CHANGES TO SPECIFICATIONS FOR BUFFALO CDF 4REPAIR
SOLCITATION NO. W912P4-10-R-0005
1. Section 31 32 23.00 02, Paragraph 3.6, Insert the following information after the seventh sentence:
"If the Contractor can demonstrate that the Type F Filter Slag layer cannot be grouted due to the fineness of the existing materials, the 80% recovery length will be adjusted to only include the actual depth of existing materials grouted as approved by the Contracting Officer."
2. Section 31 32 23.00 02 Part 3.5.2.4
Delete this paragraph in its entirety from the contract specifications.
Other files
| File | Type | Posted |
|---|---|---|
| CDF-4 Ques.docx | DOCX document | |
| Responses to Questions From Bidders doc.docx | DOCX document | |
| Bid opening date will be postponed until April 14.docx | DOCX document | |
| CHANGES TO SPECIFICATIONS FOR BUFFALO CDF 4REPAIR.docx | DOCX document | |
| Questions.docx | DOCX document | |
| RFP 3-8-2010.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
File details come from the government source that posted it. Updated .