholding of Funds FEB 1988 52.222-8 Payrolls and Basic Records FEB 1988 52.222-9 Apprentices and Trainees JUL 2005 52.222-11 Subcontracts (Labor Standards) JUL 2005 52.222-12 Contract Termination-Debarment FEB 1988 52.222-13 Compliance with Davis-Bacon and Related Act Regulations. FEB 1988 52.222-14 Disputes Concerning Labor Standards FEB 1988 52.222-15 Certification of Eligibility FEB 1988 52.222-21 Prohibition Of Segregated Facilities FEB 1999 52.222-26 Equal Opportunity MAR 2007 52.222-27 Affirmative Action Compliance Requirements for
Construction
FEB 1999
52.222-35 Equal Opportunity For Special Disabled Veterans, Veterans of the Vietnam Era, and Other Eligible Veterans
SEP 2006
52.222-36 Affirmative Action For Workers With Disabilities JUN 1998 52.222-50 Combating Trafficking in Persons FEB 2009 52.223-10 Waste Reduction Program AUG 2000 52.223-14 Toxic Chemical Release Reporting AUG 2003 52.223-14 Toxic Chemical Release Reporting AUG 2003 52.225-13 Restrictions on Certain Foreign Purchases JUN 2008 52.228-5 Insurance - Work On A Government Installation JAN 1997 52.228-11 Pledges Of Assets SEP 2009 52.228-14 Irrevocable Letter of Credit DEC 1999 52.228-15 Performance and Payment Bonds--Construction NOV 2006 52.229-3 Federal, State And Local Taxes APR 2003
52.232-5 Payments under Fixed-Price Construction Contracts SEP 2002 52.232-27 Prompt Payment for Construction Contracts OCT 2008 52.232-33 Payment by Electronic Funds Transfer--Central Contractor
Registration
OCT 2003
52.233-1 Disputes JUL 2002 52.233-3 Protest After Award AUG 1996 52.233-4 Applicable Law for Breach of Contract Claim OCT 2004 52.236-2 Differing Site Conditions APR 1984 52.236-3 Site Investigation and Conditions Affecting the Work APR 1984 52.236-4 Physical Data APR 1984 52.236-5 Material and Workmanship APR 1984 52.236-6 Superintendence by the Contractor APR 1984 52.236-7 Permits and Responsibilities NOV 1991 52.236-8 Other Contracts APR 1984 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements
APR 1984
52.236-10 Operations and Storage Areas APR 1984 52.236-11 Use and Possession Prior to Completion APR 1984 52.236-12 Cleaning Up APR 1984 52.236-13 Accident Prevention NOV 1991 52.236-15 Schedules for Construction Contracts APR 1984 52.236-17 Layout of Work APR 1984 52.236-21 Specifications and Drawings for Construction FEB 1997 52.236-26 Preconstruction Conference FEB 1995 52.236-28 Preparation of Proposals--Construction OCT 1997 52.242-13 Bankruptcy JUL 1995 52.242-14 Suspension of Work APR 1984 52.246-12 Inspection of Construction AUG 1996 52.246-21 Warranty of Construction MAR 1994 52.249-2 Termination For Convenience Of The Government (Fixed-
Price)
MAY 2004
52.249-10 Default (Fixed-Price Construction) APR 1984 252.201-7000 Contracting Officer's Representative DEC 1991 252.203-7000 Requirements Relating to Compensation of Former DoD
Officials
JAN 2009
252.203-7001 Prohibition On Persons Convicted of Fraud or Other Defense- Contract-Related Felonies
DEC 2008
252.203-7002 Requirement to Inform Employees of Whistleblower Rights JAN 2009 252.209-7004 Subcontracting With Firms That Are Owned or Controlled By
The Government of a Terrorist Country
DEC 2006
252.227-7022 Government Rights (Unlimited) MAR 1979 252.232-7003 Electronic Submission of Payment Requests and Receiving
Reports
MAR 2008
52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)
The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 150 calendar days after the Notice to Proceed. The time stated for completion shall include final cleanup of the premises.
*The Contracting Officer shall specify either a number of days after the date the contractor receives the notice to proceed, or a calendar date.
(End of clause)
52.225-9 BUY AMERICAN ACT—CONSTRUCTION MATERIALS (FEB 2009)
(a) Definitions. As used in this clause--
Commercially available off-the-shelf (COTS) item—
(1) Means any item of supply (including construction material) that is--
(i) A commercial item (as defined in paragraph (1) of the definition at FAR 2.101);
(ii) Sold in substantial quantities in the commercial marketplace; and
(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and
(2) Does not include bulk cargo, as defined in section 3 of the Shipping Act of 1984 (46 U.S.C. App. 1702), such as agricultural products and petroleum products.
Component means an article, material, or supply incorporated directly into a construction material.
Construction material means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site.
Materials purchased directly by the Government are supplies, not construction material.
Cost of components means--
(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or
(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.
Domestic construction material means--
(1) An unmanufactured construction material mined or produced in the United States;
(2) A construction material manufactured in the United States, if--
(i) The cost of its components mined, produced, or manufactured in the United States exceeds 50 percent of the cost of all its components. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic; or
(ii) The construction material is a COTS item.
Foreign construction material means a construction material other than a domestic construction material.
United States means the 50 States, the District of Columbia, and outlying areas.
(b) Domestic preference.
(1) This clause implements the Buy American Act (41 U.S.C. 10a-10d) by providing a preference for domestic construction material. In accordance with 41 U.S.C. 431, the component test of the Buy American Act is waived for construction material that is a COTS item (See FAR 12.505(a)(2)). The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.
(2) This requirement does not apply to the construction material or components listed by the Government as follows:
[Contracting Officer to list applicable excepted materials or indicate “none”]
(3) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(2) of this clause if the Government determines that
(i) The cost of domestic construction material would be unreasonable. The cost of a particular domestic construction material subject to the requirements of the Buy American Act is unreasonable when the cost of such material exceeds the cost of foreign material by more than 6 percent;
(ii) The application of the restriction of the Buy American Act to a particular construction material would be impracticable or inconsistent with the public interest; or
(iii) The construction material is not mined, produced, or manufactured in the United States in sufficient and reasonably available commercial quantities of a satisfactory quality.
(c) Request for determination of inapplicability of the Buy American Act. (1)(i) Any Contractor request to use foreign construction material in accordance with paragraph (b)(3) of this clause shall include adequate information for Government evaluation of the request, including--
(A) A description of the foreign and domestic construction materials;
(B) Unit of measure;
(C) Quantity;
(D) Price;
(E) Time of delivery or availability;
(F) Location of the construction project;
(G) Name and address of the proposed supplier; and
(H) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(3) of this clause.
(ii) A request based on unreasonable cost shall include a reasonable survey of the market and a completed price comparison table in the format in paragraph (d) of this clause.
(iii) The price of construction material shall include all delivery costs to the construction site and any applicable duty (whether or not a duty-free certificate may be issued).
(iv) Any Contractor request for a determination submitted after contract award shall explain why the Contractor could not reasonably foresee the need for such determination and could not have requested the determination before contract award. If the Contractor does not submit a satisfactory explanation, the Contracting Officer need not make a determination.
(2) If the Government determines after contract award that an exception to the Buy American Act applies and the Contracting Officer and the Contractor negotiate adequate consideration, the Contracting Officer will modify the contract to allow use of the foreign construction material. However, when the basis for the exception is the unreasonable price of a domestic construction material, adequate consideration is not less than the differential established in paragraph (b)(3)(i) of this clause.
(3) Unless the Government determines that an exception to the Buy American Act applies, use of foreign construction material is noncompliant with the Buy American Act.
(d) Data. To permit evaluation of requests under paragraph (c) of this clause based on unreasonable cost, the Contractor shall include the following information and any applicable supporting data based on the survey of suppliers:
Foreign and Domestic Construction Materials Price Comparison Construction material description Unit of measure Quantity Price (dollars) \1\ Item 1 Foreign construction material Domestic construction material Item 2 Foreign construction material Domestic construction material Include all delivery costs to the construction site and any applicable duty (whether or not a duty-free entry certificate is issued).
List name, address, telephone number, and contact for suppliers surveyed. Attach copy of response; if oral, attach summary.
Include other applicable supporting information.
52.225-10 NOTICE OF BUY AMERICAN ACT REQUIREMENT--CONSTRUCTION MATERIALS (FEB
2009)
(a) Definitions. “Commercially available off-the-shelf (COTS) item,” “construction material,” “domestic construction material,” and “foreign construction material,” as used in this provision, are defined in the clause of this solicitation entitled “Buy American Act--Construction Materials” (Federal Acquisition Regulation (FAR) clause 52.225-9).
(b) Requests for determinations of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American Act should submit the request to the Contracting Officer in time to allow a determination before submission of offers. The offeror shall include the information and applicable supporting data required by paragraphs (c) and (d) of the clause at FAR 52.225-9 in the request. If an offeror has not requested a determination regarding the inapplicability of the Buy American Act before submitting its offer, or has not received a response to a previous request, the offeror shall include the information and supporting data in the offer.
(c) Evaluation of offers. (1) The Government will evaluate an offer requesting exception to the requirements of the Buy American Act, based on claimed unreasonable cost of domestic construction material, by adding to the offered price the appropriate percentage of the cost of such foreign construction material, as specified in paragraph (b)(3)(i) of the clause at FAR 52.225-9.
(2) If evaluation results in a tie between an offeror that requested the substitution of foreign construction material based on unreasonable cost and an offeror that did not request an exception, the Contracting Officer will award to the offeror that did not request an exception based on unreasonable cost.
(d) Alternate offers.
(1) When an offer includes foreign construction material not listed by the Government in this solicitation in paragraph (b)(2) of the clause at FAR 52.225-9, the offeror also may submit an alternate offer based on use of equivalent domestic construction material.
(2) If an alternate offer is submitted, the offeror shall submit a separate Standard Form 1442 for the alternate offer, and a separate price comparison table prepared in accordance with paragraphs (c) and (d) of the clause at FAR 52.225-9 for the offer that is based on the use of any foreign construction material for which the Government has not yet determined an exception applies.
(3) If the Government determines that a particular exception requested in accordance with paragraph (c) of the clause at FAR 52.225-9 does not apply, the Government will evaluate only those offers based on use of the equivalent domestic construction material, and the offeror shall be required to furnish such domestic construction material. An offer based on use of the foreign construction material for which an exception was requested--
(i) Will be rejected as nonresponsive if this acquisition is conducted by sealed bidding; or
(ii) May be accepted if revised during negotiations.
(End of provision)
52.228-1 BID GUARANTEE (SEP 1996)
(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.
(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States.
The Contracting Officer will return bid guarantees, other than bid bonds, (1) to unsuccessful bidders as soon as practicable after the opening of bids, and (2) to the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.-
(c) The amount of the bid guarantee shall be ____20____ percent of the bid price or $__3,000,000______, whichever is less.-
(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.-
(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.
52.232-18 AVAILABILITY OF FUNDS (APR 1984)
Funds are not presently available for this contract. The Government's obligation under this contract is contingent upon the availability of appropriated funds from which payment for contract purposes can be made. No legal liability on the part of the Government for any payment may arise until funds are made available to the Contracting Officer for this contract and until the Contractor receives notice of such availability, to be confirmed in writing by the Contracting Officer.
52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) – ALTERNATE I (FEB 1995)
(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.
(b) An organized site visit has been scheduled for-- 03/25/10 at 9:30 AM,
(c) Participants will meet at-- Buffalo District Office, 1776 Niagara Street, Buffalo, NY 14207
(End of provision)
52.243-4 CHANGES (JUN 2007)
(a) The Contracting Officer may, at any time, without notice to the sureties, if any, by written order designated or indicated to be a change order, make changes in the work within the general scope of the contract, including changes--
(1) In the specifications (including drawings and designs);
(2) In the method or manner of performance of the work;
(3) In the Government-furnished property or services; or
(4) Directing acceleration in the performance of the work.
(b) Any other written or oral order (which, as used in this paragraph (b), includes direction, instruction, interpretation, or determination) from the Contracting Officer that causes a change shall be treated as a change order under this clause; provided, that the Contractor gives the Contracting Officer written notice stating
(1) the date, circumstances, and source of the order and
(2) that the Contractor regards the order as a change order.
(c) Except as provided in this clause, no order, statement, or conduct of the Contracting Officer shall be treated as a change under this clause or entitle the Contractor to an equitable adjustment.
(d) If any change under this clause causes an increase or decrease in the Contractor's cost of, or the time required for, the performance of any part of the work under this contract, whether or not changed by any such order, the Contracting Officer shall make an equitable adjustment and modify the contract in writing. However, except for an adjustment based on defective specifications, no adjustment for any change under paragraph (b) of this clause shall be made for any costs incurred more than 20 days before the Contractor gives written notice as required. In the case of defective specifications for which the Government is responsible, the equitable adjustment shall include any increased cost reasonably incurred by the Contractor in attempting to comply with the defective specifications.
(e) The Contractor must assert its right to an adjustment under this clause within 30 days after
(1) receipt of a written change order under paragraph (a) of this clause or (2) the furnishing of a written notice under paragraph (b) of this clause, by submitting to the Contracting Officer a written statement describing the general nature and amount of the proposal, unless this period is extended by the Government. The statement of proposal for adjustment may be included in the notice under paragraph (b) above.
(f) No proposal by the Contractor for an equitable adjustment shall be allowed if asserted after final payment under this contract.
52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and…